AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 14
0002 May 11, 2018
W912DQ
USACE, KANSAS CITY
FEDERAL BUILDING, RM 647
601 EAST 12 STREET
KANSAS CITY, MO 64106-2896
SEE ITEM 6
W912DQ18B4003
Apr 16, 2018
Bids are due May 16, 2018 at 1:30 PM local time.
BOLLING FEDERAL BUILDING ENHANCED SECURITY: Due to enhanced security in the Bolling Federal Building the Bid Opening Room, Room G41, will open 30 minutes prior to bid opening and will remain open until all bids are opened and read.
"SEE CONTINUATION"
VA Call Center, Bldg 409 W912DQ-18-B-4003
Fort Riley, Kansas Amendment 0002
Amendment 0002 – Page 2
CONTINUATION PAGE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this amendment:
The Solicitation is amended as follows:
Deleted text is shown with a strikethrough. Added text is shown with underline.
1. SPECIFICATION CHANGE
a. Section 01 33 29 “Sustainability Reporting”, Paragraph 1.4 “Guiding Principles Validation (GPV)”
Item e. is changed to read as follows:
e. Provide construction related documentation for the project Sustainability eNotebook, and keep updated with regularly-scheduled construction meetings. Include construction related documentation containing the following components;Refer to Attachment 2, Guiding Principles
Checklist at the end of this specifications section.
(1) HPSB Checklist
(2) Sustainability Action Plan
(3) Documentation illustrating HPSB Guiding Principles Requirements compliance (including submittals that pertain to sustainability reporting)
b. Section 01 33 29 “Sustainability Reporting”, Paragraph 1.4 “Guiding Principles Validation (GPV)”
ADD the following New Item f. to the end of Paragraph 1.4.
f. Provide construction related documentation for the project Sustainability eNotebook, and keep updated with regularly-scheduled construction meetings. Include construction related documentation containing the following components;
(1) HPSB Checklist
(2) Sustainability Action Plan
(3) Documentation illustrating HPSB Guiding Principles Requirements compliance
(including submittals that pertain to sustainability reporting)
(4) Guiding Principles Checklist
c. Section 01 33 29 “Sustainability Reporting”, ADD the following two NEW attachments to the end of Section 01 33 29. Copies of the attachments accompany this amendment.
Attachment 1 - Energy Sustainability Record Card
Attachment 2 – Guiding Principles Checklist – LEED v4 for New Construction and Major
Renovations
d. Section 09 30 10 “Ceramic, Quarry, And Glass Tiling”, ADD the following New Paragraphs 2.4.8
“Patch Leveler”:
2.4.8 Patch Leveler
VA Call Center, Bldg 409 W912DQ-18-B-4003
Fort Riley, Kansas Amendment 0002
Amendment 0002 – Page 3
Provide cementitious, trowelable, patch material to remedy any depressions/deviations in wall and floor substrates to allow for plumb/flat installation meeting the minimum mortar coverage requirements. It is understood that the substrate may not be in tolerance for large unit tile, and furthermore, prep shall be under the scope of the tile installation package.
Provide patch leveler in locations where wood floor substrate meets existing concrete to provide flush transition. Product shall be Mapei, Mapecem Quickpatch or equal.
e. Section 09 66 16 “Terrazzo Floor Tile”, ADD the following New Paragraph 2.5 “Patch Leveler”
2.5 PATCH LEVELER
Provide cementitious, trowelable, patch material to remedy any depressions/deviations in floor substrates to allow for plumb/flat installation meeting the minimum adhesive coverage requirements. It is understood that the substrate may not be in tolerance for large unit tile, and furthermore, prep shall be under the scope of the tile installation package. Provide patch leveler in locations where wood floor substrate meets existing concrete to provide flush transition. Product shall be Mapei, Mapecem Quickpatch or equal.
2. DRAWING CHANGES
a. DELETE the following Drawing Sheets and REPLACE with the REVISED Drawing Sheets that accompany this amendment.
CS100 SITE PLAN
CU100 UTILITY PLAN
AD120 SECOND FLOOR DEMOLITION PLAN
A-201 BUILDING ELEVATIONS
A-611 WINDOW DETAILS AND ELEVATIONS
F-001 GENERAL LIFE SAFETY NOTES
High Performance Sustainabile Buildings - Guilding Principles Compliance Worksheet
Element Color Coding:
Compliance Indications:
Yes - Compliant with Element
No Entry Maybe - Possible Compliance Not Required No - Not Compliant with Element
Federal Requirements for High Performance Sustainable Buildings (HPSB) HPSB I: Employ Integrated Design Principles Achievable Points 2 Possible Points 2
Yes HPSB I.1 Integrated Design 1 Yes HPSB I.2 Commissioning 1
HPSB II: Optimize Energy Performance Achievable Points 5 Possible Points 5
Yes HPSB II.1 Energy Efficiency, Achieve Option 1 or 2 and insert design percentage 1
1 Yes Reduce energy use 30% Below ANSI/ASHRAE/IESNA Standard 90.1-
2013, OR
If not at least 30% below ANSI/ASHRAE/IESNA Standard 90.1- 2013, will the design achieve the maximum level of energy efficiency that is life-cycle cost-effective?
Insert percentage below ANSI/ASHRAE/IESNA Standard 90.1-2013 in terms of energy use (e.g. 32) Insert building energy intensity (Btu/SF) calculated with the energy model per 10 CFR 433
Roof Attributes (Recommended) Cool roof (LEED SS cr 7.2 or Energy Star) Green roof Solar electric Solar thermal Solar passive
No Achieve "Designed to Earn the Energy Star" rating - Benchmark from first year of operation (Recommended)
Yes HPSB II.2 1
Yes HPSB II.3 On-site Renewable Energy - Solar Hot Water Heater System 1
Yes Lifecycle cost assessment found solar hot water heater system not effective When lifecycle cost effective, solar hot water system installed - min 30% demand Insert percentage achieved
Yes HPSB II.4 On-site Renewable Energy 1
Yes Lifecycle cost assessment found renewable energy generation projects not effective
When lifecycle cost effective, renewable energy generation projects installed
Renewable energy type Insert first renewable energy type, if applicable Insert second renewable energy type, if applicable
Insert generation capacity (kW) Insert percentage of total building
Yes HPSB II.5 Measurement and Verification - Advanced Metering 1 Yes Water Metering: Select N/A if not used Yes Electric Metering: Select N/A if not used Yes Natural Gas Metering: Select N/A if not used N/A Steam Metering: Select N/A if not used
HPSB II.6
EISA 2007 II.7 Reduction in fossil fuel-generated energy consumption (Recommended) EISA 2007 II.8 Data Center Energy Consumption (Recommended)
Entry/Drop-Down Box Selection Data-Entry Subquestions
Preferential use of ENERGY STAR or FEMP-designated equipment, when lifecycle cost effective
Project Case Study Entered in High Performance Federal Buildings Database (Recommended)
5/9/2018 1
Amendment 0002
01 33 29 - Attachment 1
High Performance Sustainabile Buildings - Guilding Principles Compliance Worksheet
Element Color Coding:
Compliance Indications:
Yes - Compliant with Element
No Entry Maybe - Possible Compliance Not Required No - Not Compliant with Element
Federal Requirements for High Performance Sustainable Buildings (HPSB)
Entry/Drop-Down Box Selection Data-Entry Subquestions
HPSB III: Protect and Conserve Water Achievable Points 7 Possible Points 7
Yes HPSB III.1 Indoor Water - 20% Reduction 1 20.0% Insert percentage achieved
Yes HPSB III.2 Outdoor Water - Reduce Potable Water Use by 50% 1 Yes HPSB III.3 Outdoor Water - Stormwater runoff 1
Yes HPSB III.4 1
Insert cost to implement Yes HPSB III.5 Process water potable water use 1
Yes Energy efficiency measures using water were considered and the cost was included in lifecycle cost assessment Energy efficiency measures using water were not considered for the design
Yes HPSB III.6 1 Yes HPSB III.7 Water Efficient Products - Irrigation Contractors 1
HPSB IV: Enhance Indoor Environmental Quality Achievable Points 9 Possible Points 9
Yes HPSB IV.1 Thermal Comfort, ASHRAE 55-2004 1 Yes HPSB IV.2 Ventilation: ASHRAE 62.1-2007 1 Yes HPSB IV.3 1 Yes HPSB IV.4 Daylighting - 75% of Spaces 1 Yes HPSB IV.5 Daylighting - Controllability of Systems 1 Yes HPSB IV.6 1 Yes HPSB IV.7 Protect Indoor Air Quality during Construction 1 Yes HPSB IV.8 Protect Indoor Air Quality after Construction 1 Yes HPSB IV.9 Environmental Tobacco Smoke (ETS) Control 1
HPSB V: Reduce Environmental Impact of Materials Achievable Points 6 Possible Points 6
Yes HPSB V.1 Recycled Content 1 Yes HPSB V.2 Biobased Content 1 Yes HPSB V.3 Environmentally Preferable Products 1 Yes HPSB V.4 Waste and Materials Management - Recycling 1 Yes HPSB V.5 Waste and Materials Management - Divert 60% from Disposal 1 Yes HPSB V.6 Ozone Depleting Compounds 1
HPSB Totals Possible Points 29 29 Federal Requirements Achieved (29 line items) 0 Federal Requirements Maybe Achieved 0 Federal Requirements Not Achieved
100% Overall Compliance with High Performance Sustainable Buildings (HPSB) Guiding Principles
Water-Efficient Products
Moisture Control
Low Emitting Materials
Outdoor Water - Achieve Pre-Development Hydrology when technically feasible, when disturbance
> 5,000 GSF
5/9/2018 2
01 33 29 - Attachment 1
Department of Veterans Affairs Checklist published: September 10, 2015
Introduction:
The attached LEED v4 for New Construction and Major Renovations (LEED‐NC) points are mandatory for a project to be considered sustainable per the Federal Guiding Principles for High Performance Sustainable Buildings.
Application:
Major Construction and Renovation ($10 million or higher): Checklist must be completed and provided to the VA project manager at every design submission and reported after the certification is awarded (post‐construction). LEED certification is also required.
Minor Construction and Renovation (less than $10 million): Checklist must be completed and provided to the VA project manager at every design submission and reported after post‐ construction. Verification by a LEED Accredited Professional is required. LEED certification is optional.
Completion:
The checklist may be completed by the contracted project team, but must be verified by the VA Project Manager. The signed version must be retained in the project record.
Reporting:
A copy of this checklist, signed by the VA Project Manager, must be submitted to:
Major Construction: Facilities Standards Service (OCFM), SustainableDesign@va.gov, not later than December 1 of the calendar year in which VA received the third‐party certification.
Minor Construction: VA Office of Asset Enterprise Management, GreenVA@va.gov, not later than December 1 of the calendar year of end of construction.
VERIFICATION – check one The project is certified under LEED v4 for New Construction and Major Renovations and has achieved the points and thresholds indicated in the following table.
In my professional opinion, the project has met all credit and threshold requirements indicated in the following table.
PRINTED NAME: DATE
VA PROJECT MANAGER TITLE:
VA PROJECT MANAGER EMAIL:
VA PROJECT MANAGER PHONE NUMBER:
GUIDING PRINCIPLES CHECKLIST
LEED v4 for New Construction and Major Renovations
01 33 29 - Attachment 2
PROJECT TITLE:
FACILITY NAME:
LEED‐NC Credit Description Guiding
Principle
Integrative Process None Required ‐
Location and Transportation None Required ‐
Sustainable Sites Rainwater management III.B.2
Water Efficiency Outdoor water use reduction (select one option below) III.B.1
Option 1. No irrigation required
Option 2. Reduced irrigation 50%
Option 2. Reduced irrigation 100%
Indoor water use reduction (prerequisite 20% minimum) III.A and III.D
Energy and Atmosphere Fundamental Commissioning of Building Energy Systems I.B and II.C
Minimum energy performance II.A.2
Building‐level energy metering II.D Fundamental refrigerant management V.E Enhanced commissioning (option 1) I.B Renewable energy production (VA requirement is 10% renewable electric and 30% solar hot water)
II.B
Enhanced refrigerant management V.E
Materials and Resources Storage and collection of recyclables V.D
Construction and demolition waste management (select one option below) V.D divert 50% and three material streams divert 75% and four material streams
Indoor Environmental Quality Minimum indoor air quality performance IV.A
Environmental tobacco smoke control IV.F
Low‐emitting materials: (maximum points; select all of the following) IV.D
Interior paints and coatings
Interior adhesives and sealants
Flooring
Composite wood
Ceilings, walls, thermal, and acoustic insulation
Furniture
Construction indoor air quality management plan IV.E
Indoor air quality assessment (option 1: flush out) IV.E
Daylight (any option, 75%) IV.C
S O
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
S U
B M
IT
T E
D B
Y
D A
T E
C O
N T
R A
C T N
O
C H
E C
K E
D B
Y
D R
A W
N B
Y
IS
S
U E D
A T
E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
®of Engineers
US Army Corps
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
BUILDING 409
BUILDING 410
(A S
P H
A L T
P E
R S
H
IN
G A
V E
N U
E
PERSHING COURT (ASPHALT)
DS
DS
DS DS
DS
DS
(A S
P H
A L T
DS
P E
R S
H
IN
G A
V E
N U
E
DS
DS
DS
DS
DS
DS
DSDS DS
DSDSDS
DS: AEC_Screen.dscript.dscriptPD: AEC_pdf.pltcfg11:51:34 AM 5/11/2018 c:\users\g5edgjla\pw_working\cenwk500\d0172245\V001_CS100.dgn
F
IL
E N
A M
E
A N
S I
D
CS100
E
E C
O V
E R S
H E
E T
P -4
B
L D
G
V
A C
A L L C
E N
T E
R
B U
IL
D
IN
G
R
E N
O V
A T
IO
N
F O
R T R
IL
E Y
K A
N S
A S
S E
E C
O V
E R S
H E
E T
K A
N S
A S C
IT
Y
M O
E T
H S
T R
E E
T
K A
N S
A S C
IT
Y D
IS
T R
IC
T
D R
A W
IN
G C
O D
E
D R
A W
IN
G
C O
D E
V
C S .d g nA P
R
IL
H
M
IL
D E
N B
E R
G E
R
C F
O R
S Y
T H
F
O R
S Y
T H
E
GENERAL SHEET NOTES
A1 SCALE: 1" = 20' 20' 40'0
N
S
IT
E P
L A
N
ATFP BOUNDARY (39')
A T F P B
O U
N D
A R
Y (3
A T F P B
O U
N D
A R
Y (5
A T F P B
O U
N D
A R
Y
A T F P B
O U
N D
A R
Y
ATFP BOUNDARY (54')
ATFP BOUNDARY (54')
A T F P B
O U
N D
A R
Y (5
ATFP BOUNDARY (54')
SITE PLAN
J
S
C
IA
R R
A
WHEEL STOP (TYP)
4' SIDEWALK
S
ID
E W
A L
K
S
ID
E W
A L
K
S
ID
E W
A L
K
6' SIDEWALK
6' SIDEWALK
TIE INTO EXISTING ASPHALT
TIE INTO EXISTING CURB AND GUTTER
TIE INTO EXISTING CURB AND GUTTER
TIE INTO EXISTING CURB AND GUTTER
TIE INTO EXISTING ASPHALT
TIE INTO EXISTING ASPHALT
TIE INTO EXISTING CURB AND GUTTER
ADA ACCESSIBLE SIGN (TYP)
LOADING ZONE SIGN
TIE INTO EXISTING CURB AND GUTTER
TIE INTO EXISTING ASPHALT
CONSTRUCTION/STAGING LIMIT
INSTALL CONCRETE DITCH
SEE SE111 FOR DETAILS
CONCRETE ADA RAMP
INSTALL SPLASHBLOCK
INSTALL SPLASHBLOCK
INSTALL SPLASHBLOCK
INSTALL SPLASHBLOCK
REMOVE & REPLACE SIDEWALK
S
ID
E W
A L
K
SEE F6/CP501 FOR DETAILS
INSTALL CONCRETE CURB
SEE NOTE 3
GRATE
EQUIPMENT PAD
INSTALL SPLASHBLOCK
SEE NOTE 3
GRATE
A7/CS501
BOLLARD (TYP)
E1/CS501
INSTALL SPLASHBLOCK
D8/CP501
GUTTER (TYP)
INSTALL CURB AND
A7/CS501
BOLLARD (TYP)
TIE INTO EXISTING SIDEWALK
TIE INTO EXISTING SIDEWALK
TIE INTO EXISTING SIDEWALK
TIE INTO EXISTING SIDEWALK
M A
Y
R E
V
IS
E D I
N A
C C
O R
D A
N C
E W
IT
H A
M E
N D
M E
N T
FINAL
SEE NOTE 8
EQUIPMENT PAD
PLACEMENT. SEE ELECTRICAL PLANS FOR CONNECTION COORDINATION.
EQUIPMENT PAD FOR GENERATOR IS 7'x15'. COORDINATE WITH COR FOR 8.
TOTAL STALLS: 8
ADA ACCESSIBLE: 8
REGULAR STALLS: 0
POV PARKING INFORMATION:7.
SEE CS501 FOR SITE DETAILS.6.
SEE CG100 FOR CONTROL POINTS.5.
SEE MECHANICAL AND ELECTRICAL PLANS FOR EQUIPMENT.4.
PENETRATIONS THROUGH THE GRATING WITH MECHANICAL DRAWINGS.
SPECIFICATION 05 50 13 FOR ADDITIONAL REQUIREMENTS. COORDINATE
NEW GALVANIZED STEEL GRATING COVERS AT WINDOW WELLS. REFER TO 3.
SEE STRUCTURAL PLANS FOR ADA RAMP DETAILS.2.
ATFP SETBACK DISTANCES ARE MET PER UFC 4-010-01.1.
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
S U
B M
IT
T E
D B
Y
D A
T E
C O
N T
R A
C T N
O
C H
E C
K E
D B
Y
D R
A W
N B
Y
IS
S
U E D
A T
E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
®of Engineers
US Army Corps
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
BUILDING 409
BUILDING 410
(A S
P H
A L T
P E
R S
H
IN
G A
V E
N U
E
CB
D
S
D
PERSHING COURT (ASPHALT)
CB
W
WW
E
DS
DS
CO
DS DS
DS
DS
(A S
P H
A L T
DS
P E
R S
H
IN
G A
V E
N U
E
CB
DS
DS
DS
DS
CO
DS
W
G
DS
G
C
C
E
DSDS DS
E
E
C
DSDS
C
DS
CO
CO
MH-24C
MANHOLE
TELECOMMUNICATIONS
DS
DS
DS: AEC_Screen.dscript.dscriptPD: AEC_pdf.pltcfg3:00:30 PM 5/9/2018 pw://COE-NWKPWP50KAN.nwk.ds.usace.army.mil:PWNWK500/Documents/MIL/VA/v001Riley Bldg 409/6.0 Engineering-Design/6.1 Drawings/CAD_BIM/_Sheets/V001_CU100
F
IL
E N
A M
E
A N
S I
CU100
E
E C
O V
E R S
H E
E T
P -4
B
L D
G
V
A C
A L L C
E N
T E
R
B U
IL
D
IN
G
R
E N
O V
A T
IO
N
F O
R T R
IL
E Y
K A
N S
A S
S E
E C
O V
E R S
H E
E T
K A
N S
A S C
IT
Y
M O
E T
H S
T R
E E
T
K A
N S
A S C
IT
Y D
IS
T R
IC
T
D R
A W
IN
G C
O D
E
D R
A W
IN
G
C O
D E
A P
R
IL
H
M
IL
D E
N B
E R
G
F
O R
S Y
T H
F
O R
S Y
T H
E
GENERAL SHEET NOTES
20' 40'0
N
U T
IL
IT
Y P
L A
N J S
C
IA
R R
A
V
C U
.d g n
WITH PAVEMENT ELEVATION
ADJUST WATER VALVE TO BE FLUSH
E 1,659,380.37
N 269,647.00
INSTALL CLEANOUT
E 1,659,379.52
N 269,639.69
INSTALL CLEANOUT
E 1,659,316.69
N 269,591.15
INSTALL 22.5° BEND
E 1,659,308.15
N 269,578.51
INSTALL 22.5° BEND
E 1,659,303.08
N 269,575.31
INSTALL POST INDICATOR VALVE
E 1,659,289.47
N 269,566.72
INSTALL 6" x 6" TEE
SEE F1/CU501
FL = 1109.66'
E 1,659,435.46
N 269,680.63
CONNECT TO EXISTING 8" VCP
FL = 1111.15'
TO WITHIN 5' OF THE BUILDING
EXTEND SANITARY SERVICE
BUILDING
TO WITHIN 5' OF THE
EXTEND FIRE SERVICE LINE
3 1/2 '
2'
/8
T Y
P
1'
SEE NOTE 3
3' x 3' CONDENSING UNIT (TYP)
A1
UTILITY PLAN
SCALE: 1" = 20' A8
ENLARGED PLAN
SCALE: 1" = 10' 10' 20'0
SEE NOTE 3
EQUIPMENT PAD
SEE NOTE 3
EQUIPMENT PAD
FINAL
NW FL IN 8" VCP ELEV = 1108.44
N/NW FL IN 8" VCP ELEV = 1108.36
SE FL OUT 8" VCP ELEV = 1108.28
TOP SS MH ELEV= 1113.11
CONNECTION OF SANITARY SERVICE TO EXISTING SANITARY SEWER.
CONTRACTOR SHALL COORDINATE WITH THE INSTALLATION PRIOR TO 10.
SEE SHEETS CU501 & CU502 FOR UTILITY DETAILS.9.
REFERENCE ELECTRICAL DRAWINGS FOR LIGHTING AND POWER LINES.
ELECTRICAL COMPONENTS SHOWN FOR CONFLICT INFORMATION. 8.
IF REQUIRED. SEE MECHANICAL PLANS FOR FURTHER INFORMATION.
RPZ AND BACKFLOW PREVENTER SHALL BE LOCATED INSIDE THE BUILDING, 7.
MEET SPRINKLER SYSTEM REQUIREMENTS.
DEPARTMENT CONNECTION LOCATION AND DETAILS. SIZE FIRE LINE TO
REFER TO ARCHITECTURAL AND MECHANICAL PLAN FX100 FOR EXACT FIRE 6.
ALL WATER LINES SHALL BE PVC (AWWA C-900) UNLESS OTHERWISE NOTED. 5.
ALL WATER LINES SHALL HAVE A MINIMUM OF 36-INCHES OF COVER.4.
DETAILS. SEE STRUCTURAL PLANS E7/SE510 FOR EQUIPMENT PAD DETAILS.
SEE MECHANICAL OR ELECTRICAL PLANS M-400 AND MP100 FOR EQUIPMENT 3.
AND PLUMBING PLANS P-100.
FOR EXACT SANITARY SERVICE LINE LOCATIONS REFER TO MECHANICAL 2.
OF ALL UTILITIES PRIOR TO CONSTRUCTION.
CONTRACTOR SHALL FIELD VERIFY AND DETERMINE THE EXACT LOCATION
ALL EXISTING UTILITIES SHOWN ARE APPROXIMATE IN NATURE. THE 1.
SEE NOTE 6
INSTALL FIRE LINE
SANITARY SERVICE LINE
REMOVE AND REPLACE 6"
CAP. APPROXIMATELY 4.58 L.F.
LINE TO BACK OF CURB AND
SANITARY SEWER SERVICE
REMOVE EXISTING 4"
LINE. APPROX. 9.4 L.F.
SANITARY SEWER SERVICE
REMOVE EXISTING 4"
M A
Y
R E
V
IS
E D I
N A
C C
O R
D A
N C
E W
IT
H A
M E
N D
M E
N T
A8
CU100
A
B
C
D
E
F
G
H
J
1 2 3 4 5 6 16 17 18 19 20 21 22 23
8 9 10 11 12 13 14 15
K
L
M
N
P
Q
S O
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
S U
B M
IT
T E
D B
Y
D A
T E
C O
N T
R A
C T N
O
C H
E C
K E
D B
Y
D R
A W
N B
Y
IS
S
U E D
A T
E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
®of Engineers
US Army Corps
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
UP
DOWN
UP
DOWN
DOWN
DOWN DOWN
DOWN
TYP.
TYP.
TYP.
TYP.
WOMEN
MEN
TYP.
TYP.
MECHANICAL
ELECTRICAL
TELECOM/
STAIRS
OFFICE OFFICE
OFFICEOFFICE
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE OFFICE
OFFICE
OFFICE
OFFICE
OFFICEOFFICEOFFICE
OFFICE OFFICE OFFICE
OFFICE
OPEN OFFICE
6 6 6
GENERAL NOTES - DEMOLITION
CONSTRUCTION TO LIKE NEW CONDITIONS.
RESULT OF DEMOLITION AND
ASSEMBLIES AND FINISHES DAMAGED AS A
CONTRACTOR SHALL REPAIR ALL DAMAGED
ASSEMBLIES AND FINISHES TO REMAIN.
CONTRACTOR SHALL PROTECT ALL EXISTING 6.
INTERIORS
SUBFLOOR FOR NEW FINISHES. RE:
AND FLOORING THROUGHOUT. PREP
ADHESIVE RESIDUE CARPET, CARPET TILES,
SUBSTRATES, ATTACHMENTS, TRIM,
INCLUDES BUT IS NOT LIMITED TO ALL
REMOVE ALL ROOM FLOOR FINISHES. THIS 5.
INFORMATION.
DRAWINGS FOR FURTHER DEMOLITION
REFER TO OTHER DISCIPLINE DEMOLITION 4.
WORK.
REMAIN PRIOR TO START OF DEMOLITION
LOCATIONS OF WALLS AND DOORS TO
RECORD ROOM DIMENSIONS AND
CONTRACTOR TO FIELD VERIFY AND 3.
MATCH EXISTING FINISH.
APPLICATION OF SCHEDULED FINISH OR
A SMOOTH SURFACE FOR SUITABLE
TO MATCH ADJACENT SURFACES TO CREATE
WORKED SHALL BE DONE WITH MATERIALS
CONSTRUCTION. REPAIR AND PATCH
REMOVAL OF PIPING, CONDUIT, AND SIMILAR
FLOOR PENETRATIONS RESULTING FROM
BEHIND. FILL ALL EXISTING WALL AND
PATCH AND REPAIR ANY HOLES LEFT
ELECTRICAL AND MECHANICAL EQUIPMENT.
BUILDING. AFTER REMOVAL OF WALLS,
AND DETAILING THROUGHOUT THE
PROTECT THE HISTORIC PLASTER WALLS
CONTRACTOR SHALL PRESERVE AND 2.
REHABILITATION OF HISTORIC PROPERTIES.
INTERIOR'S STANDARD AND GUIDELINES FOR
SHALL CONFORM TO THE SECRETARY OF
ALL WORK ON THIS HISTORIC BUILDING 1.
ON DEMO RCP PLANS.
AND SYSTEMS THROUGHOUT AS INDICATED
DEMO ALL EXISTING CEILING TILES, GRIDS 14.
SHALL BE TURNED OVER TO THE BASE.
CLOSER'S FROM DEMOE'D DOORS. CLOSER'S
BASE LOCKSMITH. SALVAGE ALL DOOR
BE SALVAGED AND TURNED OVER TO THE
LOCK CORES FROM DEMO'D DOORS SHALL 13.
FRAMES AND DOORS.
SHALL REFINISH AND REPAIR ALL EXISTING
DOORS TO REMAIN, THE CONTRACTOR
ON EXISTING INTERIOR AND EXTERIOR 12.
AND REPAIR AS NECESSARY.
WINDOW, CONTRACTOR SHALL REPLACE
DURING REMOVAL OR REPAIR OF ANY
IF SILL STONES OR FLASHING IS DAMAGED 11.
RESEALING.
EXISTING PUTTY OR SEALANT BEFORE
SHALL BE FULLY FUNCTIONING. REMOVE
REFINISHED ALL OPERABLE WINDOWS
PANES, MULLIONS, AND FRAMES. ONCE
RESEALED. RESEAL AROUND ALL GLASS
(ON WOOD AND GLASS), REFINISHED AND
ALL WINDOWS SHALL BE STRIPPED OF PAINT 10.
ARE TO MATCH EXISTING.
NOTED ON DRAWINGS. NEW GLAZED PANES
BROKEN/DAMAGED GLAZING IN WINDOWS AS
REMOVE VENTS AND PLEXI AND REPLACE 9.
WAY CHANGE THE PROFILE OF THE FRAMES.
DAMAGE THE EXISTING FRAMES OR IN ANY
UNLESS NOTED OTHERWISE. DO NOT
EXISTING WOOD WINDOWS TO REMAIN 8.
PLAN.
FOLLOW APPROVED WASTE MANAGEMENT
MATERIALS REMOVED FROM SITE SHALL
DISPOSE OF ALL DEMOLITION DEBRIS. ALL
CONTINUOUS CLEAN- UP AND REMOVE AND
CONTRACTOR IS RESPONSIBLE FOR 7.
SHEET LEGEND
SHOWERS, ETC.
WALLS, DOORS, FRAMES, SINKS,
COMPLETELY DEMO ITEMS;
EGRESS WINDOW.
OPENING FOR EMERGENCY
REMOVE WINDOW AND PREP
SHEET KEY NOTES - DEMOLITION
REPAIR WINDOW AS NOTED
WINDOW.
PLYWOOD. PRESERVE EXISTING FRAME AND
REMOVE AC UNIT, MECH LOUVERS OR 7
PRESERVE EXISTING FRAME AND WINDOW.
WINDOWS AND PREP FOR NEW GLASS PANE.
REMOVE ALL EXISTING PLEXI GLASS IN 6
EXISTING FRAME AND WINDOW.
REMOVE BROKEN GLASS PANES. PRESERVE 5
PRESERVE EXISTING FRAME AND WINDOW.
REMOVE BROKEN GLASS IN STORM WINDOW. 4
04-401-01) REQUIREMENTS.
LIFE SAFETY (NFPA) AND ATFP (UFC
EGRESS WINDOW. NEW WINDOW TO MEET
OVER TO SHPO. PREP OPENING FOR NEW
REMOVE AND SALVAGE WINDOW AND TURN 3
NEW WORK DRAWINGS.
FIXTURES AND RESTROOM EQUIPMENT PER
PREPARE SPACE FOR NEW WALLS AND
LAVATORIES AND PLUMBING FIXTURES.
TOPS, SHOWERS, WATER CLOSETS,
DEMO ALL SINKS, CASEWORK, COUNTER 2
LIFE SAFETY REQUIREMENTS.
WITH NEW DOOR AND FRAME TO MEET NFPA
REMOVE DOOR AND FRAME AND REPLACE 1
SHEET.
NOT ALL KEY NOTES LISTED ARE USED ON THIS
OPENING.
AND TAKE OPENING TO F.F. FOR NEW DOOR
DEMO OLD EXISTING ARMS VAULT WINDOW 15
LIFE SAFETY REQUIREMENTS.
SCHEDULE. ADD EGRESS BARS TO MEET
THRESHOLD PER DOOR HARDWARE
AND ADD WEATHER STRIPPING AND
PANES WITH NEW GLASS PANES. REFURBISH
REPLACE PLEXIGLAS AND BROKEN GLASS
EXISTING DOOR FRAME TO REMAIN.
REMOVE DOOR, FLIP SWING AND REINSTALL 14
RAIL PER A-100'S.
DEMOLISH CHAIR LIFT AND REPAIR HAND 13
PER DOOR SCHEDULE.
ALLOW FOR NEW 6'-8" DOOR AND FRAME,
FOR NEW DOOR. DEMO HEIGHT OF WALL TO
DEMO DOOR, FRAME AND LENGTH OF WALL 12
EXISTING WINDOW TO EXPOSE WINDOW.
REMOVE INFILL ON INTERIOR SIDE OF 11
DOOR AND TRANSOM.
DOOR AND PREP FOR NEW ATFP COMPLIANT
REMOVE LIMESTONE INFILL OF ORIGINAL 10
ADA RAMP AND EXTERIOR DOOR.
REMOVE RAILING FOR LOCATION OF NEW 9
HISTORIC PLASTER DURING DEMO WORK.
PROTECT AND PRESERVE EXISTING 8
NEW 1/4" METAL BLANK OUT PANEL.
REMOVE ON PANE OF GLASS AND PREP FOR 24
PATIO REPAIR.
RE: STRUCTURAL FOR CONCRETE STEP AND 23
OVER TO SHPO.
ALL HARDWARE COMPONENTS AND TURN
DOOR AND FRAME. SAVE DOOR, FRAME AND
CAREFULLY REMOVE AND SALVAGE WOOD 22
ROOM (RM 208).
REMOVED FROM TELECOM/ELECTRICAL
PREP OPENING FOR HISTORIC WINDOW
REMOVE EXISTING LOUVER AND FRAME. 21
INSIDE OF WINDOW.
REMOVE LAYER OF PLEXIGLAS COVERING 20
WEST.
6 1/2" STEP. STEPS UP TOWARDS PLAN 19
DEEP.
TO REMAIN. APPROX. 11 5/8" TALL BY 1'-3"
PROTRUSION OF EXISTING STRIP FOOTING 18
A-100
VENTS. PREP OPENING FOR NEW INFILL RE:
REMOVE EXISTING PLYWOOD INFILL AND 17
FOR NEW WORK PER A-100'S
OR TURN OVER TO FT. RILEY. PREP OPENING
PRESERVATION. REUSE IN NEW LOCATION
WINDOW AND FRAME FOR HISTORIC
REMOVE, REFINISH AND SALVAGE EXISTING 16
F
IL
E N
A M
E
A N
S I
D
AD120
A
N A
E G
E C
O V
E R S
H E
T
P -4
B
L D
G
V
A C
A L L C
E N
T E
R
B U
IL
D
IN
G
R
E N
O V
A T
IO
N
F O
R T R
IL
E Y
K A
N S
A S
S E
E C
O V
E R S
H E
E T
A P
R
IL
K A
N S
A S C
IT
Y
M O
E T
H S
T R
E E
T
K A
N S
A S C
IT
Y D
IS
T R
IC
T
D R
A W
IN
G C
O D
E
C
B R
O W
N
C O
N D F
L O
O R D
E M
O L
IT
IO
N P
L
N A
E G
E R
B
W H
IT
E
V
A D
.d g n
A1
SECOND FLOOR DEMOLITION PLAN
SCALE: 1/8" = 1' 0 8'4' 16'
FINAL
M D -0
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
S U
B M
IT
T E
D B
Y
D A
T E
C O
N T
R A
C T N
O
C H
E C
K E
D B
Y
D R
A W
N B
Y
IS
S
U E D
A T
E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
®of Engineers
US Army Corps
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
EL. 100'-0"
FIRST FLOOR
THIRD FLOOR
EL. APPROX. 126'-2"
SECOND FLOOR
EL. APPROX. 113'-1"
9 10
15 15
4 4 3
EL. 100'-0"
FIRST FLOOR
THIRD FLOOR
EL. APPROX. 126'-2"
SECOND FLOOR
EL. APPROX. 113'-1"
BEYOND
STAIRS
6 6
6 4 4
3 3
14 14
GENERAL ELEV. NOTESELEVATION KEY NOTES
SHEET LEGEND
AS NOTED
REPAIR OR REPLACE WINDOW
EGRESS WINDOW.
OPENING FOR EMERGENCY
REMOVE WINDOW AND PREP
REHABILITATION OF HISTORIC PROPERTIES.
INTERIOR'S STANDARD AND GUIDELINES FOR
SHALL CONFORM TO THE SECRETARY OF
ALL WORK ON THIS HISTORIC BUILDING 10.
MATCH ADJACENT MATERIAL AND COLOR.
LOCATION OF REPAIRS. REPAIRS SHALL
LIKE NEW CONDITION. RE: STRUCTURAL FOR
TREADS, STRINGERS, AND HANDRAILS TO
REPAIR ALL EXTERIOR METAL STAIRS, 9.
TO ADJACENT HISTORIC APPEARANCE.
WHERE KEY NOTED ON ELEVATIONS. REPAIR
REPAIR HOLE IS EAVE SOFFIT'S AT PATIO 9.
TO ADJACENT HISTORIC APPEARANCE.
WHERE KEY NOTED ON ELEVATIONS. REPAIR
PATCHES IN ROOF SOFFIT'S AT PATIOS
REPLACE AND REPAIR ALL EXISTING 8.
ROOF EAVES
ARE UNDER PATIO OVER HANG AND HIGH
CALLED OUT ON ELEVATIONS. LOCATIONS
SEAL AROUND ALL WOOD ROOF FASCIA AS 7.
GUTTERS AND REPAIRING HOLES.
DOWNSPOUTS, REPAIRING SEAMS IN
ARE NOT LIMITED TO; REATTACHING
WITH SAME MATERIAL. REPAIRS INCLUDE BUT
ALL EXISTING GUTTERS AND DOWNSPOUTS
CONTRACTOR SHALL EVALUATE AND REPAIR 6.
AS NECESSARY
CONTRACTOR SHALL REPLACE AND REPAIR
DURING REMOVAL OF WINDOW,
IF SILL STONES OR FLASHING IS DAMAGED 5.
MATCH EXISTING.
ON DRAWINGS. NEW GLAZED PANES ARE TO
AND REPLACE WITH NEW GLAZING AS NOTED
BROKEN/DAMAGED GLAZING IN WINDOWS
REMOVE VENTS, PLEXI AND 4.
BEFORE RESEALING.
REMOVE EXISTING PUTTY OR SEALANT
WINDOWS SHALL BE FULLY FUNCTIONING.
FRAMES. ONCE REFINISHED ALL OPERABLE
AROUND ALL GLASS PANES, MULLIONS, AND
REFINISHED AND RESEALED. RESEAL
ALL WINDOWS SHALL BE STRIPPED, 3.
WAY CHANGE THE PROFILE OF THE FRAMES
DAMAGE THE EXISTING FRAMES OR IN ANY
UNLESS NOTED OTHERWISE. DO NOT
EXISTING WOOD WINDOWS TO REMAIN 2.
APPEARANCE OF ORIGINAL HISTORIC FABRIC
DOOR SHALL REPLICATE LOOK AND
MATCH ORIGINAL HISTORIC AESTHETICS.
NEW EXTERIOR DOOR AND TRANSOM TO 1.
ORIGINAL HISTORIC AESTHETICS.
NEW HAND RAIL. MATCH ADJACENT 23
OF ORIGINAL HISTORIC FABRIC.
SHALL REPLICATE LOOK AND APPEARANCE
ORIGINAL HISTORIC AESTHETICS. DOOR
NEW DOOR AND TRANSOM TO MATCH 22
DRAWINGS RE: SE311.
STAIRS TO BE REPAIRED PER STRUCTURAL 21
RE- ANCHOR DOWNSPOUT.20
REPAIR SPLIT OR SEPARATION IN GUTTER.19
STRAIGHTEN BOWED OUT DOWNSPOUT18
DOWNSPOUT AT GUTTER.
REPAIR DISCONNECTED AND SEPARATED 17
PATCH AND REPAIR PORCH SOFFIT HOLES.16
ROOF VENTS AND CAPS.
RE-BIRD-SCREEN AROUND ALL EXISTING 15
AROUND ATTIC VENTS
REFINISH, REPAINT, RESCREEN AND RESEAL 14
ROOF EAVES.
SEAL AROUND ENTIRE WOOD FASCIA AT ALL 13
UNDERSIDE OF PATIO ROOF. RE: D1/A-511
SEAL AROUND ENTIRE WOOD FASCIA AT 12
OPENING.
RE: A-611 FOR INFILL OF EXISTING WINDOW 11
EXISTING PROFILE AND PAINT.
INSTALL NEW HANDRAIL TO MATCH 10
MATCH IN MATERIALS AND DESIGN.
EXISTING RAILING. NEW RAILING SHALL
NEW RAILING AT RAMP SHALL MATCH 9
AND FRAME.
STRIP, CLEAN AND REPAINT EXISTING DOOR 8
PATIO REPAIR.
RE: STRUCTURAL FOR CONCRETE STEP AND 7
WAS REMOVED.
AC UNITS, MECH LOUVERS OR PLYWOOD
MULLIONS IN WINDOWS WHERE PREVIOUS
INSTALL NEW GLASS PANES AND WOOD 6
OPENING. RE: MECHANICAL
INSTALL LOUVER IN EXISTING WINDOW 5
REMOVED, INSTALL NEW GLASS PANES.
WHERE PLEXIGLAS WAS PREVIOUSLY 4
DEMO WORK.
GLASS WAS PERVIOUSLY REMOVED IN
WINDOW AT LOCATIONS WHERE BROKEN
INSTALL NEW GLASS PANES IN RESTORED 3
INTO OPENING.
INSTALL REFINISHED HISTORIC WINDOW 2
REQUIREMENTS.
SAFETY (NFPA) AND ATFP (UFC 04-401-02)
EGRESS WINDOW. WINDOW TO MEET LIFE
REMOVE WINDOW AND REPLACE WITH NEW 1
SHEET.
NOT ALL KEY NOTES LISTED ARE USED ON THIS
DS: AEC_Screen U4.dscriptPD: AEC_pdf.pltcfg7:28:33 AM 5/9/2018 pw://COE-NWKPWP50KAN.nwk.ds.usace.army.mil:PWNWK500/Documents/Military/Veterans Administration/v001Riley Bldg 409/6.0 Engineering-Design/6.1 Drawings/CAD_BIM/_Sheets/ELEVATIONS
E N
A M
E
A N
S I
D
A-201
A
N A
E G
E C
O V
E R S
H E
-4
B
L D
G
V
A C
A L L C
E N
T E
R
B U
IL
D
IN
G
R
E N
O V
A T
IO
N
F O
R T R
IL
E Y
K A
N S
A S
S E
E C
O V
E R S
H E
E T
A P
R
IL
K A
N S
A S C
IT
Y
M O
E T
H S
T R
E E
T
K A
N S
A S C
IT
Y D
IS
T R
IC
T
D R
A W
IN
G C
O D
E
C
B R
O
L E
V A
T
IO
N S
D R
A W
IN
G
C O
D E
A
N A
E G
E R
B
W H
IT
E
V
A -2
.d g n
A1
SOUTH ELEVATION
SCALE: 1/8" = 1' 0 8'4' 16'
D1
WEST ELEVATION
SCALE: 1/8" = 1' 0 8'4' 16'
M D -0
A1
A-300
D1
A-300
A7
A-300
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
S U
B M
IT
T E
D B
Y
D A
T E
C O
N T
R A
C T N
O
C H
E C
K E
D B
Y
D R
A W
N B
Y
IS
S
U E D
A T
E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
®of Engineers
US Army Corps
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
EX
V A
R
IE
S
W1
F
IE
L D V
E R
IF
Y F
IE
L D V
E R
IF
Y
FIELD VERIFY
3'-8"
W2
F
IE
L D V
E R
IF
Y F
IE
L D V
E R
IF
Y
FIELD VERIFY
3'-8"
W3
F
IE
L D V
E R
IF
Y F
IE
L D V
E R
IF
Y
FIELD VERIFY
3'-8"
EXTERIOR WINDOW TRIM
OF PLY WOOD TO MATCH
PAINT EXTERIOR SURFACE
AS SCHEDULED
INFILL BEHIND WINDOW
EXTERIOR WINDOW TRIM
OF PLY WOOD TO MATCH
PAINT EXTERIOR SURFACE
AS SCHEDULED
INFILL BEHIND WINDOW
WALL
EXISTING EXTERIOR
WALL
EXISTING EXTERIOR
WALL
EXISTING EXTERIOR
2" RIGID INSULATION
AND VAPOR RETARDER
AIR / MOISTURE BARRIER
METAL STUDS
5/8" GWB ON 3 5/8"
METAL STUDS
5/8" GWB ON 3 5/8"
5/8" GWB
AND FRAMING
EXISTING WOOD WINDOW
3 5/8" METAL STUDS
5/8" GWB
2" RIGID INSULATION
AND VAPOR RETARDER
AIR / MOISTURE BARRIER
5/8" GWB
AND FRAMING
EXISTING WOOD WINDOW
AND FRAMING
EXISTING WOOD WINDOW
AND VAPOR RETARDER
AIR / MOISTURE BARRIER
METAL STUDS
5/8" GWB ON 3 5/8"
2" RIGID INSULATION
A
A B
WALL
EXISTING EXTERIOR
2" RIGID INSULATION
AND VAPOR RETARDER
AIR / MOISTURE BARRIER
METAL STUDS
5/8" GWB ON 3 5/8"
METAL STUDS
5/8" GWB ON 3 5/8"
5/8" GWB
WALL
EXISTING EXTERIOR
3 5/8" METAL STUDS
5/8" GWB
2" RIGID INSULATION
AND VAPOR RETARDER
AIR / MOISTURE BARRIER
5/8" GWB
WALL
EXISTING EXTERIOR
AND VAPOR RETARDER
AIR / MOISTURE BARRIER
METAL STUDS
5/8" GWB ON 3 5/8"
2" RIGID INSULATION
EGRESS WINDOW
ATFP COMPLIANT
EGRESS WINDOW
ATFP COMPLIANT
EGRESS WINDOW
ATFP COMPLIANT
B
C
C
2" RIGID INSULATION
AIR / MOISTURE BARRIER
3-5/8" MTL STUD W/ BATT INSULATION
5/8" GWB
RE: STRUCTURAL
8" CMU REINFORCED & GROUTED
2" RIGID INSULATION
AIR / MOISTURE BARRIER
3-5/8" MTL STUD W/ BATT INSULATION
5/8" GWB
NEW WINDOW PER SCHEDULE
EXISTING LIMESTONE WALL
2" RIGID INSULATION
AIR / MOISTURE BARRIER
5/8" GWB
RE: STRUCTURAL
8" CMU REINFORCED & GROUTED
2" RIGID INSULATION
AIR / MOISTURE BARRIER
5/8" GWB
NEW WINDOW PER SCHEDULE
EXISTING LIMESTONE WALL
2" RIGID INSULATION
AIR / MOISTURE BARRIER
5/8" GWB
RE: STRUCTURAL
8" CMU REINFORCED & GROUTED
2" RIGID INSULATION
AIR / MOISTURE BARRIER
5/8" GWB
NEW WINDOW PER SCHEDULE
EXISTING LIMESTONE WALL
3-5/8" MTL STUD W/ BATT INSULATION
3-5/8" MTL STUD W/ BATT INSULATION
A B C
3-5/8" MTL STUD W/ BATT INSULATION
3-5/8" MTL STUD W/ BATT INSULATION
CONTINUOUS SEALANT
CONTINUOUS SEALANT
5/8" GWB
5/8" GWB
CONTINUOUS SEALANT
BATT INSULATION
TAPE AND PAINT
METAL J-TRIM.
BATT INSULATION
TAPE AND PAINT
METAL J-TRIM.
BATT INSULATION BATT INSULATION
TAPE AND PAINT
METAL J-TRIM.
TO MATCH WINDOW FRAME
PAINTED OFF WHITE/CREAM
3/4" EXTERIOR PLYWOOD
TO MATCH WINDOW FRAME
PAINTED OFF WHITE/CREAM
3/4" EXTERIOR PLYWOOD
TO MATCH WINDOW FRAME
PAINTED OFF WHITE/CREAM
3/4" EXTERIOR PLYWOOD
D
2" RIGID INSULATION
AIR / MOISTURE BARRIER
3-5/8" MTL STUD W/ BATT INSULATION
2" RIGID INSULATION
AIR / MOISTURE BARRIER
3-5/8" MTL STUD W/ BATT INSULATION
EXISTING LIMESTONE WALL
5/8" GWB
5/8" GWB
PER SCHEDULE
EXISTING WINDOW
2" RIGID INSULATION
AIR / MOISTURE BARRIER
3-5/8" MTL STUD W/ BATT INSULATION
5/8" GWB
2" RIGID INSULATION
AIR / MOISTURE BARRIER
3-5/8" MTL STUD W/ BATT INSULATION
5/8" GWB
EXISTING LIMESTONE WALL
PER SCHEDULE
EXISTING WINDOW
2" RIGID INSULATION
AIR / MOISTURE BARRIER
3-5/8" MTL STUD W/ BATT INSULATION
5/8" GWB
2" RIGID INSULATION
AIR / MOISTURE BARRIER
3-5/8" MTL STUD W/ BATT INSULATION
5/8" GWB
EXISTING LIMESTONE WALL
EXISTING WINDOW PER SCHEDULE
CONTINUOUS SEALANT
D
D
TAPE AND PAINT
METAL J-TRIM.
TO MATCH WINDOW FRAME
PAINTED OFF WHITE/CREAM
3/4" EXTERIOR PLYWOOD
TO MATCH WINDOW FRAME
PAINTED OFF WHITE/CREAM
3/4" EXTERIOR PLYWOOD
TO MATCH WINDOW FRAME
PAINTED OFF WHITE/CREAM
3/4" EXTERIOR PLYWOOD
DS: AEC_Screen U4.dscriptPD: AEC_pdf.pltcfg7:27:52 AM 5/9/2018 pw://COE-NWKPWP50KAN.nwk.ds.usace.army.mil:PWNWK500/Documents/Military/Veterans Administration/v001Riley Bldg 409/6.0 Engineering-Design/6.1 Drawings/CAD_BIM/_Sheets/WINDOW DETAILS AND ELEVATIONS
E N
A M
E
A N
S I
A-611
E
E C
O V
E R S
H E
-4
B
L D
G
V
A C
A L L C
E N
T E
R
B U
IL
D
IN
G
R
E N
O V
A T
IO
N
F O
R T R
IL
E Y
K A
N S
A S
S E
E C
O V
E R S
H E
E T
A P
R
IL
K A
N S
A S C
IT
Y
M O
E T
H S
T R
E E
T
K A
N S
A S C
IT
Y D
IS
T R
IC
T
D R
A W
IN
G C
O D
E
C
B R
O
IN
D O
W D
E T
A
IL
S A
N D E
L E
V A
T
IO
N A
E G
E R
B
W H
IT
E
V
A -6
.d g n
A1 SCALE: 1 1/2" = 1'
FINAL
WINDOW SILL DETAILS
1' 2'0 6"
C1 SCALE: 1 1/2" = 1'
WINDOW JAMB DETAILS
1' 2'0 6"
E1 SCALE: 1 1/2" = 1'
WINDOW HEAD DETAILS
1' 2'0 6"
A8 SCALE: 1 1/2" = 1'
WINDOW ELEVATIONS
F8 SCALE: 1 1/2" = 1'
WINDOW SCHEDULE
A
N A
E G
E R
A M
D -0
11 1/2 " 9 1/2 "
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
S U
B M
IT
T E
D B
Y
D A
T E
C O
N T
R A
C T N
O
C H
E C
K E
D B
Y
D R
A W
N B
Y
IS
S
U E D
A T
E
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
SHEET ID
®of Engineers
US Army Corps
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
2.
1.
CONSTRUCTION TYPE, HEIGHT & AREA LIMITS (IBC):
1.
1.
FIRE SUPPRESSION SYSTEM:
PROTECT THROUGHOUT PER NFPA 13 AND UFC 3-600-01
FIRE ALARM AND MASS NOTIFICATION:
DOOR REMOTENESS (NFPA 101):
OVERALL DIAGONAL
EXIT - EXIT ACCESS DOORS, SEPARATED BY 1/3
MINIMUM NUMBER OF EXITS
FOUR - MORE THAN 1,000 PEOPLE (NFPA 101-7.4.1.2)
THREE - BETWEEN 500 AND 1,000 PEOPLE.
TWO - LESS THAN 500 PEOPLE
3.
FIRE EXTINGUISHER CABINETS:
3.
EGRESS WIDTH (NFPA 101):
1.
BALANCED EGRESS CAPACITY (7.3.3.1):
COMMENTARY)
BALANCE EGRESS CAPACITY (LSC HDBK 7.3.3.1
TRAVEL DISTANCE (NFPA 101):
ILLUMINATION AND EMERGENCY LIGHTING:
WITHIN 10 FEET OF EXIT DOOR (NFPA 101-7.9)
EXIT DISCHARGE - 1 FT-CANDLE AT GROUND LEVEL
FLOOR. (NFPA 101-7.8)
ALL BUILDING SPACES ILLUMINATED TO 1 FT-CANDLE AT
101-7.9, 7.9.2)
AVERAGE, AND 0.06 FT-CANDLES MINIMUM (NFPA
IN 1-1/2 HOURS CAN DECREASE TO 0.6 FT-CANDLES
AVERAGE AT GROUND, WITH 0.1 FT-CANDLE MINIMUM.
ILLUMINATION DURING POWER FAILURE, 1 FT-CANDLE
EMERGENCY LIGHTING PROVIDED FOR EGRESS
101-7.8.1.1, 7.9.1.2)
EGRESS ILLUMINATION AND EMERGENCY LIGHTING (NFPA
DISCHARGE, AISLES, CORRIDORS, WALKWAYS, ETC. FOR
AHJ DETERMINES DESIGNATED EXIT ACCESS, AND EXIT
4.
3.
EXTINGUISHERS
PER NFPA 10, STANDARD FOR PORTABLE FIRE
3.
STROBES IN WHITE HOUSING FOR MAINTENANCE.
STROBES IN RED HOUSING FOR FIRE ALARM. AMBER
ALARM AND MASS NOTIFICATION SYSTEM. CLEAR
SPEAKERS AND STROBES - COMMON SPEAKERS FOR FIRE
38.3.4.1.
(MN), 3-600-01, UFC 4-021-01, NFPA 101-12.3.4.1,
FIRE ALARM (FA) AND MASS NOTIFICATION SYSTEM
SYSTEM - AN ADDRESSABLE, INTELLIGENT COMBINED
4.
5.
CASES IS NOT LESS THAN 28" (7.3.4.1)
WIDTH FORMED BY FURNITURE, FIXTURES, DISPLAY
PERSONS FOR MORE THAN 2000, USE CALCULATION.
STAIR WIDTH = 44 INCHES FOR LESS THAN 2000
PERSON.
FOR MORE THAN 160 PEOPLE, USE 0.2 INCHES PER
NOT ACCESSIBLE FOR DISABILITIES (7.2.1.2.3.2(4)).
BUILDINGS (7.2.1.2.3). EXCEPTION, 70 SQFT ROOMS
DOOR WIDTH = NOT LESS THAN 28 INCHES FOR EXISTING
WIDTH PERSON (STAIR) = 0.3
WIDTH/PERSON (LEVLE) = 0.2
DRAWINGS.
CALCULATED WIDTH OF DOORS AND STAIRS ARE ON
THAN 50 PEOPLE (NFPA 101-12.2.2.3).
PEOPLE BUT LESS THAN 220; 36 INCHES FOR LESS
CORRIDOR WIDTH = 44 INCHES FOR GREATER THAN 50
18, 843 SQ FTFLOOR AREA:
APPROX. 57'-6"TOP OF ROOF:HEIGHT:
TYPE VA, FULLY SPRINKLERED, THREE-STORY:
CONFLICTS WITH IBC, COMPLY WITH NFPA 101.
NONBEARING PARTITION FIRE RESISTANCE. FOR
NFPA 101 - USE FOR EGRESS, SAFETY TO LIFE AND
ABOVE GRADE PLANE IS LIMITED TO THREE
FEET ( PER IBC EQUATION 5-2), NUMBER OF STORIES
AND HEIGHT. AREA IS LIMITED TO 81,675 SQUARE
IBC - USE FOR CONSTRUCTION TYPE, FIRE RESISTANCE,
FIRE RESISTANCE RATING REQUIREMENTS FOR BUILDING ELEMENTS:
1.
BALANCED EGRESS CAPACITY (7.3.3.1):
COMMENTARY)
BALANCE EGRESS CAPACITY (LSC HDBK 7.3.3.1 1.
50 FEETBUSINESS
20 FEETASSEMBLY
DEAD END CORRIDORS (FT):
100FEETBUSINESS
50 FEETASSEMBLY
COMMON PATH OF TRAVEL (FT):
300 FEETBUSINESS
250 FEETASSEMBLY
TRAVEL DISTANCE (FT):
BUSINESS - REMAINDER OF THE BUILDING
ASSEMBLY - TRAINING ROOM & BREAK ROOM
- 0 HOURS
MEMBERS
- ROOF CONSTRUCTION AND ASSOCIATED SECONDARY
- 0 HOURS
MEMBERS
- FLOOR CONSTRUCTION AND ASSOCIATED SECONDARY
- SEE OTHER F-SERIES SHEETS.
- NON-BEARING WALLS, INTERIOR:
- 0 HOUR
- NON-BEARING WALLS, EXTERIOR:
- 0 HOUR
- BEARING WALLS, INTERIOR:
- 0 HOUR
- BEARING WALLS, EXTERIOR:
- 0 HOUR.
- PRIMARY STRUCTURAL FRAME
TYPE VA CONSTRUCTION:
USE OF IBC AND NFPA 101:
DS: AEC_Screen U4.dscriptPD: AEC_pdf.pltcfg7:30:01 AM 5/9/2018 pw://COE-NWKPWP50KAN.nwk.ds.usace.army.mil:PWNWK500/Documents/Military/Veterans Administration/v001Riley Bldg 409/6.0 Engineering-Design/6.1 Drawings/CAD_BIM/_Sheets/GENERAL LIFE SAFETY NOTES
E N
A M
E
A N
S I
D
F-001
A
N A
E G
E C
O V
E R S
H E
-4
B
L D
G
V
A C
A L L C
E N
T E
R
B U
IL
D
IN
G
R
E N
O V
A T
IO
N
F O
R T R
IL
E Y
K A
N S
A S
S E
E C
O V
E R S
H E
E T
K A
N S
A S C
IT
Y
M O
E T
H S
T R
E E
T
K A
N S
A S C
IT
Y D
IS
T R
IC
T
D R
A W
IN
G C
O D
E
M L
IT
T L
G
R E
R A
L L
IF
E S
A F
E T
Y N
O T
N A
E G
E R
B
W H
IT
E
V F -0
.d g nA
P R
IL
M D -0
| VA Call Center Amdt 0002 attachments.pdf |
| Attachment 1_Energy+Sustainability_Record_Card |
| Attachment 2_VA_GPChecklist-LEED-NCv4 |
| VA Call Center - Drawings Amendment 0002 |
| V001_AD120 |
| V001_A-201 |
| V001_A-611 |
| V001_F-001 |