W912DQ-17-R-1008

US Army Corps of Engineers Kansas City District Building Strong

Harry S. Truman Dam and Reservoir Powerhouse Exciter Replacement

Warsaw Missouri

Request for Proposal

Construction Solicitation and Specifications

As Advertised

August 2017

This page was intentionally left blank for duplex printing.

DEPARTMENT OF THE ARMY

KANSAS CITY DISTRICT, CORPS OF ENGINEERS

647 FEDERAL BUILDING

KANSAS CITY, MISSOURI 64106

SPECIFICATIONS FOR CONSTRUCTION OF

HARRY S. TRUMAN DAM AND RESERVOIR POWERHOUSE EXCITER REPLACEMENT

WARSAW MISSOURI

TABLE OF CONTENTS

COVER

TABLE OF CONTENTS

DIVISION 00 - BIDDING REQUIREMENTS, CONTRACT FORMS AND CONTRACT

CONDITIONS

00 11 00 SOLICITATION/CONTRACT FORM

00 21 00 INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFEROR

00 22 11 BEST VALUE EVALUATION FACTORS ONE STEP

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 72 00 CONTRACT CLAUSES

00 73 00 SPECIAL CONTRACT REQUIREMENTS

00 73 46 WAGE DETERMINATION SCHEDULE

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 12 00.00 23 SPECIAL PROJECT REQUIREMENTS

01 22 00.00 10 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 82 13.00 10 ASBESTOS ABATEMENT

DIVISION 03 - CONCRETE

03 60 00.01 26 CONCRETE DEMOLITION AND REPAIR OF CONCRETE SURFACES

TABLE OF CONTENTS CONT

TC-2

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT

DIVISION 26 - ELECTRICAL

26 05 00.00 26 GENERAL ELECTRICAL WORK

26 05 13.00 26 MEDIUM-VOLTAGE CABLE

26 05 19.00 26 INSULATED WIRE AND CABLE

26 05 26.00 26 GROUNDING

26 20 00.00 26 RACEWAYS AND ELECTRICAL DISTRIBUTION SYSTEMS

26 25 00.00 26 BUS STRUCTURES

DIVISION 48 - ELECTRICAL POWER GENERATION

48 19 26.00 26 DIGITAL EXCITERS

48 19 26.01 26 AUXILIARY EQUIPMENT FOR DIGITAL EXCITERS

48 70 01.00 26 NERC COMPLIANCE FOR HYDROGENERATORS

End of Table of Contents

Construction Activities are necessary to remove the existing HST Excitation System at Truman Lake Facility and replace all 6 units w ith new units. Work includes demo of current units, manufacture of replacement units, installation of replacement units.

Title of Project: Harry S. Truman Dam and Reservoir Pow erhouse Exciter Replacement Location: Warsaw , Missouri Magnitude of Construction: $5,000,000 to $10,000,000

This project is issued as a Request for Proposal (RFP) - Full and Open Competition.

TRACI A DAVIS 816-389-2399

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

14-Aug-2017

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________840 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________5 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________14 Sep 2017 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USACE, KANSAS CITY +

FEDERAL BLDG, CT-C

601 E 12TH ST RM 647

KANSAS CITY MO 64106-2896

W912DQ

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

816-389-2029/2030FAX:TEL: 816-389-3812 TEL: FAX:

W912DQ-17-R-1008 114

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00 01 10 - Table of Contents

CAUTION

CAUTION PAGE

CAUTION!

BEFORE SIGNING AND MAILING YOUR PROPSOAL, please take note of the following, as failure to perform any one of these actions may cause your proposal to be rejected.

1. AMENDMENTS: Have you acknowledged receipt of ALL Amendments? If in doubt as to number of amendments issued, please contact our office.

2. SEALED PROPOSALS: Sealed envelopes containing proposals shall be marked to show the contractor’s name and address, the solicitation number, title of project, amendments received, and the date and time proposals are due.

3. AMENDED PROPOSAL PAGES: If any of the Amendments furnished amended proposal pages, the amended proposal page(s) must be used in submitting your proposal.

4. LATE PROPOSALS: In order for a late mailed proposals to be considered, generally it must have been sent by either registered or certified mail not later than 5 calendar days before the receipt of proposals due date.

5. BID GUARANTEE: Sufficient bid guarantee in proper form must be furnished with your proposal, if your proposals exceeds $150,000.

6. MISTAKE IN PROPOSAL: Have you reviewed your proposal prices for possible errors in calculations or work left out?

7. FACSIMILE PROPOSALS AND MODIFICATIONS: Will not be considered. Facsimile withdrawals will be considered.

8. HAND-DELIVERED PROPOSALS: If proposals are hand-delivered, you must be aware of enhanced security requirements in effect in the Federal Building and allow for extra time to clear security. You must have a valid picture ID in order to enter the building. No additional time will be allowed due to security requirements. Please ensure that the solicitation number and title of project appear or can be identified on the outside of proposal package.

9. BUY AMERICAN ACT: All are cautioned that, prior Government conduct notwithstanding, the Contractor's selection of a domestic construction material which would require the subsequent selection of a foreign construction material for compatibility is not a justification for waiver of the Buy American Act. It is the Contractor's responsibility to verify, prior to submitting the materials for approval, that each system can be built to meet the contract specifications without the use of foreign construction materials.

10. BOLLING FEDERAL BUILDING ENHANCED SECURITY

If proposals are hand-delivered, you must be aware of enhanced security requirements in effect in the Federal Building and allow for extra time to clear security. You must have a valid picture ID in order to enter the building. No additional time will be allowed due to security requirements. Under The Federal Acquisition Regulations proposals cannot be accepted after the time set that proposals are due.

Section 00 11 00 - Solicitation/Contract Form

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Unit 1 - Equipment Replacement

FFP

Price each subclin separately below and do NOT roll up into one price on this bid line.

NET AMT

0001AA 1 Job Excitation system

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the Specifications for additional information.

Specific supply clauses for this subclin are included in the "Supply Clauses" in section 00 72 00. These applicable supply clauses will take precedence over construction clauses for this subclin when appropriate.

FOB: Destination

0001AB 1 Job Disassemble/remove current sys

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the Specifications for additional information.

0001AC 1 Job Concrete replacement

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0001AD 1 Job Install/test excitation systems

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0001AE 1 Job OPTION Refurb existing collector ring

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0001AF 1 Job O&M Man;CADD Files, As-Builts

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0001AG 1 Job Training

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

Unit 2 - Equipment Replacement

FFP

0002AA 1 Job Excitation system

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the Specifications for additional information.

Specific supply clauses for this subclin are included in the "Supply Clauses" in section 00 72 00. These applicable supply clauses will take precedence over

0002AB 1 Job Disassemble/remove current sys

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0002AC 1 Job Concrete replacement

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0002AD 1 Job Install/test excitation systems

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0002AE 1 Job OPTION Refurb existing collector ring

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0002AF 1 Job O&M Man;CADD Files, AS-Builts

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

Unit 3 - Equipment Replacement

FFP

0003AA 1 Job Excitation system

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the Specifications for additional information.

Specific supply clauses for this subclin are included in the "Supply Clauses" in section 00 72 00. These applicable supply clauses will take precedence over

0003AB 1 Job Disassemble/remove current sys

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0003AC 1 Job Concrete replacement

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0003AD 1 Job Install/test excitation systems

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0003AE 1 Job OPTION Refurb existing collector ring

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0003AF 1 Job O&M Man;CADD Files, As-Builts

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

Unit 4 - Equipment Replacement

FFP

0004AA 1 Job Excitation system

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the Specifications for additional information.

Specific supply clauses for this subclin are included in the "Supply Clauses" in section 00 72 00. These applicable supply clauses will take precedence over

0004AB 1 Job Disassemble/remove current sys

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0004AC 1 Job Concrete replacement

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0004AD 1 Job Install/test excitation systems

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0004AE 1 Job OPTION Refurb existing collector ring

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0004AF 1 Job O&M Man;CADD Files, As-Builts

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

Unit 5 - Equipment Replacement

FFP

0005AA 1 Job Excitation system

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the Specifications for additional information.

Specific supply clauses for this subclin are included in the "Supply Clauses" in section 00 72 00. These applicable supply clauses will take precedence over

0005AB 1 Job Disassemble/remove current sys

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0005AC 1 Job Concrete replacement

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0005AD 1 Job Install/test excitation systems

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0005AE 1 Job OPTION Refurb existing collector ring

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0005AF 1 Job O&M Man;CADD Files, As-Builts

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

Unit 6 - Equipment Replacement

FFP

0006AA 1 Job Excitation system

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the Specifications for additional information.

Specific supply clauses for this subclin are included in the "Supply Clauses" in section 00 72 00. These applicable supply clauses will take precedence over

0006AB 1 Job Disassemble/remove current sys

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0006AC 1 Job Concrete replacement

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0006AD 1 Job Install/test excitation systems

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0006AE 1 Job OPTION Refurb existing collector ring

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0006AF 1 Job O&M Man;CADD Files, As-Builts

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0007 1 Job Mobilize and Demobilize

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0008 1 Job Specified Factory Tests

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the Specifications for additional information.

Specific supply clauses for this clin are included in the "Supply Clauses" in section 00 72 00. These applicable supply clauses will take precedence over construction clauses for this subclin when appropriate.

0009 1 Job Field Tests

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

0010 1 Job Tools and Spare Parts

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the Specifications for additional information.

Specific supply clauses for this clin are included in the "Supply Clauses" in section 00 72 00. These applicable supply clauses will take precedence over construction clauses for this subclin when appropriate.

0011 1 Job Model Validation Testing and Reports

FFP

Refer to Price and Payment Procedures Section 01 22 00.00 10 of the

CLAUSES INCORPORATED BY FULL TEXT

SCR_CT_002 FIELD OFFICE OVERHEAD (JUL 2002)(RFP)

NOTICE TO OFFERORS: you must declare below the single accounting practice that you apply to contracts to calculate field office overhead for all change orders, modifications and requests for equitable adjustment. Pursuant to Federal Acquisition Regulations (FAR) Parts 31.105(d)(3) and 31.203(d)(1), an accounting practice that varies from modification to modification is not allowable. Select one of the following:

1. TIME DISTRIBUTION BASE FOR A PER DIEM RATE

If you use this practice, see Special Clause “Field Office Overhead Per Diem Rate” _____

2. DIRECT COST DISTRIBUTION BASE FOR A PERCENTAGE MARKUP

If you use this practice, see Special Clause “Field Office Overhead Percentage Markup” _____

3. OTHER ACCOUNTING PRACTICE THAT IS ALLOWABLE _____

UNDER THE FAR AND THAT USES A SINGLE DISTRIBUTION BASE.

If you choose 3, you must describe the accounting practice in sufficient detail below to allow the contracting officer to determine what accounting practice is being utilized by your company and that it complies with the FAR.

FAILURE TO FULLY COMPLY WITH THE ABOVE REQUIREMENT OR, IF ALTERNATIVE 3 IS

DECLARED AND YOUR DESCRIPTION DOES NOT CLEARLY STATE OR DESCRIBE A CONSISTENT

ACCOUNTING PRACTICE USING A SINGLE DISTRIBUTION BASE, MAY CAUSE YOUR PROPOSAL

TO BE EVALUTED AS UNACCEPTABLE.

(End)

TPL_NWK_001 Points of Contact

CONTRACT

SPECIALIST:

Traci Davis PHONE: 816-389-2399 E-MAIL: Traci.A.Davis@usace.army.mil

PROJECT MANAGER: Jared Mewmaw PHONE: 816-389-3666 E-MAIL: Jared.D.Mewmaw@usace.army.mil

TPL_NWK_002 PROPOSALS TO BECOME PART OF THE CONTRACT

1. When an offeror submits its proposal in response to a Request For Proposals, and a staffing plan including the names and qualifications of key personnel who are proposed to work on the project is required to be submitted, those personnel who are offered will be the same personnel who will actually perform on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute personnel for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute employee. The Contracting Officer shall have the right to review the qualifications of the proposed substitute employee and to approve or disapprove his or her qualifications. If the proposed substitute employee's qualifications are disapproved by the Contracting Officer, the contractor will propose another employee who does possess equivalent qualifications.

2. When an offeror submits its proposal in response to a Request For Proposals, and the name of a specific subcontractor is a required submittal, then that subcontractor who is offered will be the same subcontractor who will actually perform the specified work on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute a subcontractor for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute subcontractor. The Contracting Officer shall have the right to review the qualifications of the proposed substitute subcontractor and to approve or disapprove its qualifications. If the proposed substitute subcontractor's qualifications are disapproved by the Contracting Officer, the contractor will propose another subcontractor who does possess equivalent qualifications.

3. When an offeror submits its proposal in response to a Request For Proposals, and a schedule for the performance of the work on the project is a required submittal, the terms of the proposed schedule will become the schedule that will be utilized for completion of the project, adjusted as necessary to reflect the actual issue date of the Notice to Proceed

4. When an offeror submits its proposal in response to a Request For Proposals and that proposal contains any work, materials, methods or other type of betterment that provides an advantage to the Government that is above the minimum requirements contained in the RFP, the terms of the proposal will be the basis for evaluation and, if successful, will become the terms of the contract upon award. If a change in one of those terms is made to one that is less favorable to the Government than the one on which the award of the contract was based, a credit to the Government will be negotiated by the contractor. Only the Contracting Officer has the authority to negotiate a waiver of the terms of the contract.

Section 00 21 00 - Instructions, Conditions and Notices to Offeror

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.236-28 Preparation of Proposals--Construction OCT 1997

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed Price (FFP) contract resulting from this solicitation.

(End of provision)

52.217-5 EVALUATION OF OPTIONS (JUL 1990)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY

2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

6% 10%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Benton County, Missouri

52.225-12 NOTICE OF BUY AMERICAN ACT REQUIREMENT-- CONSTRUCTION MATERIALS UNDER

TRADE AGREEMENTS (MAY 2014) ALTERNATE II (JUN 2009)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American Act-- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).

(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American Act should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American Act before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American Act, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material, except foreign construction material from a designated country other than Bahrain, Mexico, or Oman that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material. An offer based on use of the foreign construction material for which an exception was requested--

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be __20__ percent of the bid price or $_3,000,000_, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

U.S. Army Corps of Engineers, Kansas City District ATTN: Matthew Wilson, CECT-NWKC 647 Federal Building 601 E. 12th Street Kansas City, Missouri 64106-2896

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for--

Date: 24 August 2017

Time: 10:00 AM – 12:00 PM Central Time (US & Canada)

(c) Participants will meet at—

US Army Corps of Engineers Harry S Truman Power Plant 15968 Truman Rd Warsaw, MO 65355

NOTE: Neither Google nor MapQuest place the contractor in the right place for the site visit.

The following coordinates are for the meeting location at the gate to Truman Power House:

38.261350, ‐93.405858

Point of Contact for Site Visit:

Jared Mewmaw Jared.D.Mewmaw@usace.army.mil

(816) 389‐3666

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

Federal Acquisition Regulations System (FAR) http://farsite/hill.af.mil/VFFAR1.HTM Defense Federal Acquisition Regulation upplement (DFARS) http://farsite.hill.af.mil/VFDFAR1.HTM

SCR_CT_007 MAGNITUDE OF PROJECT—CONSTRUCTION (Jul 2002)

The magnitude of this project is represented by the following estimated price range (contracting officer mark as appropriate):

_XX _Between $5,000,000 and $10,000,000

Section 00 22 11 - Best Value Evaluation Factors One Step

SUBMSSION REQUIREMENTS

RFP SECTION 00 22 11:

PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA,

AND BASIS OF AWARD

1.0 OVERVIEW

The proposal should be prepared simply and economically, providing straightforward, concise delineation of capabilities to perform the contract. The proposal should be practical, legible, clear and coherent.

The technical proposal shall address the offeror’s proposed approach to fully perform the requirements of the Request for Proposals (RFP). Offerors are discouraged from providing information not required by the RFP.

2.0 GENERAL PROPOSAL SUBMISSION INSTRUCTIONS

All offerors shall be required to submit a proposal with the minimum content as specified herein. Proposals without the minimum content may be rejected. Proposals will be received until the date and time indicated on Standard Form 1442 at the following address:

Federal Building Room 647 ATTN: CECT-NWK-CT-C/Traci Davis 601 East 12th Street

3.0 PROPOSAL FORMAT AND SUBMITTAL REQUIREMENTS

1. In order to be considered for award of a contract for the requirements of this solicitation, the offeror must submit a proposal with its offer. Failure to submit a complete proposal may result in the entire offer being rejected. The proposals shall be submitted in Volumes as follows:

VOLUME 1, TECHNICAL PROPOSAL:

TAB A, FACTOR 1 Corporate Experience TAB B, FACTOR 2 Past Performance TAB C, FACTOR 3 Key Personnel TAB D, FACTOR 4 Utilization of Small Business

VOLUME 2: PRICE PROPOSAL:

TAB A, FACTOR 5 Price. Consisting of an original signed Standard Form 1442 “Solicitation, Offer, and Award”; providing a price for all line items in the corresponding bid schedule; and acknowledgement of all amendments to the solicitation.

2. Proposal Characteristics

a) Submit original and five copies of the proposal. An electronic copy shall also be provided on one CD/DVD in PDF format and be *Optical Character Recognition (OCR) compatible. Each Volume shall contain a table of contents and all pages of each factor shall be sequentially numbered. All text must be legible and easily read. The page size of the offeror’s proposal shall not exceed 8-1/2 by 11 inches. Diagrams, charts and tables shall conform to the paper size.

All text shall be typed single-spaced with a minimum size 12 font. Margins (1-inch) shall be clean and clear. If fold-out charts are unavoidable, and are to be utilized, all sheets shall be reproduced on 11 by 17 inch, and folded to 8-1/2 by 11 inch size. Submit the SF 1442, completed and signed by a person authorized by the offeror. Offerors shall limit Volume 1 proposals to a maximum of 30 pages. A page is defined as text or information on one side of the paper. If it is printed double sided, each face will be counted as a page. TAB B - Factor 2 – Past Performance will not be counted towards this page limit.

b) Volumes 1 and 2 shall be contained within separate 3-ring loose leaf binders and submitted in the following quantities (no heat or spiral bound volumes).

Volume 1 – Technical Proposal Original & 5 copies Volume 2 – Price Proposal Original & 2 copies

c) An electronic copy of each volume shall also be provided on one (1) CD/DVD in PDF format and be *Optical Character Recognition (OCR) compatible.

All text must be legible and easily read.

d) Each Volume of the proposal shall be identified by the Solicitation Number

(W912DQ-17-R-1008), project title (Harry S. Truman Power House:

Excitation System Replacement), name, address, and telephone number of the Offer, and the following on the volume in bold letters:

VOLUME 1: TECHNICAL PROPOSAL

VOLUME 2: PRICE PROPOSAL

e) The Proposal shall be organized by factors. They shall be described in separate sections, appropriately tabbed in a report form. All pages of each factor shall be sequentially numbered. Elaborate or lengthy presentations are not necessary or desirable. The Proposal’s clarity, organization and cross referencing are mandatory. No material shall be incorporated by reference.

The Technical proposal shall not refer the reviewer to information contained in the Price proposal.

f) Additional Information to be provided in Volume 2. The following items should be submitted in an envelope labeled “Pro Forma Requirements”:

a. Offeror will submit a cover letter containing:

i. Solicitation number

ii. Name, address, email, and telephone and fax numbers of the offeror

iii. Names, title, email, and telephone and fax numbers of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this RFP.

iv. Name, title and signature of the person authorized to sign the proposal

v. A statement specifying agreement with all terms, conditions and provisions included in the RFP

vi. CAGE Codes for the offeror, and all teaming partners who participated in Factors 1 and 2– Weld or Paint Qualifications and Experience Projects

b. For Joint Ventures, the information required by paragraph “5.0 Joint

Ventures”

c. Acknowledgement of all amendments to the RFP in accordance with the instructions on the Standard Form 30 (amendment form).

d. The completed Section 00 45 00 of the RFP (Representations and

Certifications), including the Printed entity record from System for Award Management (SAM) certification.

e. Bid Guarantee. See FAR 52.228-1.

f. Financial statement and bank letter that verify that sufficient funds will be available to finance the work

g. The completed FOOH certification

4.0 INQUIRIES/QUESTIONS

Technical inquiries and questions relating to this solicitation shall be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org). To submit and review inquiry items, prospective offerors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective offeror who submits a comment /question will receive an acknowledgement of their comment/question via email. Another email to the same address will notify the prospective offeror once the reply is available for viewing.

***Please Note: Offerors shall only submit one question per inquiry. All inquiries containing multiple questions shall be rejected.

The Solicitation Number is: W912DQ-17-R-1008

The Bidder Inquiry Key is: AQ8GSG-GVBY3Z

The Plan Room Key is: E3ZSHP-UWSPME

Instructions for first-time ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. Select agency USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret

Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the

ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Instructions for future ProjNet Bidder Inquiry Access:

1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. Select agency USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your

Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

The Bidder Inquiry System will be unavailable for new inquiries ten calendar days before proposal due date in order to ensure adequate time is allotted to form an appropriate response to inquiries and amend the solicitation if necessary.

Offerors are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

The ProjNet call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago) or by appointment for OCONUS. The telephone number for the Call Center is 1-800-428-HELP. Email to staff@rcesupport.com.

5.0 JOINT VENTURES

Joint Ventures shall submit the following additional documentation regarding their business entities:

1) A certified copy of their Joint Venture agreement.

2) A detailed statement outlining the following in terms of percentages, where appropriate.

a. The relationship of the joint venture parties in terms of business ownership, capital contribution, and profit distribution or loss sharing.

b. The management approach of the joint venture in terms of who will conduct, direct, supervise and control the project and have custody and control of the assets of the Joint Venture and perform the duties necessary to complete the work.

c. The structure of the joint venture and decision-making responsibilities of the Joint Venture parties in terms of who will control the manner and method of performance of the work.

d. The bonding responsibilities of the Joint Venture parties.

e. Identification of the key personnel having authority to legally bind the Joint Venture to subcontracts and state who will provide or contract for the labor and materials for the Joint Venture.

f. Identification of party maintaining the Joint Venture bank accounts for the payment of all expenses and the deposits of all receipts, keep the books and records, and pay applicable taxes for the Joint Venture.

g. Identification of party furnishing the facilities, such as office supplies and telephone service.

h. Identification of party having overall control of the Joint Venture.

Other sections of the proposal shall identify, where appropriate, whether key personnel are employees of the individual Joint Venture parties and identify the party, or hired as employees of the Joint Venture.

If one of the Joint Venture parties possesses experience and/or past performance that experience and/or past experience will be included as the experience and/or past experience of the Joint Venture.

6.0 SUBCONTRACTORS/TEAMING PARTNERS

If an offeror wishes to receive credit for the experience or past performance of a subcontractor or teaming partner, the offeror must submit a letter of commitment to use the proposed firm on the project, signed both by the subcontractor/teaming partner and the offeror. The commitment letter must be submitted even if the subcontractor/teaming partner is in some way affiliated with the offeror (for example, the subcontractor/teaming partner is a subsidiary of a joint venture partner, or a subsidiary of a firm to which the joint venture partner is also a subsidiary). Include the subcontractor letters of commitment in Volume 1, Factor 1: Corporate Experience.

SAMPLE LETTER OF COMMITMENT to USE SUBCONTRACTOR/TEAMING

PARTNER [COMPANY LETTERHEAD]

TO: Contracting Officer, Kansas City District, United States Army Corps of Engineers

SUBJECT: Letter of Commitment for Proposed Task Order for [insert project name]

Dear Sir or Madam:

[Insert name of offeror] and [insert name of subcontractor/teaming partner] hereby make the unequivocal commitment that, in the event that the company receives award of the Task Order for [insert project name], [insert name of subcontractor/teaming partner] will perform the following work required by the Task Order.

[Insert list of tasks to be performed by the subcontractor/teaming partner]

Sincerely, [Authorized Official] [Legal Name of Offeror] Date:

[Subcontractor/Teaming Partner]

[Legal Name of Firm] Date:

7.0 BASIS FOR AWARD

The selection will be based on evaluation of technical and price factors. There are four non-price (technical) factors: Technical Factor 1 - Corporate Experience; Technical Factor 2 - Past Performance; Technical Factor 3 – Key Personnel; and Technical Factor 4 – Utilization of Small Business.

Price will be evaluated by the Price Team. Proposal prices must be entered for all items in the Proposal. The Price Team will evaluate the price proposals to recommend fair and reasonableness.

The Government intends to award a contract to the responsible offeror whose proposal conforms to the solicitation and proposes the Best Value to the Government under a Traditional Subjective Tradeoff Process under FAR 15.101-1. The selection will be based on Factors identified in Table 1 below. The relative importance of the evaluation factors is as follows:

Table 1: Relative Importance of Factors

Volume Factor

Number

FACTOR RELATIVE IMPORTANCE

1 - Tab B 1 Corporate Experience Equal in importance to Factor 3 and significantly more important than Factors 2 & 4.

1 – Tab C 2 Past Performance Significantly less important than

Factors 1 & 3. More important than Factor 4.

1 – Tab D 3 Key Personnel Equal in importance to Factor 1 and significantly more important than Factors 2 & 4.

1 – Tab E 4 Utilization of Small Business Significantly less important than

Factors 1 & 3. Less important than Factor 2.

When applying the traditional subjective tradeoff process, all evaluation factors when combined, are significantly more important than price. The closer the total evaluated non-price ratings are to one another, the greater importance of the price evaluation in making the Best Value - Tradeoff determination. The closer the final price evaluations are to one another, the greater the importance of the total evaluated non-price ratings in making the Best Value - Tradeoff determination. Offerors will be cautioned that the award may not necessarily be made to the offeror providing the lowest priced proposal or the highest technically rated proposal.

8.0 SOURCE SELECTION PROCESS

All proposals received in response to this solicitation will be evaluated in accordance with source selection procedures. The principal objective of this process is to select a responsible offeror whose proposal represents the Best Value to the Government. The process is designed to ensure the impartial, equitable, and comprehensive evaluation of all proposals received in response to this solicitation.

Source Selection Team

All offers received in response to this solicitation will be evaluated in accordance with informal source selection procedures. The process is designed to ensure the impartial, equitable, and comprehensive evaluation of all responsible proposals received in response to this particular solicitation.

(a) Source Selection Team

The Source Selection Team is established as a separate organization and management chain of command whose only purpose is to accomplish the objective above. The organization consists of a Source Selection Authority (SSA) and a Source Selection Evaluation Board (SSEB). The organization is designed to ensure active ongoing involvement of appropriate contracting, technical, logistics, legal, small business, and other functional staff management expertise.

(b) Source Selection Procedure

The source selection procedures will begin with an initial review of proposals received in response to this solicitation. The SSEB shall evaluate the proposals based solely on the evaluation criteria identified below. To be considered for evaluation, each offeror shall specifically address each of the evaluation factors listed below. Sufficient detail shall be provided, citing specific data as may be required, such that the proposal may be adequately evaluated. The proposal must show clearly that the offeror has an understanding of the work tasks required and has the capability and responsibility to accomplish the work.

The results of the SSEB evaluations will be presented to the SSA, who will make the final source selection decision or determine whether it is appropriate to engage in clarifications…