This is an amendment to a solicitation for the Dodson Industrial Park Project levee maintenance and repairs in Kansas City, Missouri. The scope of work includes ramp construction, internal joint seals, gate and frame painting, actuator cover installation, hoist bar installation, site work, outlet riprap overlays, floodwall joint repairs, and toe drain flushing. One item has been changed from pipe tee replacement to valve reattachment. The applicable Davis-Bacon Act wage determination is MO20220001, modification 10 dated May 27, 2022. The solicitation number is W912DQ22B1008 and is issued by the U.S. Army Corps of Engineers Kansas City District.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment w ill modify the Supplemental Bid Schedule and update the w age rate determination.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-Jun-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DQ22B1008
X 9B. DATED (SEE ITEM 11)
09-May-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
01-Jun-2022
CODE
USACE, KANSAS CITY +
FEDERAL BLDG, CT-C +
601 E 12TH ST RM 647
KANSAS CITY MO 64106-2896
W912DQ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DQ22B1008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 2
The SOLICITATION is amended as follows:
NOTE: Deleted text is shown in RED with strikethrough. Added text is shown in GREEN with underline.
1. SPECIFICATIONS
None
2. DRAWINGS:
None
3. SOLICITATION
Supplemental Bid Schedule Updated – Pipe Tee Replacement revised to Valve Reattachment. Appendix drawings are for reference only.
Update Davis Bacon Act Wage Rate Determination.
SECTION 00 10 00 - SOLICITATION
The following have been modified:
SUPPLEMENTAL BID SCHEDULE
SUPPLEMENTAL BID SCHEDULE
The contractor shall complete the following Supplemental Bid Schedule in addition to the Bid Schedule. This
Supplemental Bid Schedule is not contractually binding. The Government will use this Supplemental Bid Schedule to assist in the evaluation of prices. The individual supplemental bid items should add up to the prices for the bid schedule. In the event that the CLIN subtotal in the supplemental bid schedule does not match the CLIN total in the bid schedule, the bid schedule shall control and will be the price evaluated by the Government.
CLIN 0001
PRIMARY FACILITY Est. Qty. Unit Unit Price Subtotal
Ramp Construction 1 JOB $ $
Weko Seals Internal Joint Seals 30 EA $ $
Paint Gates/Frames 2 EA $ $
Install Actuator Covers 2 EA $ $
Install Hoist Bars 2 EA $ $
Sitework 1 JOB $ $
Outlet Riprap Overlays 1 JOB $ $
Floodwall Joint Repairs 15 EA $ $
Toe Drain Flushing 1 JOB $ $
Pipe Tee Replacement Valve Reattachment 1 JOB $ $
Contract Total $
Note: Any work not specifically noted shall be priced with the most closely related CLIN.
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
The following have been modified:
WAGE RATES
Applicable Davis Bacon Act Wage Determination, MO20220001; Construction: Heavy; Modification: #10; Published Date: May 27, 2022. A hard copy will be provided upon request. Link provided:
https://sam.gov/wage-determination/MO20220001/10