W912DR-16-B-0017-0001.pdf

PDF 65 KB Posted

Attached to
TRED AVON OYSTER BAR CREATION Federal contract opportunity
Solicitation number
W912DR-16-B-0017
Issued by
Department of the Army Corps of Engineers Engineering District Baltimore

About this file

Amendment to update Price Schedule answer RFI Questions and to update plans and specs.

View the file

Other files for this federal contract opportunity

Other files attached to TRED AVON OYSTER BAR CREATION, newest first.
File Type Posted
G24_Bid_Abstract_.xlsx XLSX spreadsheet
G24_Bid_Abstract_.xlsx XLSX spreadsheet
W912DR-16-B-0017.pdf PDF
Final_Tred_Avon_FY16_Plans.pdf PDF
Final_Tred_Avon_FY16_Specs.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to do the follow ing:

1. Revise the Bid Schedule

2. Provide RFI Responses

3. Make Revisions to Plans & Specs ( See continuation page)

1. CONTRACT ID CODE PAGE OF PAGES

1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR-16-B-0017

X 9B. DATED (SEE ITEM 11)

03-Aug-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0001

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Aug-2016

CODE

U.S. ARMY CORPS OF ENGINEERS, BALTIMORE

10 S. HOWARD STREET

ROOM 7000

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR-16-B-0017

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

CHANGES TO SPECS

Section 35 20 90: Paragraph 1.4: Change “15,795 cubic yards” in line 1 and 2 to “12,954 cubic yards”.

Section 35 20 90 paragraph 1.4: Change “Option 3” line 2 from “7,662 cubic yards of rock and 7,662 cubic yards of clean, mixed shell” to “8,065 cubic yards of rock and 8,065 cubic yards of clean, mixed shell”.

SECTION 00010 - SOLICITATION CONTRACT FORM

The following have been modified:

PRICE SCHEDULE

ITEM

NO.

DESCRIPTION

ESTIMATED

QUANTITY

UNIT

UNIT

PRICE

ESTIMATED

AMOUNT

0001 Reimbursement of performance and payment bonds

JOB

LS

0002 Mobilization and Demobilization

JOB

LS

0003 Oyster Bar Construction 12,954 C.Y. $_____ $_____

TOTAL ESTIMATED BASE BID AMOUNT $________________

Optional Bid Items

0004 Oyster Bar Construction with mixed shell (Optional)

16,130

C.Y.

0005 Oyster Bar Construction with rock (Optional)

0006 Oyster Bar Construction with rock and mixed shell (Optional)

TOTAL ESTIMATED BASE AND OPTIONAL BID AMOUNT $________________

NOTICE TO BIDDERS

Offerors must quote all items. Failure to quote on all items may be cause for rejection of the proposal.

The Optional Items may be exercised at any time within 90 calendar days after contract award. The Contracting Officer may exercise the Optional Items by written notice to the Contractor, postmarked within the period specified above. The Government may exercise any, all or none of the listed Optional Items in any order. Additional time for contract completion will be allowed when any Optional Items are exercised. No amount of additonal time is granted for the Optional Items. Award and construction of the base bid items are contingent upon DNR concurrence. In addition, award and construction of the optional bid items are contingent upon an approved supplemental EA and MD DNR concurrence with the restoration plans.

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been added by full text:

RESPONES TO RFI QUESTIONS

Q1. Line item 0003 on the bid sheet has an estimated quantity of 15,795. When you add up the quantities specified in the specifications for TA sites 2,3,7,8, and 12 the quantity is 12,954. Please clarify A1. Bid Schedule should be changed to show CLIN 0003 as 12,954 CY of material. Remove 15,795 CY. See amended Bid Shcedule.

Q2. In the specifications, Line item 0004 calls out the use of shell. On the bid sheet, item 0004 calls out rock. Please clarify A2. Bid Schedule should be changed to show CLIN 0004 as mixed shell as the material. See amended Bid Shcedule.

Q3. In the specifications, Line item 0005 calls out the use of rock. On the bid sheet, item 005 calls out shell. Please clarify A3. Bid Schedule should be changed to show CLIN 0005 as rock as the material. See amended Bid Shcedule.

Q4. In the specifications, under paragraph 1.4 estimated quantities for the option 0006, it estimates 7,662 of shell and 7,662 of rock. That equals 15,324.

A5. Specs Section 35 20 90 Paragraph 1.4 should be changed to reflect the correct cubic yardage of 8,065 cy of rock and 8,065 cy of shell for Option 3

(End of Summary of Changes)