AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment: corrects boat ramp CLIN description; updates PWS to include the full AT/OPSEC w ording; includes insurance guidance; and updates Site Visit Location.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Apr-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DQ22Q1018

X 9B. DATED (SEE ITEM 11)

23-Mar-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

04-Apr-2022

CODE

USACE, KANSAS CITY +

FEDERAL BLDG, CT-C +

601 E 12TH ST RM 647

KANSAS CITY MO 64106-2896

W912DQ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0006

The CLIN description has changed from Boat Ramp Building Removal to Boat Ramp Removal.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

PERFORMANCE WORK STATEMENT

PERFORMANCE WORK STATEMENT:

STRUCTURE REMOVAL IN TALLEY BEND CAMPGROUND

HARRY S TRUMAN PROJECT OFFICE

8 March 2022

1. General: This is a service contract to provide the demolition and removal of structures in Talley Bend campground. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1. Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the demolition and removal of structures in Talley Bend campground as defined in this Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.

1.2. Scope: The contractor is responsible for the removal of 12 structures located in Talley Bend campground.

1.3. Period of Performance: All work shall be completed within 60 calendar days after award.

1.4. All work performed will be in accordance with EM 385-1-1 Safety and Health Manual (copy available at the Project Office). Contractor shall use personal protective equipment as required.

1.5. A representative sample of shingles and paint have been taken from each style of buildings to test for any hazardous materials, i.e., lead or asbestos. Samples have not shown any of the materials to harbor these contaminants.

1.6. General Information

1.6.1. Quality Control: The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. A written quality control plan will be reviewed prior to the start of the contract, and any changes to it as the contract progresses will be reviewed/approved by the COR.

1.6.2. Quality Assurance: The government shall evaluate the contractor’s performance under this contract. Quality Assurance will be conducted by the COR on the job site. Any deficiencies noted during these inspections will be pointed out to the contractor and remedied as soon as possible.

1.6.3. Hours of Operation: The contractor will perform the services Monday thru Friday from the hours of 0700 to 1600 hours. Deviation from this schedule must be scheduled and approved thru the

COR.

1.6.4. Place of Performance: The work to be performed under this contract will be performed at Talley

Bend campground on Harry S Truman reservoir.

1.6.5 Physical Security: The contractor shall be responsible for safeguarding all government equipment, information, and property. At the close of each work period, government facilities, equipment, and materials shall be secured.

1.6.6 Key Control: The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. No keys issued to the Contractor by the Government shall be duplicated.

The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer. At the end of the service contract the contractor shall return all keys issued back to the COR.

1.6.7 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office.The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.6.8 Contracting Officers Representative: The COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance: maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies;

coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates.

1.6.9 Key Personnel: The follow personnel are considered key personnel by the government: Rachel

Donatti, Lead Civil Engineer Tech; Dylan Roeder, Park Ranger, Recreation Program. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract.

1.6.10 Identification of Contractor Employees: All contract personnel attending meetings and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials.

1.6.11 Insurance: The Contractor shall procure and maintain during the entire period of performance under this contract the minimum amounts of insurance as specified in Section I of this contract. Proof of Insurance shall be submitted prior to the start of work.

PART 2

DEFINITIONS AND

ACRONYMS

2 DEFINITIONS AND ACRONYMS:

2.1 Definitions:

2.1.1 Contractor. A supplier or vendor having a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2 Contracting Officer. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note:

The only individual who can legally bind the government.

2.1.3 Contracting Officers Representative. An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 Defective Service. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5 Deliverable. Anything that can be physically delivered but may include non-physical things such as meeting minutes.

2.1.6 Key Personnel. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 Physical Security. Actions that prevent the loss or damage of Government property.

2.1.8 Quality Assurance. The government procedures to verify that services being performed by the

Contractor are performed according to acceptable standards.

2.1.9 Quality Assurance Surveillance Plan. An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10 Quality Control. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11 Subcontractor. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12 Workday. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.13 Work Week. Is defined as Monday through Friday, unless specified otherwise.

2.2 ACRONYMS:

AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTS Commercial Off the Shelf DA Department of the Army DOD Department of Defense FAR Federal Acquisition Regulation HIPAA Health Insurance Portability and Accountability Act of 1996 KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs

PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program QDR Quality Deficiency Report TE Technical Exhibit

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3 GOVERNMENT FURNISHED ITEMS AND SERVICES

3.1 Facilities: The Government will provide access to the buildings to be removed by this contract. The government will provide a key to the gates to these areas if requested by the contractor.

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4 CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES

4.1 General: The contractor will furnish all everything required to perform work under this contract that are not listed under Section 3 of this PWS.

4.2 Materials: The Contractor shall furnish any materials, supplies necessary to meet the requirements of the contract.

4.3 Equipment: The Contractor shall furnish any equipment needed or necessary to meet the requirements of the contract. Equipment required for this contract must be able to haul heavy loads of materials from the job site to an approved landfill. Other needs required would be busting large slabs of concrete into manageable pieces, tearing down of standing buildings/structures.

PART 5

SPECIFIC TASKS

5 Specific Tasks:

Basic Services: The contractor shall furnish all manpower and equipment to remove 12 structures Tally Bend campground.

5.1 The structures are listed and located as follows:

Talley Bend: one well house, one shower house, two playgrounds, six pit toilets, one park attendant booth, and one concrete boat ramp.

5.2 All structures shall be removed and hauled to an approved land fill.

5.3 Any concrete vault shall previously be pumped by gov’t contractors, and the vault lid shall be caved in by this contract. The vaults will be filled with local fill material designated by Corps personnel and shall be heaped to allow for any settling. No exposed concrete from either the lid or walls of the vaults will be exposed.

5.4 Any structure that has an open area underneath, will be used to bury concrete, masonry, or non-decomposable material. After filling, the area will need to have a minimum of 6” of soil placed on top of the fill and graded to blend in with the surrounding grade.

5.5 All previous shower house structures demolished have been found to have overly built concrete footings. These footings are generally four to five-foot reinforced concrete. These footings are considered clean fill and may be left in place. However, the top six inches will need to be removed to allow adequate soil placement to blend in with the surrounding grade. Design built plans for this structure will be provided upon request.

5.6 The Park attendant booth located in Talley Bend campground is located on an asphalt road.

The contractor shall avoid damage to the road while removing the structure. Local gravel material provided will be used to take the grade back up to the grade of the road.

5.7 The contractor is responsible for all work as specified in this PWS. Any deficiencies identified are the responsibility of the Contractor to correct immediately. Failure to correct the noted deficiencies will result in withholding of payment for the work not performed. Any soil disturbance will be smoothed out to prevent any tripping hazards.

5.8 The concrete boat ramp is located at the Talley Bend Day Use area and is just east of the functioning ramp. This concrete “high water” boat ramp is reinforced concrete approximately 25’ wide by 150’ long.

The ramp and associated concrete apron at the top of the ramp will be removed.

5.9 All pads/concrete sidewalks associated with each structure, shall be removed and taken to an approved landfill.

These will be identified by the COR.

PART 6

ATTACHMENT/TECHNICAL EXHIBIT LISTING

6 Attachment/Technical Exhibit List:

6.1 Attachment 1. Talley Bend Campground

6.2 Attachment 2. Talley Bend High Water Ramp

AT-OPSEC:

ANTITERRORISM/OPERATION SECURITY REQUIREMENTS

All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

Per the E-Verify Website the following exemptions apply:

Employers whose contracts are exempt from the E-Verify federal contractor rule are not required to enroll in E- Verify. A contract is considered exempt if any one of the following applies: (1) It is for fewer than 120 days. (2) It is valued at less than Simplified Acquisition Threshold ($250,000), the simplified acquisition threshold. (Source:

https://www.e-verify.gov/employers/federal-contractors/exemptions-and-exceptions).

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

SECTION H - SPECIAL CONTRACT REQUIREMENTS

The following have been added by reference:

52.228-5 Insurance - Work On A Government Installation JAN 1997

The following have been added by full text:

INSURANCE SPECIFIED

Required type of insurance listed in FAR 28.307-2, with the minimum amounts of liability indicated.

28.307-2 Liability.

(a) Workers’ compensation and employer’s liability. Contractors are required to comply with applicable Federal and State workers’ compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with a contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers. (See 28.305(c) for treatment of contracts subject to the Defense Base Act.)

(b) General liability. (1) The contracting officer shall require bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.

(2) Property damage liability insurance shall be required only in special circumstances as determined by the agency.

(c) Automobile liability. The contracting officer shall require automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

(d) Aircraft public and passenger liability. When aircraft are used in connection with performing the contract, the contracting officer shall require aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger liability, and $200,000 per occurrence for property damage. Coverage for passenger liability bodily injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

(e) Vessel liability. When contract performance involves use of vessels, the contracting officer shall require, as determined by the agency, vessel collision liability and protection and indemnity liability insurance.

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

The following have been added by full text:

52.237-1 SITE VISIT (APR 1984)

Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

(End of provision)

The following have been modified:

SITE VISIT INFORMATION

Site Visit will be held at 0900 on 06 April 2022 at Talley Bend Campground at 8950 NE Hwy C, Lowry City, MO 64763 the Project Office located at 15968 Truman Road Warsaw, MO 65355, (816) 389-3280.