A_DR-R-0055_RFI_and_responses_Part_1_8-14-18.pdf

PDF 47 KB Posted

Attached to
Enviromental AE Services/W912DRDR18R0055
Solicitation number
W912DR-18-S-0009
Issued by

About this file

Request for Information Part 1.

View the file

Other files

File Type Posted
W912DR18R0055_-_Amendment_0004_9-5-18.pdf PDF
W912DR18R0055_-_Attachment_BR_-App_G2_Final_OU_&_VMP_Tech_Memo_-_Sept_2014-11-01-15.pdf PDF
W912DR18R0055_-_Attachment_BS_-App_G1OU6_Summary_of_Subsurface_Soil_Gas_2010.pdf PDF
W912DR18R0055_-_Attachment_BQ_-2017_OU6_and_OU7_Report_Draft_7-2018.pdf PDF
W912DR18R0055_P00003_Solicitation_8-31-18.pdf PDF
W912DR18R0055_P00002_Solicitation_8-31-18.pdf PDF
W912DR18R0055_-_Attachment_BC_-DRAFT_2017_OU8_GWMR_8.4.18.pdf PDF
W912DR18R0055_-_Attachment_BA_-Draft_OU8_SSDS_Report_Tables_1-3.pdf PDF
W912DR18R0055_-_Attachment_BN_-2016-04_Draft_Comm_Inv_Plan_041216.pdf PDF
W912DR18R0055_-_Attachment_BL_-2016_Proposed_OU7_Sampling_Program.pdf PDF
W912DR18R0055_-_Attachment_AT_-_DLA-Richmond_OU-8_S_Lobe_Long_Term_Pump_Test_Tech_Memo_2015-12-01_Draft.pdf PDF
W912DR18R0055_-_Attachment_BJ_-VAG830484_tletter_2015.pdf PDF
W912DR18R0055_-_Attachment_BB_-Draft_OU8_SSDS_Report_2017_REV1_clean.docx DOCX document
W912DR18R0055_-_Attachment_BI_-VAG830484_GeneralPermit2013.pdf PDF
W912DR18R0055_-_Attachment_AS_-_Boring_Logs_PWS.pdf PDF
W912DR18R0055_-_Attachment_BM_-2016_Proposed_OU8_Sampling_Program.pdf PDF
W912DR18R0055_-_Attachment_AZ_-Draft_OU_8_Jul2016_Qtr_Monitoring_TM_092816.pdf PDF
W912DR18R0055_-_Attachment_BP_-Complete_RFI_and_Gov't_responses_8-30-18.pdf PDF
W912DR18R0055_-_Attachment_BE_-_Foma;_DSCR_Bldg_151_Vapor_Mitigation_1-22-18.pdf PDF
W912DR18R0055_-_Attachment_AW_-DRAFT_-_BDGR_OM_Manual_3.pdf PDF
W912DR18R0055_-_Attachment_BK_-2016_Proposed_OU6_Sampling_Program.pdf PDF
W912DR18R0055_-_Attachment_AY_-_OMM_Plan_Bldg_151_SSDS_May_2018.docx DOCX document
W912DR18R0055_-_Attachment_AX_-DRAFT_Bldg_151_SSDS_OMM_Manual_5.11.18_combined.pdf PDF
W912DR18R0055_-_Attachment_BF_-FINAL_OU6_Bldg_151_SSDS_DesignREV1_6.12.18_combined.pdf.nhd3u0q.partial PDF
W912DR18R0055_-_Attachment_AU_-_DRAFT_-_BDGR_OM_Manual_1.pdf PDF
W912DR18R0055_-_Attachment_BO_-Bldg_65_SSDS_O_and_M.pdf PDF
W912DR18R0055_-_Attachment_BG_-Tech_Memo_PFOS_PFOA_2_.pdf PDF
W912DR18R0055_-_Attachment_AR_-_Bldg_65_SSDS_O_and_M.pdf.5ms0eat.partial PDF
W912DR18R0055_-_Attachment_BH_-VAG830484_Discharge_Monitoring_Report_(DMR).pdf PDF
A_DR-R-0055_RFIs_8-13-18_GOVT_Response_Part_2__8-20-18.docx DOCX document
W912DR18R0055_-_Attachment_L_-_J151255-2_UDS_Level_2_Report_Final_Report.pdf PDF
W912DR18R0055_-_Attachment_AH_-_Site_visit_Northern_lobe_pump_test_1.jpg JPG image
W912DR18R0055_-_Attachment_H_-_Draft_2018_Annual_Vapor_Rpt_OU7_Bldg_72_7.24.18REV1_combined.pdf PDF
W912DR18R0055_-_Attachment_Z_-_DSCR_2017_OU_8_GWMR_Tables.pdf PDF
W912DR18R0055_-_Attachment_R_-_Site_visit_OU7_3.jpg JPG image
W912DR18R0055_-_Attachment_AG_-_Site_visit_BDGR_6.JPG JPG image
W912DR18R0055_-_Attachment_AD_-_Site_visit_BDGR_3.jpg JPG image
W912DR18R0055_-_Attachment_J_-J151095-1_UDS_Level_2_Report_Final_Report.pdf PDF
W912DR18R0055_-_Attachment_AM_-_June_2018_Planning_Meeting-Compressed.pptx PPTX presentation
W912DR18R0055_-_Attachment_AP_(2)_8_9_18_site_visit_Sign_In_sheet_Pg.2.jpg JPG image
W912DR18R0055_-_Attachment_AE_-_Site_Visit_BDGR_4.jpg JPG image
W912DR18R0055_-_Attachment_N_-_OU7_biowalls.pptx PPTX presentation
W912DR18R0055_-_Attachment_AC_-_Site_visit_BDGR_2.jpg JPG image
W912DR18R0055_-_Attachment__F_-_20171117_DSCR_FINAL_WorkPlanOU7_Remedial_Optimization.pdf PDF
W912DR18R0055_-_Attachment_AJ_-_2018_Draft_Management_Action_Plan_7.18.18REV1_clean.docx DOCX document
W912DR18R0055_-_Attachment_T_-_Figure_4-1_-_Proposed_Wells.pdf PDF
W912DR18R0055_-_Attachment_AN_-_Visit_Request_Form.pdf_-_Adobe_Acrobat_Pro.pdf PDF
W912DR18R0055_-_Attachment_X_-_DRAFT_2017_OU8_GWMR_8.4.18.docx DOCX document
W912DR18R0055_-_Attachment_P_-_Site_visit_OU7_1.jpg JPG image
W912DR18R0055_-_Attachment_G_-_DRAFT_OU-7_Optimization_Memo_-_FINAL.docx DOCX document
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DSC-Richmond RFI Part 1

NO. Question Answers 1 When is the cut off for questions on the solicitation? 2pm on 20 August 2018 2 Please clarify the past performance requirement. The instructions say nothing is required to be submitted for past performance but references a PPQ form that does not seem to be included with the RFP. Can this form be provided? How many PPQs can be submitted and are they included in page count? The evaluation criteria lists some specifics that will be evaluated for this factor to seems to indicate project write ups may be required. It says: " Projects that demonstrate multiple experiences noted above may receive higher relevancy ratings." Please clarify how this will be evaluated if project write ups are not included.

The PPQ Form was uploaded as Attachment AQ with the solicitation.

3 Are figures / maps included in the page counts? NO. figures / maps are NOT included in the page counts

4 Is an organizational chart / figure included in page count under management factor or can it be excluded from the 5 pages?

No, an organizational chart / figure is NOT included in page count under management factor.

5 Is the 2 page assumptions section within Factor I included in the 30 page limit?

No, the 2 page assumption is not included in the 30 page limit.

File details come from the government source that posted it.