North_Topeka_Amendment_0001.pdf

PDF 36 KB Posted

Attached to
Topeka Flood Risk Management, North Topeka Improvements
Solicitation number
W912DQ-16-B-1002
Issued by

About this file

Amendment 0001

View the file

Other files

File Type Posted
A.07.24_Amendment_0002.pdf PDF
03_30_53.pdf PDF
Contractor's_Right_of_Entry_01_30_00_attachment.doc DOC document
D.01.06_Amendement_0002.pdf PDF
03_20_00.00_10.pdf PDF
TFRM_NOR_PLANS_AMDT2.pdf PDF
A.02.09_Site_Visit_Rooster.pdf PDF
Drawing_Number_B-101.pdf PDF
Drawing_Number_B102.pdf PDF
Drawing_Number_CD101.pdf PDF
Drawing_Number_G-002.pdf PDF
A.07.23_Solicitation_ _Specs_RTA_(8-25-16).pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See Block 14 Continuation Page

1. CONTRACT ID CODE PAGE OF PAGES

J 1 11

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Sep-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DQ-16-B-1002

X 9B. DATED (SEE ITEM 11)

25-Aug-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-Sep-2016

CODE

USACE, KANSAS CITY +

FEDERAL BLDG, CT-C

601 E 12TH ST RM 647

KANSAS CITY MO 64106-2896

W912DQ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DQ-16-B-1002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 73 46 - WAGE DETERMINATION SCHEDULE

The following have been deleted:

DAVIS BACON RATES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

BLOCK 14 CONTINUATION PAGE

The SOLICITATION is amended as follows:

NOTE: Deleted text is shown with strikethrough. Added text is shown with underline.

1. SPECIFICATIONS: Narrative Changes

a. Section 01 30 00, delete paragraph 1.7.1 Informal Partnering

The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.

The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the Resident Engineer office or the Contractor). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to six month intervals.

b. Section 01 30 00, delete paragraph 1.22.1 Payment Withholding

If there is no separate contract line item (CLIN) for as-built drawings, the Government will withhold the amount of $35,000 or 1% of the present construction value, whichever is greater, until the final as-built drawing submittal has been approved by the Government.

c. Section 01 33 00, paragraph 1.6.1.1 Designer Review

For items to be reviewed by the designer, submittals shall be sent to the Kansas City District Office, addressed as follows Resident Office, where distribution will be made to the appropriate reviewer:.

US Army Engineer District, Kansas City ATTN: ED-DT (Construction Submittal Coordinator) Federal Building, Room 502, 601 East 12th Street Kansas City, Missouri 64106-2896

The Contractor shall furnish one copy of ENG Form 4026, five three copies of ENG

Form 4025, and five three copies of the shop drawing information, and an electronic copy of each submittal to the Designer Resident Office. For each item submitted to the designer, one copy of the corresponding ENG Form 4025 and all shop drawing enclosures shall be submitted to the Resident Office.

d. Section 01 33 00, paragraph 1.6.1.2 Resident Office Approval For items which require review and approval by the Resident Office, the Contractor shall furnish four two copies of ENG Form 4025 and four two copies of the shop drawing information to the Resident Office.

e. Section 01 33 00, paragraph 1.14.1 Review Notations

Contracting Officer review will be completed within 20 30 calendar days after date of submission.

Submittals will be returned to the Contractor with the following notations:

2. DRAWINGS: The following drawings are amended and a copy will be provided in a separate attachment.

G002: To update the signature block to show Dave Mathews signature.

B101: Changed to black and white so that it displays faster B102: Same as stated for B101 CD101: Changed one street name

3. Provide an updated copy of the wage rates.

4. All other terms and conditions remain unchanged and in full force.

UPDATED WAGE RATE

General Decision Number: KS160036 08/26/2016 KS36

Superseded General Decision Number: KS20150036

State: Kansas

Construction Type: Heavy

County: Shawnee County in Kansas.

HEAVY CONSTRUCTION PROJECTS (including sewer/water construction).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least

$10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date

0 01/08/2016

1 04/29/2016

2 08/26/2016

ELEC0226-001 09/01/2015

Rates Fringes

ELECTRICIAN......................$ 29.60 13.83

* IRON0010-016 04/01/2016

IRONWORKER (REINFORCING AND

STRUCTURAL)......................$ 32.00 28.15

LABO1290-001 04/01/2016

LABORER (Asphalt, Includes

Raker, Shoveler, Spreader and

Distributor).....................$ 16.06 9.14

PAIN2012-006 05/01/2012

PAINTER (Spray Only).............$ 22.93 11.51

TEAM0541-003 04/01/2014

TRUCK DRIVER

(1) Dump Truck and Lowboy

Truck.......................$ 30.71 13.20

SUKS2014-016 07/09/2014

CARPENTER (Form Work Only).......$ 23.39 10.16

CARPENTER, Excludes Form Work....$ 31.70 12.64

CEMENT MASON/CONCRETE FINISHER...$ 24.67 11.76

LABORER: Common or General......$ 16.25 3.06

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 31.01 13.59

OPERATOR: Boring Machine........$ 17.06 4.20

OPERATOR: Crane.................$ 37.05 13.71

OPERATOR: Loader................$ 30.13 12.34

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate

(weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or

"UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010

08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

(End of Summary of Changes)