RFI Group #4
KTR RFI #
Originating Company
Originator (Full Name) Discipline Full RFI Question
Full RFI Response (Leave Blank)
5 John C. Grimberg Co. John Meckley JCG Staff
Drawing S -503 note 2 refers to sheet A 500 which is not included in the contract documents. Please provide this drawings so we can determine where the details on drawing S 503 apply
Disregard reference to A-500.
The details apply to all exterior window and doors in new construction exterior walls .
Details apply to all exterior windows listed in window schedule on A-616 an doors 138A, 216A, and 338A.
6 John C. Grimberg Co. John Meckley JCG Staff
A question has come up with how to bid unit price items 9 and 10. Unit price item 9 is a lump sum price to epoxy paint over existing lead paint while unit price 10 is to remove the lead paint. Since the existing lead paint is chipped and coming off the existing structural components how is that to be bid? If the lead paint is removed under bid item 10 then does the existing structure still receive epoxy paint or no finish at all?
Item 0010 shall be removed from the Price Schedule. Item 0009 shall assume treatment of 150,000 sq-ft of concrete underslabs, beams, walls and columns to encapsulate the lead paint that remains after the recent effort to remove all hazardous materials from the building.
Sheet1