C.04.10 Question_and_Answers (W912DQ21Q1034) - Version #1.pdf

PDF 428 KB Posted

Attached to
Harry S. Truman Project Office Electrical Upgrades located at Warsaw, MO
Solicitation number
W912DQ21Q1034
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question and Answers for W12DQ21Q1034

Version #1

July 17 – July 29, 2021

1. Are utility company fees to be included with our proposals?

Government Response: There should be no fees associated with electric company.

Contractors will have to make contact with them on scheduling outage so they can be available to make final connection. Whoever gets award the Government will be assisting with local lineman to make the electric change over.

2. The length of cable (500 kmil) and rigid conduit (3-1/2" and 2-1/2") is not given in drawing sheet. Therefore, kindly confirm the exact length of wire and conduit so that we can bid on this project more accurately.

Government Response: It is suggested the contractor make site visit for exact measurements other wise Google Earth can be used to determine approximate distance from pole to building and estimate used for connections inside building and at outside equipment.

File details come from the government source that posted it. Updated .