B.08.03 W912DQ22B1011 AMENDMENT0003.pdf
PDF 392 KB Posted
- Attached to
- Tuttle Creek Rip Rap Placement Federal contract opportunity
- Solicitation number
- W912DQ22B1011
About this file
This amendment modifies a solicitation for a federal construction contract. The U.S. Army Corps of Engineers Engineering District Kansas City is seeking offers to perform riprap placement and debris removal on the upstream side of the Tuttle Creek Dam from station 30+00 to station 67+00. The amendment updates contract line item numbers, specifications, and drawings to address questions received from offerors. It extends the description of CLIN 0001 and modifies seeding, riprap gradation, shoring, and earthwork specifications. It also revises several drawings. Offerors must acknowledge receipt of this amendment in their bids. All other terms and conditions of the solicitation remain unchanged.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C.04.01 Abstract OF 1419 20220609.pdf | ||
| B.08.03 W912DQ22B1011 AMENDMENT0002.pdf | ||
| B.08.04 22 B 1011 amd 01.pdf | ||
| B.08.04 22 B 1011 amd 01 CS311.pdf | ||
| B.08.04 22 B 1011 amd 01 Outlet Channel Drawings.pdf | ||
| B.07.01 Site Visit Sign in.pdf | ||
| TC RIPRAP PH2 SPECS RTA.PDF |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to update the CLINs, specifications and draw ings to answ er questions received.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-May-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DQ22B1011
X 9B. DATED (SEE ITEM 11)
25-Apr-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-May-2022
CODE
USACE, KANSAS CITY +
CONTRACTING DIVISION FEDERAL BLDG CT 601 E 12
KANSAS CITY MO 64106-2896
W912DQ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DQ22B1011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
CLIN 0001
The CLIN extended description has changed from:
Includes all labor and equipment required to perform all work associated with placing riprap and removing debris on the upstream side of the dam from Sta 30+00 to Sta 76+00 and all related incidental work as outlined in specification section 01 22 00.00 10 and in accordance with contract documents.
To:
Includes all labor and equipment required to perform all work associated with placing riprap and removing debris on the upstream side of the dam from Sta 30+00 to Sta 67+00 and all related incidental work as outlined in specification section 01 22 00.00 10 and in accordance with contract documents.
(End of Summary of Changes)
The following items are applicable to this modification:
MODIFICATION CHANGES
The SOLICITATION is amended as follows:
NOTE: Deleted text is shown with strikethrough. Added text is shown with underline.
1. SPECIFICATIONS:
00 10 00 - Solicitation See amendment summary of changes for CLIN 0001
32 92 19
3.2.2 Seed Application Method
Seeding method must be drill seeding or hydroseeding unless otherwise specified.
3.2.2.1 Drill Seeding
Seeding must be drilled at a rate of 100200 pounds pure live seed per acre. Drill seed uniformly to average depth of 1/4 inch.
3.2.2 Hydroseeding
First, mix water and fiber. Wood cellulose fiber, paper fiber, or recycled paper must be applied as part of the hydroseeding operation. Fiber must be added at 1,000 pounds, dry weight, per acre. Then add and mix seed and fertilizer to produce a homogeneous slurry. Seed must be mixed to ensure broadcasting at the rate of 100200 pounds pure live seed per acre. When hydraulically sprayed on the ground, material must form a blotter like cover impregnated uniformly with grass seed. Spread with one application with no second application of mulch.
35 31 19 STONE PROTECTION
2.2.2 RIPRAP
The upper table is for “RIPRAP GRADATION FOR UPSTREAM SLOPE” and the lower table is for “RIPRAP GRADATION FOR OUTLET CHANNEL” Delete additional label at the lower table RIPRAP GRADATION FOR UPSTREAM SLOPE
3.8.3.2 Riprap
Gradation tests shall be performed in accordance with ASTM D5519, Test Method A. The Contractor shall perform gradation tests at the quarry. The sample shall be taken by the Contractor in the presence of the COR. The Contractor shall notify the COR not less than 3 days in advance of each test. In the event of the unavailability of the contracting office, the Contractor shall perform the tests and certify to the COR that the material shipped complies with the specifications. At least one gradation test shall be performed per 15,000 tons of riprap placed and shall be collected in a random manner which will provide a sample that accurately reflects the gradation arriving at the jobsite. The sample shall consist of not less than 25 tons of stone and shall be collected in a random manner which will provide a sample which accurately reflects the actual gradation arriving at the jobsite. The gradation tests shall be reported using the attached forms, GRADATION TEST DATA SHEET and ENG FORM 4055. The Contractor shall designate on the test form that portion, in tons, of the lot tested which is applicable to the contract. Any deviation from the reported tonnage shall be corrected and recorded on a revised GRADATION TEST DATA SHEET. Failure of the test on the initial sample and on an additional sample will be considered cause for rejection of the quarry and/or quarry process, and all riprap or bedding represented by the failed tests shall be set aside and not incorporated into the work. Any additional tests required because of the failure of an initial test sample will not be considered as one of the other required tests. If collected by the truckload, each truckload shall be representative of the gradation requirements. Certification and test results shall represent materials shipped from the quarry. Certification and test results must be received by the COR at the jobsite before the riprap is used in the work.
35 42 34
3.1 SHORING
Construct shoring in accordance with the safety requirements of EM 385-1-1. Submit drawings and calculations, certified by a registered professional engineer, describing the methods for shoring and sheeting of excavations at least 30 days prior to installation. Also include sequencing and methods of shoring installation and removal that will facilitate verification that the methods will not leave voids, seepage paths, or other deficiencies. The Contractor is responsible for design and maintenance of all shoring to be installed. Do not negatively impact existing and proposed work during installation. Unless otherwise authorized, remove all sheeting and bracing when backfill is completed. Do not negatively impact completed work during removal.
3.2 EARTHWORK
Bear the reinforced fill zone on undisturbed native soils, or acceptably placed and compacted fill. In the event that it is necessary to remove material or place fill below the excavation lines shown on the drawings, or not otherwise provided for in the contract, notify the Contracting Officer prior to work and an adjustment in the contract price will be considered in accordance with the contract. It is at the Contractor's expense if additional work not authorized by the Contracting Officer is performed.
Excavation
Excavate to contours, elevation, and dimensions indicated. Reuse excavated materials that meet the specified requirements for the material type required at the intended location. Keep excavations free from water. Excavate soil disturbed or weakened by Contractor's operations, soils softened or made unsuitable for subsequent construction due to exposure to weather.
Excavations below indicated depths will not be permitted except to remove unsatisfactory material. Remove as directed unsatisfactory material encountered below the grades shown.
Refill with satisfactory material and compact to 95 percent of ASTM D698 maximum density.
Replace satisfactory material removed below the depths indicated, without specific direction of the Contracting Officer, with satisfactory materials to the indicated excavation grade; except as specified for spread footings. Determination of elevations and measurements of approved overdepth excavation of unsatisfactory material below grades indicated will be done under the direction of the Contracting Officer. Perform excavation and fill in a manner and sequence that will provide proper drainage at all times. The Contractor is responsible for disposal of surplus material, waste material, and material that does not meet specifications, including any soil which is disturbed by the work operations or softened due to exposure to the elements and water.
Stockpiles
Stockpile material for backfilling in a neat and orderly manner at a sufficient distance from the banks of the excavation to avoid overloading and to prevent slides or caving. Keep stockpiles of all material to be incorporated into the work in a neat and well drained condition, giving due consideration to drainage at all times. Clear, grub, and seal the ground surface at stockpile locations. Stockpile topsoil separately from suitable backfill material. Protect stockpiles of aggregates and granular soils from contamination which can destroy the quality and fitness of the stockpiled material. If the Contractor fails to protect the stockpiles, and any material becomes frozen, saturated, intermixed with other materials, or otherwise out of specification or unsatisfactory for the use intended, remove such material and replace with new material from approved sources at no additional cost to the Government.
3.7.4 Testing Schedule
c. Sieve Analysis, (ASTM C136/C136M)
Drainage Aggregate, 1 test for each source.
3.11 SEEDING
Apply seed at the rate of 10 square yards per pound of seed. Evenly distribute the seed by hand or using broadcast seeders. Cover seed to a nominal 1/2 inch depth by rakes. See 32 92 19 SEEDING for seed mixture.
2. DRAWINGS:
G-002 – Revised Note 1 under TEMPORARY ACCESS ROAD.
CS101 – CS104 – Revised the riprap areas shown on the plan view.
CS105 – Clarification added for Concrete Safety Barrier and Access Roads.
CS501 – Added Note 3 on Detail A8, Revised Sheet Note 2.
CS502 – Revised Sheet Note 1. Revised D1/CS502, Revised sidewalk/rock interface on E7/CS502 .
CS503 – Revised layout of detail sheet to match CAD standards. Notes revised to reflect design intent.
3. Offerors are required to acknowledge receipt of this amendment on the Bidding Form in the space provided. Failure to acknowledge all amendments may cause rejection of the proposal.
4. All other terms and conditions remain unchanged and in full force.