Milford_Electrical_and_Concrete_Project_27_May_2021.pdf

PDF 762 KB Posted

Attached to
Milford Lake West Rolling Hills Electric Repair
Solicitation number
W912DQ21B1010
Issued by

About this file

This document outlines requirements for an electrical and concrete project at Milford Lake in Kansas. The U.S. Army Corps of Engineers seeks installation of electrical junction boxes, feeds, and repairs to damaged park areas, including replacement of electrical panelboards, installation of conduit and wiring, replacement of RV pedestals and hydrants, and placement of concrete pads and sidewalks. The contractor must provide materials, labor, equipment, daily reports, as-built drawings, and warranties, and adhere to specifications for electrical work, concrete mix and finishing, erosion control, and safety requirements. The submission deadline for pre-construction documents is ten days after award, with a pre-construction meeting required within ten days of award and work expected to be complete by late 2021.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Milford Electrical and Concrete Project Milford Lake

01 12 00 ‐1

SECTION 01 12 00

DESCRIPTION OF WORK AND GENERAL REQUIREMENTS

1. GENERAL:

The work covered in this section is outlined as a summary of work requirements common to all the work and the locations and items of work involved. Specific requirements for materials, processes, performance, quality, and installation are provided under the technical sections of these specifications.

1.1 Existing Conditions

The Milford Lake Project, experienced high water, and significant damage to the Western Rolling Hills and Curtis Creek recreation areas during the 2019 Flood Event. Toilets received significant damage and have since been replaced. Additional infrastructure repairs are currently on-going to reopen for public use for the 2021 recreation season.

1.2 Description of Work

Work includes the installation of electrical junction boxes, R.V. pedestals, frost free hydrants, wire, and conduit. Incidental work includes, but is not limited to trenching, boring and the installation of all incidental materials to complete the work. Work shall also include the connection of a newly placed restroom in A-loop and B-loop in Western Hills and a restroom in B-Loop of Curtis Creek. Both restrooms in Western Hills have an optional requirement of concrete placement. The Contractor shall provide all labor, materials, and equipment to complete the project unless otherwise specified.

1.3 Location: Milford Lake

U.S. Army Corps of Engineers 5203 North K-57, Junction City, KS 66641

1.4 Points of Contact: Kenneth Wenger

Ken.R.Wenger@usace.army.mil Office: 816-389-3754 Cell: 785-307-0040

William Whitworth William.R.Whitworth@usace.army.mil Office: 816-389-3795

1.5 Work Hours

The standard workday is 7:00 am to 5:00 pm Monday thru Friday, excluding Federal holidays. Work hours may be adjusted with approval of Contracting Officer Representative (COR) or Operations Project Manager. Any request for variation from these hours shall be coordinated with the COR at a minimum of 48 hours in advance.

1.6 Plans and Documentation

1.6.1 Contractor Daily Written and Photographic Documentation

Contractor shall submit daily logs of work conducted to the COR. Contractor may use own form for documentation or forms can be provided at the contractor’s request. Photos of all phases of the project are required and shall be submitted to COR in jpeg formatting upon job completion. Each photo shall have a time date stamp. It is recommended that daily logs are submitted daily.

01 12 00 ‐2

The following information must be included:

Date Equipment Used Total hours worked that day Contractor Name Size of crew Controversial Matters Weather description Methods Used Miscellaneous Remarks Air temperature Precipitation Work completed that day Size of crew Problems encountered

1.6.2 Insurance Requirements

The Contractor shall maintain the required insurance coverage throughout the duration of project.

1.6.3 Payment and Invoices:

Shall be submitted upon completion of the work. Each line item on an invoice shall give a description including the Contract Line Item Number (CLIN). Upon receipt, the COR will certify that the requested amounts are appropriate before payment will be made. Invoices shall include all necessary information, including any necessary supporting documentation required as part of this Scope of Work. All invoices shall reflect the contract number, (Block 2 of the SF-1442).

1.6.4 Contractor Exposure Hours:

The Contractor shall track the number of man hours to perform the contract requirements. The total number of man hours per day shall be submitted to the Government with the invoice.

1.6.5 Red Lined As-Built Drawings

1.6.5.1 Shall include the identification of the work completed by the Contractor and shall be on one set of Contract Drawings provided to the Contractor at the onset of the project.

1.6.5.2 Drawings shall be kept on the project site, include all necessary information as outlined in the Scope of Work, be updated as the work is progresses and shall be clearly legible. All markings shall be either red or green. Red lines shall denote deletions and green lines shall denote additions.

1.7 Site Visit

Interested parties are strongly encouraged to visit the site prior to preparing and submitting their bid.

Contractors are encouraged to attend the scheduled site visit on the solicitation prior to submitting a bid on this contract.

1.8 Occupancy of Premise

Before work is started, it is the contractor’s responsibility to arrange with COR a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and roadways.

1.9 Submittal Definitions

The Contractor is responsible for the requirements of this contract and is encouraged to review the document in detail and to provide inquiries to the Government as necessary prior to preparing a proposal.

01 12 00 ‐3

1.9.1 Construction Process Plan

Construction Plan shall include all the following:

1.9.1.1 A plan which clearly indicates the areas of work and description of the work to be completed. This shall be completed in a work breakdown structure format. Examples might include processes for demolition, excavation, backfill, building erection and concrete placement.

1.9.1.2 The construction process plan shall be submitted and approved prior to work being started.

1.9.2 Quality Control Plan (QCP)

The Contractor shall develop and maintain an effective quality control plan to ensure services are performed in accordance with this contract. Contractor shall develop and implement procedures to identify, prevent, and ensure non- recurrence of defective services. The Contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. The QCP shall be submitted within 30 days after the contract has been awarded. After acceptance of the quality control plan the Contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his QC system.

Submit a detailed Contractor Quality Control (CQC) Plan that fully represents and conforms to the requirements of these specifications. At a minimum the CQC is to include the following:

1.9.2.1 Defined responsibilities of personnel that ensure the quality requirements for this contract are met.

All responsibilities such as Superintendent, Site Safety and Health Officer (SSHO), and Quality Control Manager (QCM) shall be assigned to specific personnel and an alternate if the primary is not on-site.

Individual(s) who will be onsite during construction operations and who will have the authority to act for the Contractor to include the authority to stop work which is not in compliance with the contract.

1.9.2.2 Role definitions

It is the decision of the Contractor on whether the following roles are the duties of a single individual or are assigned to multiple individuals. The Superintendent/ QCM/ SSHO shall meet the minimum requirements as stated in the EM385- 1-1. Duties shall include, but are not limited to, maintaining project status and communication with Government personnel, weekly progress reports including a weekly look ahead report.

Coordination with the COR is critical for outages and equipment delivery. All personnel on site are required to have a photo ID on persons. The Government reserves the right to remove or reject personnel who do not meet qualifications or security requirements.

a. Superintendent is to direct the day-to-day operations on the construction site and control the short-term schedule as well as subcontractor coordination responsibilities.

b. Site Safety and Health Officer (SSHO) oversees inspecting site conditions to determine if hazards are present and has the authority to establish procedures and policies to overcome those hazardous situations.

c. Quality Control Manager (QCM) is responsible for managing and performing the daily QC responsibilities of the project to ensure the project is constructed in accordance with the established minimum standards. If minimal standards are not being met the QCM has the authority to implement changes to achieve those standards.

1.9.2.3 Submit a clearly defined proposed procedures for quality control, product sampling and testing as part of the plan.

01 12 00 ‐4

1.9.2.4 Proposed methods for product performance controls, including method and frequency of product sampling and testing both in raw material form and cured product form. All costs associated with the testing laboratory work for quality assurance and quality control, as well as rework required to meet project requirements, shall be paid for by the contractor. No separate payment will be made for this work. It will be considered incidental to the work in which the material is utilized.

1.9.2.5 A scheduled performance and product test result review with the COR at a regularly scheduled progress meeting.

1.9.2.6 Inspection Forms and guidelines for quality control inspections in accordance with the standards specified in this Contract and submitted with the QCP.

1.9.2.7 Outline specific repair or replacement procedures for potential defects that occur within the installed system, following repair or replacement procedures that are compatible with the system being used. Submit Repair or Replacement Procedures must adhere to the product manufacturer's written specifications for repair or replacement.

1.9.2.8 Key personnel phone numbers including e-mails and all other staff shall be included within the QCP.

1.9.3 Contractor Experience and Qualifications:

A statement letter of the Contractor’s experience on company letterhead.

The lead personnel including the project manager, and the foreman shall each have a minimum of three (3) years of experience with the installation of electrical systems and concrete construction proposed for this contract and must have demonstrated competency and experience to perform the scope of work contained in this contract. The name and experience of each lead individual performing work on this contract shall be submitted with the Contractor Qualifications.

1.9.4 Project Schedule

Prior to any work being completed the Contractor shall submit a project schedule for approval. The project schedule shall contain a chronological order of activities that progresses to project completion. Each activity shall have a duration with a proposed start and end date.

1.9.5 Installer Warranty

At a minimum provide warranty for a period of not less than two years that the finished products, are free from defects in installation workmanship.

1.9.6 Accident Prevention Plan

Contractor shall prepare a site-specific Accident Prevention Plan (APP). Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1. Cover all paragraph and subparagraph elements in USACE EM 385-1-1, Appendix A, "Minimum Basic Outline for Accident Prevention Plan". The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written.

1.9.7 Activity Hazard Analysis

An Activity Hazard Analysis must be provided prior to breaking ground. The Activity Hazard Analysis must address all foreseeable safety concerns including and not limited too; electrical safety, safety zone

01 12 00 ‐5 protection, fall protection, fire safety, personal protective equipment, signage/protective fencing, and hazardous material handling.

1.9.8 Demolition Plan

Prepare a Demolition Plan and submit proposed demolition, and removal procedures for approval before work is started. Include in the plan procedures for removal and disposition of materials. Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the COR.

1.9.9 Qualification of Installer

Electrical Contractor shall have a minimum of 3 years’ experience and Concrete Contractor shall have a minimum of 1-year experience in performing work contained within the specifications.

1.9.10 Operation and Maintenance Data

Submit operations and maintenance data directly to the Government for the following items:

1.9.10.1 As-built drawings following the Contract in CADD drawing format

1.9.10.2 Safety precautions and hazards

1.9.10.3 Preventive maintenance plan, schedule, and procedures

1.9.10.4 Troubleshooting guides and diagnostic techniques

1.9.10.5 Wiring diagrams

1.9.10.6 Maintenance and repair procedures

1.9.10.7 Spare parts and supply list

1.9.10.8 Manufacturer's instructions

1.9.10.9 Parts identification

1.9.10.10 Testing equipment and special tool information

1.9.10.11 Manufacturer Warranty information

1.9.10.12 Testing and performance data

1.9.11 Work Schedule

Schedule: Before the start of work, the Contractor shall coordinate for approval a schedule that includes the following as a minimum:

1.9.11.1 Mobilization

1.9.11.2 Submission of Preconstruction Submittals (Insurance, AHA, APP, QC Plan)

1.9.11.3 Submission of any Preconstruction Technical submittals of products furnished by the Contractor.

1.9.11.4 Schedule with the Cost for each Activity.

1.9.11.5 Walk through and inspection prior to final acceptance

1.9.11.6 Electrical testing results provided for each circuit.

1.9.11.7 Final As-Built Drawings reflecting installed conditions and work performed.

1.9.11.8 Final acceptance of work

1.10 Submittals

The Contractor shall provide to the Government the submittals identified within this contract and submittals that are identified as necessary to ensure performance compliance. Once submittals are

01 12 00 ‐6 received the government has 10 working days for review and acceptance. All submittals except for post construction are required prior to construction commencing.

The Government will respond to the Contractor’s submittals with email, fax, or postal mail per the Contractor’s requested preference to the Government. The Government’s approval of submittals shall not be construed as a complete check of the contract requirements. Government approval will be an indication of a satisfactory submittal of the general method of compliance with the requirements of the contract. Government approval will not relieve the Contractor of the responsibility for contract compliance.

Government disapproved submittals shall be resubmitted by the Contractor addressing corrections and contract compliance. At the discretion of the Government, the Contractor may be directed by the Government to proceed with work in advance the submittals; however, the Contractor shall practice due diligence and continuity with the submittal process. Each submittal shall be attached to a USACE provided form 4025 and emailed to the primary contact contained in Section 1.4. One copy of each submittal shall be provided as follows:

1.10.1 Preconstruction Submittals

1.10.1.1 Construction Process Plan

1.10.1.2 Material, Delivery, Storage and Placement Plan

1.10.1.3 Disposal of Demolition Materials Plan

1.10.1.4 Quality Control Plan

1.10.1.5 Daily Log Format

1.10.1.6 Project Schedule

1.10.1.7 Activity Hazard Analysis

1.10.1.8 Environmental Hazard Mitigation

1.10.1.9 Accident Prevention Plan

1.10.1.10 Demolition Plan

1.10.1.10 Material Safety Data Sheets

1.10.1.11 Concrete Joint Plan

1.10.2 Shop Drawings

1.10.2.1 Wiring Diagrams

1.10.3 Material Submittals

1.10.3.1 Control System Components

1.10.3.2 Panel Boards

1.10.3.3 Circuit Breakers

1.10.3.4 Enclosed Circuit Breakers

1.10.3.5 Conductors and Conduit

1.10.3.6 Concrete Bedding Gradation

1.10.3.7 Concrete Mix Design

1.10.3.8 Curing Compound

1.10.3.9 Framing Materials

1.10.3.10 Frost Free Hydrants

1.10.3.11 Reinforcement

1.10.5 Certificates

01 12 00 ‐7

1.10.5.1 Contractor’s Qualifications

1.10.5.2 Superintendent’s Qualification

1.10.5.4 Contractor Experience and Qualification Letter

1.10.5.5 Contractor Quality Control Personnel Qualifications

1.10.5.6 Qualifications of Installer

1.10.5 Test Reports

1.10.5.1 Functional Test Report

1.10.6 Operational and Maintenance Data

1.10.6.1 Electrical Systems

1.10.7 Closeout Submittals

1.10.6.1 Daily Reports

1.10.6.2 Photographic Documentation

1.10.6.3 As-Built Drawings

1.10.6.4 Warranty

1.10.6.5 Instructions to Government Personnel

1.10.6.6 Maintenance/Repair Material Lists

1.10.7 All submittals (one copy of each) shall be sent electronically or hard copy to the following:

Primary Contact: Alternate Contact:

U.S. Army Corps of Engineers U.S. Army Corps of Engineers Milford Lake Milford Lake Attn: Kenneth Wenger Attn: William Whitworth Ken.R.Wenger@usace.army.mil William.R.Whitworth@usace.army.mil Office: 816-389-3754 Office: 816-389-3795 Cell: 785-307-0040

1.11 Measurements and Quantities

The Contractor shall verify all measurements at the project site and shall be responsible for all dimensions, fittings, and the proper installation of all materials and equipment specified.

1.12 Permits

The Contractor shall be responsible for obtaining any required permit.

1.12.1 Hot Work Permit

The Contractor shall be liable for any fire loss to Government property attributable to negligence on the part of the Contractor.

1.13 Safety Requirements

1.13.1 Protection from Hazards

01 12 00 ‐8

During progress of work, the Contractor shall protect all personnel, whether Government or civilian, from all safety hazards caused by the construction operations.

1.13.2 Traffic Control

Contractor shall provide all temporary signs and markers as necessary to maintain safety in the worksite. All signs shall conform to the latest edition of the Manual of Uniform Control Devices (MUTCD).

1.13.2.1 When a street must be closed to traffic because of the location of the access point, submit a detailed Traffic Control Plan to the COR at least 10 working days in advance. Meet the requirements of the local agency having jurisdiction over traffic control.

1.13.2.2 Provide labor, signs, barricades, cones, arrow boards, flaggers, and any additional equipment necessary to complete the work.

1.13.3 U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL,

EM 385-1-1 (2014)

EM 385-1-1 and its changes are available at http://www.hq.usace.army.mil (at the HQ homepage, select Safety and Occupational Health). Select the appropriate manual. The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.

2014 Version:

https://www.usace.army.mil/Missions/Safety‐and‐Occupational‐Health/Safety‐and‐Health‐Requirements‐Manual/

1.13.4 Utilities Clearance

At least 72 hours prior to any excavation Kansas One-Call shall be contacted for utilities clearances.

1.14 Special Requirements

1.14.1 The Contractor shall provide a set of drawings for the completed installation of the electrical system.

Final As-Built drawings shall be provided within 30 days after final acceptance of the work included in this solicitation. Electronic copy shall be submitted in AutoCAD format along with two hard copies. If the Contractor does not have a USACE template, USACE will provide at the Contractor’s request.

1.14.2 The Contractor will locate and survey the underground location of all electrical wire and provide locations within the drawing package. The survey shall be overlaid on a map of the area that depicts proximity to above ground features.

1.14.3 Drawings shall include wiring diagrams and installation details of equipment indicating location, layout and arrangement, control panels, accessories, piping, ductwork, and other items that must be shown to ensure a coordinated installation. Wiring diagrams shall identify circuit terminals and indicate the internal wiring for each item of equipment and the interconnection between each item of equipment.

1.14.4 The Contractor is responsible to coordinate with Kansas One Call (811) and D S & O Electric Cooperative (800-376-3533) for underground service locations or any coordination with their service.

01 12 00 ‐9

1.14.5 Qualified electricians shall always be on site to perform/oversee installation during the installation of electrical equipment or components.

1.15 Security:

1.15.1 In unoccupied facilities, the Contractor shall coordinate with the COR and be responsible for securing of the facility at the completion of each day, i.e., all exterior doors shall be locked, windows closed and locked, etc.

1.15.2 The Contractor shall not be on site without prior notification to the Corps of Engineers COR or otherwise designated person(s).

1.15.3 Contractor personnel shall have valid civilian ID's and Contractor vehicles shall have a valid registration.

1.15.4 The Contractor shall be responsible for safeguarding all government equipment, information and property provided for Contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.

1.16 Antiterrorism/Operation Security Requirements

1.16.1 All contractor and all associated sub‐contractors’ employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

1.16.2 All contractor and all associated sub‐contractors employees will receive a CORPS Watch information paper (provided by the authorized government representative) and provide a written acknowledgement to the COR, no later than 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract.

1.16.3 The Contractor must pre‐screen candidates using the E‐verify Program (http://www.dhs.gov/E‐ Verify) website to meet the established employment eligibility requirements. The vendor must ensure that the candidate has two valid forms of government issued identification to ensure the correct information is entered into the E‐verify system. An initial list of verified/eligible candidates must be provided to the COR no later than 3 business days after the initial contract award.

1.16.4 Per the E-Verify Website the following exemptions apply:

Employers whose contracts are exempt from the E-Verify federal contractor rule are not required to enroll in E-Verify. A contract is considered exempt if any one of the following applies: (1) It is for fewer than 120 days. (2) It is valued at less than $150,000, the simplified acquisition threshold (Source:

http://www.uscis.gov/e-verify/federal-contractors/exemptions-and-exceptions).

01 12 00 ‐10

1.16.5 All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

1.17 Applicable Publications

The publications referenced herein shall be the most recent at the time of solicitation.

1.18 Worksite Housekeeping

1.18.1 The Contractor shall remove all trash and disposal material from the worksite before the end of each day. The Contractor shall take all possible precautions to maintain the work site, always in a condition that will prevent damage or injury to person or property, Government or otherwise. The Contractor shall be responsible for all damages caused by the negligent acts or omissions of his employees, sub-contractors, or agents during Contract performance. Do not allow scrap/waste materials to accumulate on-site; transport immediately from the government property and legally dispose of them at the end of each working day. The contractor will not be permitted to sell salvaged material on Government property. No persons other than the Contractors or sub-contractors’ employees shall be allowed to remove salvage from the site.

1.18.2 Schedule cleanup in a manner to cause the least possible obstruction and inconvenience to traffic, pedestrians, and property occupants.

1.18.3 Contractor is not to use the general public “on-site dumpsters,” for to dispose of waste materials. The site shall be left the same or in better condition prior to construction. The site shall be clean, free of any construction related materials and trash, upon completion of the work.

1.18.4 If any items are allowed to be stockpiled per the Operations Project Manager or COR, such items shall be placed in an orderly manner (i.e. dirt, rock, etc., in piles at a specified location and stackable items such as pipe, brick, lumber, etc., stacked off the ground on pallets in an orderly manner).

1.19 Responsibility for Damage

1.19.1 Damage to Personal Property:

The Contractor shall be solely responsible for all damage to Government and occupant personal property caused by the Contractors' personnel, subcontractors, his agents, or by the performance of his work.

1.19.1.1 Protect against fire and flame spread. Maintain proper and adequate fire extinguishers.

1.19.1.2 Store moisture susceptible materials above ground and protect with waterproof coverings.

1.19.1.3 Remove all traces of piled bulk materials and return the job site to its original condition upon completion of the work.

1.19.2 Damage by Negligence

Damage resulting in gas leaks, electrical outages, loss of heat during cold weather, water leaks, unsecured facilities, weather damage, or oil/hazardous waste spills shall be responded to by the Contractor within 2 hours and repaired within one workday. If the Contractor fails to comply with these requirements, the Government reserves the right to repair the damage and charge the cost to the Contractor. Contractor shall protect all areas through which he will be transporting demolition debris or construction materials. All structures, including roadways, shall be carefully protected from damage by equipment or the impact of

01 12 00 ‐11 stones or blocks. Any damaged turf, sidewalks, roads, vegetation, site amenities, etc., shall be replaced or repaired by the Contractor prior to final Contract closeout at the Contractor’s expense.

1.20 Disposal of Materials

All demolition materials for this project shall become property of the Contractor.

1.20.1 All other wastes generated during Contractor operations shall be disposed of by the Contractor at his/her expense.

1.20.2 Solid wastes (excluding clearing debris) shall be placed in containers which are emptied on a regular schedule. Handling, storage, and disposal shall be conducted to prevent contamination.

Segregation measures shall be employed so that no hazardous or toxic waste will become co-mingled with solid waste. The Contractor shall transport solid waste off Government property and dispose of it in compliance with Federal, State, and local requirements for solid waste disposal. A Subtitle D RCRA permitted landfill shall be the minimum acceptable off-site solid waste disposal option. The Contractor shall verify that the selected transporters and disposal facilities have the necessary permits and licenses to operate. The Contractor shall comply with Federal, State, and local laws and regulations pertaining to the use of landfill areas.

1.20.3 Wastes classified as hazardous wastes under the Resource Conservation and Recovery Act shall be disposed of, unless otherwise specified in this contract. No hazardous waste shall be disposed of without prior review of the disposal documents, and the approval of the Contracting Officer and the Directorate of Public Works Environmental Coordinator, or his designated representative. The Contractor shall provide an original copy of the disposal document from the approved EPA or State permitted disposal facility for each shipment of hazardous waste generated in this project to the Contracting Officers Representative.

1.20.4 Unified Facilities Guide Specifications (UFGS) 01572, “Construction and Demolition Waste Management,” indicates the Government policy is to “use all reasonable means to divert construction and demolition waste from landfills and incinerators and to facilitate their recycling and reuse.” The Contractor shall make all attempts to divert waste material from landfills in coordination of this guidance.

1.20.5 Unused/disconnected existing electrical panels, RV Pedestals, wire, existing Concrete pads around pedestals and all associated discontinued equipment will be removed and the Contractor will divert material in accordance with Federal and State Regulations.

1.21 Utilities

The Contractor is responsible for providing utilities for their employees. This shall include but not limited to electric, water, and restrooms.

1.22 Pre-Construction Meeting:

Prior to commencement of any work being performed, the contractor shall participate in a pre-construction meeting with the CORs and other pertinent government officials. Pre-construction meeting shall occur within 10 calendars days of contract award.

1.23 Quality Control

01 12 00 ‐12

Workmanship shall be of the highest grade in accordance with the best modern practices to conform to the specifications for the work being performed. The Contractor shall be responsible for quality control to ensure all components and workmanship meet requirements of this contract. Representatives of USACE reserves the right to inspect and witness the work, verify quality of workmanship and products used at any time, whether the work is performed in the field or at the Contractor’s shop.

1.24 Post Award Conference/Periodic Progress Meetings

The Contractor agrees to attend any post award conference convened by USACE in accordance with Federal Acquisition Regulation Subpart 42.5. The Contracting Officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the contracting officer will apprise the Contractor of how the government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.25 Additional Requirements

1.25.1 Environmental Requirements

1.25.1.1 The Contractor shall minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work shall be protected during the entire duration of this contract. The Contractor shall comply with all applicable environmental Federal, State, and local laws and regulations.

The Contractor shall be responsible for any delays resulting from failure to comply with environmental laws and regulations. During construction, the Contractor shall be responsible for identifying, implementing, and submitting for approval any additional requirements for environmental compliance.

1.25.1.2 If any cultural and/or human remains are inadvertently uncovered during construction, the work is to be halted until appropriate project and district personnel are notified and the remains are evaluated for National Register of Historic Places (NRHP) significance.

1.25.1.3 No clearing of trees will occur between 1 April and 31 October.

1.25.2 Concrete Rinsate

Concrete trucks may be washed out only in designated areas that have been approved for collecting spent material. Rinsate areas will be designated by COR, if required, following contract award. The designated area must be located to prevent contaminated runoff from discharging from the site.

1.25.3 Environmental Protection

Prior to the delivery of any material to the site, and before the start of any onsite construction activities, the Contractor and the Government Representative shall make a joint site survey. This survey will include a review of work constraints and resources specifically identified as environmental features requiring protection along with the condition of trees, shrubs, and grassed areas immediately adjacent to the site of work and access route(s), as applicable. The Contractor shall protect those environmental features included in this survey and any indicated on the drawings, regardless of interference which their preservation may cause to the Contractor's work under the contract. The Contractor will review the requirements in this Section and any notes from the joint site survey with each worker prior to them beginning work at the site.

01 12 00 ‐13

1.25.4 Environmental Assessment of Scope of Work Deviations

Any deviations, requested by the Contractor, from the drawings, plans and specifications, which may have an environmental impact, will be subject to approval by the COR and may require an extended review, processing, and approval time. The COR reserves the right to disapprove alternate methods, even if they are more cost effective, if the COR determines that the proposed alternate method will have an adverse environmental impact.

1.25.5 Water Resources

The Contractor shall monitor construction activities to prevent pollution of surface and ground waters. Toxic or hazardous chemicals shall not be applied to soil or vegetation unless otherwise indicated. All water areas affected by construction activities shall be monitored by the Contractor. For construction activities immediately adjacent to impaired surface waters, the Contractor shall be capable of quantifying sediment or pollutant loading to that surface water when required by State or Federally issued Clean Water Act permits.

1.25.6 Sound Intrusions

The Contractor shall keep construction activities under surveillance and control to minimize environment damage by noise. All equipment to have factory installed muffler system and comply with standard equipment decibel ratings.

1.25.7 Fuel and Lubricants

Storage, fueling and lubrication of equipment and motor vehicles shall be conducted in a manner that affords the maximum protection against spill and evaporation. Fuel, lubricants, and oil shall be managed and stored in accordance with all Federal, State, Regional, and local laws, and regulations. Used lubricants and used oil to be discarded shall be stored in marked corrosion-resistant containers and recycled or disposed in accordance with 40 CFR 279, State, and local laws, and regulations.

1.25.8 Previously Used Equipment

The Contractor shall clean all previously used construction equipment prior to bringing it onto the project site. The Contractor shall ensure that the equipment is free from soil residuals, egg deposits from plant pests, noxious weeds, and plant seeds. The Contractor shall consult with the USDA jurisdictional office for additional cleaning requirements.

1.26 Government Furnished Materials

Pursuant to Contract Clause FAR 52.245-1 Government Property, the Government will furnish the following materials and equipment for installation by the Contractor:

DESCRIPTION QUANTITY

Direct bury RV pedestals 52

Quantities indicated for the above-listed items marked with an asterisk are estimates. It is the intention of the Government to furnish all quantities of the asterisk items required to complete the work as specified, and the various quantities will be adjusted when necessary. Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government. Provide any additional quantities that are required.

1.27 Delivery, Storage and Handling

01 12 00 ‐14

1.27.1 Delivery

Deliver materials in their original, unopened containers or wrappings with labels intact and legible. Where materials are covered by a referenced specification number, the labels must bear the specification number, type, class, and shelf life expiration date where applicable. Deliver materials in sufficient quantity to allow continuity of work.

1.27.2 Storage

Store and protect materials from damage and weather in accordance with manufacturer's printed instructions, except as specified otherwise. Keep materials clean and dry. Store and maintain adhesives, sealants, primers and other liquid materials above 60 degrees F. Utilize insulated hot boxes or other enclosed warming devices in cold weather. Mark and remove damaged materials from the site. Use pallets to support and canvas tarpaulins to completely cover materials stored outdoors. Do not use polyethylene as a covering. Locate materials temporarily stored on the roof in approved areas, and distribute the load to stay within the live load limits of the roof construction. Remove unused materials from the roof at the end of each days work.

1.27.3 Handling

Prevent damage to edges and ends of roll materials. Do not install damaged materials in the work. Select and operate material handling equipment so as not to damage materials or applied roofing. Do not use materials contaminated by exposure or moisture. Remove contaminated materials from the site. Adhesives may contain petroleum distillates and may be extremely flammable; prevent personnel from breathing vapors, and do not use near sparks or open flame.

1.28 Conformance and Compatibility

Provide the entire roofing and flashing system in accordance with specified and indicated requirements.

Work not specifically addressed and any deviation from specified requirements must be in general accordance with recommendations of the National Roofing Contractors Association (NRCA) roofing manual as well as, membrane manufacturer’s published recommendations and details, ASTM D6369, and compatible with surrounding components and construction. Submit any deviation from specified or indicated requirements to the Contracting Officer for approval prior to installation.

1.29 Time Extensions for Unusually Severe Weather

This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with:

a. This provision specifies the procedure for section (d) of the CONTRACT CLAUSE 52.249-10 titled

"Default (Fixed Price Construction)". For the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect

01 12 00 ‐15 these anticipated adverse weather delays in all-weather dependent activities for the duration of the project.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORKDAYS BASED ON (5) DAY

WORK WEEK *

c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the duration of the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical path activities for 50 percent or more of the Contractor's scheduled workday.

d. Within ten days of the following month, the Contractor shall provide in writing a list of their proposed dates of the actual adverse weather delay days for each month. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph (b), above, the Contracting Officer will convert any qualifying delays to calendar days and issue a modification in accordance with the Contract Clause entitled "Default (Fixed Price Construction)". After the original contract completion date has passed, adverse weather that causes delay to the completion of the project will be granted day-for-day without deducting anticipated adverse weather delay days and will be converted from workdays to calendar days.

* Monthly anticipated weather delay days shall be adjusted proportionally if work is scheduled to be performed in a work week with greater than or less than a five-day work week. The following formula shall be used to adjust the monthly anticipated weather delays:

Adjusted monthly anticipated weather delays = A multiplied by (B divided by C); where A = The monthly anticipated adverse weather delay for a particular month based on a five-day work week. B = The actual average number of days work is scheduled to be performed in a work week during that month. C = The number five (5) e.g., If the monthly anticipated adverse weather delay for January based on a five day work week is 10 days, but the Contractor actually scheduled an average of a six-day work week for that month, the monthly anticipated weather delay would be adjusted by applying the above formula as follows: 10 x (6/5) = 12 days.

* Monthly anticipated weather delay days shall also be adjusted proportionally for those situations involving a fractional part of a month. Some examples are the month Notice to Proceed is acknowledged and the month of the original contract completion date. The following formula shall be used to adjust the monthly anticipated weather delays:

Adjusted monthly anticipated weather delays = D multiplied by (E divided by F); where

D = The monthly anticipated adverse weather delay for a particular month.

E = The number of calendar days during that fractional part of a particular month.

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Junction City, Kansas

2 3 4 5 7 7 6 6 5 7 5 4

01 12 00 ‐16

F = The number of calendar days in that month. eg., The monthly anticipated adverse weather delay for the particular month is 9 days. The original contract completion date is on the twentieth (20th) day of a thirty

(30) day month. The monthly anticipated adverse weather delay would be adjusted by applying the above formula as follows: 9 x (20/30) = 6 days.

2. MATERIALS

Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design, and workmanship and:

a. Have been in satisfactory commercial or industrial use for 2 years prior to bid opening including applications of equipment and materials under similar circumstances and of similar size.

b. Have been on sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period.

c. Where two or more items of the same class of equipment are required, provide products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in this section.

d. Products manufactured more than 3 years prior to date of delivery to site are not acceptable.

e. All products, as a minimum, meet requirements of UL, where UL standards are established for those items, and requirements of NFPA 70 for all materials, equipment, and device.

2.1 Service Panelboards

2.1.1 Provide panelboards in accordance with National Electrical Manufacturers Association (NEMA) 3R rating, 30” x 24” x 10” metallic, lockable and accommodate a 200 A service. Ensure panelboards for use as service equipment are also in accordance with UL 869A. Ensure panelboards have current rating, number of phases, and number of wires as indicated or specified herein. Ensure panelboards are rated for 240-volt, single-phase, 60-hertz. Ensure each panelboard, as a complete unit, has a short-circuit current rating equal to or greater than the integrated equipment rating indicated, but in no case less than 10,000 amperes symmetrical.

2.1.2 Ensure panelboards are designed such that individual breakers can be removed without disturbing adjacent units or without loosening or removing supplemental insulation supplied as means of obtaining required clearance. Provide main lugs or main circuit breakers mounted "above" branch breakers with current ratings as indicated. Use of sub-feed breakers is not acceptable unless specifically indicated otherwise. Where "space only" is indicated, make provisions for future installation of breakers.

2.1.3 Provide tinned copper or aluminum buses of the rating indicated, with main lugs or main circuit breaker. Provide all panelboards for use on grounded ac systems with a separate grounding bus in accordance with UL 67 bonded to the panelboard enclosure. Ensure grounding bus is a solid bus bar of rectangular cross section equipped with binding screws for the connection of equipment grounding conductors.

2.1.4 Provide bus bar connections to the branch circuit breakers that are the "distributed phase" or "phase sequence" type. Ensure single-phase, three-wire panelboard busing is such that when any two adjacent

01 12 00 ‐17 single-pole breakers are connected to opposite phases, two-pole breakers can be installed in any location.

Ensure current-carrying parts of the bus assembly are plated.

2.2 Circuit Breakers

2.2.1 Provide circuit breakers that conform to UL 489 and NEMA AB 3. Provide bolt-on type, molded-case, manually operated, trip-free circuit breakers, with inverse-time thermal-overload protection and instantaneous magnetic short-circuit protection. Completely enclose circuit breakers in a molded case, with a factory-sealed, calibrated sensing element to prevent tampering. Plug-in type, tandem, and half-size circuit breakers are not permitted.

2.2.2 Provide sufficient interrupting capacity of the panel and lighting branch circuit breakers to successfully interrupt the maximum short-circuit current imposed on the circuit at the breaker terminals.

Provide circuit breaker interrupting capacities with a minimum of 10,000 A and that conform to NEMA AB 3. Series rating of circuit breakers or overcurrent protective devices to achieve indicated interrupt rating is not permitted.

2.2.3 Provide the common-trip-type multipole circuit breakers having a single operating handle and a two-position on/off indication. Provide circuit breakers with temperature compensation for operation in an ambient temperature of 104 degrees F. Provide circuit breakers that have root mean square (rms) symmetrical interrupting ratings sufficient to protect the circuit being supplied. Interrupting ratings may have selective-type tripping (time delay, magnetic, thermal, or ground fault).

2.2.4 Provide a phenolic-composition breaker body capable of having such accessories as handle-extension, handle-locking, and padlocking devices attached where required to meet lock-out/tag-out requirements of NFPA 70E.

2.3 Rigid Nonmetallic Conduit

Ensure rigid nonmetallic conduit complies with NEMA TC 2, NEMA TC 3, and UL 651 as applicable with a wall thickness not less than Schedule 40.

2.4 Conductors

2.4.1 Rated Circuit Voltages: All power wire and cable must have minimum rated circuit voltages in accordance with NEMA WC 70, ANSI/NEMA WC 71/ICEA S-96-659, or NEMA WC 74/ICEA S-93- 639 as applicable. Power wire and cable for circuit voltages rated 0-600 volts must be rated not less than 600 volts. Control wire and cable must have minimum rated circuit voltages in accordance with NEMA WC 57 but must be rated 600 volts if routed in raceway with other conductors that are rated 600 volts. Do not use wires and cables manufactured more than 12 months prior to date of delivery to site.

2.4.2 Conductor characteristics: Conductors must conform to all the applicable requirements of NEMA WC 57, NEMA WC 70, ANSI/NEMA WC 71/ICEA S-96-659as applicable. Copper conductors must be annealed copper material and they may be bare, or tin- alloy- coated, if required by the type of insulation used. Intermixing of copper and aluminum conductors in the same raceway is not permitted. Conductors #6 AWG and smaller must be copper. Aluminum conductors of equivalent ampacity can be used instead of copper for #4 AWG and larger sizes.

01 12 00 ‐18

2.5.3 Wire Size: Minimum wire size must be No. 12 AWG for power and lighting circuits; No. 10 AWG for current transformer secondary circuits.

2.5.4 Insulation and Shielding Wires in conduit, other than service entrance, must be 600-volt, Type THWN/THHN conforming to UL 83. Insulation for control wire and cable must meet the requirements of NEMA WC 57. Insulation requirements for wire and cable rated less than 2,000 volts must meet the requirements of NEMA WC 70. Power Cables, 2,000 Volts and Below. The insulation thickness for single-conductor and multiple-conductor power cables rated 2,000 volts and below must be as required by NEMA WC 70, as applicable. Thickness of the jackets of the individual conductors of multiple-conductor cables must be as required by NEMA WC 57,NEMA WC 70, ANSI/NEMA WC 71/ICEA S-96-659 as applicable and must be in addition to the conductor insulation thickness required by the applicable respective NEMA publication for the insulation used. Thickness of the outer jackets and associated coverings of the assembled multiple-conductor cables must be as required by NEMA WC 57, NEMA WC 70, ANSI/NEMA WC 71/ICEA S-96-659, or NEMA WC 74/ICEA S-93-639 as applicable.

2.5.6 Color Coding Insulation: Individual conductors of multiple- conductor cables must be color-coded in accordance with ICEA S-58- 679, except that colored braids will not be permitted. Only one color-code method must be used for each cable construction type.