This document provides details for a federal contract solicitation to perform construction activities at Cranberry Chute in Saline County, Missouri. The scope of work includes constructing a control structure and adjacent bank protection within Cranberry Chute, which may include revetments, bank armoring, bank paving, grading and excavation. The contractor will be required to transport and place new stone for constructing a new flow control structure in Cranberry Chute. All work must be completed by land-based equipment unless otherwise authorized, and no dredging is permitted. The contractor must also comply with all applicable state and federal Clean Water Act guidelines. The solicitation was issued by the Department of the Army Corps of Engineers Kansas City District. The response due date and award date are not specified in this document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to add Specificaton 01 78 00, Closeout Submittal.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 19
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Aug-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DQ21B1017
X 9B. DATED (SEE ITEM 11)
21-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Aug-2021
CODE
USACE, KANSAS CITY +
FEDERAL BLDG, CT-C +
601 E 12TH ST RM 647
KANSAS CITY MO 64106-2896
W912DQ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DQ21B1017
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 01
Missouri River Recovery Project Cranberry Chute Saline County, MO River Mile 282-283
The SOLICITATION is amended as follows:
NOTE: Deleted text is shown in RED with strikethrough. Added text is shown in GREEN with underline.
1. SPECIFICATIONS:
Add specification 01 78 00 – Closeout Submittal. See attached.
2. DRAWINGS:
None
SECTION 00 10 00 - SOLICITATION
The Issued By organization has changed from
USACE, KANSAS CITY +
FEDERAL BLDG, CT-C
601 E 12TH ST RM 647
KANSAS CITY MO 64106-2896
to
USACE, KANSAS CITY CT
FEDERAL BLDG CT-C 601 E 12TH STREET
KANSAS CITY MO 64106-2896
SECTION 01 00 00 - GENERAL REQUIREMENTS
The following have been added by full text:
01 78 00 CLOSEOUT SUBMITTALS
SECTION TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
SECTION 01 78 00
CLOSEOUT SUBMITTALS 05/19
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 As-Built Drawings
1.2.2 Record Drawings
1.3 SOURCE DRAWING FILES
1.3.1 Terms and Conditions
1.4 SUBMITTALS
1.5 QUALITY
CONTROL PART 2
PRODUCTS
2.1 RECORD DRAWINGS
2.1.1 Additional Drawings
2.1.1.1 Sheet Numbers and File Names
2.2 PDF AS-BUILT FILES
2.3 REDLINES AND MARKUPS
2.4 AS-BUILT OR ADVANCED MODELING RE-SUBMISSION
REQUIREMENTS PART 3 EXECUTION
3.1 AS-BUILT DRAWINGS
3.1.1 Markup Guidelines
3.1.2 As-Built Drawings Content
3.2 RECORD DRAWING FILES
3.2.1 Rename the CAD Drawing files
3.3 RECORD DRAWINGS
3.3.1 Final Record Drawing Package
3.4 CLEANUP
-- End of Section Table of Contents –
01 78 00 – 1
SECTION 01 78 00
CLOSEOUT
SUBMITTALS
05/19
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ERDC/ITL TR-12-1 (2015) A/E/C Graphics Standard, Release 2.0
ERDC/ITL TR-12-6 (2015) A/E/C CAD Standard - Release 6.0
1.2 DEFINITIONS
1.2.1 As-Built Drawings
As-built drawings are the marked-up drawings, maintained by the Contractor on-site, that depict actual conditions and deviations from the Contract Documents. These deviations and additions may result from coordination required by, but not limited to: contract modifications;
official responses to submitted Requests for Information (RFI's);
direction from the Contracting Officer; design that is the responsibility of the Contractor, and differing site conditions. Maintain the as-builts throughout construction as red-lined hard copies on site and red-lined PDF files.
These files serve as the basis for the creation of the record drawings.
1.2.2 Record Drawings
The record drawings are the final compilation of actual conditions reflected in the as-built drawings.
1.3 SOURCE DRAWING FILES
Request the full set of electronic drawings, in the source format, for Record Drawing preparation, after award and at least 30 days prior to required use.
1.3.1 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files.
The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable
01 78 00 – 2 attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CAD drawing files are not construction documents.
Differences may exist between the CAD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CAD files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction drawings and data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-11 Closeout Submittals
As-Built Drawings; G, RO Record Drawings; G, RO
1.5 QUALITY CONTROL
Additions and corrections to the contract drawings must be equal in quality and detail to that of the originals. Line colors, line weights, lettering, layering conventions, and symbols must be the same as the original line colors, line weights, lettering, layering conventions, and symbols.
PART 2 PRODUCTS
2.1 RECORD DRAWINGS
Prepare the CAD drawing files in MicroStation V8i format compatible with a Windows 7 operating system.
2.1.1 Additional Drawings
If additional drawings are required, prepare them using the specified electronic file format applying the same graphic standards specified for original drawings. The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract drawings.
01 78 00 – 3
2.1.1.1 Sheet Numbers and File Names
If a sheet needs to be added between two sequential sheets, append a Supplemental Drawing Designator in accordance with ERDC/ITL TR-12-6 Adding a drawing sheet, and ERDC/ITL TR-12-1 Adding or deleting drawing sheets and index sheet procedures.
2.2 PDF AS-BUILT FILES
Provide electronic PDF "plots" of all contract drawings sheets associated with the as-built drawing submittal. Compile and organize the PDF set to match the contract drawings.
2.3 REDLINES AND MARKUPS
Provide PDFs of the current working redlines and/or markups complying with the as-builts drawing and markup requirements contained in this specification.
2.4 AS-BUILT OR ADVANCED MODELING RE-SUBMISSION REQUIREMENTS
If elements of an as-built submittal or advanced modeling package are rejected, provide the following for each re-submission, in addition to any information required in Section 01 33 00 SUBMITTAL PROCEDURES:
a. Re-submit all components required under paragraph As-Builts or Advanced
Modeling Package, including a new Advanced Modeling Submittal Checklist and updated content in response to Government comments.
b. Provide a copy of all Government review comments.
c. Provide a disposition/response to each Government review comment for a back-check of the re-submission deliverable.
PART 3 EXECUTION
3.1 AS-BUILT DRAWINGS
Provide and maintain two black line print copies of the PDF contract drawings for As-Built Drawings. Maintain the as-builts throughout construction as red-lined hard copies on site and red-lined PDF files.
Submit As-Built Drawings 30 days prior to Beneficial Occupance Date
(BOD).
3.1.1 Markup Guidelines
Make comments and markup the drawings complete without reference to letters, memos, or materials that are not part of the As-Built drawing.
Show what was changed, how it was changed, where item(s) were relocated and change related details. These working as-built markup prints must be neat, legible and accurate as follows:
a. Use base colors of red, green, and blue. Color code for changes as follows:
(1) Special (Blue) - Items requiring special information, coordination, or special detailing or detailing notes.
(2) Deletions (Red) - Over-strike deleted graphic items
(lines), lettering in notes and leaders.
01 78 00 – 4
(3) Additions (Green) - Added items, lettering in notes and leaders.
b. Provide a legend if colors other than the "base" colors of red, green, and blue are used.
c. Add and denote any additional equipment or material facilities, service lines, incorporated under As-Built Revisions if not already shown in legend.
d. Use frequent written explanations on markup drawings to describe changes. Do not totally rely on graphic means to convey the revision.
e. Use legible lettering and precise and clear digital values when marking prints. Clarify ambiguities concerning the nature and application of change involved.
f. Wherever a revision is made, also make changes to related section views, details, legend, profiles, plans and elevation views, schedules, notes and call out designations, and mark accordingly to avoid conflicting data on all other sheets.
g. For deletions, cross out all features, data and captions that relate to that revision.
h. For changes on small-scale drawings and in restricted areas, provide large-scale inserts, with leaders to the applicable location.
i. Indicate one of the following when attaching a print or sketch to a markup print:
(1) Add an entire drawing to contract drawings
(2) Change the contract drawing to show
(3) Provided for reference only to further detail the initial design.
j. Incorporate all shop and fabrication drawings into the markup drawings.
3.1.2 As-Built Drawings Content
Revise As-Built Drawings in accordance with ERDC/ITL TR-12-1. Keep these working as-built markup drawings current on a weekly basis and at least one set available on the jobsite at all times. Changes from the contract drawings which are made during construction or additional information which might be uncovered in the course of construction must be accurately and neatly recorded as they occur by means of details and notes. Submit the working as-built markup drawings for approval prior to submission of each monthly pay estimate. For failure to maintain the working and final record drawings as specified herein, the Contracting Officer will withhold 10 percent of the monthly progress payment until approval of updated drawings. Show on the as-built drawings, but not limited to, the following information:
a. The actual location, kinds and sizes of all sub-surface utility lines. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, show by offset dimensions to two permanently fixed surface features the end of each run including each change in
01 78 00 – 5 direction on the record drawings. Locate valves, splice boxes and similar appurtenances by dimensioning along the utility run from a reference point. Also record the average depth below the surface of each run.
b. Correct grade, elevations, cross section, or alignment of roads, earthwork, structures, or utilities if any changes were made from contract plans.
c. Changes in details of design or additional information obtained from working drawings specified to be prepared or furnished by the Contractor; including but not limited to shop drawings, fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment, and foundations.
d. The topography, invert elevations and grades of excavation done as part of the project construction.
e. Changes or Revisions which result from the final inspection.
f. Where contract drawings or specifications present options, show only the option selected for construction on the working as-built markup drawings.
g. If borrow material for this project is from sources on Government property, or if Government property is used as a spoil area, furnish a contour map of the final borrow pit/spoil area elevations.
h. Modifications (include within change order price the cost to change working as-built markup drawings to reflect modifications).
i. Unusual or uncharted obstructions that are encountered in the contract work area during construction.
j. Location, extent, thickness, and size of stone protection particularly where it will be normally submerged by water.
l. Modifications (include within change order price the cost to change working and final record drawings to reflect modifications) and compliance with the following procedures.
(1) Follow directions in the modification for posting descriptive changes.
(2) Place a Modification Circle at the location of each deletion.
(3) For new details or sections which are added to a drawing, place a Modification Circle by the detail or section title.
(4) For minor changes, place a Modification Circle by the area changed on the drawing (each location).
(5) For major changes to a drawing, place a Modification Circle by the title of the affected plan, section, or detail at each
(6) For changes to schedules or drawings, place a Modification
Circle either by the schedule heading or by the change in the schedule.
01 78 00 – 6
(7) The Modification Circle size shall be 1/2 inch diameter unless the area where the circle is to be placed is crowded.
Smaller size circle shall be used for crowded areas.
3.2 RECORD DRAWING FILES
If additional drawings are required, prepare them using the specified electronic file format applying the same graphic standards specified for original drawings. The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract drawings. Accomplish additions and corrections to the contract drawings using CAD files. Provide all program files and hardware necessary to prepare final PDF record drawings. The Contracting Officer will review final PDF record drawings for accuracy and return them to the Contractor for required corrections, changes, additions, and deletions.
3.2.1 Rename the CAD Drawing files
Rename the CAD Drawing files using the contract number as the Project Code field,(e.g., W91238-15-C-10A-102.DGN) as instructed in the Pre- Construction conference. Use only those renamed files for the Marked-up changes. Make all changes on the layer/level as the original item.
a. For MicroStation files (DGN), enter all as-built delta changes and notations on:
- Level #63
- Level/Layer Name contains: ANNO-REVS
- Level/Layer Description: Revisions
b. When final revisions have been completed, show the wording "RECORD DRAWING AS-BUILTS" followed by the name of the Contractor in letters at least 3/16 inch high on the cover sheet drawing. Date RECORD DRAWING AS-BUILTS" drawing revisions in the revision block.
c. Within 1020 days after Government approval of all of the working record drawings for a phase of work, prepare the final CAD record drawings for that phase of work and submit PDF drawing files and two sets of prints for review and approval. The Government will promptly return one set of prints annotated with any necessary corrections.
Within 710 days revise the CAD files accordingly at no additional cost and submit one set of final prints for the completed phase of work to the Government. Within 10 days of substantial completion of all phases of work, submit the final record drawing package for the entire project. Submit one set of electronic CAD files, and one set of the approved working record PDF files on , with two sets of prints. The CAD files must be complete in all details and identical in form and function to the CAD drawing files supplied by the Government. Prepare MicroStation files for transmittal using the Packager (Archive). Make any transactions or adjustments necessary to accomplish this. The Government reserves the right to reject any drawing files it deems incompatible with the customer's CAD system.
Paper prints, drawing files and storage media submitted will become the property of the Government upon final approval. Failure to submit final record PDF drawing files, CAD files and marked prints as specified will be cause for withholding any payment due under this contract. Approval and acceptance of final record drawings must be accomplished before final payment is made.
01 78 00 – 7
3.3 RECORD DRAWINGS
Prepare final record drawings after the completion of each definable feature of work as listed in the Contractor Quality Control Plan (such as
Foundations, Utilities, or Structural Steel as appropriate for the project). Transfer the changes from the approved working as-built markup drawings to the original electronic CAD drawing files. Modify the as-built CAD drawing files to correctly show the features of the project as-built by bringing the working CAD drawing set into agreement with approved working as-built markup drawings, and adding such additional drawings as may be necessary. Refer to ERDC/ITL TR-12-1. Jointly review the working as-built markup drawings with printouts from working as-built CAD drawing PDF files for accuracy and completeness. Monthly review of working as-built CAD drawing PDF file printouts must cover all sheets revised since the previous review. These PDF drawing files are part of the permanent records of this project. Any drawings damaged or lost must be satisfactorily replaced at no expense to the Government.
Drawing revisions (include within change order price the cost to change working and final record drawings to reflect revisions) and compliance with the following procedures.
(1) Follow directions in the revision for posting descriptive changes.
(2) The revision delta size must be 5/16 inch unless the area where the delta is to be placed is crowded. Use a smaller size delta for crowded areas.
(3) Place a revision delta at the location of each deletion.
(4) For new details or sections which are added to a drawing, place a revision delta by the detail or section title.
(5) For minor changes, place a revision delta by the area changed on the drawing (each location).
(6) For major changes to a drawing, place a revision delta by the title of the affected plan, section, or detail at each
(7) For changes to schedules or drawings, place a revision delta either by the schedule heading or by the change in the schedule.
3.3.1 Final Record Drawing Package
Submit the final record PDF and CAD drawings package for the entire project within 20 days of substantial completion of all phases of work.
Submit one set of ANSI D size PDF and CAD files on optical disc, read-only memory (ROM), two sets of ANSI D size prints and one set of the approved working record drawings. The package must be complete in all details and identical in form and function to the contract drawing files supplied by the Government.
3.4 CLEANUP
Leave premises "broom clean." Clean debris from drainage systems.
Sweep paved areas and rake clean landscaped areas. Remove waste and surplus materials, rubbish and construction facilities from the site.
01 78 00 – 8
MRRPCRANBERRYCHUTE
Saline County, MO
-- End of Section --
01 78 00 - 9
(End of Summary of Changes)