B.08.03.02__AMEND_0001_TO_RFQ_EXTEND;REVISE_EVAL;_RFI.pdf

PDF 172 KB Posted

Attached to
WIRE ROPE, 10 ROLLS OF 500'
Solicitation number
W912DR19Q0096
Issued by

About this file

AMENDMENT 0001 TO SOLICITATION (RFQ)

View the file

Other files

File Type Posted
B.08.02_FILE_COPY_OF_BASIC_RFQ_WIRE_ROPE.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to: 1) answ er requests for information; 2) revise the evaluation; and 3) extend the closing date of the solicitation per the enclosed summary of changes.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Aug-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR19Q0096

X 9B. DATED (SEE ITEM 11)

13-Aug-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Aug-2019

CODE

U.S. ARMY CORPS OF ENGINEERS, BALTIMORE

2 HOPKINS PLAZA

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR19Q0096

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 27-Aug-2019 10:00 AM to 29-Aug-2019 10:00 AM.

The following have been added by full text:

REQUESTS FOR INFORMATION (RFI)

QUESTION 1: Could you please offer the last awarded price for our reference?

ANSWER 1: We have not procured this type of wire rope in the past (galvanized). Previous purchases were for carbon steel wire.

QUESTION 2: Could you please check the Warrington Seale Class, it is 6 x 37 ?

ANSWER 2: Yes

The following have been modified:

EVALUATION

EVALUATION AND BASIS OF AWARD REVISED 08-23-2019

1. Technical

Contractor to submit a narrative not to exceed one page detailing the contractor’s understanding of the requirement. No pricing information shall be included in the narrative.

RATING

ACCEPTABLE The contractor understands the requirement and the Government has a reasonable expectation that the contractor can provide the supplies IAW the Statement of Objective.

UNACCEPTABLE The contractor does not understand the requirement and the Government does not have a reasonable expectation that the contractor can provide the supplies IAW the Statement of Objective.

The Government will evaluate the contractor’s technical submission. An acceptable rating will be eligible for award. An unacceptable rating will be ineligible for award.

2. Price

All item(s) must be priced. Quotes providing partial pricing may be considered non-responsive and ineligible for award. Price will be evaluated in accordance with FAR 13.106-2. The government may require additional pricing information to assist in determining the extent to which the price is fair and reasonable and the pricing information shall be provided if requested.

W912DR19Q0096

BASIS FOR AWARD

Award based lowest price, technically acceptable. To qualify, the responsible contractor provides a quote which conforms to the solicitation, is technically acceptable, and submits the lowest price.

(End of Summary of Changes)