W912DR-15-R-0007-0002

This project w ill be a Tw o Phase Acquistion for Single Aw ard Task Order Contract (SATOC) for Design-Build and Design-Bid-Build Construction projects. Projects w ill generally be located in the Baltimore-Washington corridor but may be used throughout CONUS and Haw aii. The period of performance of the contract is f ive years from the date of aw ard. The resultant aw ard w ill be firm f ixed priced. This solicitation is issued on an unrestricted basis.

The maximum capacity for this contract is $103,000,000.00. The mimimum guarantee is $5,000.00.

NAICS: 236220

Size Standard: $36.5M

A Top Secret Facility Site Clearance is required for the offeror named in block 14 at the time the offer is due, at the time of aw ard and for the duration of the contract.

There w ill be no site visit in Phase 1. Offerors may submit w ritten “Requests for Information” (RFI) in w riting to Gregory Hodgson at gregory.hodgson@usace.army.mil.

The last day to submit RFIs is 14 October 2015. RFIs should be submitted to Gregory Hodgson via email.

The required amount for a bid bond is $103,000,000. See FAR 52.228-1.

GREGORY HODGSON 443-654-7495

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

18-Sep-2015

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________1826 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________5 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________27 Oct 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USACE, BALTIMORE

10 SOUTH HOWARD STREET, ROOM 7000

BALTIMORE MD 21201

W912DR

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

11:00 AM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W912DR-15-R-0007

Section 00010 - Solicitation Contract Form

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0001 1 Job

Single Award Task Order Const. Contract

FFP

This is a five year Indefinite Delivery Indefinite Quantity (IDIQ) Single Award Task Order Construction Contract (SATOC) that encompasses a broad varieties of construction services. Geographic area is CONUS plus Hawaii.

FOB: Destination

MAX

NET AMT

COEFFICIENT SCHEDULE

All Offerors will fill in the price (coefficient) schedule. The price (coefficient) schedule is made up of the coefficients for the following breakdown of task orders. The Statement of Work, included in the solicitation, contains information as to what is included in the coefficient. This is located under Section 00100, Statement of Work, Local Provisions paragraph 2.0.

Chart A Pre-Priced Line Items Non-Pre-Priced Line Items

Design-Bid-Build

(DBB)

Design-Build

(DB)

Design-Bid-Build

(DBB)

Design-Build

(DB)

Non-Classified: $0 to $1M

Non-Classified: >$1M

Classified: $0 to $1M

Classified: >$1M

A-E PRICING SCHEDULE

Architect-Engineer Pricing Schedule. Note: These rates will only be used if a modification to the design is required that is outside the Division 1 deliverables. Design fees in the task orders will be compensated through the Design- Build coefficient and fees will not be negotiated separately. See Section 00100, Statement of Work, Local Provisions paragraph 2.1 last bullet list.

ITEM DESCRIPTION U/M Unit Price

DIRECT LABOR ( with AE’s Burden & Profit)

1 Principal/Project Manager HR

2 Supervisory Engineer HR

3 Architect HR

4 Mechanical Engineer HR

5 Electrical Engineer HR

6 Civil Engineer HR

7 Structural Engineer HR

8 Geotechnical Engineer HR

9 Fire Protection Engineer HR

10 Environmental Engineer HR

11 Certified Industrial Hygienist (CIH) HR

12 Industrial Hygienist HR

13 Interior Designer HR

14 Cost Estimator HR

15 Survey Crew (2 Person) HR

16 CADD Operator/Draftsman HR

17 Typist/Word Processor HR

18 Specification Writer HR

19 Landscape Architect HR

20 Engineering Technician HR

OTHER DIRECT COSTS (ODC’S)

All cost for drawings, reproduction, mailings, telephone and travel will be negotiated on a per task order requirement for such services

GENERAL CONTRACTOR’S COSTS**

21 Superintendent HR

22 Quality Control Manager HR

23 Safety Manager HR

24 Project Manager HR

25 Home Office Overhead * JOB

*ALL TRAVEL WILL BE IN ACCORDANCE WITH JOINT TRAVEL REGULATION (JTR) RATES.

**GC’s cost should be incorporated into the “Direct Labor” costs if the work will be done with in-house staff.

CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE

The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

1.00 $5,000.00 999.00 $103,000,000.00

DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE

The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

1.00 $5,000.00 999.00 $103,000,000.00

CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE

The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.

CLIN

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

0001 5 yrs. ADC 1 REAL PROPERTY SERVICES F.O.

KEYSHA CUTTS-WASHINGTON

300 SENTINEL DRIVE

STE 400

ANNAPOLIS JUNCTION MD 20701

443-654-7854 FOB: Destination

W912DR

Section 00100 - Bidding Schedule/Instructions to Bidders

STATEMENT OF WORK

Statement of Work For

Single Award Task Order Construction Contract For

The Real Property Services Field Office

1.0 Purpose: The Real Property Services Field Office’s (RSFO) mission is to provide all aspects of real estate leasing, acquisition, facility management, and associated engineering, planning, and design and construction services (to include standard military design and construction) for the secure community. Projects are often time-critical and of a highly visible nature. The purpose of this contract is for RSFO to have the ability to respond rapidly and professionally to Government requirements, without compromising safety, current mission requirements, and/or readiness.

2.0 General Requirements: The scope of this contract encompasses a broad variety of major and minor repair, modification, rehabilitation, alterations, Design-Build, Design-Bid-Build and new construction projects in support of DOD organizations and other agencies, organizations, and branches of the U.S. Government and other customers within the secure community. The geographic locations covered under this contract are primarily for the Washington/Baltimore corridor and may include areas within the Continental United States (CONUS) and Hawaii.

Customers (Users) to be serviced by this contract will generally belong to secure agencies.

This contract performs both Design-Build and Design-Bid-Build construction services. Design services will only be applied to Design-Build task orders and no task orders will be issued solely for design.

Task orders issued against this contract may include the following types of work: construct new buildings, architectural renovations, mechanical upgrades and repairs, electrical upgrades and repairs, major utility work (including power substation and chilled water plant with all associated duct bank construction), paving, roofing, Supervisory Control and Data Acquisition (SCADA) systems, site preparation, demolition, and all other activities associated with general and heavy construction. It may also include: communications systems, security systems, data systems infrastructure, Heating Cooling and Air Condition systems, Counter-Terrorism, and Anti-Terrorism Force Protection construction, and Secret Compartmented Information Facilities (SCIF) construction. The contractor will be responsible for integrating, managing, and executing all aspects of all work related to each task order.

All task orders issued under this contract will be firm fixed price.

Projects will be issued via task orders. Multiple task orders may be issued concurrently. The contractor shall be responsible for integrating, managing, coordinating, and executing all aspects of the design and construction work ordered under this contract in accordance with all elements of the individual task orders.

The Contractor shall provide a flexible and multi-disciplined work force to include a team of subcontractors. Work may be performed in either secure or non secure sites. As such, the contractor is required to maintain a balanced work force of Top Secret (TS) cleared personnel to work on such projects.

It is mandatory that the prime contractor have an active Top Secret Facility Site Clearance during the duration of this contract.

The work requirements to be executed via this contract are a part of the mission of RSFO. Other contractors and Government personnel perform services which fall within the general description contained in this contract. The contractor has no entitlement to any work in the mission area. It is the discretion of the Government as to how to execute work. The Government’s minimum obligation under this contract is set forth in other areas of the contract. This is not a requirements contract or a Job Order Contract. This is a single award task order construction contract (SATOC).

3.0 Points of Contacts: The nature of this contract requires a strong and effective partnership between the Government and the contractor. The contractor's management and supervision will interface with the Government through different personnel. The Contracting Officer, the Contacting Officer's Representative (COR) and Project Managers will interface with the contractor. Each position holds different roles and responsibilities. It is imperative that the contractor understand these roles and responsibilities. The Contracting Officer is the only person that has the authority to alter the terms and conditions of the contract. A COR has certain authorities for oversight of the contract. These authorities will be officially issued in writing to both the COR and the contractor. Project Managers have the overall responsibility for the individual projects as issued via task orders.

The contractor shall provide a single point of contact (POC), with an alternate, who shall both be available 24 hours per day, seven days per week, and 365 days per year via telephone.

4.0 Contractor’s Management and Supervision: The contractor's effort will extend beyond conventional single job design and/or construction efforts in that the contractor must plan, program, design, schedule, coordinate, manage, construct, and otherwise execute a flow of several independent orders simultaneously. The contractor must be capable of adjusting to a wide variation between unrelated tasks without significantly impacting on-going work.

The contractor is expected to select quality subcontractors and design firms as their team members and as necessary to perform elements of work. The contractor is expected to effectively manage and provide project resources to ensure that the Government is provided with a coordinated level of effort on all assigned task orders.

The Government must consent prior to any changes or deviations to the contractor’s key personnel from those accepted in the successful proposal. Since the contractor’s management has the only direct interface with the Government, it is essential that all contractor key personnel remain briefed on the status of all tasks within the scope of this contract, such that the contractor can insure a prompt response to new or changed conditions with a minimum of disturbance to the Government. The contractor, during negotiations and prior to task order award, is expected to alert the Government to any areas of the project(s) that presents unique challenges that have the potential to increase or decrease the project cost or schedule. Together, the Government and the contractor will work through all project challenges to arrive at a defined scope of work, schedule and a firm fixed price for the defined requirement.

The contractor will be required to schedule and run master schedule meeting which shall review all current task orders, their status and any issues. This meeting shall be attended by contractor’s management team, at least one officer of the contractor’s company (corporation or joint venture), the Government Project and Program Managers, and the Contracting Officer. The meeting will be held at the Real Property Services Field Office.

5.0 Work Categories: The work included may vary from routine general construction to installation of technically complex systems. Historically, the following types of task orders have been issued on this type of contract:

• Electrical systems repair, construction or replacement

• Structural, Mechanical, Electrical, and foundation systems repair, construction, or replacement

• Utility Infrastructure and Systems repair, construction or replacement

• Renovations, HVAC upgrades, Paving, Fencing.

• Anti-Terrorism/Force Protection (AT/FP) features

• Fire protection, Sprinkler, and alarm systems repair, construction or replacement

• Sensitive Compartmented Information Facilities (SCIF) with Electro Magnetic Radiation (EMR) shielding

• Supervisory Control and Data (SCADA) and Energy Management System (EMS)

• Security Systems

All task orders will clearly define the work required to the greatest extent possible and shall indicate whether classified (with security clearance) or unclassified (without security clearance) design and construction workers must be used for each task order. The work definitions will vary from basic narrative descriptions to detailed plans and specifications, depending on the requirements, size, and complexity of the tasks. The jobs included will require a variety of professional management, architectural, engineering, and craft skills.

Task order Scopes of Work (SOW) may contain complete drawings and specifications. Other task orders may only provide a narrative scope of work with defined performance objectives. These will require the contractor to secure the services of licensed design professionals to provide drawing and specifications, and coordinate construction trades in order to perform tasks of a Design-Build nature. The contractor shall be required to have a professional architect and/or engineer, licensed and registered as required by federal, state and local laws and regulations as well as any local jurisdictions in the state where the project is located, to stamp and sign the drawings as required.

6.0 Contractor Provided Items: As part of the basic contract, the contractor shall provide the following:

6.1 RS Means/Cost Works: One complete set of the most current year RS Means Cost Works CD Software and Databases for each Data Book indicated below, along with 25 user licenses for use on a network system running the Microsoft XL Professional network operating system. The software shall include online updates every three months. The software shall also include Cost Works Estimator for every licensed user. The software shall be purchased through the RSFO Representative to ensure all licenses being provided through different contracts are capable of being utilized concurrently. This name can and will be provided when requested. The software shall be provided to the Government.

The following databases and cost books/packages shall be provided: Building Construction Cost Data Book, Mechanical Cost Data Book, Electrical Cost Data Book, Plumbing Cost Data Book, Square Foot Cost Data Book, Heavy Construction Cost Data Book, Assemblies Cost Data Book, Light Commercial Cost Data Book, Site Work & Landscape Cost Data Book, Concrete & Masonry Cost Data Book, Facilities Construction Cost Data Book, Facilities Maintenance and Repair Cost Data Book, Commercial Renovation Cost Data Book, Green Building Cost Data Book and the Interior Cost Data Book. The Building Construction Cost Databases and Cost Data Books shall be used as the primary source of pricing data. These include the Mechanical, Electrical, Plumbing, Heavy Construction, Light Commercial, Site Work & Landscaping, Concrete & Masonry, and the Interior Databases and books. The Square Foot, Assemblies and Green Buildings Cost databases and cost data books shall be used as required, without regard to the databases and books references above. The Facilities Construction, Facilities Maintenance and Repair and Commercial Renovation Cost Databases and Cost Data Books shall not be used to price any work unless specifically required by the Task Order Statement of Work or by the Contracting Officer.

Three sets of books for each of these titles shall also be provided.

The contractor will provide the newest software and 25 licenses and three sets of books in January of each year throughout the duration of the contract.

6.2 RS RS Means Online Estimating Seminar: The Contractor is required to provide one Unit Price Estimating seminar. The seminar will be two eight hour sessions at a publicly accessible facility containing a seminar room located within 15 miles of Fort Meade, MD. The first eight hour session will include an overview of all features of using RS RS Means Online. The second eight hour session will include unit price estimating and a Q&A session with questions the Government provides in advance of the seminar. Each student will be provided with a course workbook. The Contractor is responsible for providing all necessary equipment and materials to conduct the seminar, to include as a minimum, a PC or laptop for each student to use during the seminar and a high speed internet connection available for the entire seminar. The seminar sessions will be taught by a third party certified RS RS MEANS instructors. The date of the seminar shall be scheduled with the Government. A maximum of 20 Government personnel will attend.

6.3 Formal Partnering: A formal partnering session will be scheduled within first four weeks after contract award.

The session will be planned for a six hour period at a conference facility located within 15 miles of Fort Meade, MD. The initial session shall include key Government personnel, key contractor personnel, subcontractors, associates, designers, and consultants, as required. It is anticipated that approximately 20 Government personnel will attend.

It is the Government’s intent that one formal partnering session be required throughout the duration of the contract.

However, if the Government or the contractor deems additional partnering sessions, informal or formal, are required, these sessions shall be scheduled by the contractor. Additional costs incurred for these sessions shall be a contractor expense and will not be added into the contract.

7.0 Government Provided Items: As part of the basic contract, the Government shall not provide any items.

However, if any Government provided items are required per task order, those items will be identified in the scope of work for that task order.

8.0 Specific Requirements:

8.1 Unified Facilities Guide Specifications: The contractor is responsible for complying with all requirements set forth in the edited General UFGS Division One Specifications and the Division One Security Specification, set forth in Attachment B. This includes all LEED requirements set forth in the edited general UFGS Division 1 specifications.

8.2 Safety: The US Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1) and the Occupational Safety and Health Administration (OSHA) requirements (29 CFR 1910 & 1926) are part of this contract. In the event of a conflict, the more stringent requirements will take precedent. All requirements of EM 385-1-1, in its most recent edition, with all amendments to date, for all submissions, shall be complied with fully by the contractor and all subcontractors at all tiers.

8.3 Specifications/Scopes of Work: For Design-Build projects, if preparation of separate written “book” specifications sets is not included as a requirement of the task order, then the contract specifications shall be located on the drawings. Contract specifications on drawings shall not be abbreviated unless prior approval from the Contracting Officer allows such abbreviations. The contract specifications will be Division 1 Specifications found in Attachment B and the Unified Facilities Guide Specifications required for the individual task order(s). LEED specifications are always required for all task orders unless otherwise specifically identified in the scope of work and/or directed in writing from the Contracting Officer. Specification section substitutions using industry guide specifications may be considered on a case-by-case basis, but only if prior approval is obtained from the Contracting Officer. Other guide specifications (industry standards) may be directed or required by the Government based on individual project needs. The DOD Unified Facilities Guide Specifications can be obtained from the website at:

http://www.hnd.usace.army.mil//techinfo/gspec.htm

8.4 Work Hours: Work hours shall be eight hour long (eight hours of actual work), five days per week, with a standard work shift starting at 7:00 a.m. local time or as specified in individual task orders or as directed by the

Contracting Officer. No work shall be scheduled on weekends or Federal Holidays. Exceptions to these hours may be requested by the Contracting Officer in relation to a specific task order.

8.5 Personnel Security Clearances: Contractor key personnel and all required licensed professionals shall possess a current Top Secret (TS) security clearance based on a Single Scope Background Investigation completed within the last five years. The contractor's security clearances shall be passed to the U.S. Army Corps of Engineers Security Officer. These shall be provided to the Customer’s Security Manager prior to the commencement of performance of any task order. The Customer Security Manager Point of Contact (POC) shall be provided to the Government to facilitate direct communications on personnel security issues. The Government Project Manager (PM) shall be copied on all such communications. All contractor personnel performing under this contract shall be required to execute a Standard Form 312, REV 1-91, entitled "Classified Information Nondisclosure Agreement," prior to beginning work.

All personnel working under this contract shall be U. S. citizens.

8.6 Disclosure of Information: Performance under this contract may require the contractor to access data and information proprietary to a Government agency, another Government contractor, or of such a nature that its dissemination or use, other than as specified in the Statement of Work, would be adverse to the interests of the Government or others. Neither the contractor, nor contractor's personnel, shall divulge or release data or information developed or obtained during performance of this contract, except to authorize personnel or upon written approval of the Contracting Officer. The contractor shall not use disclose or reproduce proprietary data that bears a restrictive legend, other than as specified in this contract, or any information at all regarding any agency under this contract.

Disclosure of information regarding operations and services of any agency to entities not entitled to receive it and failure to safeguard any classified information that may come to the contractor (or any persons under the contractor's control) in connection with work under this contract may subject the contractor, contractor's agent, or employees to criminal liability under Title 18, Sections 793 and 798, of the United States Code (U.S.C.).

Neither the contractor nor the contractor's employees shall disclose or cause to be disseminated any information concerning the operations of any agency which could result in, or increase the likelihood of, the possibility of a breach of the agency's security or interrupt the continuity of its operations. The contractor shall direct to the Contracting Officer all inquiries, comments, or complaints arising from matters observed, experienced, or learned as a result of or in connection with, the performance of this contract, the resolution of which may require the dissemination of official information. The contractor shall not release any information, including photographs, files, public announcements, statements, denials, or confirmations, or marketing materials on any part of the subject matter of this contract or any phase of any program hereunder without the authorized prior written approval of the Contracting Officer.

The contractor shall not release information regarding individuals without authorized prior written consent of the Contracting Officer. All documents showing individuals' names or other personal information, including Social Security Numbers, shall be controlled and protected. The provisions of the Privacy Act of 1974, Public Law 93-579, 5 U.S.C., Section 552a, shall apply. All products, deliverables, and documents developed under this contract shall be considered to be classified at a minimum level of “Unclassified/For Official Use Only.”

Local Provisions

1.0 Services to be Furnished:

The contractor shall provide all management, supervision, labor, materials, tools and equipment necessary for the performance of all work in relation to this contract in direct support of the Real Property Services Field Office

(RSFO), Baltimore District, U.S. Army Corps of Engineers, in accordance with the Scope of Work, and as required.

The services to be provided shall be priced in accordance with the most recent RS Means Cost Data publications listed and the coefficient pricing factors as indicated in this section and as otherwise required.

2.0 Coefficient Factors:

Any Division 1 line items that reference line items in other RS RS Means Divisions (2 – 44) shall not be considered Division 1 costs and shall not be included in the coefficients. Division 1, dated April 27, 2015, is to be used in the resultant contract.

2.1 The purpose of coefficient based pricing is to permit the Government and the contractor to quickly arrive at a fair and reasonable firm fixed price for the requirements that fall under this contract. All RS RS Means Division 1 line items NOT specifically excluded from the coefficients shall be included in the coefficients. There will not be a separate annual escalated coefficient rate. The coefficient rates negotiated at time of contract award will be used throughout the life of the contract. The coefficients shall include all costs listed in RS RS Means Division 1 with the following exceptions:

Food Service and Kitchen Consultants, Educational Facility Consultants, and Elevator and Conveying Systems Consultants services, as referenced in Division 1, are not contained within the coefficient and will be treated as non-pre-priced line items on a per task order basis.

Non-Contractor Generated Hazardous Materials or Waste (including asbestos, lead paint and mold) will be addressed as follows:

Surveys and Soil Investigations will be treated as non-pre-priced line items on a per task order basis and shall not be included in coefficients.

Abatement, Decontamination, Encapsulation, or Removal are pre-priced line items contained in Division 2 of RS RS Means.

Rubbish Removal as defined in RS RS Means Division 1, Section 01 74, line item 01 74.13.20.0200 is not included in the coefficient and shall be included as Division 2 pre-priced line items.

Any design on Shipyards, Waterways, Marine Construction, Floating construction, Railway construction, Security Vehicle barriers, Traffic signal systems, Vehicle guide rails, Fixed vehicle delineators, and Rail Track construction line items, as defined by Division 34 (only) – Transportation – of RS RS Means and Division 35 (only) – Waterway and Marine of RS RS Means, is excluded from the coefficients and will be treated as non-pre-priced line items for surveys, plans, and design deliverables under design build task orders.

All Models, Photographic Documentation (if allowed by site Security Officers), Renderings, and Temporary Security line items as defined by Division 1 section 11 31.50 (Models), 11 31.75 (Renderings), 32 33.50 (Photographs), and 56 32.50 (Watchmen) of RS RS Means shall be excluded from the coefficients and shall be priced as a pre-priced line item on a per task order basis.

Deletion of Division 1 line item 01 52 13 20.5000, Air Supported structures. Air Supported structures shall not be used for Office or Storage space as defined in Division 1 and are not included in any coefficients.

Any design or construction work items under Division 01, section 91 13.50, Commissioning (only), of RS RS Means, is excluded from both the construction and the design build coefficients and will be treated as non-pre-priced line items on a per task Order basis. NOTE: This exception does not include any work associated with Contract Specification Section 01 78 00, Closeout Submittals, or Contract Specification Section 01 33 29, LEED Documentation.

Design and Consulting services as referenced in Division 1 will remain the same. Any additional effort of design and consulting services necessary either as an added design deliverable as identified in the SOW for the task order or as necessary during the life of the task order (i.e. re-design not due to contractor performance) are not contained within the coefficient. These will be treated as negotiable hours against pre-priced line items as per Architectural Engineer Price Schedule (AEPS). Reproduction of the extra copies will be treated as pre-priced line items as per AEPS. NOTE: Design and Consulting Services for Design- Build task orders are to be included in the coefficient and will not be negotiated separately.

2.2 Compliance with Division 1 Specification Sections 01 30 00 through 01 86 26.07 40 (inclusive), as found in Attachment B, are included in the coefficients. The coefficients shall include all work listed in UFGS Division 1.

2.3 Travel and per diem costs for all projects shall be determined on an individual task order basis as a separate line item cost to be reimbursed in accordance with Joint Travel Regulations and shall not be applied to any coefficient. It is generally not the intention to include travel and per diem in these task orders unless specifically identified in the SOW, it should be implied that it will not be paid. If the contractor believes travel and per diem are necessary and it is not included in the SOW, the contractor may ask permission from the Contracting Officer for inclusion.

2.4 The coefficient(s) for Design-Build task orders shall contain the LEED requirements to be certifiable and meet the level for Silver. Higher level (Gold, Platinum, etc.) and full accreditation (via USGBC) shall be priced as a non pre-priced line item if required by the scope or work for the individual task orders.

3.0 Task Order Pricing:

3.1. For each task order, the contractor shall make a site visit prior to completing their proposal. A field survey of the project shall be included with the proposal.

3.2. The task order firm fixed-price shall be arrived at by adding all of the RS MEANS line items and multiplying that total by the appropriate coefficient. The RS MEANS lines item totals are arrived at by multiplying the RS Means unit cost from the “including Overhead and Profit” column by the Number of Units.

4.0 Pricing Methods:

4.1. RS RS Means Pricing. Utilize RS RS Means line item cost from the “Total with Overhead and Profit” column.

This method is required unless requested and approve by the Contracting Officer prior to submission of proposal.

4.2. Alternate Price Method (Pre-Priced). Where a suitable match between the cost items required and those published in RS Means may not be found, combining labor from one published item with the materials and equipment from another may arrive at a fair and reasonable cost. In these cases the proposal construction line item shall be presented as a pair of construction items, with the descriptions amended to note: “Labor only” and “Material only” along with the RS Means reference numbers to permit the Government to evaluate the applicability of the item to the intended construction scope. Each line of the pair shall include its published proportion of overhead and profit. The selected RS Means line item shall be subject to Government approval. The alternate price method shall not be used when a suitable approximate or edited RS Means line item is available. Cost items derived in this manner must be delineated as required. A minimum of 90% of the total construction proposal cost must be calculated using RS Means pre-priced cost line items. The appropriate pre-priced coefficient applies to any line item utilizing this method.

4.3. Approximate Price Method (Pre-Priced). Where a suitable match between the cost items required and those published in RS Means may not be found, an item that closely matches may be substituted with the concurrence of the Government. The work item selected must be the closest match available from the RS Means published data as approved by the Contracting Officer. Cost items derived in this manner must be delineated as required. A minimum of 90% of the total construction proposal cost must be calculated using RS Means pre-priced cost line items. The appropriate pre-priced coefficient applies to any line item utilizing this method.

4.4. Edited Price Method (Pre-Priced). Where a suitable match between the cost items required and those published in RS Means may not be found, an edited line item may be substituted. The edited method is similar to the approximate method except that the description of the work is edited to match the required construction, as approved by the Contracting Officer. Each line shall include its published proportion of overhead and profit. Cost items derived in this manner must be delineated as required. A minimum of 90% of the total construction proposal cost must be calculated using RS Means pre-priced cost line items. The appropriate pre-priced coefficient applies to any line item utilizing this method.

4.5. Non Pre-Priced Method. Where a suitable match between the cost items required and those published in RS RS Means may not be found, the contractor may propose a unit cost by using a non pre-priced item. Non pre-priced items shall be supported by three responsive bids. Non pre-priced items that encompass scopes larger than line items (i.e. trade bid) shall be considered non-responsive. Non pre-priced line items exceeding 10% of the price of the task order must be approved in advance by the Contracting Officer. Unit costs established other than by RS Means pre-priced unit costs must be clearly identified to the satisfaction of the Government or they will be disallowed.

4.6 Architect Engineer Price Schedule (AEPS). Utilize AEPS line item costs for additional design and consulting services if additional Architect and Engineering services are necessary as identified in the SOW or as authorized by the Contracting Officer.

The total of the non pre-priced total line item costs shall not exceed 10% of the total proposal cost of each task order.

NOTE: This method shall be used in modifications if the Contracting Officer authorizes re-design efforts. If the non-prepriced items exceed 10%, written permission from the Contracting Officer must be given.

5.0 Period of Performance:

5.1 The period of performance of the base contract shall be five years from the date of the contract award.

5.2 Task orders may be issued under this contract during the entire performance period. Expiration of the performance period during which orders may be issued shall not affect any order placed prior to the expiration of such period. Terms of the contract shall remain in full force and effect in their application to such task orders for the life of the task order.

5.3 Periods of Performance for each task order shall be identified in the scope of work. Failure to meet contract deadlines and milestones shall be reflect in the contractor’s evaluation of performance on both the task order and the overall contract. Additional remedies as allowed by the FAR clauses may be utilized to include the assessment of liquidated damages. Amount of liquidated damages will be included in each task order.

6.0 Place of Performance:

6.1 The place of performance for the base contract is primarily located in the Washington/Baltimore area, but may be used throughout the Continental United States (CONUS) and Hawaii.

6.2 It is estimated that 80% of the task orders issued on this contract will be issued within the Washington/Baltimore area. It is anticipated that the other 20% of the task orders will be issued outside of that area.

6.3 There is no cost differential for location. The national average of 1.0 shall be used on all task orders.

7.0 Task Order Proposal Preparation:

7.1 Task orders shall be initiated with a Request For Proposal (RFP) signed by the Contracting Officer, which includes the Government’s Statement of Work (SOW). Following issuance of the RFP, the Government will schedule a new task order meeting. The initial meeting shall be attended by Contractor personnel with sufficient experience to permit a meaningful meeting. At the meeting, the Government Project Manager (PM) shall review the Scope of Work (SOW) with the contractor. The SOW may consist of anything from a list of project performance objectives to a set of 100% construction drawings. At the conclusion of the initial meeting the contractor and the Government shall agree on the schedule for the next step in the project development process. The contractor shall perform a pre-proposal field survey to ascertain the conditions present at the construction site that may impact the scope, schedule, or budget. This site visit shall be documented by the contractor and presented to the Government for review and approval with the contractor’s proposal and prior to issuing any task order. It shall describe any assumptions that the contractor used in developing their proposal. Costs for all pre-task order work, site visits, and proposals shall be included within the contractor’s coefficients.

7.2 The Design-Build coefficients shall include all design type costs for each task order. This includes, but is not limited to, project managers, CADD operators, word processors, and all other disciplines and services required to provide design type deliverables.

7.3 Task order proposals shall include all necessary work to provide the Government with a fully functional facility which is suitable for its intended purpose, as determined by the Contracting Officer.

7.4 Design-Bid-Build Task Orders. The Contractor shall prepare a firm fixed priced proposal to satisfy the scope of work. The proposal will be based on “pre-priced” method as described above unless a different method is approved by the Contracting Officer. The proposal shall reflect the Statement of Work and the site visit and field survey. The proposal shall utilize the appropriate Design-Bid-Build coefficient applied to the line item costs. The proposal shall be submitted to the Government by the date required in the Request for Proposal letter. The total of the non pre-priced total work item costs shall not exceed 10% of the total proposal price. The task order will be issued as a firm-fixed priced task order.

7.5 Design-Build Task Orders. The Contractor shall prepare a firm fixed priced proposal to satisfy the scope of work. The proposal will be based on “pre-priced” method as described above unless a different method is approved by the Contracting Officer. The proposal shall reflect the Statement of Work and the site visit and field survey. The proposal shall utilize the appropriate Design-Build coefficient applied to the line item costs. This proposal may also include a list of betterments as described in the contract clauses. The proposal shall be submitted to the Government by the date required in the Request for Proposal letter. The non pre-priced work item costs shall not exceed 10% of the total proposal price. The task order will be issued as a firm-fixed priced task order.

The design deliverables portion of the work shall be executed by professional architects and engineers licensed and be qualified to do business in the jurisdiction scheduled to receive the Construction work. The design deliverables produced shall be detailed as required by the scope for each task order. The design deliverables shall meet all CADD standards applicable and required by the Government for each task order. During the process of providing the design deliverables, the contractor shall promptly alert the Government of any requests by the Government that will cause the construction cost or schedule to increase beyond that in the initial construction proposal. When so notified, the Government shall either, a) reject the change in scope requested by the Government, b) offset the cost increase with a corresponding decrease in other areas of the project scope to return to budget or c) issue a change order altering the project cost or schedule.

7.6 The contractor shall transmit proposals electronically, by RS Means of e-mail, computer disk, or network connection. Electronic transmissions shall be readable using Microsoft Office, Microsoft Excel, or other approved software. CDs shall be appropriately labeled as to the classification of the CD, the contract number and title of project. Drawings shall be transmitted via CDs only unless otherwise directed by the Government.

7.7 The contractor shall use the Government contract number, task order number, and task order name to identify all proposals, submittals, and any other documents submitted to the Government. Any document (including invoices) submitted without this required information will result in rejection of the document and return to the contractor for correction. Rejection of a document for not containing the above required information shall not be the basis for any claim against the Government.

7.8 Upon receipt of the contractor’s proposal, the Government shall review the proposal for completeness, accuracy, and reasonableness. The Government may accept the proposal as stated or negotiate any aspect of that proposal. The Government shall negotiate with the contractor all non pre-priced items and any exceptions to the performance period required by the Government’s schedule. Task orders will be issued by the Contracting Officer.

7.9 Each proposal by the contractor shall include the following information:

Date of the proposal Contract number and name of project Item number and description, quantity, and unit prices for pre-priced, alternate priced, approximate priced, edited priced, and non pre-priced items, including all appropriate multipliers and coefficients; and the total task order price

Commencement date and task order performance length Preliminary project schedule Certificate of Current Cost and Pricing Data (if the task order is greater than $700,000.00) Any other pertinent data

8.0 Emergency Ordering Procedures:

8.1 When an emergency occurs, the contractor shall adhere to the following: When the development of a situation or problem arises at any time which jeopardizes the operation of the customer’s facilities and is within the geographic boundaries covered under this contract, the contractor shall be required to respond to the needs of the Government within two hours following telephonic notification. This may occur at any time in any twenty-four hour period. To accomplish this, the contractor will provide the Contracting Officer a number at which he/she can be reached on a 24 hour a day basis.

8.2 If directed by the Contracting Officer, verbally or in writing, to mobilize immediately, the contractor shall, within four hours mobilize efforts to accomplish the needs of the Government as created by the emergency.

Immediately following the emergency being stabilized, the contractor shall provide a written proposal to the Government. The Government shall negotiate and issue the task order as soon as possible.

9.0 Government Furnished Property:

If Government furnished property will be issued, this will be identified in the scope of work for the specific task order. If this is the case, the contractor shall be responsible for the pick-up and transportation of all

Government furnished property. The contractor assumes the risk and responsibility for the loss or damage to Government furnished property upon issuance of a written receipt at time of turn over to the contractor by the Government. The contractor shall follow the instructions of the Contracting Officer’s Representative (COR) regarding the disposition of all Government-furnished property not consumed in performance of a task order.

The cost of transporting Government furnished equipment shall be included as a line item in the proposal.

10.0 Schedule:

10.1 The period of performance for each project will be identified in the Request for Proposal and is negotiable.

10.2 If mission requirements dictate, the Contracting Officer may, at his/her discretion, unilaterally determine the required schedule…