COMMUNITY INVOLVEMENT
DRAFT
MANAGEMENT ACTION PLAN
FOR
DEFENSE SUPPLY CENTER RICHMOND
RICHMOND, VIRGINIA
Prepared For
Defense Logistics Agency
And
Defense Supply Center Richmond
July 2018
DRAFT
MANAGEMENT ACTION PLAN
FOR
DEFENSE SUPPLY CENTER RICHMOND
RICHMOND, VIRGINIA
Prepared for:
And
Prepared by:
Arcadis W912DR-13-D-0019, Delivery Order 0005
July 2018
PURPOSE
In an effort to coordinate planning information among Installation Restoration Program (IRP) managers, Department of Defense (DoD) Commands, the installation, executing agencies, and the public, this Management Action Plan (MAP) has been updated for (calendar year) 2018 for the Defense Supply Center Richmond. The purpose of the MAP is to outline the multi-year restoration program for the installation. The MAP defines the IRP requirements and proposes a comprehensive approach to conduct future investigations and remedial actions at each Operable Unit (OU) at the installation. The MAP is used to track requirements, progress towards cleanup objectives, and schedules. Under the current project schedule and projected funding, all OUs at the installation are expected to attain Remedy in Place (RIP) status by the end of FY 2021. This time frame will allow additional treatment of off-site areas at OUs 6 and 7, if needed, and to mitigate OU 8 plume off-site migration considering the complexities associated with the hydrogeologic regime at OU 8.
Defense Supply Center Richmond – Management Action Plan Contributors to the MAP – Page 4 REVIEWed by
ACRONYMS AND ABBREVIATIONS
| ANP | Acid Neutralization Pit |
| CAP | Corrective Action Plan |
| COR | Contracting Officer Representative |
| CSM | Conceptual Site Model |
| CVOC | Chlorinated Volatile Organic Compound |
| DDD | Dichlorodiphenyldichloroethane |
| DDE | Dichlorodiphenyldichloroethylene |
| DDT | Dichlorodiphenyltrichloroethane |
| DES | DLA Environmental & Safety Directorate |
| DGSC | Defense General Supply Center |
| DLA | Defense Logistics Agency |
| DoD | Department of Defense |
| DPE | Dual Phase Extraction |
| DSERTS | Defense Site Environmental Restoration Tracking System |
| EBS | Environmental Baseline Survey |
| ER | Environmental Restoration |
| ESD | Explanation of Significant Differences |
| ESI | Expanded Site Investigation |
| EVO | emulsified vegetable oil |
| FFA | Federal Facilities Agreement |
| FFS | Focused Feasibility Study |
| FS | Feasibility Study |
| FTA | Fire Training Area |
| FY | Fiscal Year |
| HHRA | Human Health Risk Assessment |
| IRA | Interim Remedial Action |
| IRP | Installation Restoration Program |
| LTM | Long Term Monitoring |
| LUC | Land Use Control |
| MAP | Management Action Plan |
| MNA | Monitored Natural Attenuation |
| NOV | Notice of Violation |
| NGA | National Guard Area |
| NPL | National Priorities List |
| OSA | Open Storage Area |
| OU | Operable Unit |
| PA | Preliminary Assessment |
| PAH | Polycyclic Aromatic Hydrocarbon |
| PCB | Polychlorinated Biphenyl |
| PCE | Tetrachloroethene |
| PX | Post Exchange |
| RA | Remedial Action |
| RA-C | Remedial Action - Construction |
| RA-O | Remedial Action – Operation |
| RAB | Restoration Advisory Board |
ACRONYMS AND ABBREVIATIONS (contd)
| RBC | Risk Based Concentration |
| RC | Response Complete |
| RD | Remedial Design |
| REM | Removal Action |
| RI | Remedial Investigation |
| RIP | Remedy in Place |
| ROD | Record of Decision |
| RRSE | Relative Risk Site Evaluation |
| SC | Site Closure |
| SI | Site Investigation |
| SLERA | Screening Level Ecological Risk Assessment |
| SVE | Soil Vapor Extraction |
| SVOC | Semivolatile Organic Compound |
| TCA | Trichloroethane |
| TCE | Trichloroethene |
| TRC | Technical Review Committee |
| TS | Transitory Shelter |
| USACE | United States Army Corps of Engineers |
| USAEHA | United States Army Environmental Hygiene Agency |
| USEPA | United States Environmental Protection Agency |
| UST | Underground Storage Tank |
| VDEQ | Virginia Department of Environmental Quality |
| VOC | Volatile Organic Compound |
| WBU | Water Bearing Unit |
Defense Supply Center Richmond – Management Action Plan Acronyms and Abbreviations – Page 6 summary Placed on National Priorities List (NPL) - July 1987 32 DSERTS (Defense Site Environmental Restoration Tracking System) Sites
Defense Supply Center Richmond – Management Action Plan Summary – Page 7
ACTIVE DSERTS SITES -
OUs AND SITE TYPES:
| 14 active DSERTS sites (Environmental Restoration [ER] Eligible) |
| OU1 – Open Storage Area | OU 2 – Former Landfill |
| OU 5 – Acid Neutralization Pit (ANP) Area | OU 13 – Spill Area |
| Post Exchange (PX) – Gasoline Filling Station | OUs 6, 7, 8 – Groundwater Sites |
OUs 10, 11, 12 – Former Chemical Storage Buildings OU 9 – Interim Groundwater Treatment System OU 4 – Unlined chemical dumping area/fire training area OU 3 – Vehicle Maintenance Area 18 inactive DSERTS sites
| CONSTITUENTS: |
| Chlorinated volatile organic compounds (CVOCs), petroleum hydrocarbons, polycyclic aromatic hydrocarbons (PAHs), pesticides, metals |
| AFFECTED MEDIA: |
| Groundwater, soil, and sediment |
| COMPLETED RECORD OF DECISION (ROD): |
| 13 RODs completed at ER Eligible Sites (OUs 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12 |
and 13)
| COMPLETED IRA/REM/RA: |
| · Interim Remedial Action (IRA) |
· Groundwater pump and treat system at OU 9
· Removal Action (REM)
· Soil excavation at OU 3
· Soil excavation at OU 4
· Soil excavation at OU 13
· Remedial Action (RA)
· Soil cover at OU 2
· Concrete cover and soil vapor extraction (SVE) at OU 5
· Vegetative covers at OU 10 and OU 11
· Asphalt cover at OU 12
· Low permeability soil backfill at OU 13
· Groundwater extraction and treatment for PX Gas Station
| CURRENT DSERTS PHASES: |
| · Remedial Action (RA) ongoing at groundwater OUs 6, 7 and 8 |
· Long-term monitoring (LTM) for soil OUs 1, 2, 3, 4, 5, 10, 11, 12, 13 and the PX Gasoline Station. Note land use controls (LUCs) for soil OUs 4 and 5 are included under OUs 7 and 8, respectively.
| PROJECTED DSERTS PHASES: |
| · RA expected at OU 8 |
· LTM for all OUs
| FUNDING: |
| · Need funding for RA at groundwater OUs 6, 7, and 8 |
| DURATION: |
| Year of IRP Inception: 1981 Estimated year of IRP Completion: 2046 |
Final Deletion from the NPL: 2043 (All OUs). Deletion of specific OUs is anticipated prior to 2043.
INSTALLATION INFORMATION
LOCALE
Defense Supply Center Richmond (the installation) is located approximately 8 miles south of the city of Richmond, Virginia, along Jefferson Davis Highway. The installation consists of over 600 acres, approximately 1 mile wide (east to west) and 2 miles long (north to south). The property is roughly L-shaped, and the southeastern section currently consists of primarily administrative, operations, maintenance, housing, daycare facilities, and recreational areas (see Figure 1). The remaining areas include warehouses, open storage, and light industrial facilities. The installation’s current workforce is over 2,000 employees. The area surrounding the installation is primarily residential and woodland with a lesser proportion of commercial/light industrial property.
COMMAND ORGANIZATION
| Headquarters: | Defense Logistics Agency (DLA) Headquarters, Installation Operations Richmond, Environmental Management Division |
| Installation: | DLA Installation Support at Richmond |
IRP EXECUTING AGENCY
· Investigation, Remedial Design and Remedial Action Phases Executing Agency: United States Army Corp of Engineers (Baltimore District)
REGULATORY PARTICIPATION
| FEDERAL: | U.S. Environmental Protection Agency (USEPA), Region 3 |
| STATE: | Virginia Department of Environmental Quality (VDEQ), Division of Waste Operations |
REGULATORY STATUS
· NPL Installation – 1987
· Federal Facilities Agreement (FFA) – 1990
Defense Supply Center Richmond – Management Action Plan Installation Information and Description – Page 12
INSTALLATION DESCRIPTION
Defense Supply Center Richmond is the home to DLA Aviation which supports more than 1,340 weapon systems as the U.S. military's integrated material manager for more than 1.2 million national stock number items, industrial retail supply and depot-level repairable acquisitions. In addition, DLA Aviation manages supply, storage and distribution operations alongside its military customers at Robins Air Force Base, GA; Tinker Air Force Base, OK; Hill Air Force Base, UT; Marine Corps Air Station Cherry Point, NC; Naval Air Station North Island, CA; and Naval Air Station Jacksonville, FL. DLA Aviation also manages depot-level reparable procurement operations at Robins, Tinker and Hill Air Force Bases; Navy Inventory Control Point Philadelphia; and Redstone Army Arsenal in Huntsville, AL. The aviation supply chain has personnel at over a dozen stateside sites directly supporting the warfighters. DLA Aviation also operates the federal government's only industrial plant equipment facility at Navy Inventory Control Point, Mechanicsburg, PA.
The United States government purchased the land from private owners in 1941, and construction activities began in September of that year. The installation was activated as the Richmond Quartermaster Depot on 1 January 1942, after the United States government purchased the land from private land owners in 1941. In 1943, the installation became the Richmond Armed Service Forces Depot. The Quartermaster Branch Depot was established on-site in 1949, followed by the U.S. Army General Supply Center in 1958. DLA began overseeing operations in 1962, when the installation became known as the Defense General Supply Center (DGSC). In 1996, the installation was renamed the Defense Supply Center Richmond.
Past operations at the installation have encompassed a variety of industrial operations including the following: tent, refrigerator, and parachute repair; military vehicle and equipment overhauling; automotive engine repair and rebuilding; sanitary and industrial waste treatment and disposal; helmet refurbishing; gas cylinder refurbishing and replenishing; firefighter training; and hazardous chemical storage, recoupment, and shipping.
Current missions at the installation include the following:
· Managing, controlling, storing, and distributing general military, administrative, and other supplies worldwide for DLA
· Storing industrial chemicals with no recoupment activities involved as damaged containers, if any are shipped for disposal
· Refurbishing and refilling chemical gas cylinders
· Storing and supplying operational and maintenance parts for military aircraft
· Disposing of excess inventory
· Maintaining and storing military and government vehicles
· Storing and distributing maps to DoD installations and other government agencies worldwide
· Providing professional development and training opportunities for Government supply and inventory specialists
· Maintaining the U.S. Army’s National Technical Information System for hazardous substances
· DLA Distribution Mapping - responsible for inventory and worldwide physical distribution of all maps, charts and other geodetic material for DoD, storing 85,000 map items for its military customers worldwide
INSTALLATION DESCRIPTION
DSERTS Site Descriptions and Status
| DSERTS Number | Site Description | Active |
| 002 | Transitory Shelter (TS) 202 (OU 11) | Yes |
| 004 | Malathion Contamination (Part of OU 1) | No |
| 006 | Building 68 – Polychlorinated Biphenyl (PCB) Storage (OU 10) | Yes |
| 008 | Recoupment Area (Part of OU 1) | No |
| 009 | Area 50 Landfill (OU 2) | Yes |
| 010 | Dichlorodiphenyltrichloroethane (DDT) Storage (Warehouse 9) | No |
| 011 | Asbestos Storage (Warehouse 4) | No |
| 012 | Mercury Storage (Warehouse 9) | No |
| 013 | Pesticide Storage (Roads and Grounds) | No |
| 014 | Pesticide Storage and Mixing Facility (OU 12) | Yes |
| 015 | Rubble Disposal Area | No |
| 017 | Former Fire Training Pit Soils (OU 4) | Yes |
| 018 | Waste Oil Underground Storage Tank (UST) – Mechanical, Heating | |
| and Electrical shop (CAP 2) | No |
| 019 | Waste Oil UST – Automotive Shop | No |
| 020 | Aluminum Phosphide Ash Burial Area | No |
| 021 | Sludge from Sewage Treatment Plant | No |
| 022 | PCB Storage | No |
| 023 | Pistol Range | No |
| 024 | Paint Residue Area (Paint Shed) | No |
| 025 | Calcium Hypochlorite Fire – 1977 | No |
| 026 | USTS-National Guard Area (Part of OU 3) | No |
| 027 | ANP Soils (OU 5) | Yes |
| 028 | Open Storage Area Soils (OU 1) | Yes |
| 029 | Parker Pond – Expanded Site Investigation (ESI) 2 | No |
| 030 | Fuel Storage Area (Part of OU 4) | No |
| 031 | National Guard Area Soils (OU 3) | Yes |
| 032 | Former Fire Training Area (FTA) Groundwater (OU 7) | Yes |
| 033 | PX Gas Station (CAP 1) | Yes |
| 034 | Area 50 Groundwater (OUs 6 and 9) | Yes |
| 036 | ANP Groundwater (OU 8) | Yes |
| 037 | PAH Area (OU 13) | Yes |
| 038 | Tank Farm (CAP 3) | No |
Note: Numbers 001, 003, 005, 007, 016, and 035 were not used.
PROJECT TEAM
| Defense Supply Center Richmond – Management Action Plan |
| Project Team – Page 13 |
PROJECT TEAM
ROLES AND RESPONSIBILITIES
· DLA – Lead agency for remedial actions at Defense Supply Center Richmond; resource advocate; policy development; provides consultative support; decision validation and approval.
· DLA Installation Support at Richmond – Directs the installation’s daily restoration program execution (ensure costs/performance/ schedule are on target).
· USACE Baltimore District Service Center – Provide contracts for contractors and review contractor performance.
· Program Manager
· Manages budget/schedule/quality of deliverables produced by contractors.
· Provides timely funds obligation and contract execution and oversees costs/performance/ schedule as the Program Manager.
· VDEQ – Supporting regulatory agency for remedial actions at the installation.
· USEPA – Lead regulatory agency for remedial actions at the installation.
· ARCADIS
· Performs on-time, cost-effective consulting services for restoration activities.
· Meets DLA’s completion strategy for technically defensible site restoration.
Defense Supply Center Richmond – Management Action Plan Project Team – Page 14
INSTALLATION ASSESSMENT
Past industrial operations at the installation have resulted in the use, storage, management, inadvertent release, and/or disposal of hazardous materials, such as chlorinated solvents, petroleum products, and wastewater treatment sludge. Past storage operations at the installation have led to the accidental release of these and other hazardous materials, such as PAHs, pesticides, petroleum hydrocarbons, PCBs, and metals.
An initial assessment was completed in August 1981 that indicated potential soil impacts at six OUs and possible groundwater impacts at three OUs. During 1982, the U.S. Army Environmental Hygiene Agency (USAEHA) investigated the hydrogeologic setting, identified two areas of significant groundwater impacts associated with the Area 50 landfill and the former FTA, and installed monitoring wells in the vicinity of the most impacted areas. Elevated groundwater concentrations of CVOCs such as trichloroethene (TCE), tetrachloroethene (PCE), and chlorobenzenes were detected and compared to VDEQ Groundwater Quality Standards. A third possible source of groundwater impacts was determined to be the National Guard Area (NGA). Subsequent investigations showed CVOC constituents in both the upper and lower water bearing units (WBUs) east of Area 50, extending to and beyond the eastern boundary of the installation.
Initial testing of residential water wells near the installation was performed between 1982 and 1984. In 1984, chloroform was detected, but the concentration was well below the USEPA limit for drinking water. Trace amounts of 1,1,1-trichloroethane (TCA) and 1,1-dichloroethane were also detected. Monitoring wells were installed off-installation to the east of NGA. Off-installation wells were analyzed, along with the associated NGA and Area 50 monitoring wells, during subsequent investigations of the hydrogeology and the extent of potential groundwater impacts between 1985 and 1987.
Based on the results of these investigations, the installation was officially placed on the NPL in 1987 with a Hazard Ranking System score of 33.85 due to CVOCs in on-site groundwater, potential off-site migration of CVOC-contaminated groundwater, and groundwater discharge into surface water. In 1990, USEPA, VDEQ, and DGSC (now Defense Supply Center Richmond) entered into an FFA to continue monitoring the installation and to develop and implement remedial action plans. Thirteen OUs were ultimately defined for the IRP.
An RI was initiated in 1986 to characterize the nature and extent of CVOCs in soil at four OUs:
· Open Storage Area (OSA) – OU 1
· Area 50 Landfill – OU 2
· NGA – OU 3
· Former FTA – OU 4 The acid neutralization pits (ANPs – OU 5) were investigated as a possible CVOC source area.
The groundwater plumes associated with soil impacts were considered separately from the soil OUs:
· OSA/Area 50/NGA groundwater – OU 6
· Former FTA groundwater – OU 7
· ANP groundwater – OU 8 An installation-wide pesticide monitoring study completed in 1986 by USAEHA identified three additional possible areas of concern:
· Former Building 68 – OU 10
· Former Building 202 – OU 11
· Former Building 112 – OU 12 These areas were identified due to the various pesticide residues (i.e., DDT, chlordane, heptachlor, arsenic) discovered in the surface soils and storm drain sediments. In 1992, an area of PAH impacts was encountered near the FTA, which was associated with a past fuel oil release from an aboveground storage tank. This area was designated as OU 13. An IRA for OU 6, consisting of a groundwater extraction, CVOC treatment, and discharge system, began operating in 1996. This area was designated as OU 9.
In 2000, the installation began integrating RIs and Focused Feasibility Studies (FFSs) for source and groundwater OUs. RI/FFSs were conducted as part of a comprehensive, installation-wide completion strategy recognizing the interdependence of soil and groundwater impacts. This strategy involves removing or treating continuing sources of impacts, controlling migration in the environment, and limiting exposure to impacts that pose unacceptable human health or ecological risk through institutional or engineered controls. Response decisions made under this completion strategy are results-focused, with clearly defined performance expectations. DLA strives to effectively and efficiently meet its response action obligations under the Comprehensive Environmental Response Compensation and Liability Act.
Implementation of this completion strategy required an update of the installation’s Conceptual Site Model (CSM). Completed in 2006, the CSM summarizes relevant information on the nature, extent, and migration of constituents in soil and groundwater; provides a framework for cleanup programs; and serves as a foundation for risk assessments. Data gaps for the updated CSM were addressed in a supplemental FS investigation between August 2003 and April 2004. HHBRAs for each OU were subsequently revised using updated risk assessment guidance and industrial land use scenarios.
Three creeks near the installation property (Kingsland Creek, No Name Creek, and an unnamed tributary of Falling Creek) were evaluated to determine the potential impact from past on-site activities. Between 2001 and 2004, a creek monitoring study determined there were no significant impacts on habitat quality for aquatic organisms in the monitored creeks. HHBRAs were also performed on the creeks, and unacceptable cancer risk was determined for residential recreational users (waders) in each creek. However, the estimated risk was driven by infrequently detected constituents in groundwater and conservative exposure scenarios. Therefore, no further action was recommended to protect human health from potential installation impacts to the creeks.
Since the completion of the CSM, considerable progress has been achieved at the installation’s DSERTS sites. Records of Decision have been completed for OUs 2 (2008), 6 (2013), 7 (2012), 8 (2007), 10 (2007), 11 (2007), 12 (2005) and 13 (2011) and remedial action completion status has been achieved for OUs 2, 10, 11, 12 and 13. In addition, the interim remedial action (OU 9) has been decommissioned. As part of the feasibility studies at OU 6 and 7, low-cost passive groundwater treatment treatability studies were implemented in 2007. An in situ bioremediation treatability study at OU 8 was implemented in 2010 prior to full-scale application in 2013 and 2014. Full scale application was completed at OU 7 in 2013 and at OU 6 in 2015, and pressurized and gravity fed EVO injections took place at OU 6 in July 2015. These studies have shown favorable results for the treatment of the groundwater contamination at these OUs. Remedial action activities are ongoing at OUs 6, 7, and 8. In 2015, direct-push technologies were utilized to investigate the north-eastern edge of the OU 8 plume extending towards Bensley Elementary School. DLA initiated a long term pump test along the northern lobe of the OU 8 plume in 2015 and a long term pump test well int the southern lobe of the OU 8 plume in 2016. A targeted groundwater extraction and recirculation system for OU 8 was implemented successfully in 2017 to enhance biodegradation of the dissolved-phase plume beneath portions of OU-5 and Bay F of Warehouse 65 which are source areas of the OU 8 plume. Twelve new injection wells were installed in October 2017 for OU 7 in the intermediate zone followed by USACE completing an ISB injection of Lactoil (or equivalent) a blended carbon donor consisting of 35% EVO and 35% sodium lactate into 31 injection wells (12 new and 19 existing wells) from November 2017 to January 2018. Additional remedial action activities are planned for August 2018 for OU 8.
As a result of the building 65 sub-slab-depressurization system effectiveness study, modification activities to enhance the systems impact were made to Bldg 65 SSDS in 2016 to address ROI issues of the system. Additional SSDS optimization activities were completed in June 2018 to address operational deficiencies.
LUCs have been implemented at OUs 1, 2, 3, 6, 7, 8, 10, 11, 12, 13 and the PX Gas Station. These LUCs are documented in the LUC RD (AECOM, 2015). Annual inspections are conducted to verify that the LUCs are being implemented as proposed. Any deficiencies noted during the annual inspections are rectified. LUCs for OUs 4 and 5 are incorporated in the OUs 7 and 8 LUCs, respectively.
All open DSERTS sites listed under the Defense Supply Center Richmond IRP are eligible for funding. Sites that pose the greatest risk to public health (based on the Relative Risk Site Evaluation [RRSE]) are generally given priority in funding allocations. The RRSE is a qualitative tool used to group sites into low, medium, and high-risk categories based on site information and the contaminant hazard factor, the migration pathway factor, and the receptor factor. These sites are organized in the Site Descriptions section of the MAP by their DSERTS identification number but are primarily described by their OU number (1-13) or common name (PX Gas Station). RRSEs are not required at DSERTS sites classified as RIP or Response Complete (RC).
Defense Supply Center Richmond – Management Action Plan Installation Assessment – Page 17
| Aug 81 |
| Installation Assessment Report |
| US Army Toxic and Hazardous Materials Agency |
| Mar 82 |
| Geohydrologic Study No. 38-26-0164-82 |
| US Army Environmental Hygiene Agency |
| Nov 82 |
| Phase II, Geohydrologic Study No. 38-26-0164-83 |
| US Army Environmental Hygiene Agency |
| Nov 83 |
| Final Geohydrologic Study No. 38-26-0164-84 |
| US Army Environmental Hygiene Agency |
| Jul 84 |
| Phase I, Final Contamination Assessment Report, OU 2, OU 6 |
| Dames & Moore |
| Sep 84 |
| Groundwater Contamination Progress Report |
| US Geological Survey |
| Dec 84 |
| On Post Quarterly Well Testing, Mar 94-Dec 94, OU 2, OU 6 |
| US Geological Survey |
| Jan 85 |
| Groundwater Contamination Progress Report, Oct 84-Dec 84, OU 6 |
| US Geological Survey |
| Apr 85 |
| Groundwater Contamination Progress Report, Jan 85-Mar 85, OU 6 |
| US Geological Survey |
| Jun 85 |
| Groundwater Contamination Progress Report, Apr 85-Jun 85, OU 6 |
| US Geological Survey |
| Oct 85 |
| Groundwater Contamination Progress Report, Jul 85-Sep 85, OU 6 |
| US Geological Survey |
| Nov 85 |
| Phase II, Final Contamination Assessment Report |
| Dames & Moore |
| Sep 86 |
| Pesticide Monitoring Study, Evaluation of Pesticide Residue Associated with Pest Control Operations |
| US Army Environmental Hygiene Agency |
| Jan 87 |
| Phase II, Groundwater Contamination Administrative Report |
| US Geological Survey |
| Oct 87 |
| Soil Gas Survey Report, OU 5 |
| Target Environmental Services |
| Oct 88 |
| Phase II, Soil Gas Survey Report, OU 3 |
| Target Environmental Services |
| Apr 89 |
| RI, Final Report, OU 5, OU 8 |
| Dames & Moore |
| May 89 |
| RI, Report, OU 4, OU 7 |
| Dames & Moore |
| Nov 89 |
| Soil Gas Survey Report, OU 1 |
| Target Environmental Services |
| Nov 90 |
| FFA, Investigation and Response of Past and Present Environmental Impacts |
| Defense Logistics Agency, Virginia Department of Waste Management, DGSC-WI, EPA Region 3 |
| Jul 91 |
| Technical Memorandum Report, Interim Groundwater Sampling Results, United States Geological Survey Off-Post Wells, Rayon Park |
| CH2M Hill |
| Sep 91 |
| Proposed Preliminary ARAR Report, OU 4 |
| LAW Environmental, Inc. |
| Oct 91 |
| FFS, Final Report, OU 1 |
| LAW Environmental, Inc. |
| Oct 91 |
| FFS, Final Report, OU 5 |
| LAW Environmental, Inc. |
| Jan 92 |
| Final Proposed Plan, OU 5 |
| LAW Environmental, Inc. |
| Jan 92 |
| Final Proposed Plan, OU 1 |
| LAW Environmental, Inc. |
| Mar 92 |
| ROD, OU 5 |
| LAW Environmental, Inc. |
| Apr 92 |
| ROD, Final, OU 1 |
| LAW Environmental, Inc. |
| Dec 92 |
| RD, Pilot Study for Vacuum Extraction System Work Plan, OU 5 |
| Engineering-Science, Inc. |
| Apr 93 |
| FFS, Draft Report, OU 6 |
| LAW Environmental, Inc. |
| Apr 93 |
| RD, 100% Design Submittal Report, OU 5 (Volume I & Volume 2) |
| Engineering-Science, Inc. |
| Sep 93 |
| ROD, IRA, OU 9 |
| LAW Environmental, Inc. |
| Feb 94 |
| RI, Final Field Investigation Report, OU 7 |
| Engineering-Science, Inc. |
| Jun 94 |
| ESI, Final Report, OU 12 |
| LAW Environmental, Inc. |
| Jun 94 |
| ESI, Final Report, OU 11 |
| LAW Environmental, Inc. |
| Jun 94 |
| ESI, Final Report, OU 10 |
| LAW Environmental, Inc. |
| Jun 94 |
| ESI, Final Report, OU 4 |
| LAW Environmental, Inc. |
| Jun 94 |
| RI, Final Report Addendum, OU 6 |
| LAW Environmental, Inc. |
| Feb 95 |
| FFS, Final Report, OU 3 |
| LAW Environmental, Inc. |
| May 95 |
| Final Exploratory Trenching Characterization Report, OU 2 |
| LAW Environmental, Inc. |
| Jul 95 |
| Final Proposed Plan, OU 3 |
| LAW Environmental, Inc. |
| Sep 95 |
| Explanation of Significant Differences Report, OU 5 |
| US Army Corps of Engineers - Huntsville Division |
| Sep 95 |
| Explanation of Significant Differences Report, OU 9 |
| LAW Environmental, Inc. |
| Oct 95 |
| Quarterly Groundwater Sampling Report, Aug 95, PX Station |
| Parsons Engineering Science Inc. |
| Oct 95 |
| ROD, Final, OU 3 |
| LAW Environmental, Inc. |
| Nov 95 |
| RI, Report, Addendum, OU 5 |
| LAW Environmental, Inc. |
| Jan 96 |
| RI, Final Report Addendum, OU 4, OU 7 |
| LAW Environmental, Inc. |
| Jan 96 |
| Quarterly Groundwater Sampling Report, Dec 95, PX Station |
| Parsons Engineering Science Inc. |
| Jan 96 |
| Final Pilot Test Report, PX Station |
| LAW Engineering and Environmental Services, Inc. |
| Feb 96 |
| Final Pilot Test Report, OU 5 |
| LAW Environmental, Inc. |
| Apr 96 |
| FFS, Final Report, OU 7 |
| LAW Engineering and Environmental Services, Inc. |
| Apr 96 |
| Quarterly Groundwater Sampling Report, Feb 96, PX Station |
| Parsons Engineering Science Inc. |
| Oct 96 |
| Quarterly Groundwater Sampling Report, Intrinsic Remediation, Oct 96, PX Station |
| Parsons Engineering Science Inc. |
| Dec 96 |
| RI, Final Supplemental Report, OU 4, OU 7 |
| LAW Engineering and Environmental Services, Inc. |
| Jan 97 |
| Final Pilot Test Report, OU 4, OU 7 |
| LAW Engineering and Environmental Services, Inc. |
| Jan 97 |
| Quarterly Groundwater Sampling Report, Intrinsic Remediation, Jan 97, PX Station |
| Parsons Engineering Science Inc. |
| Jan 97 |
| Revised Final Corrective Action Plan, PX Station |
| Parsons Engineering Science Inc. |
| Apr 97 |
| Quarterly Groundwater Sampling Report, Intrinsic Remediation, Apr 97, PX Station |
| Parsons Engineering Science Inc. |
| May 97 |
| Revised Final Background Characterization Report |
| LAW Engineering and Environmental Services, Inc. |
| Jul 97 |
| RI, Final Report, OU 11 |
| LAW Engineering and Environmental Services, Inc. |
| Jul 97 |
| RA, Summary Report, OU 3 |
| Omega Environmental Services |
| Jul 97 |
| Quarterly Groundwater Sampling Report, Jul 97, PX Station |
| Parsons Engineering Science Inc. |
| Aug 97 |
| FFS, Final Report, OU 4 |
| LAW Engineering and Environmental Services, Inc. |
| Aug 97 |
| RA, Final Five-Year Review Report, OU 1 |
| LAW Engineering and Environmental Services, Inc. |
| Oct 97 |
| Quarterly Groundwater Sampling Report, Oct 97, PX Station |
| Parsons Engineering Science Inc. |
| Jan 98 |
| RI, Final Report, OU 10 |
| LAW Engineering and Environmental Services, Inc. |
| Jul 98 |
| FFS, Final Report, OU 8 |
| LAW Engineering and Environmental Services, Inc. |
| Feb 98 |
| Quarterly Groundwater Sampling Report, Feb 98, PX Station |
| Parsons Engineering Science Inc. |
| Aug 98 |
| Quarterly Groundwater Sampling Report, Aug 98, PX Station |
| Parsons Engineering Science Inc. |
| Sep 98 |
| IRA, Final Action Memorandum Decision Document, OU 2 |
| LAW Engineering and Environmental Services, Inc. |
| Oct 98 |
| Report of Video Inspections of Storm Sewers, OU 2, OU 12 |
| LAW Engineering and Environmental Services, Inc. |
| Nov 98 |
| Final Treatability Study Report, OU 8 |
| LAW Engineering and Environmental Services, Inc. |
| Feb 99 |
| Final Proposed Plan, OU 4 |
| LAW Engineering and Environmental Services, Inc. |
| Feb 99 |
| Final Corrective Action Plan Annual Report, Intrinsic Remediation, PX Station |
| Parsons Engineering Science Inc. |
| Feb 99 |
| Biannual Groundwater Sampling Report, Feb 99, PX Station |
| Parsons Engineering Science Inc. |
| May 99 |
| FFS, Third Revised Final Report, OU 2 |
| LAW Engineering and Environmental Services, Inc. |
| Jun 99 |
| ROD, Final, OU 4 |
| LAW Engineering and Environmental Services, Inc. |
| Jun 99 |
| Final Groundwater Model Update Report, Bioplume II, PX Station |
| Parsons Engineering Science Inc. |
| Jul 99 |
| RI, Revised Final Report, OU 13 |
| LAW Engineering and Environmental Services, Inc. |
| Jul 99 |
| Density Driven Convection Pilot Test Report, OU 7 |
| Wasatch Environmental, Inc. |
| Sep 99 |
| FS, Letter Report Addendum, OU 7 |
| LAW Engineering and Environmental Services, Inc |
| Oct 99 |
| Final Proposed Plan, OU 2 |
| LAW Engineering and Environmental Services, Inc. |
| Jan 00 |
| Revised Final Treatability Study Report, OU 8 |
| LAW Engineering and Environmental Services, Inc. |
| Jan 00 |
| FS, Final Report, OU 11 |
| LAW Engineering and Environmental Services, Inc. |
| Mar 00 |
| FS, Final Report, OU 10 |
| LAW Engineering and Environmental Services, Inc. |
| Jun 00 |
| FFS, Revised Final Report, OU 12 |
| LAW Engineering and Environmental Services, Inc |
| Jun 00 |
| RI, Second Revised Final Report, OU 12 |
| LAW Engineering and Environmental Services, Inc. |
| Jun 00 |
| Final Natural Attenuation Studies Report, OU 6 |
| LAW Engineering and Environmental Services, Inc. |
| Dec 00 |
| Final Pilot Test Report, OU 6 |
| LAW Engineering and Environmental Services, Inc. |
| Nov 01 |
| After Action Plan, Groundwater Pump and Treat System, OU 9 |
| Horne Engineering Services, Inc. |
| Dec 01 |
| Final Groundwater Summary Report, OU 11 |
| LAW Engineering and Environmental Services, Inc. |
| Dec 01 |
| Technical Memorandum Report, Quarterly Groundwater Sampling, Oct 01, OU 8 |
| LAW Engineering and Environmental Services, Inc. |
| Jan 02 |
| Technical Memorandum Report, First Quarterly Groundwater Sampling, |
Oct 01, PX Station LAW Engineering and Environmental Services, Inc.
| Jan 02 |
| Data Summary Report, No Name Creek, Kingsland Creek |
| LAW Engineering and Environmental Services, Inc. |
| Jan 02 |
| Basewide Environmental Baseline Survey Report |
| Rasco, Inc. |
| Feb 02 |
| Final Quarterly Groundwater Sampling Plan, OU 6, OU 8, PX Station |
| LAW Engineering and Environmental Services, Inc. |
| Feb 02 |
| Technical Memorandum Report, First Quarterly Groundwater Sampling, Sep 01-Oct 01, OU 6 |
| LAW Engineering and Environmental Services, Inc. |
| Apr 02 |
| Final Updated Residential Well Survey Report |
| LAW Engineering and Environmental Services, Inc. |
| Apr 02 |
| Final Groundwater Summary Report, OU 10 |
| LAW Engineering and Environmental Services, Inc. |
| Dec 02 |
| Technical Memorandum Report, Quarterly Groundwater Sampling, |
Mar 02-Apr 02, OU 6 MACTEC Engineering and Consulting, Inc. (f/k/a LAW Engineering and Environmental Services, Inc.)
| Dec 02 |
| Technical Memorandum Report, Creek Monitoring, Nov 01, Kingsland Creek, No Name Creek, Falling Creek Tributary |
| MACTEC Engineering and Consulting, Inc. |
| Dec 02 |
| Technical Memorandum Report, Quarterly Groundwater Sampling, |
Mar 02-Apr 02, OU 8 MACTEC Engineering and Consulting, Inc.
| Jan 03 |
| Technical Memorandum Report, Quarterly Groundwater Sampling, |
Mar 02-Apr 02, OU 7 MACTEC Engineering and Consulting, Inc.
| Jan 03 |
| Summary of Findings Report, OU 6 |
| MACTEC Engineering and Consulting, Inc. |
| Feb 03 |
| Summary of Findings Report, OU 7 |
| MACTEC Engineering and Consulting, Inc. |
| Mar 03 |
| Technical Memorandum Report, Quarterly Groundwater Sampling, Jul 02, OU 6 |
| MACTEC Engineering and Consulting, Inc. |
| Apr 03 |
| Technical Memorandum Report, Quarterly Groundwater Sampling, Jul 02, OU 7 |
| MACTEC Engineering and Consulting, Inc. |
| Apr 03 |
| Technical Memorandum Report, Quarterly Groundwater Sampling, Jul 02, OU 8 |
| MACTEC Engineering and Consulting, Inc. |
| Apr 03 |
| Technical Memorandum Report, Quarterly Groundwater Sampling, Jul-Aug 02, PX Station |
| MACTEC Engineering and Consulting, Inc |
| Jul 03 |
| Technical Memorandum Report, Creek Monitoring, Nov 02, Kingsland Creek, No Name Creek, Falling Creek Tributary |
| MACTEC Engineering and Consulting, Inc. |
| Jul 03 |
| Final Consolidated Five-Year Review Report, OU 1, OU 3, OU 9 |
| MACTEC Engineering and Consulting, Inc. |
| Aug 03 |
| Annual Groundwater Report, Oct 02, OU 7 |
| MACTEC Engineering and Consulting, Inc. |
| Nov 03 |
| Environmental Investigation Report, Proposed Sanitary, Sewer Installation Rayon Park |
| EEE Consulting, Inc. |
| Jan 04 |
| Annual Groundwater Sampling Report, Oct 01-Oct 02, OU 8 |
| MACTEC Engineering and Consulting, Inc. |
| Jan 04 |
| Supplemental FS, Final Work Plan (Volume I and Volume II) |
| MACTEC Engineering and Consulting, Inc. |
| Jan 04 |
| Annual Groundwater Sampling Report, Oct 01-Oct 02, PX Station |
| MACTEC Engineering and Consulting, Inc. |
| Feb 04 |
| Quarterly Groundwater Sampling Report, 03, OU 8 |
| MACTEC Engineering and Consulting, Inc. |
| Feb 04 |
| Quarterly Groundwater Sampling Report, 03, PX Station |
| MACTEC Engineering and Consulting, Inc. |
| Mar 04 |
| Quarterly Groundwater Sampling Report, 03, OU 6 |
| MACTEC Engineering and Consulting, Inc. |
| Mar 04 |
| Quarterly Groundwater Sampling Report, 03, OU 7 |
| MACTEC Engineering and Consulting, Inc. |
| Apr 04 |
| Revised Final Letter Work Plan, Potential Source Material Investigation, Former Fire Training Pit Area, OU 4 |
| MACTEC Engineering and Consulting, Inc. |
| Sep 04 |
| Final Action Memorandum Report, Principal Threat Source Material Removal, OU 4 |
| MACTEC Engineering and Consulting, Inc. |
| Oct 04 |
| Final General SAP (Volume I, Volume II and Volume III) |
| MACTEC Engineering and Consulting, Inc. |
| Mar 05 |
| Third Revised Final Focused Feasibility Study Report, OU 12 |
| MACTEC Engineering and Consulting, Inc. |
| Mar 05 |
| Proposed Plan, OU 12 |
| MACTEC Engineering and Consulting, Inc. |
| July 05 |
| Final Removal Action Completion Report, Principal Threat Source Material Removal, OU 4 |
| MACTEC Engineering and Consulting, Inc. |
| Sep 05 |
| ROD, Final, Rev. 1 OU 12 |
| MACTEC Engineering and Consulting, Inc. |
| Dec 05 |
| Final Work Plan Addendum for the Bi-Annual Groundwater Sampling |
| MACTEC Engineering and Consulting, Inc. |
| Dec 05 |
| Final Results of Bi-Annual Groundwater Sampling – July 2005 OUs 6, 7, and 8 (Volume 1 and Volume 2) |
| MACTEC Engineering and Consulting, Inc. |
| Feb 06 |
| Supplemental Feasibility Study Investigation Report |
(Volume 1, Volume 2 Part 1 & Part 2, Volume 3 Part 1 & Part 2 and Volume 4) MACTEC Engineering and Consulting, Inc.
| Apr 06 |
| Environmental Land Use Control Implementation Plan |
| MACTEC Engineering and Consulting, Inc. |
| Apr 06 |
| Human Health Baseline Risk Assessment Work Plan |
| MACTEC Engineering and Consulting, Inc. |
| May 06 |
| Final Focused Feasibility Study Report, OU 8 (Part 1, Part 2 and Part 3) |
| MACTEC Engineering and Consulting, Inc. |
| May 06 |
| Final Proposed Plan, OU 8 |
| MACTEC |
| Jun 06 |
| Human Health Baseline Risk Assessment of the Creeks |
Adjacent to DSCR MACTEC Engineering and Consulting, Inc.
| Jun 06 |
| Final OU 12 Remedial Design |
| MACTEC Engineering and Consulting, Inc. |
| Jun 06 |
| Groundwater Sampling Report, January 2006, PX Gasoline Station |
| Earth Tech, Inc. |
| Jul 06 |
| OU 2 Technical Memorandum |
| MACTEC Engineering and Consulting, Inc. |
| Jul 06 |
| Final Feasibility Study Addendum, OU 10 |
| MACTEC Engineering and Consulting, Inc. |
| Jul 06 |
| Final Feasibility Study Addendum, OU 11 |
| MACTEC Engineering and Consulting, Inc. |
| Aug 06 |
| Final Results of Bi-Annual Groundwater Sampling – January 2006 |
| MACTEC Engineering and Consulting, Inc. |
| Aug 06 |
| Final Conceptual Site Model Report |
| MACTEC Engineering and Consulting, Inc. |
| Sep 06 |
| Results of Three-Year Creek Monitoring Program (2001-2004) |
(Part 1 and Part 2) MACTEC Engineering and Consulting, Inc.
| Sep 06 |
| Final Remedial Action Work Plan, OU 12 |
| Earth Tech, Inc. |
| Oct 06 |
| Final Proposed Plan, OU 10 |
| Earth Tech, Inc. |
| Oct 06 |
| Final Proposed Plan, OU 11 |
| Earth Tech, Inc. |
| Dec 06 |
| Final Revised Human Health Baseline Risk Assessment, OU 1 |
| Earth Tech, Inc. |
| Jan 07 |
| Final Results of Bi-Annual Groundwater Sampling – July 2006 |
| MACTEC Engineering and Consulting, Inc. |
| Feb 07 |
| Final Technical Memorandum for Revised Remedy Selection, OU 2 |
| MACTEC Engineering and Consulting, Inc. |
| Feb 07 |
| Final Record of Decision, OU 8 |
| Earth Tech, Inc. |
| Mar 07 |
| Final Treatability Studies Work Plan, OU 6 and OU 7 |
| Earth Tech, Inc. |
| May 07 |
| Final Remedial Action Report, OU 12 |
| Earth Tech, Inc. |
| Jun 07 |
| Final Explanation of Significant Differences, OU 1 |
| Earth Tech, Inc. |
| Jul 07 |
| Final Operable Units 6/9 IRA Evaluation Report (Part 1 and Part 2) |
| Earth Tech, Inc. |
| Jul 07 |
| Final Results of Bi-Annual Groundwater Sampling – January 2007 |
| Earth Tech, Inc. |
| Jul 07 |
| Final Record of Decision, OU 10 |
| Earth Tech, Inc. |
| Jul 07 |
| Final Record of Decision, OU 11 |
| Earth Tech, Inc. |
| Sep 07 |
| Groundwater Sampling Report, December 2006, PX Gasoline Station |
| Earth Tech, Inc. |
| Oct 07 |
| Final Environmental Land Use Control Implementation Plan |
| Earth Tech, Inc. |
| Nov 07 |
| Final Proposed Plan, OU 2 |
| Earth Tech, Inc. |
| Nov 07 |
| Final Protectiveness Determination Addendum, OU 3 (Part 1 and Part2) |
| Earth Tech, Inc. |
| Jan 08 |
| Community Involvement Plan |
| Earth Tech, Inc. |
| Feb 08 |
| Final Remedial Design/Remedial Action Work Plan, OU 10 and OU 11 |
| Earth Tech, Inc. |
| Jul 08 |
| Final July 2007 Groundwater Monitoring Report, PX Gasoline Station |
| Earth Tech, Inc. |
| Jul 08 |
| Final Results of Bi-Annual Groundwater Sampling – July 2007 |
(Volume 1 and Volume 2) Earth Tech, Inc.
| Aug 08 |
| Final Five-Year Review Report for OUs 1, 3, 8, 9, 10, 11, and 12 |
| Earth Tech, Inc. |
| Aug 08 |
| Final Record of Decision, OU 2 |
| Earth Tech, Inc. |
| Sep 08 |
| Final Amendment to the ROD (OU 9) |
| Earth Tech, Inc. |
| Sep 08 |
| Final Remedial Action Report for OU 10 and OU 11 |
| Earth Tech, Inc. |
| Sep 08 |
| Final Remedial Design/Remedial Action Work Plan, OU 8 |
| Earth Tech, Inc. |
| Sep 08 |
| Final Revised SLERA for Low Lying Wooded Area, OU 13 |
| Earth Tech, Inc. |
| Sep 08 |
| Final Decommissioning Plan for PX Treatment System |
| Earth Tech, Inc. |
| Sep 08 |
| Final Decommissioning Plan for OU 9 Treatment System |
| Earth Tech, Inc. |
| Oct 08 |
| Final Results of Bi-Annual Groundwater Sampling – January 2008 |
| Earth Tech, Inc. |
| Nov 08 |
| Final Environmental Land Use Control Implementation Plan |
| Earth Tech, Inc. |
| Nov 08 |
| Groundwater Sampling Report, January 2008, PX Gasoline Station |
| Earth Tech, Inc. |
| Feb 09 |
| Final Decommissioning Report for PX Treatment System |
| Earth Tech, Inc. |
| Jun09 |
| Final Remedial Design Remedial Action Work Plan – OU 2 |
| AECOM |
| Jun 09 |
| Final Results of Annual Groundwater Sampling – January 2009 |
| AECOM |
| Jun 09 |
| Final 2009 LUCIP Inspection Report |
| AECOM |
| Sep 09 |
| Final Revised Focused Feasibility Study – OU 13 |
(Part 1 and Part 2)
AECOM/MACTEC
| Mar 10 |
| Final Proposed Plan – OU 13 |
| AECOM |
| Apr 10 |
| Final Remedial Action Completion Report – OU 2 |
| AECOM |
| Apr 10 |
| Final Remedial Action Monitoring Report – OU 8 |
| AECOM |
| Jun 10 |
| Final 2010 LUCIP Inspection Report |
| AECOM |
| Jul 10 |
| Final Revised FFS – OU 7 |
(Volume I, Volume II, Volume III)
AECOM
| Sep 10 |
| Final Results of Annual Monitoring – OUs 6, 7, and 12 |
| AECOM |
| Jan 11 |
| Final Proposed Plan – OU 7 |
| AECOM |
| Jan 11 |
| Final Technical Memorandum – Results of Oct 2010 Investigations at |
PX Gas Station
AECOM
| Feb 11 |
| Final Letter Report for Soil and Groundwater Investigations at PX Gas Station |
| AECOM |
| Mar 11 |
| Final Remedial Action Monitoring Report (Sept 09 Mar 10) – OU 8 |
| AECOM |
| Aug 11 |
| Final ESD for OU-8 |
| AECOM |
| Aug 11 |
| Final Environmental LUCIP – Revision 4 |
| AECOM |
| Sep 11 |
| Final Results of Annual Groundwater Monitoring – OUs 6, 7, and 12 |
| AECOM |
| Sep 11 |
| Final Revised FFS for OU 6 |
Part 1, Part 2 and Part 3
AECOM
| Sep 11 |
| Final Site Activities Report – Soil and Groundwater Investigations at |
PX Gas Station
AECOM
| Oct 11 |
| Final ROD for OU 13 |
| AECOM |
| Nov 11 |
| Final Technical Memorandum – Emerging Contaminants Sampling |
(PFOS and PFOA)
AECOM
| Dec 11 |
| Final Remedial Action Monitoring Report – OU 8 (Apr 2010 to Mar 2011) |
| AECOM |
| Mar 12 |
| Final Management Action Plan |
| AECOM |
| Mar 12 |
| Final Proposed Plan- OU6 |
| AECOM |
| Apr 12 |
| Final Results of Annual Monitoring at Operable Units 6 & 7- February 2012 |
| AECOM |
| Apr 12 |
| Final Remedial Action Monitoring Report (April 2011 to December 2011) For Operable Unit 8 |
| AECOM |
| Apr 12 |
| Final Quality Assurance Project Plan |
| AECOM |
| May 12 |
| Record of Decision for Operable Unit 7 Fire Training Area Groundwater |
| AECOM |
| Jun 12 |
| Technical Memorandum Groundwater Monitoring at OUs 6 and 7 – 2012 |
| AECOM |
| Sept 12 |
| Final Results of Groundwater Monitoring & Well Inspection/Repair at OU 6 & 7 |
| AECOM |
| Aug 12 |
| 2012 LUCIP Inspection Report for Defense Supply Center Richmond, Virginia |
| AECOM |
| Dec 12 |
| Technical Memorandum Off-Installation Groundwater Monitoring Results at Operable Unit 8 |
| AECOM |
| Feb 13 |
| Technical Memorandum, Groundwater Monitoring at OUs 6 and 7 |
| AECOM |
| Feb 13 |
| Final 2012 Monitoring Report for Operable Unit 8 |
| AECOM |
| Feb 13 |
| Technical Memorandum, Semi-Annual Groundwater Monitoring Results at |
OU 8
AECOM
| Apr 13 |
| Technical Memorandum, Semi-Annual Groundwater Monitoring at OU 8 – April 2013 |
| AECOM |
| May 13 |
| Subsurface Vapor Intrusion Investigation, OU 6 |
| AECOM |
| May 13 |
| Final Remedial Design/Remedial Action Work Plan for OU 7 |
| AECOM |
| May 13 |
| Final Remedial Design/Remedial Action Work Plan Addendum for OU 8 |
| AECOM |
| May 13 |
| Final Remedial Design/Remedial Action Work Plan OU 13 |
| AECOM |
| Jun 13 |
| Final Management Action Plan |
| AECOM |
| Aug 13 |
| Final Five-Year Review Report for OUs 1, 2, 3, 7, 8, 9, 10, 11, 12 &13 |
| AECOM |
| Sept 13 |
| Final Record of Decision for OU 6 |
| AECOM |
| Sept 13 |
| Final Results of Annual Monitoring for OUs 6 & 7-Feb/Mar 2013 |
| AECOM |
| Oct 13 |
| Technical Memorandum, Semi-Annual Groundwater Monitoring at OU 8 – Sept/Oct 2013 |
| AECOM |
| Jan 14 |
| Final 2013 Project Management Plan |
| AECOM |
| Jul 14 |
| Final Technical Memorandum Work Plan, Groundwater and Surface Water Monitoring at OU 6, OU 7 and OU 8 and Soil Vapor Monitoring at OU 7 |
| AECOM |
| Jul 14 |
| Final Technical Memorandum Work Plan, Monitoring Well Installation at OU 8 |
| AECOM |
| Jul 14 |
| Final Technical Memorandum, Completion of Phase 1 of the Direct Push Groundwater Sampling and Injection Well Installation at OU 8 |
| AECOM |
| Jul 14 |
| Final Technical Memorandum, Synoptic Air/Groundwater Study Work Plan for Off-Site Residences and OU 8 |
| AECOM |
| Aug 14 |
| Final 2013 LUCIP Inspection Report |
| AECOM |
| Aug 14 |
| Final 2013 Monitoring Report for OU 8 |
| AECOM |
| Aug 14 |
| Final OU13 Remedial Action Completion Report |
| AECOM |
| Aug 14 |
| Final Quality Assurance Project Plan for Defense Supply Center Richmond |
| AECOM |
| Oct 14 |
| Final Remedial Design/Remedial Action Work Plan for OU 6 |
| AECOM |
| Oct 14 |
| Final Buildings 65 & 66 Vapor Intrusion Human Health Risk Assessment |
| AECOM |
| Nov 14 |
| Final Management Action Plan |
| AECOM |
| Nov 14 |
| Revised Final Subsurface Vapor Intrusion Investigation for OU 8 |
| AECOM |
| Nov 14 |
| Final Technical Memorandum Work Plan, Direct-Push Investigation at OU 8 |
| AECOM |
| Mar 15 |
| Final Technical Memorandum Work Plan, Direct-Push Investigation at Bensley Elementary School, Eastern Edge of OU 8 and Warehouse 66 |
| AECOM |
| May 15 |
| Final Subslab Depressurization System Quarterly Monitoring Report for OU 8 – October 2014 |
| AECOM |
| Jul 15 |
| Final Subsurface Vapor Intrusion Investigation for the Motor Pool and Butler Buildings at the Dervishian Army Reserve Center |
| AECOM |
| Aug 15 |
| Final Semi-Annual Groundwater Monitoring Results for OU 8 – March 2014 |
| AECOM |
| Aug 15 |
| Final Technical Memorandum Work Plan, Semi-Annual Groundwater Monitoring at OU 8 |
| AECOM |
| Aug 15 |
| Final Source Investigation and Assessment Technical Memorandum for OU 8 |
| AECOM |
| Aug 15 |
| Final Groundwater and Surface Water Monitoring Technical Memorandum Work Plan for OU 6, 7 & 8 |
| AECOM |
| Aug 15 |
| Final Revised Remedial Design/Remedial Action Work Plan for OU 6 |
| AECOM |
| Oct 15 |
| Final 2014 Land Use Control Inspection Report |
| AECOM |
| Oct 15 |
| Final Quarterly Vapor Monitoring Technical Memorandum – September 2014 |
| AECOM |
| Nov 15 |
| Final Technical Memorandum - Synoptic Crawl Space, Soil Gas and Groundwater Study Results for Off-Site Residences Near OU 8 |
| AECOM |
| Nov 15 |
| Final Environmental Site-Wide Land Use Control Remedial Design |
| AECOM |
| Nov 15 |
| Final 2015 Management Action Plan |
| AECOM |
| Nov 15 |
| Final Results of Annual Monitoring at OU 6 & 7 – March 2014 |
| AECOM |
| Nov 15 |
| Final Human Health Risk Assessment for Subsurface Vapor Intrusion at Off-Installation Properties on Strathmore Road |
| AECOM |
| Nov 15 |
| Final 2014 Groundwater Monitoring Report for OU 8 |
| AECOM |
| Nov 15 |
| Final Quarterly Vapor Monitoring Technical Memorandum for OU 7 – September 2014 |
| AECOM |
| Dec 15 |
| Final Technical Memorandum Remedial Design/Remedial Action Work Plan Addendum for OU 7 |
| AECOM |
| Jan 16 |
| Final Technical Memorandum, Building 65 Sub-Slab Depressurization System Effectiveness Study |
| AECOM |
| Feb 16 |
| Final Subsurface Vapor Intrusion Investigation of Additional Off-Installation Properties on Strathmore Road Work Plan for OU 8 |
| AECOM |
| Feb 16 |
| Final Sub-Slab Depressurization System Quarterly Monitoring Report (Oct-Dec 2014) for OU 8, Building 65 |
| AECOM |
| Feb 16 |
| Technical Memorandum, RD/RA Work Plan Addendum, OU 6 |
| AECOM |
| May 16 |
| Sub-Slab Depressurization System Quarterly Monitoring Report (Jan-Mar 2015) for OU 8, Building 65 |
| AECOM |
| May 16 |
| Sub-Slab Depressurization System Quarterly Monitoring Report (Jul-Sep 2015) for OU 8, Building 65 |
| AECOM |
| Jun 16 |
| Technical Memorandum, Vapor Intrusion Monitoring Point Installation, OU 7, Building 72 |
| Arcadis |
| Jun 16 |
| Technical Memorandum, Fence Line Vapor Sampling, OU 8 |
| Arcadis |
| Aug 16 |
| Technical Memorandum, Direct Push Investigation (Dec 2014) for OU 8 |
| Arcadis |
| Sep 16 |
| Sub-Slab Depressurization System Quarterly Monitoring Report (Apr-Jun 2015) for OU 8, Building 65 |
| AECOM |
| Nov 16 |
| Technical memorandum, Quarterly Fence Line Monitoring (Jan 2016) for OU8 |
| AECOM |
| Nov 16 |
| Technical memorandum, Quarterly Fence Line Monitoring (Jul 2016) for OU8 |
| AECOM |
| Feb 17 |
| Land Use Control Inspection Report, 2015 |
| AECOM |
| Feb 17 |
| Land Use Control Inspection Report, 2016 |
| AECOM |
| Feb 17 |
| Land Use Control Inspection Report, 2016 |
| AECOM |
| Jun 17 |
| Technical Memorandum, Direct Push Investigation, Phase 2 (Mar 2015) for |
OU 8
AECOM
| Jun 17 |
| Groundwater Monitoring Report (2015) for OU 8 |
| AECOM |
PREVIOUS STUDIES
Date Title Author
Defense Supply Center Richmond – Management Action Plan Previous Studies – Page 21
ER ELIGIBLE DSERTS SITES
Defense Supply Center Richmond – Management Action Plan ER Eligible DSERTS Sites – Page 32 Defense Supply CENTER RICHMOND – DSERTS Site 002 transitory shelter 202: ou 11
Defense Supply Center Richmond – Management Action Plan Site Descriptions – Page 45 Site Description Former Building 202, referred to as a Transitory Shelter (TS), was an open-front storage shed located along the western installation boundary). Formerly, the northern end of the shelter was used to store approximately 800 drums of DDT. In 1981, seepage from the drums was discovered. Soil from the floor was removed and backfilled with clean soil. The area was paved over, and a containment berm was constructed along the floor to contain future potential leakage. The drums were subsequently removed for off-site disposal in the early 1980s.
In 1986, soil samples were collected as part of a pesticide monitoring study. Analytical results indicated that the soil contained residues of DDT and its primary metabolites (dichlorodiphenyldichloroethane [DDD] and dichlorodiphenyldichloroethylene [DDE]). In 1992, an ESI revealed toluene, semivolatile organic compounds (SVOCs), metals, and pesticides in surface soil and sub-floor samples. As a result, the soil impacts were designated as OU 11.
Additional soil and storm drain sediment samples were collected in 1995. Soils were found to contain seven metals, DDT and its metabolites, and PCB-1254 above the USEPA Region 3 risk-based concentrations (RBCs) for residential exposure. Maximum concentrations were found in surface samples. Lead, DDD, and DDT concentrations exceeded residential soil RBCs in sediment samples, but there was not a complete receptor exposure pathway for impacted storm drain sediments. Groundwater collected in 2000 contained two metals and two volatile organic compounds (VOCs) at concentrations above the USEPA Region 3 tap water RBCs but below VDEQ groundwater quality standards. However, downgradient results were below upgradient groundwater concentrations.
An RI was submitted in 1997 and an FS in 2000. An FS Addendum was submitted in 2005 evaluating potential remedial alternatives for future industrial re-use of the site. The HHBRA was updated in 2006 for current and future on-site industrial workers and future construction workers. There was no unacceptable risk for any exposure scenario. The shed was demolished in October 2004, and the area was paved with asphaltic concrete in October 2005. The area is currently used for materials storage. A ROD for OU 11 was signed in 2007. Based on existing OU-specific data, the selected remedial alternative includes LUCs, maintenance of the existing cover system, and proper soil disposal and erosion control in case of future excavation. A vegetative cover was also recommended at OU 11. The RD and RA-C were completed in 2008, and the site has achieved RC.
Path Forward Annual LUCs and LTM of vegetative cover are ongoing and will continue at OU 11.
IRP STATUS
| RRSE Rating: | Low Risk |
| Constituents: | Metals, SVOCs, pesticides |
| Affected Media: | Soil, Storm Sewer Sediment |
| Completed IRP Phases: | Preliminary Assessment (PA), Site Investigation (SI), RI, FS, RD, RA-C, RC |
| Current IRP Phase: | LTM |
| Future Phases: | LTM |
Defense Supply CENTER RICHMOND – DSERTS Site 006 Building 68: OU 10
Site Description OU 10 is the former site of Building 68, a small (30foot x 30-foot) brick building surrounded by an asphalt and gravel lot. OU 10 is located in Zone 1 in the northern part of the installation. From 1954 to 1972, the area served as a pesticide storage and operations facility. Additionally, in 1972 the surrounding gravel lot was used to store electrical transformers. A spill of transformer oil containing PCBs occurred during 1980. Affected soil was excavated and removed from the site. The lot surrounding the former building is currently used for vehicle parking. Storm drains in the area discharge into the Falling Creek Tributary, just west of the installation.
Soil and storm drain sediment samples were collected during a pesticide monitoring study in 1986. A human health risk assessment (HHRA) was performed using a residential exposure scenario. Dieldrin was detected in surface soils above the USEPA Region 3 RBC for residential exposure and above background concentrations. No evidence of pesticide migration to groundwater was found.
An ESI was performed in 1992, which included collecting surface and subsurface soil samples. Toluene, 16 SVOCs, 6 pesticides, and 20 metals were detected. Arsenic, benzo(a)pyrene, and manganese concentrations resulted in unacceptable human health risk under residential exposures, and the soil impacts were designated OU 10.
An RI report was submitted in 1998. Groundwater, subsurface soil, and storm sewer sediment samples were collected during 1995.