RESPONSE_to_QUESTIONS_1_25JUN2017.docx

DOCX document 22 KB Posted

Attached to
Temporary Sensitive Compartmented Information Facility Federal contract opportunity
Solicitation number
W912D1-17-R-0013
Issued by
Department of the Army Materiel Command Expeditionary Contracting Command Regional Contracting Office Kuwait 408th CSB

About this file

Response to Vendor Questions 1, dated 25-June-2017

View the file

Other files for this federal contract opportunity

Other files attached to Temporary Sensitive Compartmented Information Facility, newest first.
File Type Posted
RFQ_W912D1-17-R-0013-0001TF_Sinai_TSCIF_10JUL17_Amendment_3.pdf PDF
RFQ_TF_Sinai_TSCIF_25JUN17.docx DOCX document
2._RFQ_-_W912D1-17-R-0013_TF_Sinai_T-SCIF.docx DOCX document
3._CLAUSES_W912D1-17-R-0013.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RESPONSE TO VENDOR QUESTIONS #1: 25-June-2017

Conflicting/Confusing SOW information pertaining to ports in workstations –

CHANGE: T-SCIF “WORK AREA” shall be configured with fifteen (15) workstations, each with the following: one (1) JWICS port, one (1) SIPR port, one (1)NIPR port, two (2) additional RJ45 ports, and four (4) power outlets. Total workstation ports: fifteen (15) JWICS, fifteen (15) SIPR, fifteen (15) NIPR, thirty (30) RJ45 ports. Total workstation power outlets is sixty (60).

This change does not affect the power outlets and port requirements for T-SCIF printers.

Question pertaining to HVAC tonnage –

ADDITION: The following load information is provided for rough estimating purposes only. Prospective offerors may recommend different HVAC options and pricing as desired. Offerors should explain calculations and estimates as excessive capacity is not desired.

Stations will have two (2) small form factor desktop computers (SIPR and NIPR) which share a monitor using a KVM switch. One computer will always be in sleep mode. Expected occupation of the facility is no more than ten (10) 100W heat producing individuals at any given time.

Question pertaining to On-Site Contractor Representative (CAMP SOUTH, SINAI) –

ADDITION: Vendors should plan for a maximum of three (3) weeks on-site. Concrete pad and utility connections are expected to be available upon delivery of T-SCIF container. The requiring activity will coordinate Egyptian Visa not later than sixty (60) prior to arrival and will coordinate base access.