This document is an amendment to a federal solicitation for levee rehabilitation work along the Missouri River Levee System 500R in Kansas. The amendment provides updates to specifications, drawings, bid schedule line items, and submission instructions. Key changes include extending the response deadline; modifying estimated quantities and descriptions for uncompacted and compacted pervious fill, new channel excavation work, and berm fill; and reducing the estimated quantity for overtopping erosion compacted fill. The amendment also updates benching details, borrow area notes, and adds requirements for impervious caps on breach repairs and riprap extents. Bidders must acknowledge all amendments and submit one original and one copy of their bid, bid schedule, and bid bond by the new deadline of June 25, 2020 at 2:00 PM through the provided conference line andProjNet system, with no new bidder inquiries accepted after June 8.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Update to conference line information
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DQ20B1034
X 9B. DATED (SEE ITEM 11)
22-May-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Jun-2020
CODE
USACE, KANSAS CITY +
FEDERAL BLDG, CT-C
601 E 12TH ST RM 647
KANSAS CITY MO 64106-2896
W912DQ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DQ20B1034
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGE
The SOLICITATION is amended as follows:
NOTE: Deleted text is shown with strikethrough. Added text is shown with underline.
1. SPECIFICATIONS:
a. Delete Section 01 12 00.00 23 in its entirety.
b. See attached revised Section 01 22 00.00 10
c. Section 35 41 00 Paragraph No. 3.2.2 Overtopping and Toe Erosion Areas
The preconstruction survey in areas of overtopping and toe erosion shall consist of a full topographic survey of the areas where fill will be placed. This 3D surface will be compared to the governments CAD design surface for determination of fill quantities to be paid out under the unit price items for each repair.
The preconstruction survey in areas of overtopping erosion area shall consist of a minimum of one point at every 25ft along the levee top to document the maximum depth of the scour. This depth will be compared to the estimated depth shown on the contract documents. If a change in the depth of excavation is necessary a contract modification will be issued to compensate for the additional depth of repairs. The contractor is repsonsible for determining their estimated volume of borrow necessary to reconsruct the levee to its required elevation.
d. Section 35 41 00 Paragraph No. 3.9 DEWATERING AND DIVERSION
Anticipated dewatering varies by feature. Contractor is responsible for design and performance of whatever means are necessary for dewatering to maintain a groundwater level depth of 3ft below the excavation for the structure with an assumed river elevation of 15ft on the Rulo Gage. This may include dewatering wells or well points. All wells or well points shall be grouted in place and maintain impervious nature of embankment zones.
All fill shall be placed in the dry. Exception will be made for placement of pervious fill in the Breaches shown on sheet CS302 which may be completed underwater. The contractor is responsible for design of and is to assume the dewatering of SCOUR holes can be completed with use of sump pumps, diversion ditches and earthen cofferdams. Contractor should assume sumps with 4 pumps capable of 1,500 gpm each for dewatering efforts for placement of fill in the scour hole. Wells are not required for scour holes.
Periods of high river elevation or elevated groundwater will be treated as weather delays within the requirements of the contract and as determined by the COR. Extended periods longer than 2 weeks for which groundwater is an issue while the site is otherwise workable will constitute a modification to address design features to accommodate or add additional groundwater controls.
Accomplish surface and groundwater control in coordination with the required excavation and embankment construction. Surface and/or groundwater control may necessitate the use of temporary diversion ditches, cofferdams and/or dewatering by the use of pumping. Methods for care of surface water and for controlling the surface and groundwater levels will be subject to approval of the Contracting Officer. Borrow pits must be drained and kept dry during excavation, as excavation will not be permitted in water nor will excavated material be scraped, dragged or otherwise moved through water. Drain borrow areas by ditching, sump pumping, or other approved methods. Drain borrow areas excavated under this contract and flooded from rains or high river stages and allow to dry as quickly as practicable after the high river stage has passed.
Minimize surface runoff from entering the work areas. Complete the necessary ditching or earthwork shaping at the end of each workday or as necessary to prevent surface runoff from entering the work area. Drain excess precipitation that collects in the work areas and allow to dry as quickly as practicable before work resumes.
e. Section 32 92 19 Paragraph No. 3.1.1. EXTENT OF WORK
Provide mowing, herbicide, fertilizing, seeding, and surface topdressing of all newly graded finished earth surfaces as required in all areas identified for overseeding or rehabilitation, and at all areas inside or outside the limits of construction that are disturbed by the Contractor's operations.
Provide mowing, herbicide, fertilizing, seeding and maintenance in all areas identified for overseeding on sheet CS501. See paragraph RENOVATION OF EXISTING TURF. Mulching is not required as sufficient natural mulch is assumed available from mowing operations in overseeding areas.
Provide mowing, herbicide, fertilizing, seeding, surface topdressing and maintenance in all areas within the levee footprint (including stability berms) and within a 15ft proximity of the levee toe on both land and riversides which the contractor disturbs. See paragraph SEEDING DISTURBED
AREAS.
Borrow areas to be left as discussed on the respective plan sheet for natural revegetation or agricultural use.
f. Section 32 92 19 Paragraph No. 3.1.1.1 TOPSOIL
Provide 4 inches of topsoil to meet indicated finish grade in disturbed areas. Underseepage berms shall receive 1 ft as discussed on the plan sheets. Borrow areas do not require topsoil placement.
Remove debris and stones larger than 3/4 inch in any dimension remaining on the surface after finish grading. Correct irregularities in finish surfaces to eliminate depressions. Protect finished topsoil areas from damage by vehicular or pedestrian traffic.
g. Section 35 41 00 Paragraph No. 3.5 STRIPPING
The entire area within the limits of existing ground to receive embankment and structures, together with strips 5 feet wide, beyond and contiguous thereto, existing levees to be degraded, ponding areas, and ditches shown on the drawing must be stripped to remove crops, weeds, grass, and other vegetative materials to the ground surface and topsoil to a depth of 4 inches.
Borrow pits shall be stripped of available topsoil for incorporation into the levee. This excludes agricultural areas which are identified for utilization of pervious deposits from flooding.
Following completion of borrow activities, topsoil is NOT required to be replaced in borrow areas.
h. Section 35 41 00 Paragraph No 3.3 CLEARING
Accomplish clearing within the limits of existing ground to receive embankment and structures, together with strips 5 feet wide, beyond and contiguous thereto, existing levees to be degraded, ponding areas, ditches, structures, traverses, channels, riprap, revetment, borrow areas and ramps.
Clear trees, downed timber, snags, slash, brush, garbage, trash, debris, fencing and other items flush with the existing ground surface. Protect trees and vegetation designated to be left standing or to remain from damage from construction operations. Limit clearing of borrow areas to the minimum area required for construction operations.
The levee district is responsible for removing the flood debris from the levee slopes. The contractor is responsible for removing debris from any other areas as required to complete the work including but not limited to the berm, and borrow locations. Debris shall be piled within the construction limits, in proximity to where it was deposited by the flood, and left for disposal by others.
2. DRAWINGS:
a. Sheet CS101 - updated excavation and benching limit lines per updated detail on D7/CS501
b. Sheet CS102 - added general note 5 about protecting agricultural supply lines around pump
c. Sheet CS104 - updated excavation and benching limit lines per updated detail on D7/CS501
d. Sheet CS105 - updated excavation and benching limit lines per updated detail on D7/CS501
e. Sheet CS111 - updated excavation and benching limit lines per updated detail on D7/CS501
f. Sheet CS114 - added keynote 9 to remove existing drainage structures within construction limits and added width to pumping pipe rip rap discharge
g. Sheet CS201 - updated available borrow material available in borrow area 1
h. Sheet CS302 - added requirement of minimum 3’ impervious cap to breach repair
i. Sheet CS303 - added rip rap extents to channel realignment
j. Sheet CS304 - updated excavation and benching limit lines per updated detail on D7/CS501
k. Sheet CS305 - updated excavation and benching limit lines per updated detail on D7/CS501
l. Sheet CS501 - updated benching detail to require minimum 1’ of horizontal bench instead of 10’, added note that benching is not required in pervious materials, and updated note 3 on detail A6 to have clearer language on what is required of contractor
m. Sheet CS503 - added detail A7 for riprap required around the inlet and outlet structures, updated detail E1 to show rip rap limits better
n. Sheet CS504 - added pipe type and size note
o. Sheet SF110 - added dimension strings showing the length of the cradles on detail A7
3. Offerors are required to acknowledge receipt of this amendment on the Bidding Form in the space provided. Failure to acknowledge all amendments may cause rejection of the proposal.
4. All other terms and conditions remain unchanged and in full force.
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 23-Jun-2020 02:00 PM to 25-Jun-2020 02:00 PM.
CLIN 0006
The CLIN extended description has changed from:
Breach Un-compacted Pervious Fill Station 204+00 to 207+00 estimated 21,000 cubic yards
To:
Breach Un-compacted Pervious Fill Station 204+00 to 207+00 estimated 27,000 cubic yards
CLIN 0007
Breach Compacted Fill Station 204+00 to 207+00 Estimated 15,000 cubic yard
Breach Compacted Fill Station 204+00 to 207+00 Estimated 11,000 cubic yard
CLIN 0008
New Channel Excavation, Placement, Compation Estimated 7,500 Cubic yard
New Channel Excavation, Placement, Compation Estimated 8,700 Cubic yard
CLIN 0009
Berm un-compacted fill Station 114+00 to 138+00 Estimated 9,000 cubic yard
Berm un-compated fill of landside toe scour on berm Station 114+00 to 138+00 Estimated 9,000 cubic yard
CLIN 0010
Overtopping Erosion Compacted Fill Remaining Levee Estimated 40,000 cubic yard
Overtopping Erosion Compacted Fill Remaining Levee Estimated 20,000 cubic yard
SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS
The following have been modified:
SUBMISSION REQUIREMENTS
All bids are due by the time specified in box 13 A.
The public bid opening will begin at the time specified in Box 13 A, through the following conference line:
Conference Line Number:
1-888-2512909 or 1-215-861-0692 then access code : 6307173 security: 1234
Submit one (1) original and one (1) copy of the following:
a. Bid schedule - complete by fully entering all amounts in the supplemental bid schedule.
b. Ensure Bid is signed by a Principal of your company with authority to do so.
c. Ensure all Amendments are acknowledged.
d. Bid Bonds - Ensure the raised seals are legible in the electronic copy.
INQUIRIES/QUESTIONS
Prospective Bidders shall submit contracting and technical inquiries and questions concerning this solicitation document via Bidder Inquiry in ProjNet at www.projnet.org/projnet, along with emailing the Program Manager Kent Myers at kent.n.myers@usace.army.mil and the Contract Specialist richard mathena at richard.a.mathena@usace.army.mil.
a. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into the system. To self-register, go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, enter the Bidder Inquiry Key for this solicitation listed below, your email address, and then click login.
Fill in all required information and click create user. Verify that information on the next screen is correct and click continue.
b. From this page, you may view all bidder inquiries or add a new inquiry.
c. Bidders will receive an acknowledgement of their questions via email, followed by an answer to their questions after it has been processed by our technical team. ***Please Note: Bidders shall only submit one
(1) Question per inquiry. All inquiries containing multiple questions shall be rejected***
d. The Solicitation Number is: W912DQ20B1034
e. The Bidder Inquiry Key is: TZ52W2-NR4WD5
f. Plan Room Key is: K3CJJ6-D6XM7Y
The Bidder Inquiry System will be unavailable for new inquiries after 8 June 2020, at 3:00 PM local, Kansas City, time in order to ensure adequate time is allotted to form an appropriate response to inquiries and amend the Solicitation if necessary.
Bidders are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The ProjNet call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago) or by appointment for OCONUS. The telephone number for the Call Center is 1- 800-428-HELP. Email to staff@rcesupport.com.
(End of Submission Requirements)
(End of Summary of Changes)