W912DR20Q0001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide the request for information responses, revised performance w ork statement, revised map attachment and to extend the solicitation close date from 18 November 2019 at 1100 am (EST) to 20 November 2019 at 1100 am (EST). No further questions w ill be accepted. All other terms remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 19

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Nov-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DR20Q0001

X 9B. DATED (SEE ITEM 11)

30-Oct-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Nov-2019

CODE

U.S ARMY CORPS OF ENGINEERS

2 HOPKINS PLACE 03-B-07

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REQUEST FOR INFORMATION

Request for Information Stillwater Lake Bridge Demolition

Q1. Could you please tell me if the Combined Synopsis/Solicitation posted as solicitation number W912DR20Q0001 on FBO contains requirements similar to any work performed currently or in the past, or will this be a new requirement?

If possible, can you please provide the most recent contract or task order number?

A1. This is a new requirement.

Q2. Can you please verify if a bid bond is required for the Stillwater Lake Bridge Demolition Project?

A2. No, a bid bond is not required for this requirement. This is a service contract.

Q3. Can you tell me if the project engineer has an estimate on this project?

A3. Government estimates are not disclosed to the public.

Q4. Would the contractor have to perform bypass pumping during demolition?

A4. No pumping is required, though if the waterway is blocked during demolition, work may be complicated by rising water.

REVISED PWS

STILLWATER DAM

FOREST CITY, PENNSYLVANIA

BRIDGE DEMOLITION

REVISED

STATEMENT OF WORK

Statement of Work: The US Army Corps of Engineers at Stillwater Dam in Forest City, Pennsylvania requires bridge demolition of an out of service bridge. The Contractor shall provide all labor, supervision, materials, equipment, and supplies to complete the following:

1. Summary: Demolish and remove the deck, parapets, and girders of an existing road bridge over the East Branch Lackawanna River at Stillwater Lake near Forest City, PA

2. Location and Access: The abandoned concrete road leading to the bridge parallels State Route 171. The primary route of access is from the north (See attached Figure 1) near the boat launch parking area. An alternate route from the south is no longer available or would require significant roadway improvement or tree and brush removal.

3. Structure: The bridge is a two-span structure. The deck of each span is 34’-4” long on an approximately 47 degree skew and 26’-4” wide. The deck is covered by a 1.5” asphalt overlay.

The reinforced concrete rails are 35” high. An unknown quantity of 2’ tall reinforced concrete beams support the deck. The clearance between the bridge and the water is between 2’ and 3’ at normal pool elevation. See attached Photographs for pictures of the structure.

4. Demolition: The bridge deck, rails, and beams shall be removed by any means excluding explosive demolition. The abutments and mid-stream pier may remain. No continuous path of travel shall remain across the river. The demolition spoils shall be placed at the north and south ends of the roadway as a barrier to travel. If possible to remove the beams intact, they may be placed transversely across the roadway as a barrier. Rebar protruding from concrete must be cut off flush with the concrete and disposed of off-site; all rebar encapsulated by concrete may remain. The water depth at the bridge is around 5’ to 8’ deep. To prevent restricting the river flow, accumulations of concrete in the water will not be allowed.

DELIVERABLES

1. Pre-Work Submittals - A paper or digital copy of the following shall be submitted within 10 days of award to the COR:

A. Accident Prevention Plan B. Activity Hazard Analysis C. Work Plan

2. Post-Work Submittals: A paper or digital copy of the following shall be submitted within

15 days of work completion to the COR: Daily Construction Quality Control Reports

SPECIAL CONDITIONS

1. Period of Performance: Work shall commence no later than 15 days award and be completed within 90 days. The start date will be coordinated with Head Dam Operator, Mr. Joe Chernesky.

2. Performance of Work: The Contractor shall perform work only during normal Corps of

Engineers duty hours (7:00 a.m. to 3:30 p.m., Monday through Friday, excluding national holidays). Exceptions to this condition must be coordinated with and approved in advance by the Operations Manager, Susquehanna River Project.

3. Accident Prevention: In performing this contract the Contractor shall comply with all current Federal, State, and Local safety regulations, including Corps of Engineers Safety and Health Requirement Manual EM 385-1-1 and shall comply with any subsequent changes.

Information regarding acquiring the Corps of Engineers Safety and Health Requirement Manual EM 385-1-1 may be found on the USACE Headquarters website at http://www.usace.army.mil/SafetyandOccupationalHealth/EM38511,2008BeingRevised.aspx Prior to commencement of work under this contract the Contractor shall furnish to the Government an Accident Prevention Plan in accordance with Section I, Article 01.A.12 of the EM 385-1-1, dated 30 November 2014.

4. Accident Reporting: In the event of an accident or injury involving contractor personnel or equipment in performance of work, the Contractor shall immediately notify the Government representative by the most expedient means feasible. The Contractor shall complete forms furnished and/or provide a written description of the incident within 24 hours of notification to do so.

5. Operations and Storage Areas: The Contractor shall confine all operations (including storage of materials) to areas authorized or approved by the Construction Control Representative.

The Contractor shall hold and save the Government, its officers, and agents free and harmless from liability of any nature occasioned by the Contractor’s performance.

6. Access and General Protection/Security Policy and Procedures: All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

7. Escorting: All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

8. Pre-screen candidates using E-Verify Program: The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

9. Housekeeping: The Contractor shall keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the Contractor shall remove from the work site and premises, any rubbish, tools, equipment, and materials that are not property of the Government. Upon completing the work the Contractor shall restore the work area to the original condition, to be approved by the Contracting Officer.

10. Environmental Protection: The Contractor is required to comply with all Federal, State, and

Local environmental regulations.

11. Permits and Licenses: The Contractor shall, at his/her own expense, obtain any license or permits required to perform the contract. The Contractor shall comply with all Federal, State, and Local laws and regulations and shall comply with any subsequent changes.

12. Records and Reports: In addition to the administrative requirements dictated elsewhere in this contract, the Contractor shall complete a Daily Construction Quality Control Report form to maintain record of contract performance, accident/injury incidence, and observance of project deficiencies. Forms will be distributed at pre-work conference.

13. Superintendent: The Contractor shall act as or provide a Superintendent who acts as a quality control manager whenever the work specified herein is being performed. The Superintendent shall conduct overall management coordination and be the central point of contact with the Government for performance of all work under this contract. The Superintendent and any individual designated to act for him/her shall have full authority to contractually commit the Contractor for prompt action on matters pertaining to the administration of the entire contract. Such authorization shall be submitted in writing to the Government representative. The Superintendent shall deal directly with the Government representative for normal day-to-day administration of the contract provisions. The Superintendent will be required to attend pre-work conference(s) prior to commencing work under this contract.

14. Project Operation: Stillwater Lake is a flood control project and the Contractor’s access to the work area and the execution of the requirements specified herein shall not significantly interfere with the daily operations of the projects or employees. The site of the work is subject to periodic flooding. The Contractor shall consider the potential for high levels in the scheduling of this contract. A specific program shall be established by the Contractor to evacuate personnel, equipment, and materials as necessary in the event of high water. It is the responsibility of the Contractor to coordinate all work with Mr. Chernesky.

INVOICES AND PAYMENT

1. Invoices: The Contractor shall submit itemized invoices no sooner than 5 days from the completion of the contract activity and no later than 15 days from the completion of the total contract activity. The invoice shall accurately reflect work completed. Each invoice at a minimum shall contain the following information:

Contractor name and address, exactly as it appears on the contract Contract number Date of invoice submission Invoice or Call Order number Invoice total

2. Corrections: Incorrect invoices will be returned to the Contractor for correction before processing payment. Corrected invoices shall be re-dated to reflect the new submission date.

3. Remittance: Invoices shall be submitted via post-mail and/or electronic mail to the following addresses for payment. Should changes occur to the mailing addresses the Contractor shall be notified of the correct recipient.

VIA Post Mail: U.S. Army Corps of Engineers Susquehanna River Project ATTN: Ann Derr 5960 Susquehanna Trail, Suite 1

Turbotville, PA 17772

VIA Electronic Mail: Ann.L.Derr@usace.army.mil

South Access Route no longer available. Route would require significant roadway shoring or tree and brush clearing.

PHOTOGRAPHS

Photograph 1: Bridge deck and parapets.

Photograph 2: North access route approach road

Photograph 3: South access route approach road

The following have been modified:

INSTRUCTION TO OFFERORS

Please see block 8. Any questions concerning this solicitation must be submit Request for Information (RFIs) by e-mail only to aisha.r.boykin@usace.army.mil no later than 12 November 2019 at 11:00 AM (EST).

Quotes can be submitted via e-mail to Aisha Boykin, Purchasing Agent at e-mail aisha.r.boykin@usace.army.mil, Contracting Division, Services and Supply Branch.

Site visits must be conducted prior to the submission of quote. The site visit will be held on 06 November 2019 at 1100 am (EST). Please meet at the PA Fish and Boat Access Parking lot off of State Route 171, 4.1 miles north of Forest City, PA.

The point of contact for the site vist is Jeff Meadows at 570-213-2264.

By submission of a quote, the Offeror acknowledges the requirement that prospective awardee must have an active registration in the SAM database prior to award, during performance, and through final payment of any contract resulting from this proposal.

Lack of active registration in the SAM database will make an Offeror ineligible for award. Offerors and contractors may obtain information on registration and annual confirmation requirements by calling 1-888-227-2423, or at: http://www.sam.gov.

Interested Offeror’s shall submit the required technical documents, past performance information and complete the price schedule as stated below in the “Evaluation and Basis of Award.” All line items must be priced. Quotes providing partial pricing shall be considered non-responsive.

EVALUATION CRITERIA:

A. TECHNICAL:

The offer will be evaluated to ensure all the items below are provided:

Technical Requirements: This information consists of the Offeror’s intended approach to executing the contract.

1. Equipment plan: The proposed equipment list should only include the equipment which will be used on this contract. Equipment listed should be identified for use on roadways. Include size, make, model, and ownership (owned or rented) of equipment.

2. Capabilities plan: The proposed capabilities should include adequate documentation to illustrate the Offeror’s capabilities to successful complete the work identified within the solicitation.

The Government will check Offeror’s equipment, staffing and capabilities plans for each project for completeness and reasonableness. A complete and reasonable equipment, staffing and capabilities plan will receive an Acceptable rating. Incomplete or unreasonable plans will receive a rating of Unacceptable. Government will evaluate the clarity and strength of the overall organization and how well it is organized and structured to execute the entire scope of work. The Government will evaluate the capability of the firm to execute the project. The Government will evaluate the Contractor’s resources to determine if it has the capability to self-perform the required amount of the project, in accordance with public policy to assure adequate interest in and supervision of all work.

The following ratings will be assigned to each Offeror’s Technical Submission:

Technical Submission Rating Definition

TECHNICAL RATING DEFINITION

ACCEPTABLE Offeror meets the minimum requirements of the solicitation.

UNACCEPTABLE Offeror does not clearly meet the minimum requirements of the solicitation.

B. PAST PERFORMANCE:

Technical Requirements: The Offeror shall demonstrate recent, relevant experience on similar projects. If the Offeror is a joint venture, each firm shall demonstrate experience.

Submit at least 2 detailed examples of relevant work that are currently well underway or performed within the past 5 years. Work experience shall be demonstrated for at least 5 years.

1. Evaluation Criteria: The Government will evaluate how well the Offeror demonstrated their recent (within three years of the issue date of the RFQ), relevant experience with similar projects. If the Offeror is a joint venture, each entity must demonstrate qualifying experience comparable to its role on the project. The Government reserves the right to verify the experience record of cited projects or other recent projects or to interview owners or references. The Government reserves the right to check any or all cited references to verify supplied information. A rating of Unacceptable will be given to an Offeror who cannot demonstrate a history of recent, relevant experience. The Government will consider extent of recent experience, degree of relevance of such experience to this project, demonstrated familiarity with similar sites and local conditions. Some examples of relevancy to this project may include, but not be limited to: (1) Number, size, type work, location; (2) Dates (completion within last 3 years); and (3) Firm's role and extent of work self-performed (subcontracting out all work is an examples of less relevant experience).

2. The past performance questionnaire (form PPQ-0) contained herein must be provided to two references. The references need to complete and submit the questionnaire directly to Aisha Boykin via email at aisha.r.boykin@usace.army.mil.

The following ratings will be assigned to each Offeror’s Past Performance Submission:

Past Performance Rating Definition

PAST PERFORMANCE RATING DEFINITION

ACCEPTABLE Based on the Offeror’s recent/relevant performance record, the Government has a reasonable expectation that the Offeror will successfully perform the required effort.

UNACCEPTABLE Based on the Offeror’s recent/relevant performance record, the Government has no expectation that the Offeror will be able to successfully perform the required effort.

NEUTRAL No past performance or reference information submitted.

C. PRICE

Bid schedule must be filled out completely. Government template provided. All line items must be priced. Quotes providing partial pricing shall be considered non-responsive.

Pricing will be evaluated in accordance with FAR 15.402. The government may require additional pricing information to assist in determining the extent to which the price is fair and reasonableness and the pricing information shall be provide if requested. The Government will evaluate quotes for award purposes by adding the total of all CLIN prices to ensure that pricing is not unbalanced. Offeror must complete all line items to be considered for award. This submission item is not rated. Award will be made for the lowest-price, technically acceptable offer.

USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)

CONTRACT INFORMATION (Contractor to complete Blocks 1- 4)

1. Contractor Information

Firm Name: CAGE Code:

Address: DUNs Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information

Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine

How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information

Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: Past performance refers to the quality of recent project experience from the customer’s perspective. The Offeror shall arrange for the reference customer point of contact for three projects to fill out the Questionnaire and return directly to Aisha Boykin, Purchasing Agent, e-mail at aisha.r.boykin@usace.army.mil. The questionnaires must be forwarded directly by the references. Ensure the reference is clearly marked for the applicable Offeror when submitted. The Government will not release the questionnaire forms to the Offeror at any time, in order for the Government to solicit candid, unbiased responses and comments.

Two References from previously completed jobs must be submitted and include a point of contact and phone numbers. These references must be relevant to the work which will be performed in this contract. Relevant work is defined as bridge demolition services. References must be recent within the past 5 years.

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit.

The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract.

There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable

No information or did not apply to your contract Rating will be neither positive nor negative.

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

TO BE COMPLETED BY CLIENT

1. QUALITY:

a) Quality of technical data/report preparation efforts E VG S M U N

b) Ability to meet quality standards specified for technical performance E VG S M U N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance

E VG S M U N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E

VG

S

M

U

N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met please address below)

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract

E VG S M U N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project? E VG S M U N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;

responsiveness to administrative reports, businesslike and communication)

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?

E VG S M U N

d) Overall customer satisfaction E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?

E VG S M U N

b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N

c) Government Property Control E VG S M U N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N

e) Utilization of Small Business concerns E VG S M U N

f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes

E VG S M U N

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)

E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)?

E VG S M U N

b) Contractor proposed innovative alternative methods/processes that reduced E VG S M U N

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

cost, improved maintainability or other factors that benefited the client

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back- up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)

d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.

Yes

No

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.

f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below.

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?

(Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)

b) Contractor complied with all security requirements for the project and personnel security requirements.

E VG S M U N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).

b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N

c) Would you hire or work with this firm again? (If no, please explain below) Yes No

d) In summary, provide an overall rating for the work performed by this contractor.

E VG S M U N

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 18-Nov-2019 11:00 AM to 20-Nov-2019 11:00 AM.

(End of Summary of Changes)