AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to respond to the requests for information (RFI), changes in specs and drawings, and provide the attendees sign-in sheet for 24 April 2019. All other terms and conditions remain unchanged.
Contracting POC: Tamara Bonomolo, tamara.c.bonomolo@usace.army.mil
1. CONTRACT ID CODE PAGE OF PAGES
1 32
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-May-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DR19R0009
X 9B. DATED (SEE ITEM 11)
12-Apr-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-May-2019
CODE
U.S. ARMY CORPS OF ENGINEERS, BALTIMORE
2 HOPKINS PLAZA
03-G-04
BALTIMORE MD 21201
W912DR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
Solicitation No. W912DR-19-R-0009, Raystown Dam Tainter Gate Rehabilitation
W912DR19R0009
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been modified:
Section 00 21 16 – Instructions to Proposers –
Delete paragraph 2.1.1 - The Offeror shall submit information on a minimum of two (2) but no more than three (3) completed projects. Each project submitted does not need to demonstrate all functional categories (structural, mechanical, and electrical work) for each individual project. Rather, to meet this factor, an offeror must submit a proposal that collectively demonstrates the offeror’s experience within all three discrete categories of work: structural, mechanical and electrical. If the Offeror’s submission exceeds the maximum project limitation of three completed projects, then the additional project(s) will not be evaluated. These projects must be of relevant scope and complexity and demonstrate a minimum completion value of $2,000,000. The Offer will demonstrate experience by the successful and contractual completion of applicable projects under this factor.
And replace with:
2.1.1. The Offeror shall submit information on a minimum of two (2) but no more than five (5) completed projects. Each project submitted does not need to demonstrate all functional categories (structural, mechanical, and electrical work) for each individual project. Rather, to meet this factor, an offeror must submit a proposal that collectively demonstrates the offeror’s experience within all three discrete categories of work: structural, mechanical and electrical. If the Offeror’s submission exceeds the maximum project limitation of three completed projects, then the additional project(s) will not be evaluated. These projects must be of relevant scope and complexity and demonstrate a minimum completion value of $2,000,000. The Offer will demonstrate experience by the successful and contractual completion of applicable projects under this factor.
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Bid Inquiry Contractor Report All Inquiries
Project: Raystown Dam Tainter Gate Rehabilitation Review: Raystown Dam Tainter Gate Rehabilitation (00001) (sorted by CommentID ) Displaying 43 inquiries.
Id Discipline Sheet Detail Spec
7943249 Specifications 52.236-27
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The site visit is specified to be held on Monday, April 22,2019 @ 10:30 am (EST).
We are from out of town and would have to travel on Easter Sunday in order to make the scheduled site visit time.
In order to avoid traveling on Easter Sunday we are requesting the site visit day be moved to Thursday April 25, 2019.
If not can we make arrangements for a non-formal site visit at another time?
On: Apr 17 2019.
Government Response. . Please see Amendment 01 posted on FBO on April 17th, 2019. On: Apr 18
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7944491 Contracting 00 21 16 - Instructions to Proposers
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
In the Instructions to Proposers specifications Factor 1 - Experience in Relevant Projects requires the submission of a minimum of two projects but no more than three completed projects. Can the quantity of submitted projects for this factor be increased? The reason, the proposer or Team must have Elements 1 through 5 and at least 6 of 9 total elements. However, three of these elements, are specialized trades. Specifically the diving, electrical, and the painting work (especially since there are SSPC QP-1 & QP-3 requirements in the specs). Those specialized trades alone consume every possible project submission without the possible General Contractor submitting their, mechanical, building, and steel experience on their own.
A team will need to submit at least one project from their subs to gain the required experience on the electrical, diving, and painting elements with a teaming commitment letter. In order to meet the required experience elements, additional projects are needed so the remaining elements can be addressed for a Team's experience.
On: Apr 18 2019.
Government Response. . Under Section 00 21 16 - Instructions to Proposers, Paragraph 2.1.1, the requirement has changed to "...a minimum of two (2) but no more than five (5) completed projects." On:
Apr 26 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7945184 Specifications 133419.0025 (1.7.3)
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The specification noted states that the metal building manufacture must be a member of MBMA. Would the government accept a building manufacture that is International Accreditation Service certified with an ultrasonic testing endorsement but not a member of MBMA?
On: Apr 18 2019.
Government Response. . The government would accept building manufacturers that are not a member of MBMA. However, all other manufacturer's qualifications and design requirements are still applicable. On:
Apr 26 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7945212 Specifications M-572
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Page 1 of 11ProjNet: Logged In User
5/13/2019https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAl...
Per drawing M-572 the material for the warm water gate wheels is stainless steel 300 series, this series include many options. Is 304ss acceptable? Also there is no requirement to quench and temper the wheels so we assume this is not required?
On: Apr 18 2019.
Government Response. . 304 stainless steel with a minimum ultimate strength of 75ksi and minimum yield strength of 30ksi was used as the basis of design so is an acceptable material. Heat treatment is not necessary as long as the minimum strengths are met. On: Apr 26 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7947022 Specifications 00 20 00 No. 4
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The deadline for questions seems extremely early in relation to the bid date. We will struggle to identify all of the subcontractors and suppliers by that date much less give them an opportunity to review the plans and specifications and ask questions. Please extend the date for questions.
On: Apr 19 2019.
Government Response. . Please see Amendment 02 posted on FBO on Tuesday, April 23, 2019. On:
Apr 24 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7947040 Specifications 13 34 19.00 25
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Paragraph 1.5.1 states "The Army Corp of Engineer's Road shall be repaired to the pre-existing condition prior to the demolition and construction of the storage building. All site work shall connect existing grades to the new grades supplied by Multi-Purpose Storage Building and it's concrete slabs." If repair work is required before construction can the Government clearly define the scope of repairs?
On: Apr 19 2019.
Government Response. . There is no current need for repair. This requirement is to repair any damage done during demolition and construction. Contractor must return the road to its current condition (or better) once construction is complete.
Paragraph 1.5.1 is changed to read "...repaired to the pre-existing condition after both the demolition and construction of the storage building." ... to ensure that the final condition is returned to original condition.
On: Apr 26 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7947058 Specifications 00 21 16
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Solicitation Section 2 Paragraph 2.1.1 states Experience Element 4 as "Successful experience of performing work below water surfaces of up to 150 feet in confined spaces. This includes utilizing scuba gear to inspect, repair, remove, or install equipment and structures. (Structural)" Please clarify as we do not feel scuba gear is acceptable.
On: Apr 19 2019.
Government Response. . Terminology for deep diving equipment would be erroneous in this case, however the expected depth is not. The experience element needs to show the relevant experience required to perform dive work at these required depths. On: Apr 26 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7947081 Specifications 01 05 00
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Paragraph 1.6 States "The site of the work is at a Government lake and all rules and regulations issued by the manager covering general safety, security, sanitary requirements, pollution control, traffic regulations and parking, shall be observed by the Contractor. Information regarding these requirements may be obtained by contacting the
Page 2 of 11ProjNet: Logged In User
Contracting Officer, who will provide such information or assist in obtaining same from appropriate authorities.
(MEMO)" Please provide this information.
On: Apr 19 2019.
Government Response. . No specific documents will be provided prior to bid. If spec section 1.6 is applicable during construction, the Government will furnish such information at that time. On: May 01 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7947108 Specifications 01 14 00
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Paragraph 1.2.2 states "The Contracting Officer will attempt to provide notification for such evacuation as early as possible but the Contractor must be aware of the inconsistencies of weather forecasting and should be prepared to suspend all spillway bay activities and remove all work and site access equipment within 24 hours." In particular during the work for the trunnion rehabilitation with the pins removed and temporary supports with the capacity to resit the full hydrostatic head of the gate, we do not feel it will be necessary to remove anything in 24 hours. Please clarify
On: Apr 19 2019.
Government Response. . During the duration of this project, the stoplogs will be deployed which are effective to an approximate elevation of 788.767'. The intent of this paragraph is to forewarn the contractor if there is a high pool event, the stoplogs could be overtopped, inundating areas downstream. During the work while the gate is temporary supported, this would still apply to the immediate area between the Tainter gate and stoplogs. On: Apr 26 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7947113 Specifications 01 14 00
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please verify that the two timeframes given in paragraph 1.2.4 are not required to be preformed concurrently. In other words, for a single gate, there are 4 weeks to perform the work while the trunnion pins are removed, and 2 weeks to perform the trunnion welding operations for a total of 6 weeks
On: Apr 19 2019.
Government Response. . The two timeframes given in paragraph 1.2.4 do not have to be performed concurrently. The 6 week assumption to complete the work is correct (4 weeks while trunnion pins are removed and 2 weeks during trunnion welding). On: Apr 26 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7947118 Specifications 01 14 00
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Paragraph 1.2.7 refers to weight limits on bridges leading to the project site. Please provide the contact information for the owners of the bridges so that we can attempt to coordinate what they will require us to do to get the tools and equipment to and from the project site.
On: Apr 19 2019.
Government Response. . The location of the bridges are shown on sheet G-005, Local Vicinity Map with the label "10 ton load restriction". Contact PA State and Juniata Township. On: Apr 26 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7951735 Mechanical SL005
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
According to drawing SL005, lifting beam wire rope, thimbles and shackles must be replaced with new. Does the master link require replacement and if so what material is required (carbon, steel, galvanized, stainless, etc.) for the master link and other components such as wire rope, thimbles, etc?
On: Apr 23 2019.
Page 3 of 11ProjNet: Logged In User
Government Response. . The intent was to replace the entire lifting beam sling from the shackles to the master link. The original pieces are carbon steel with a corrosion resistant coating. Replacement items should match or improve the strength and corrosive properties of the original components. On: Apr 26
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7952560 Contracting Standard Form 1442 Item 13 Proposal Due Date
Comment Classification: UNCLASSIFIED (U)
The proposal due date is very aggressive for the scope of work to be priced and preparation of the technical proposal. Please extend the due date by 6 weeks and allow questions to be submitted up to 2 weeks prior to the revised bid date.
On: Apr 23 2019.
Government Response. . Please see question 7947022 for the answer. On: Apr 24 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7953321 Other 1442-101 Due Date Solicitation
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
RFI #1
With the additional site visit held on 4/24/2019 and the questions cutoff date following the day after, will the Corps consider extending the bid date an additional 2 weeks?
On: Apr 24 2019.
Government Response. . Please see question 7947022 for the answer. On: Apr 24 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7956411 Mechanical SE004
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
According to drawing number SE004, the seal heater duct must be replaced. Should the entire length of this pipe be replaced from the sill beam to top or just top part that is going to be cut and what is the size and material of the pipe?
On: Apr 25 2019.
Government Response. . Replacement of the seal heater duct is only required in the area of where the embedded seal plate and surrounding concrete are shown to be replaced on sheet SE004. The duct is a 3" diameter steel pipe. On: May 01 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7966634 Mechanical ST009
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
On sheet ST009 there is a photo of the side seal showing it is clad with fluorocarbon. Detail A on the same drawing does not show cladding on the side seal. Are the side seals to have cladding?
On: May 01 2019.
Government Response. . Seal material and requirements are specified in section 05 59 13.00 of the specifications. On: May 02 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7967588 Civil S-006
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Page 4 of 11ProjNet: Logged In User
1. Sheet S-006 depicts the bottom crane mats cut on a bevel. This set of new mats will be delivered to the Government at the end of the project. Do the mats the contractor uses for construction have to be cut on a bevel?
2. Given the due date falls immediately after a holiday weekend. Would you please consider extending the due date to the following week?
On: May 01 2019.
Government Response. . 1. The mats that the contractor uses does not need to be cut on a bevel.
Crane matting requirements during construction stated in Division 01 of the specifications.
2. The proposal due date will not be extended. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7968833 General NA NA NA
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Amendment #2 included the sign-in sheet from the 04.22.19 pre-bid meeting but no sign in sheet from the 04.24.19 pre-bid meeting. Will the sign-in sheet from the 04.24.19 pre-bid meeting be distributed?
On: May 02 2019.
Government Response. . The second site visit sign-in sheet from 24 April 2019 will be included in the next amendment. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7969089 General CEV58M-00051
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
RE: W912DR-19-R-009 Raystown Dam Tainter Gate Rehabilitation
QUESTION 1:
The 4 bolt expansion description and part #069423 (2 bolt, non-expansion) on the drawing M-552 and M-553 do not agree. The correct Dodge part number for the 4 bolt expansion pillow block is 069547.
Please clarify.
QUESTION 2:
Regarding the encoder TR Electronic CEV-58M on sheet M-501, M-551, M-552 and M-553.
Please review the letter from TR Electronic and advise.
Regards, Jack Conway Sr.
(Attachment: Pam_1.pdf) On: May 02 2019.
Government Response. . QUESTION 1: The basis of design for these bearings was the Dodge Imperial- IP 4 bolt expansion bearing. An equivalent bearing that meets specification 35 20 16.51 25 Section 2.2.3 may be used.
QUESTION 2: An equivalent encoder that meets specification 35 20 16.47 25 Section 2.3.1 a. through j.
may be used. AMCI DC60 has been used in the past as well. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7969910 Civil Page M-520 Page M-520
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
1. Request an extension to RFI due date to May 10, 2019.
2. There is no commercially available drilling machine that is capable of producing ¾"-10 holes which can also fit in the limited space between the Trunnion Hub and the concrete surface of the Abutment/Pier, Sheet M-520. How does the USACE suggest these holes be produced?
3.Please provide the sign in sheet from the pre-bid meeting held on April 24th 2019.
Page 5 of 11ProjNet: Logged In User
4. Please provide the name of the diving company that has worked on the tunnel access gates.
5. Will all of the materials currently in the storage building be removed by the owner?
On: May 02 2019.
Government Response. . 1. There will be no extension to the RFI due date.
2. During construction, the Tainter gate will be rotated out of the yoke for a portion of time and access to the yokes will be available during that time
3. Please see question number 7968833 for the answer.
4. Names of diving companies will not be provided by the Government.
5. The government will remove all materials except for the tunnel bulkheads. The tunnel bulkheads shall be removed from the existing building as well as placed into the new building by the contractor. On: May 09
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971342 Structural S-001
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Note 3.12 states "ALL WELDS SHALL BE GROUND HAND SMOOTH AND FLUSH SUCH THAT THERE ARE NO BURRS, OFFSETS OR ROUGH AREAS." Ground smooth and ground flush have two very different meanings and cost impacts. Smooth basically means no burrs while flush means ground flush with the surrounding metal. They also have two very different costs. Please clarify whether you want all welds ground smooth or flush.
On: May 03 2019.
Government Response. . The intent of this note is to ensure that all welds are smooth, free of spatter, and other sharp geometric discontinuities. The welds that require grounding flush are identified as such in the drawings. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971347 Structural M-001
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Note 2 states "THE EXIT NOZZLES ON THE SURFACE OF THE SPILLWAY WEIR ARE ONLY ACCESSIBLE WHEN
STOPLOGS ARE IN PLACE. THE GOVERNMENT THEREFORE INTENDS TO PERFORM ADDITIONAL
MAINTENANCE WORK WITH ITS OWN PERSONNEL DURING THE CONSTRUCTION CONTRACT WHILE
STOPLOGS ARE IN PLACE AT EACH GATE. SUCH WORK WILL INCLUDE BUT NOT BE LIMITED TO REMOVAL, CLEANING AND RE-INSTALLATION (OR REPLACEMENT) OF NOZZLES AT THE SURFACE OF THE SPILLWAY
AND REPLACEMENT OF VALVES AND OTHER COMPONENTS WITHIN THE SPILLWAY GALLERY. THE
CONTRACTOR SHALL ANTICIPATE SUCH WORK BY THE GOVERNMENT AND SHALL COORDINATE WITH THE COR TO ALLOW GOVERNMENT PERSONNEL ACCESS TO THESE AREAS TO ACCOMPLISH SUCH WORK. THE
CONTRACTOR SHALL ALSO ASSIST THE GOVERNMENT TO ENSURE PROPER PURGING AND TEST
OPERATION OF THE AIR BUBBLER SYSTEM ONCE THE WORK HAS BEEN PERFORMED AND THE NEW
COMPRESSOR AND ASSOCIATED SYSTEMS ARE INSTALLED AND OPERATIONAL." Please quantify how much time the government will need to be in these areas for scheduling purposes.
On: May 03 2019.
Government Response. . The Government will perform it's work concurrently with the contractor operations in these areas and separate scheduling is not required. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971352 Structural M-001
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Note 2 states "THE EXIT NOZZLES ON THE SURFACE OF THE SPILLWAY WEIR ARE ONLY ACCESSIBLE WHEN
STOPLOGS ARE IN PLACE. THE GOVERNMENT THEREFORE INTENDS TO PERFORM ADDITIONAL
MAINTENANCE WORK WITH ITS OWN PERSONNEL DURING THE CONSTRUCTION CONTRACT WHILE
STOPLOGS ARE IN PLACE AT EACH GATE. SUCH WORK WILL INCLUDE BUT NOT BE LIMITED TO REMOVAL, Page 6 of 11ProjNet: Logged In User
CLEANING AND RE-INSTALLATION (OR REPLACEMENT) OF NOZZLES AT THE SURFACE OF THE SPILLWAY
AND REPLACEMENT OF VALVES AND OTHER COMPONENTS WITHIN THE SPILLWAY GALLERY. THE
CONTRACTOR SHALL ANTICIPATE SUCH WORK BY THE GOVERNMENT AND SHALL COORDINATE WITH THE COR TO ALLOW GOVERNMENT PERSONNEL ACCESS TO THESE AREAS TO ACCOMPLISH SUCH WORK. THE
CONTRACTOR SHALL ALSO ASSIST THE GOVERNMENT TO ENSURE PROPER PURGING AND TEST
OPERATION OF THE AIR BUBBLER SYSTEM ONCE THE WORK HAS BEEN PERFORMED AND THE NEW
COMPRESSOR AND ASSOCIATED SYSTEMS ARE INSTALLED AND OPERATIONAL." Please quantify how much time the government will need the contractors assistance to purge and test operation of the bubbler system.
On: May 03 2019.
Government Response. . The Government will require approximately one (1) day assistance for purging and test operation at each tainter gate. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971358 Structural SE005 C
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please clarify the weld symbols shown in section C on drawing SE005. For the upstream guide, please confirm that the member will not be water tight as it is open on the top and bottom.
On: May 03 2019.
Government Response. . The intent for the seal weld is to limit the cement paste that enters this cavity during concrete placement. In order to allow supply the required piping in this cavity, the area can not fill with concrete during the placement. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971359 Structural SE005 C
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
For the downstream guide, please confirm that the weld is only on one side of each web plate and is not needed on the inside.
On: May 03 2019.
Government Response. . The downstream guide only requires a weld on each web plate and not on the interior. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971366 Specifications 03 30 00.00 25
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please verify that paragraph 3.12 applies only to new concrete structures constructed under this contract.
On: May 03 2019.
Government Response. . Paragraph 3.12 of this section applies only to new concrete structures constructed under this contract. However, there are other areas of concrete repair that are identified in the specifications that the contractor must consider. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971373 Specifications 03 62 16.00 25
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please verify that paragraph 3.8 applies only to new concrete structures constructed under this contract.
On: May 03 2019.
Government Response. . Paragraph 3.8 of this section applies only to new concrete structures constructed under this contract. However, there are other areas of concrete repair that are identified in the specifications that the contractor must consider. On: May 08 2019
Current Request Status: Request Closed
Page 7 of 11ProjNet: Logged In User
Information for this report is procurement sensitive.
7971379 Specifications 05 12 00.00 25
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Paragraph 1.6.1.4e requires "If a Welding Procedure is required to be qualified by test, a representative of the Government will witness the WPS qualification welding and the subsequent mechanical testing. Submit all test data results procured in the development of a PQR for engineer approval," Please verify that the government is responsible for any and all travel expenses to the various fabrication facilities
On: May 03 2019.
Government Response. . The Government will bear all travel expenses related to these testing/witness points for Federal employees. On: May 09 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971395 Specifications 09 97 03.00 25
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Paragraph 3.3.1.1 states "Apply the General Paint System to the following list of mechanical components with the color Silver/Aluminum:" Subparagraph j. states "Manufactured components prepainted with manufacture's standard paint system" Are we to repaint components that already have the manufacture's standard paint system?
On: May 03 2019.
Government Response. . Specification 09 97 03.00 25 Section 2.1.2 states that all purchased components must be coated with the General Paint System described in Part 3. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971447 Civil ED 110 ED 110
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
1. Demolition Drawings ED-102,109-118 Notes say to remove all water from existing un-used embedded conduit, grout entire length and seal on both ends. Is there a conduit schedule for existing embedded conduits with size and location?
2. The new multi-purpose storage has electric overhead doors, sheet SB001. Plans do not show any electric service to the new building. Please advise..
On: May 03 2019.
Government Response. . 1. Note on drawings ED-102,109-118 will be changed/ammended to read as follows: "...remove all water from existing un-used embedded conduit and seal on both ends." Conduits will NOT need to be grouted for the entire length but they will need to have the water removed and the ends sealed. An existing embedded conduit schedule will not be provided. Contractor should estimate costs based on removed equipment as shown on plan drawings.
2. No electric service will be provided at the new multi-purpose storage building. The electric overhead doors will be operated via a portable generator from site personnel. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971509 Contracting 52.225-11
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Suppliers are indicating that procuring the stainless steel wire ropes in accordance with the Buy America requirements will require minimum orders of 10,000LF for each size and lay with a lead time of 26-30 weeks. Can the Buy America requirements for the wire ropes be revised to require domestic assembly, but not necessarily domestic (need a word here to include their other approved countries) materials.
On: May 03 2019.
Government Response. . The preferences of the Buy American Act will apply to the awarded Contract.
There is currently no indication that the price is unreasonable in accordance with FAR 25.204 and DFAR
225.105. The Corps does not currently intend to pursue an exception for impracticability under FAR 25.202.
Page 8 of 11ProjNet: Logged In User
If an offeror is interested in submitting a pre-award determination of inapplicability of the Buy American statute under FAR 25.203 and FAR 52.225-11, we will evaluate such a request when appropriate supporting data is provided.
If an offeror chooses to submit a proposal utilizing foreign construction material, it will be evaluated under the terms of FAR 25.204 and DFAR 225.105. Submission of alternate offers is permissible under FAR 52.204(c). On: May 09 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971512 Contracting 52.225-11
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Suppliers are indicating that procuring the stainless steel wire ropes in accordance with the Buy America requirements will require minimum orders of 10,000LF for each size and lay with a lead time of 26-30 weeks. Can the Buy America requirements be modified to exclude the wire ropes from the Buy American Clause?
On: May 03 2019.
Government Response. . Please see the answer to inquiry id number 7971509. On: May 09 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971515 Structural SL-005
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will any load testing of the bulkhead lifting beam be required after modifications per the Below The Hook design requirements?
On: May 03 2019.
Government Response. . The stoplog lifting beam will not require load testing after modifications. On:
May 13 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971517 Structural M-524
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The note in the upper left corner of the page states "MODIFY THRUST SURFACE THICKNESS BY APPROVED METHOD" What methods will be approved?
On: May 03 2019.
Government Response. . The intent for the thrust surface is for the contractor to disassemble the yoke connection, inspect the thrust surface, clean and prepare it as needed in order to achieve a sound and flat surface. Methods to achieve this will vary depending on the severity of work needed. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971528 Specifications 01 30 00
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Paragraph 1.5 states "Applying for and obtaining any and all permits that are or may be required for this project is the sole responsibility, and at the expense of, the Contractor." As this is a federal project, what permits would we need to get?
On: May 03 2019.
Government Response. . The government is not aware of specific permits that are required. If, however, specific portions of the Contractor's work require permits, the Contractor will be responsible to acquire those permits. On: May 09 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971531 Specifications 01 32 01.00 10
Page 9 of 11ProjNet: Logged In User
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please Clarify the Paragraph "Early Completion" Is the contractor not allowed to propose a schedule with an early completion?
On: May 03 2019.
Government Response. . This paragraph does not prohibit a schedule with early completion. It indicates that a finish constraint should be included in the schedule corresponding to the required contract completion date and that any difference between contract completion date and early completion date will calculate as positive float. On: May 09 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971532 Specifications 01 32 01.00 10
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please Clarify the Paragraph "Early Completion" Is the contractor required to include the full jobiste overhead for the contract period regardless of how long we feel the project actually requires to complete?
On: May 03 2019.
Government Response. . The contractor is not required to include full overhead for the contract period regardless of schedule. The Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971535 Specifications 03 62 16.00 25
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The survey shall be taken from the centerline of the Tainter gate bay. Propose means and methods to verify that the survey bearing is taken from the center of the Tainter gate bay and that it is accurate within 1 second.
On: May 03 2019.
Government Response. . This is a direct copy from the specifications. No response necessary. On: May 09 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971536 Contracting SE004
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
RE: Answer to question 7956411 - The embedded side seal has a 2-1/4" Ø opening (Deatil Part 1, Sheet SE005) for this 3" pipe to pass through. Should the pipe be smaller or the opening be larger? Is the new piping to be welded, or will fittings be allowed? Please confirm that no filler material is needed in the new side seals around the new 3" pipe.
On: May 03 2019.
Government Response. . The opening should be increased to reflect the piping. Fittings would be allowed for the piping. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971539 Specifications M-001 09 97 03.00 25
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm whether machined surfaces requiring 125 Microinch surface texture shall be protected from blasting/painting to maintain the specified surface texture.
On: May 03 2019.
Government Response. . The specific surface textures are to be the final surface finish, and it is up to the contractor on how this is accomplished as long as specification 09 97 03.00 25 is adhered to. On: May 08 2019
Current Request Status: Request Closed
Page 10 of 11ProjNet: Logged In User
Information for this report is procurement sensitive.
7971543 Contracting Solitication
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Based on the significant number of questions and tight bidding timeframe please consider another extension to the bid date.
On: May 03 2019.
Government Response. . Please see question 7967588 for the answer. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971547 Contracting Solicitation
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Based on the significant number of questions will there be a time frame allowed for follow up questions?
On: May 03 2019.
Government Response. . Please see question 7969910 for the answer. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7971549 Contracting G-005
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The local vicinity map in the upper right corner of the page indicates strutures with weight restictions. From talking to the state and Juanita Township , the structures are not restricted, it is the entire length of the road. They will require a bond, an agreement with a PennDOT road contractor for repairs, and any damage done during constuction to be paid for at the contractors expense. There will be more than our traffic on this road, the contractor in worse case could have to pay sign costs to repair this road , is that what the COE intends
On: May 03 2019.
Government Response. . The roadway does have a 10 ton limit and the Contractor would be required to acquire a bond and perform repairs of any direct damage as required by regulations of PennDOT and Juniata Township. On: May 08 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
Report Complete
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Patent 11/892,984 ProjNet property of ERDC since 2004.
Page 11 of 11ProjNet: Logged In User
SPECIFICATIONS: N/A
DRAWINGS:
1) ED102, GATED SPILLWAY PLAN AND ELEVATION - ELECTRICAL REMOVAL: Delete Note 5 and replace with following text: “All existing tainter gate conduit shown as removal items must be removed from the spillway along with all pull boxes, enclosures, and panels. Embedded conduits are to remain. Remove water from all existing un-used embedded conduit and seal conduit on both ends with a urethane sealant, per specifications.”
2) ED109, WARM WATER INTAKE GATE ROOM PLAN AND ELEVATIONS - ELECTRICAL REMOVAL:
Delete Note 4 and replace with following text: “All existing warm water gate conduit and conductors must be removed from the warm water gate room.
Embedded conduits are to remain. Remove water from all existing un-used embedded conduit and seal conduit on both ends with a urethane sealant, per specifications.”
3) ED110, GATED SPILLWAY AND GALLERY LIGHTING - REMOVAL: Delete Note 2 and replace with following text: “All existing tainter gate conduit shown as removal items must be removed from the spillway along with all pull boxes, enclosures, and panels. Embedded conduits are to remain. Remove water from all existing un-used embedded conduit and seal conduit on both ends with a urethane sealant, per specifications.”
4) ED112, MAIN CONTROL AND CONDENSER ROOM LIGHTING - REMOVAL: Delete Note 2 and replace with following text: “All lighting and receptacle cabling shall be removed back to the electrical panel board DR-1. Embedded conduits are to remain. Remove water from all existing un-used embedded conduit and seal conduit on both ends with a urethane sealant, per specifications.”
5) ED114, ACCESS TOWER LIGHTING - REMOVAL: Delete Note 2 and replace with following text: “All lighting and receptacle cabling must be removed back to the electrical panel board DR-2. Embedded conduits are to remain. Remove water from all existing un-used embedded conduit and seal conduit on both ends with a urethane sealant, per specifications.”
6) ED115, ACCESS TOWER LIGHTING - REMOVAL: Delete Note 2 and replace with following text: “All lighting and receptacle cabling must be removed back to the electrical panel board DR-3. Embedded conduits are to remain. Remove water from all existing un-used embedded conduit and seal conduit on both ends with a urethane sealant, per specifications.”
7) ED118, WARM WATER INTAKE GATE ROOM LIGHTING REMOVAL - PLAN AND ELEVATIONS:
Delete Note 2 and replace with following text: “All lighting and receptacle cabling must be removed back to the electrical panel board DR-1. Embedded conduits are to remain. Remove water from all existing un-used embedded conduit and seal conduit on both ends with a urethane sealant, per
8) ED510, TAINTER GATE CONTROL PANEL (TGCP) - PANEL LAYOUT REMOVAL: Delete Note
2 and replace with following text: “The existing tainter gate control panel (TGCP) must be removed in its entirety. Embedded conduits are to remain.
Remove water from all existing un-used embedded conduit and seal conduit on both ends with a urethane sealant, per specifications.”
9) ED530, DECK WASHING PUMP MOTOR STARTER CABINET (DWPC) - PANEL LAYOUT
REMOVAL: Delete Note 2 and replace with following text: “The existing deck washing pump panel must not be removed. The back panel of the enclosure must be removed and replaced with new equipment. All associated cabling and conduit must be removed back to its originating equipment. Embedded conduits are to remain. Remove water from all existing un-used embedded conduit and seal conduit on both ends with a urethane sealant, per specifications.”
10) ED580, AIR COMPRESSOR CONTROL PANEL (ACCP) - PANEL LAYOUT REMOVAL: Delete
Note 2 and replace with following text: “The existing air compressor control panel must be removed in its entirety. All associated power and control cabling and conduit must be removed back to its originating equipment.
Embedded conduits are to remain. Remove water from all existing un-used
11) ED590, MAIN CONTROL CONTROL CABINET (MCCP) - REMOVAL DETAILS: Delete Note 2 and replace with following text: “The existing MCCP must be removed in its entirety. All associated power and control cabling and conduit must be removed back to its originating equipment unless otherwise indicated.
Embedded conduits are to remain. Remove water from all existing un-used
APPENDICES:
N/A
GENERAL:
SPECIFICATIONS:
1) Section 13 34 19.00 25, Part 1.5.1: Change the last paragraph in part
1.5.1 from “The Army Corp of Engineer's Road shall be repaired to the pre-existing condition prior to the demolition and construction of the storage building. All site work shall connect existing grades to the new grades supplied by Multi-Purpose Storage Building and it's concrete slabs.” to “The Army Corp of Engineer's Road shall be repaired to the pre-existing condition after both the demolition and construction of the storage building. All site work shall connect existing grades to the new grades supplied by Multi-Purpose Storage Building and its concrete slabs.”
DRAWINGS:
APPENDICES:
N/A
GENERAL:
N/A
ATTACHMENTS:
1) Section 35 20 16.48 25, Title: Change “SPILLWAY & WARM WATER INTAKE GATE
WIRE ROPE FABRICATION AND INSTALLATION” to “SPILLWAY, WARM WATER INTAKE GATE, AND SPILLWAY STOPLOG LIFTING BEAM WIRE ROPE FABRICATION AND INSTALLATION”
2) Section 35 20 16.48 25, Part 1.1, First paragraph: Replace the first paragraph with “This Section covers the procurement, testing, and installation of the hoist wire ropes and associated components for the Raystown Dam spillway gates, warm water intake gates, and spillway stoplog lifting beam.”
3) Section 35 20 16.48 25, Part 1.1: Immediately after the last paragraph, add the following paragraph:
“The spillway stoplog lifting beam at Raystown Dam is connected to a wire rope sling which in turn is connected to a crane for hoisting. Remove the existing wire rope sling, shackles, and master link as shown in the Contract drawings.
Procure, test, and prepare new wire ropes, thimbles, shackles, and master link for attachment to the lifting beam to be installed as shown in the Contract drawings.”
4) Section 35 20 16.48 25, Part 1.3, Subpart SD-01: Immediately after the paragraph “Warm Water Intake Gate Wire Rope Fabrication Plan: G, AO” add the following paragraph:
“Spillway Stoplog Lifting Beam Wire Rope Fabrication Plan; G, AO”
5) Section 35 20 16.48 25, Part 1.3, Subpart SD-06: Immediately after the paragraph “Warm Water Intake Gate Wire Rope Tensile Strength Report: G, DO” add the following paragraph:
“Spillway Stoplog Lifting Beam Wire Rope Tensile Strength Report; G, DO”
6) Section 35 20 16.48 25, Part 2.2: Immediately after Subpart 2.2.2 add the following Subpart:
“2.2.3 Spillway Stoplog Lifting Beam Wire Rope
Provide a total of two wire ropes per lifting beam sling for installation and one test piece of wire rope for tensile testing. Wire rope must be 1.5-inch diameter, 6x37 IWRC, corrosion resistant steel rope conforming to the requirements of FS RR-W-410. The wire ropes must be pre-formed, pre-stretched, and must all be from the same factory run including test pieces. The wire rope must be manufactured with thimbles as per Contract drawings. Submit a Spillway Stoplog Lifting Beam Wire Rope Fabrication Plan which must include certifications verifying rope type, pre-stretching procedure, thimble, shackle, and master link product data, and methods of installing new thimbles on wire rope and new thimbles on new master link.”
DRAWINGS:
N/A
APPENDICES:
N/A
GENERAL:
ATTACHMENTS:
RMSRT451
LTERM: DEYERTY
ROADWAY MANAGEMENT INFORMATION SYSTEM 05/10/2019 10:23:40
PAVEMENT HISTORY
SEGMENT OFFSET -------LANES-------/- NOTES: NO
COUNTY NO/NAME SR NO. LENG FROM TO THRU PARK TURN BIKE/--RANGE TO---
-------------------------------------------------------------/SEGMNT: N.A.
31 HUNTINGDON 3043 0080 2122 0000 1903 02 N N N /OFFSET: N.A.
s
E
L NO TYPE CODE
01 NS NSTRl
02 BW SPWL3
03 WB SPBBl
04 BW ID2U0
05 BW FBlU0
06 WB CABC0
07 NS NSTR3
08 SB NSB00
-----LAYER DESCRIPTION------ YEAR
SURFACE TREATMENT- SEAL COAT 2015
SPAV,HMA WRG,64-22, 9.5MM,L 2004
SPAV,HMA BASE,64-22,25 MM 2004
BITUMINOUS WEARING CRSE ID-2 1978
BITUMINOUS WEARING CRSE FB-1 1967
CRUSHED AGGREGATE BASE CRSE 1967
SURF TREAT- DOUBLE SEAL COAT 1933
NATIVE STONE (GRANULAR) SUBB 1933
I SURF .. : 52
DEPTH WIDTH/ TRTMT.: L
(IN) (FT) I SN .... : 1 . 9
+1.50
+3.00
+l.00
+2.50
+8.00
+1.00
+6.00
/VERIFICATION INFO
I DATE:
01 /24 /2012
VER IND: VC
VER ID.: GEZAMAN
--- MAXIMUM --
AADT .. : 1,120
TRK %.: 09
ESAL .. : 000047
IRI. .. : NO TEST
TOTAL +12.00 PAVED +5.00
ACTION: I A B D E F G H I J K N P Q R S U UO V X Y
MESSAGES: 3 10 NO DATA FOUND FOR FORWARD BROWSE REQUEST
ATTACHMENT 1
1) Delete Section 01 14 00, Paragraph 1.2.7 as originally issued and replace with:
1.2.7 Roads and Bridges on Route to the Dam
The Contractor shall note that there are two small bridges (10 ton load restriction) between Route 22 and the Dam. The Contractor is responsible to obtain all necessary permits for travel over the bridges and for any associated requirements (ex. bracing) that may be required. The roads to the dam from Route 22 have a 10 ton load restriction. The Contractor is responsible to obtain permits for the roads, post bonds and follow all associated requirements in accordance with PennDOT and Juniata Township regulations. Historical information on the composition of portions of State Route 3043 and 3045 are included in Attachment 1 as background information. This does not include any historic information on the Juniata Township portion of the access route.
XX
| I.B.08.02 - Amendment 03 Instruction to Proposers 5.14.2019 |
| I.B.08.02 - Projnet Questions and Answers 5.13.2019 |
| I.B.08.02 - Amendment 03 Drawings 7971447 |
| I.B.08.02 - Amendment 03 Specification 7947040 |
| I.B.08.02 - Amendment 03 Specification 7971515 |
| I.B.08.02 - Amendment 03 Specification 7971528 PERMIT Attachment A |
| image2019-05-10-103407 |
| image2019-05-10-103826 |
| I.B.08.02 - Amendment 03 Specification 7971528 PERMITS |