Webinar Slides presented on 20241219.pdf
PDF 2 MB Posted
- Solicitation number
- W912DQ25SSJCMC
About this file
This is a set of presentation slides from an industry webinar about a major VA hospital replacement project in St. Louis, MO. The slides detail plans for replacing the bed tower, clinical expansion, and parking garages at the VA John J. Cochran Division facility, with an estimated FY26 appropriation of $1.6B.
The project will use an Integrated Design and Construction (IDaC) delivery method, with key milestones including advertising an AE SATOC contract in Q4 FY25, FY26 VA appropriation in Q2 FY26, and IDaC solicitation in Q4 FY26. The scope includes a new seismically designed inpatient tower, central energy plant, IT/engineering/admin facilities, substance abuse clinic, elevated parking, water storage, and demolition of aged buildings. The project timeline extends from FY24 through FY34, with preconstruction services beginning after 15% design completion. The procurement will use a fixed price incentive concept with government/contractor risk sharing. The webinar was scheduled for December 19, 2024, with sources sought responses due by January 6, 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Summary of IDAC Delivery Method.pptx | PPTX presentation |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA JOHN J COCHRAN DIVISION, ST LOUIS, MO
REPLACE BED TOWER, CLINICAL EXPANSION, & PARKING GARAGES
AE SATOC Industry Webinar
Kansas City District Hamze Fares, PMP VA Program Manager
David Walsh Contracting Officer Chief, Military Contracting
December 2024
Controlled by: USACE Controlled by: CENWK-PMG POC: Hamze Fares, 816-389-3306
2VA JOHN COCHRAN DIVISION, ST. LOUIS, MO
REPLACE BED TOWER, CLINICAL EXPANSION & PARKING GARAGE
VA PROGRAM OVERVIEW
VA St. Louis Health Care System is a full-service health care facility providing inpatient and ambulatory care in medicine, surgery, psychiatry, neurology, and rehabilitation, as well as over 65 subspecialty areas.
It is a two-division facility that serves veterans and their families in east central Missouri and southwestern Illinois.
The John Cochran (JC) Division is located in midtown St. Louis at 915 N Grand Blvd near its affiliated medical schools - St. Louis University and Washington University. It has all of the medical center’s operative surgical capabilities, the ambulatory care unit, and a six-story Clinical Addition that includes surgical facilities, intensive care units, outpatient psychiatry clinics, and expanded laboratory.
The DVA Major Project 657-309 at the JC Division will address a variety of issues including: patient safety and privacy, physical security, mission critical mandates, building seismic deficiencies, facility condition deficiencies, and lack of on-site parking; all working to improve and “right-size” the medical center. Many existing inpatient functions will be relocated into a new seismically designed bed tower.
Scope: New work includes a Seismically Designed Inpatient Tower, Central Energy Plant, IT/Engineering/Admin Facilities, Substance Abuse Clinic, Elevated Parking, Water Storage (96hr Supply) and Demolition of Aged/Deficient Ancillary Buildings.
SD
-1
S ite
P la n
PROJECT AUTHORIZATION
2010 Requirements Gathering $43.34M
2022 CA $92.00M
Pending FY26 Appropriation $1.6B
KEY MILESTONES
Advertise AE SATOC 4QFY25
FY26 VA Appropriation 2QFY26
FY26 VA Authorization 4QFY26
IDaC Solicitation 4QFY26
IDaC Award Design Resumes 3QFY27
JC
D iv is io n
-9
N G ra nd
B lv d
KEY DESIGN EFFORTS
Project Book 2019 Economic Analysis (TO1) 2020 Concepts (TO2) 2021 Schematic Design Level 1 (SD-1, TO3) 2022 Hazardous Material Surveys (TO4) 2022 Early Work Items (TO5) 2023 EWI AE Services during construction (TO7) 2024 NE Parking Structure DB RFP Development (TO8) 2025
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Real Estate Demo
Relocation 54" Waterline
Utilities & Streets
ICT Swing Space
Temp Govt Facilities
VA Swing Space
West Campus Demo
Opioid Treatment Clinic
East Site Work
Construction:
Acquisition:
Design:
RLF SATOC:
Activation:
Award:
FY24
New A/E SATOC
ID
aC
(P ha se
Pre-Construction Services &
Construction Options
Sm al l B us in es s
Co ns tru ct io n se
A)
Sm al l Bu si ne ss
Co ns tru ct io n se
B)
Northeast Parking Garage
FY26 FY31 FY34
FY34
FY30FY25 FY32 FY33
FY24 FY25 FY33FY27 FY28 FY29 FY30 FY31 FY32FY26
FY27 FY28 FY29
SD-
Waterline Relocation
Impacts & Ameren
DD-2 CDs
CLIN0002 CUP & Motor Pool & Eng Bldg.
CLIN0004 South Garage
Temp
ICT
VA Sw ing
West Campus
Design NE Prk Grg
OTP
East Sitew eork
CLIN0003 Bed Tow er
Design
Design
- FY26 Authorization & executed 7600b.- RLF 5 year SATOC base expires.
- FY26 Approriation
AdverPlan
AdvertisePreco
VA JOHN COCHRAN DIVISION, ST. LOUIS, MO
PROGRAM SCHEDULE
COA - Hard Stop
HARD STOP COA - PROJECT SCHEDULE
Fiscal Year FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
Quarter 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
USACE Temp Space Lease
RLF SATOC
Small Business Construction (Phase 1) Real Estate Demo
Relocation 54" Waterline
Utilities & Streets
Temp Govt Facilities
ICT Swing Space
VA Swing Space Facilities
West Campus Demo
| IDaC | |
| (Phase 2) | PreConstruction / Constr. |
Small Business Construction (Phase 3) NE Garage and Paving
Opioid Treatment Program
East Site Work
FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
Construction :
Acquisition :
Design :
RLF SATOC :
Activation :
Award :
- RLF 5 year option SATOC expires.
- FY26 Authorization & executed 7600b.
- RLF 5 year SATOC base expires.
SD-2
Demo
Waterline Relocation
Impacts & Ameren
DD-2
CDs
CLIN0001 CUP & Motor Pool & Eng Bldg.
CLIN0003 South Garage
Temp Gov't
ICT Swing Space
VA Swing Space
West Campus Demo
Design
NE Prk Grg
OTP
East Siteweork
CLIN0002 Bed Tower
DO NOT EXERCISE
Temp Gov't Leased Space
Design
Design
- FY26 Approriation
COA - SATOC
HARD STOP COA - PROJECT SCHEDULE
Fiscal Year FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
Quarter 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
USACE Temp Space Lease
RLF SATOC / New SATOC
Small Business Construction (Phase 1) Real Estate Demo
Relocation 54" Waterline
Utilities & Streets
Temp Govt Facilities
ICT Swing Space
VA Swing Space Facilities
West Campus Demo
| IDaC | |
| (Phase 2) | PreConstruction / Constr. |
Small Business Construction (Phase 3) NE Garage and Paving
Opioid Treatment Program
East Site Work
FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
Construction :
Acquisition :
Design :
RLF SATOC :
Activation :
Award :
- RLF 5 year option SATOC expires.
- RLF 5 year SATOC base expires.
SD-2
Demo
Waterline Relocation
Impacts & Ameren
DD-2
CDs
CLIN0001 CUP & Motor Pool & Eng Bldg.
CLIN0003 South Garage
Temp Gov't
ICT Swing Space
VA Swing Space
West Campus Demo
Design
NE Prk Grg
OTP
East Siteweork
CLIN0002 Bed Tower
Advertise
Temp Gov't Leased Space
Design
Design
SATOC Plan
COA - NE Garage
HARD STOP COA - PROJECT SCHEDULE
Fiscal Year FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
Quarter 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
USACE Temp Space Lease
RLF SATOC / New SATOC
Small Business Construction (Phase 1) Real Estate Demo
Relocation 54" Waterline
Utilities & Streets
Temp Govt Facilities
ICT Swing Space
VA Swing Space Facilities
West Campus Demo
| IDaC | |
| (Phase 2) | PreConstruction / Constr. |
Small Business Construction (Phase 3) NE Garage and Paving
Opioid Treatment Program
East Site Work
FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
Construction :
Acquisition :
Design :
RLF SATOC :
Activation :
Award :
SD-2
Demo
Waterline Relocation
Impacts & Ameren
DD-2
CDs
CLIN0001 CUP & Motor Pool & Eng Bldg.
CLIN0003 South Garage
Temp Gov't
ICT Swing Space
VA Swing Space
West Campus Demo
Design
NE Prk Grg
OTP
East Siteweork
CLIN0002 Bed Tower
Temp Gov't Leased Space
Design
Design
- RLF 5 year option SATOC expires.
- FY26 Authorization & executed 7600b.
- RLF 5 year SATOC base expires.
Advertise
SATOC Plan
COA - ICT
FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33 FY34
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
New A/E SATOC
Small Business Construction (Phase 1A) Real Estate Demo
Relocation 54" Waterline
Utilities & Streets
ICT Swing Space
Northeast Parking Garage
Small Business Construction (Phase 1B) Temp Govt Facilities
VA Swing Space
West Campus Demo
| IDaC | |
| (Phase 2) | Pre-Construction Services & Construction Options |
Opioid Treatment Clinic
East Site Work
FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33 FY34
Construction:
Acquisition:
Design:
RLF SATOC:
Activation:
Award:
Waterline Relocation
Impacts & Ameren
DD-2
CDs
CLIN0002 CUP & Motor Pool & Eng Bldg.
CLIN0004 South Garage
Temp Gov Office
ICT
VA Swing Space
West Campus Demo
Design
NE Prk Grg
OTP
East Siteweork
CLIN0003 Bed Tower
Design
Design
- FY26 Authorization & executed 7600b.
- RLF 5 year SATOC base expires.
- FY26 Approriation
Advertise
Plan
Advertise
Precon Plan
COA - SD2
HARD STOP COA - PROJECT SCHEDULE
Fiscal Year FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
Quarter 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
USACE Temp Space Lease
RLF SATOC
Small Business Construction (Phase 1) Real Estate Demo
Relocation 54" Waterline
Utilities & Streets
Temp Govt Facilities
ICT Swing Space
VA Swing Space Facilities
West Campus Demo
| IDaC | |
| (Phase 2) | PreConstruction / Constr. |
Small Business Construction (Phase 3) NE Garage and Paving
Opioid Treatment Program
East Site Work
FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
Construction :
Acquisition :
Design :
RLF SATOC :
Activation :
Award :
Demo
Waterline Relocation
Impacts & Ameren
DD-2
CDs
CLIN0001 CUP & Motor Pool & Eng Bldg.
CLIN0003 South Garage
Temp Gov't
ICT Swing Space
VA Swing Space
West Campus Demo
Design
NE Prk Grg
OTP
East Siteweork
CLIN0002 Bed Tower
Temp Gov't Leased Space
Design
Design
- RLF 5 year option SATOC expires.
- RLF 5 year SATOC base expires.
COA - IDaC PCS
HARD STOP COA - PROJECT SCHEDULE
Fiscal Year FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
Quarter 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
USACE Temp Space Lease
RLF SATOC
Small Business Construction (Phase 1) Real Estate Demo
Relocation 54" Waterline
Utilities & Streets
Temp Govt Facilities
ICT Swing Space
VA Swing Space Facilities
West Campus Demo
| IDaC | |
| (Phase 2) | PreConstruction / Constr. |
Small Business Construction (Phase 3) NE Garage and Paving
Opioid Treatment Program
East Site Work
FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33
Construction :
Acquisition :
Design :
RLF SATOC :
Activation :
Award :
Demo
Waterline Relocation
Impacts & Ameren
DD-2
CDs
CLIN0001 CUP & Motor Pool & Eng Bldg.
CLIN0003 South Garage
Temp Gov't
ICT Swing Space
VA Swing Space
West Campus Demo
Design
NE Prk Grg
OTP
East Siteweork
CLIN0002 Bed Tower
Temp Gov't Leased Space
Design
Design
- RLF 5 year option SATOC expires.
- RLF 5 year SATOC base expires.
VA SWING
SPACE
CUP
IDaC Option 1
BED TOWER
IDaC Option 2
NE PARKING
GARAGE
EXISTING
NORTHWEST
PARKINGGARAGE
SOUTH PARKING
GARAGE
IDaC Option 3
OTPCLINIC
EXISTING HOSPITAL
EAST SITE
WORK
SPINALCORD INJURYCENTER
PARKINGGARAGEBELOW Small Business Set Asides
Integrated Design & Construction
WEST CAMPUS BUDILING DEMO
COMMERCIAL AND RESIDENTIAL PROPETY DEMO
AWARDED - UNDERWAY
WATERLINE RELOCATION
STREETS VACATED & REPAIR WORK
ICT SWING SPACE
EXISTING SITE & EARLY WORK
Small Business Set Asides – Early Work Items
SOUTHWEST AERIAL VIEW
VA JOHN COCHRAN DIVISION, ST. LOUIS, MO
SCHEMATIC DESIGN
TRADITIONAL VS ECI DELIVERY METHODS
AE
Bid
Fixed Price Incentive Construction
Finish
AE
PreCon Svcs
Firm Fixed Price Construction Finish
AE
PreCon Svcs Non-Traditional Administration Fast Tracking Cost Accounting Standards Earned Value Mgmt System
Firm Fixed Price Construction Bid
Bid
Traditional FFP Administration
Integration Collaboration Cost Schedule Quality Shared Risk
FinishFirm Fixed Price Construction
PRECONSTRUCTION SERVICES
-Preconstruction Services include:
-Consultation in construction methodology, current market conditions and identification of coordination issues;
-Construction cost estimates -to validate designer prepared estimates at each review phase -for alternative designs and materials -for changed market conditions
-Cost control when there is a significant difference or the construction estimate exceeds the target, the estimates will be examined to determine the cause for the differences and steps made to correct the Government or contractor estimates
NOTE: The contractor shall not be responsible for any design services.
The responsibility of the design will remain wholly with the Designer of Record.
AE Contract 15% Design 35% Review 65% Review 95% Review 100% Complete
Construction Contract … Issue RFP to convert Option
PreConst Services Construction
FIXED PRICE INCENTIVE CONCEPT
Government point of view As cost decreases, price to the
Government decreases Share the risk of cost increase Ceiling Price limits the
Government’s exposure
Contractor point of view Contractor can increase profit dollars and profit percentage by reducing cost below target cost
Share Ratio above target price provides risk mitigation to the Contractor
THANK YOU!
SOURCES SOUGHT CLOSES ON
JANUARY 6, 2025
What experiences or ideas do you have that may contractually encourage an A-E DOR to collaborate and be open to cost saving changes proposed by a third-party construction contractor?
| VA John J Cochran division, st louis, MO�Replace Bed tower, clinical expansion, & parking garages |
| VA JOHN COCHRAN DIVISION, ST. LOUIS, MO �REPLACE BED TOWER, CLINICAL EXPANSION & PARKING GARAGE |
| Slide Number 3 |
| Slide Number 4 |
| Traditional vs ECI Delivery Methods |
| Preconstruction services |
| Fixed Price Incentive concept |
| Thank you!��Sources sought closes on�January 6, 2024��What experiences or ideas do you have that may contractually encourage an A-E DOR to collaborate and be open to cost saving changes proposed by a third-party construction contractor? |
File details come from the government source that posted it. Updated .