Questions and Answers_W912DQ26QA039.pdf

PDF 63 KB Posted

Attached to
Harlan County Lake Mowing
Solicitation number
W912DQ-26-Q-A039
Issued by

About this file

This is a Contractor Questions and Answers document for federal contract opportunity W912DQ26QA039 regarding Harlan County Lake Mowing services, issued on 05 May 2026.

The document addresses five contractor inquiries related to the solicitation. The current contract number for this requirement is W912DQ-21-P-1070, with incumbent contractor information and historical award details available in the existing contract documentation. Regarding pricing methodology, contractors must submit the total seasonal estimate calculated by multiplying the rate per acre by 13 mowing occurrences, as clarified in the revised supplemental bid sheet. For equipment requirements, contractors are responsible for understanding the Performance Work Statement (PWS) specifications and providing all necessary equipment to complete the mowing work, including specialized slope mowers required for dam maintenance. The document does not provide specific response deadlines, award amounts, contract period of performance, or incumbent contractor names within the Q&A itself, instead referring respondents to the current contract file and supplemental bid sheets for this information.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912DQ26QA039 – Harlan County Lake Mowing

Contractor Questions & Answers

05MAY2026

1. Q: What is the current contract number?

A: W912DQ-21-P-1070

2. Q: What is the name of the incumbent Contractor?

A: Information is available in the current contract

3. Q: What is the total award amount and contract period of performance for the most recent award?

A: Information is available in the current contract

4. Q: Regarding the "total estimate per season" field, please confirm if I should enter the total seasonal amount—calculated as the rate per acre multiplied by 13 mowings—rather than the rate for a single occurrence.

A: See revised supplemental bid sheet.

5. Q: As the dam requires the use of specialized slope mowers, should these be included in the list of required machinery?

A: The contractor must understand the requirement and provide the necessary equipment to complete the job per the PWS.