Bidder Inquires and Answers-Overton Chute.pdf
PDF 90 KB Posted
- Attached to
- Overton Chute Repairs
- Solicitation number
- W912DQ23B1037
About this file
This document contains bidder inquiries and responses regarding a federal construction contract opportunity for repairs to Overton Chute on the Missouri River. The U.S. Army Corps of Engineers, Kansas City District is seeking a contractor to perform work including repair and modification of control structures, construction of bank protection, road improvements, grading and excavation. The work consists of transport and placement of new stone by land-based equipment, with no dredging allowed. The solicitation is set aside for total small businesses, with one firm-fixed price award between $1-5 million anticipated. Inquiries covered contract terms, stage limits, mobilization costs, access routes and safety procedures for off-loading materials. Responses addressed where information could be found in specifications or clarified requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Inquiry Contractor Report All Inquiries
Project: IIJA Overton Chute Repair FY23 (sorted by CommentlD )
Review: Overton Construction Contract (00001)
Displaying 7 inquiries.
I Id II Discipline II Sheet II Detail II Spec 1102253ss I I Contracting II II II 01 30 00 Comment Classification
Paragraph 1.2 Time Extension for Unusually Severe Weather only mentions weather and provides anticipated weather days per month. If work is delayed for high river levels will additional time be subject to anticipated delay chart or be provided on day for day basis?
On: Apr 21 2023.
Government Response. . The information on stages limits is located in Section 35 35 00.00 23 Dikes and Section 35 35 0100 23 Revetments identify stage limits for construction. Stages above these limits will count as weather days in accordance with Section 01 30 00, paragraph 1.9 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. On:
May 01 2023
I llcurrent Request Status: Request Closed
I 11022539911
Contracting 11 11 II 01 11 00
Comment Classification:
This specification mentioned work stage limits being set forth in contract. But we have not found stage limites for work on this contract. Can these be provided?
On: Apr 21 2023.
I I
I I I
D Government Response. . Stage limits are available in Section 35 35 00.00 23 and Section 35 35 01.00 23 and also referenced within the notes on the Plans. On: May 01 2023 I
I I llcurrent Request Status: Request Closed
11022541411
Contracting II II II 01 22 00
Since there is no Mobilization/Demobil ization CUN item shall these be set up as a pay activity under one of the base CUN items? Does it matter which one?
On: Apr 21 2023. □ Government Response. . MobmzaUon and DemobmzaUon costs shall be ;ncorporated ;nto the various CLINs.
Separate pay activities for mobilization and demobilization will not be allowed. A separate pay activity for Bonding would be appropriate. On: May 01 2023
I llcurrent Request Status: Request Closed
11022542111
Contracting II CS304 - CS308 II
These sheets contain labels but show no cross sections
On: Apr 21 2023.
II
I IIGovernment Response . . An amendment has been issued to correct this error in the drawings. On: May 01 2023
I llcurrent Request Status: Request Closed
I 11 023033511 Civil II G002 II D6 II Comment Classification:
The access route shows crossing an at-grade railroad crossing. Will Railroad Flaggers be required when hauling?
On: Apr 25 2023.
I I I
I I
I
D Government Response. . Refer to SECTION 01 30 00 and SECTION 01 50 00, which requires coordination with Federal, State, and Local Authorities. This coordination includes potential need for flaggers On: May 01 2023
I I llcurrent Request Status: Request Closed
11023035811 Civil II II II 01 11 00
Comment Classification:
The Summary of Work states "No adjustments will be made to the contract price solely related to the approximate estimated quantities provided." Will adjustments to contract price be made in the event the existing bankline and riverbed differ from what's shown in the project plans?
On: Apr 25 2023.
D Government Response. . The information is located in contract clause 52.236-2 Differing Site Conditions, which is incorporated by reference. On: May 01 2023
I
11023041111 Civil II II II 35 31 24.00 23
The specifications state "Stone shall be off loaded directly onto bank near placement location ... " The bank lines on the island are steep and unstable, having loaded over-the-road rock trucks cross the chute and dump on the island bank lines will create safety concerns. Can rock for the island bank paving be stockpiled in the staging and storage area and hauled to the island with off-road equipment?
On: Apr 25 2023.
Government Response. . Safety is priority #1 and contractor shall refer to Section 01 35 26 Government Safety Requirements which includes ensuring stable slopes at work locations. Refer to Section 35 31 24.00 23, paragraph 2.1, which prohibits stockpiling of rock. On: May 01 2023
I
Report Complete
Patent 11/892,984 ProjNet property of ERDC since 2004.
I I I I
I I I I
File details come from the government source that posted it. Updated .