Project: CHP-16010-6J & DPW-17139-7J Move Sign and Replace Sidewalks

Building 4107

SCOPE OF WORK

(30 August 2018)

Project Description. The Contractor shall provide all labor, materials, equipment, tools, accessories, site security, and transportation as required to relocate one LED marquee-type sign and to replace two concrete sidewalks at building 4107, Southern Cross Chapel. The Contractor shall perform all work in accordance with this SOW and these specifications, commercial practices and industry standards. All work shall be accomplished in accordance with applicable federal, state, and local regulations.

Work includes but is not limited to the following, identified in two parts, Part A and Part B:

Part A. Relocate Existing Sign to New Location.

1. The point of contact (POC) for this project will be the contracting office until time of award. Additional project POC’s will be provided to the awardee.

2. The Contractor shall accept directions only from the Regional Contracting Office- Alaska (RCO-AK) Contracting Officer (KO). Requests or desires of the users or using agency made directly to the Contractor will be immediately brought to the attention of the KO, and the Contracting Officer’s Representative (COR) if applicable. Any changes to the project scope or other provisions of the SOW must be authorized in writing by the KO.

3. Construct New Concrete Base. The Contractor shall excavate and install a new concrete base to move/mount the existing sign onto. See the attached drawings/pictures for the locations and descriptions. The tasks anticipated under this portion of the scope include but are not limited to:

a. A dig permit will be required for this project.

b. The Contractor shall install all necessary barricades and warning signs around the job site area to protect workers, building occupants and the public. The warning barriers will be put in place for the duration of time that the contractor is working this project.

c. The Contractor shall excavate a hole of sufficient size and depth to accommodate the formwork for the new concrete base at the new sign location. The new hole for the base will be of sufficient width that a commercial vibraplate or vibrafoot compactor or equivalent can be used to properly compact the soils underneath and around the new concrete footing and base when it is back filled.

d. The Contractor will excavate a trench of sufficient size and depth to install the circuit and control wiring from the exterior wall mounted junction box through the new concrete base to the new sign location. The trench will be of sufficient width that a commercial vibrafoot compactor or equivalent can be used to properly compact the soils underneath and above the new circuit and control wiring when it is back filled.

e. Where necessary to prevent physical damage to power and control conduits;

protection around the conduits shall be provided in the form of granular or selected material, or other approved means.

f. All conductors shall be installed in conduit from the exterior junction box to and through the concrete base to the sign. All circuit wiring shall include an appropriately sized grounding conductor. Except where rising to the sign base or junction box, all conduits shall be installed buried a minimum of 36 inches below final finish grade.

g. All wires shall be copper, installed in conduit with type XHHW or RHW-USE) insulation.

h. A direct burial polyethylene or other acceptable warning tape shall be installed directly above all underground conduits/conductors at 12 inches below finish grade the length of the trench up to and adjacent to the junction box and the sign base.

i. The Contractor shall remove and dispose of any conduits, conductors supplying the old base. Removed shall be considered accomplished once the conduits, conductors and bolts have been cut off within one inch of the surface if the old concrete base.

j. Compaction of the trenches and under and around the sign base will be done in one foot or less lifts with a commercial compacter.

k. The Contractor shall take special care to uniformly compact all portions of the conduit access points and the lengths of trench as well as the bases.

l. The conduits to the new sign and the sign itself shall be grounded to a single grounding rod located adjacent to the sign base. The ground rod shall be a minimum 1/2" in diameter and 8 feet in length, installed with the top 4- 6 inches below finish grade. All ground connections shall be clamp type grounding connection and securely tightened.

m. All disturbed ground will be returned to their original or better condition except for the excess soil that will be removed from the job site. This is to include the area over the old concrete base as well as areas damaged from the operation of the excavation equipment.

n. The Contractor may cut and preserve the existing grass sod (root base) to reinstall once the trenches and sign base once they have been backfilled and compacted.

o. The Contractor shall vibrate the concrete pours for the new sign base to eliminate voids, taking care not to puncture, deform or float the conduit. The concrete will be installed in one continuous pour. The concrete base will have rounded edges around the top edge of base with the use of a standard concrete edging tool.

p. The new base will be poured with 3000psi or better concrete that will be installed from four feet below the surface of the ground to four inches below surface of the ground. The Contractor will install a full cage of ½” rebar in the concrete base and ¾” J bolt anchors will be tied to the concrete base rebar cage to remount the old sign.

The bolts will be sufficiently threaded to allow for sign adjustment, see drawing. The sign base will be installed on the anchor bolts at the midway point of the threads; so any future adjustments can be accomplished 1” up or down for a total of 2” of adjustment.

q. The Contractor shall remove the concrete forms.

r. The Contractor shall be required to paint the conduit, boxes and fittings that he installs for this project where they are exposed above the ground. The paint color will match the surface color upon which the conduit, box or other equipment are mounted.

s. All other circuits, components and/or utilization equipment will be left energized and operational.

t. The finished product and all of its components shall be constructed and assembled to handle the environments in which it is installed and provide a complete operational and functional system.

u. The completed project shall provide a complete functional system and a re-established lawn.

4. Anything mentioned in the Scope of Work and not shown on the drawings, or shown on the drawings and not mentioned in the Scope of Work, shall be of like effect as if shown or mentioned in both.

5. The Contractor shall make a reasonable effort to verify dimensions and shall examine the project to become aware of the existing conditions and difficulties involved in the completion of the work in accordance with the Scope of Work prior to the submission of your bid and commencement of work.

6. Completion date-Period of Performance not to exceed 60 days after NTP issuance.

7. Upon award of the contract, contractor shall meet with Facility Management staff for a Pre-Con meeting, before beginning work. Work will only commence after the issuance of a Notice to Proceed (NTP). The building included in the scope of this contract will likely be occupied. The Contractor will schedule and perform work under this contract in such a manner as to allow the occupants of the building to continue their normal activities with the least amount of interference. NTP will be issued 10 days after the date the contract is awarded. The construction period includes material and equipment delivery times.

8. The completed installation shall comply with all applicable provisions of the NEC and the SOW (Drawings and Specifications), enclosed and/or attached.

9. All work will be performed by certified personnel, as applicable. All required training and certification costs will be paid by the Contractor.

10. The Contractor will contact and verify with all necessary material suppliers; a secure date when materials will be on hand to complete this project prior to submitting your bid on this project.

11. When the contractor requests approval of substitute materials and/or equipment, it shall be understood and agreed that such substitution, if approved, will be made without cost to the government, regardless of changes in connections, spacing, electrical service, and all other appurtenances.

12. Contractor shall provide Quality Control. The government’s Quality Assurance (QA) individual shall work closely with the Contractor’s QC individual to ensure all contract requirements are included.

13. Contractor shall verify all equipment operational and insure your quality control inspections and corrections have been accomplished before calling Contract Management for the final inspection!

14. The Contractor shall perform all activities so as to avoid interference with operations of the facility and the work of others.

15. Required submittals:

a. With proposal: Please include construction schedule with the proposal

b. Submittals required prior to start of construction: None

c. Submittals before final inspection: Copy of receipt for concrete, rebar and J bolt anchors.

Part B. Replace Sidewalks.

1. Protect building doors and exterior finish from damage from this work. Place temporary signage on the interior of these doors to minimize accidental use during the project. NOTE: Doors shall remain available for immediate use during emergency egress. Demo and dispose of existing deteriorated sidewalks. Demo terminates at the existing expansion joint approximately ten feet from each door. All demo’d materials are to be removed from Ft Wainwright.

2. Excavate as necessary to below the active layer, backfill with base course crushed aggregate, and compact to 95% density.

3. Install no less than three each steel dowels at both door locations (six total).

Dowels shall penetrate both the existing building slab and the new concrete at least six inches. Notify PM and QA 24 hours prior to concrete placement to allow inspection of steel reinforcement.

4. Install ½ inch expansion material between old and new concrete. Install 6” X 6” welded wire fabric throughout, and add rebar as needed.

5. Form up and place new 6” thick concrete sidewalk, 3,000 psi, broom finish. New concrete placement shall conform to UFGS 32 16 13. Protect new concrete from vandalism and the weather until protection no longer necessary.

6. Rotate existing gutter downspouts 90 degrees, so the outflow goes to the east. Any new or additional gutter/down spout components shall exactly match existing in color and type.

Reuse existing splash blocks. Regrade area from sidewalk as necessary (approximately 5-10 feet) to ensure water drains to the east away from sidewalk and building.

7. Thoroughly clean up job site. Place new topsoil and grass seed as needed along new sidewalk and other disturbed areas.

8. Seal all joints with Sikaflex or equal arctic-grade crack sealant.

9. The Contractor shall perform all activities so as to avoid interference with operations of the facility and the work of others. The completed project will provide a complete functional system. The completed installation shall comply with the SOW.

10. Upon award of the contract, contractor shall meet with Facility Management staff for a Pre-Con meeting, before beginning work. Work will only commence after the issuance of a Notice to Proceed (NTP).

11. If applicable and where available, on-site utilities will be provided at no cost to the Contractor. These utilities will be used only in performance of and in support of this project. Any temporary connection to the utility system will be coordinated with the contracting officer’s representative prior to hook-up, and are the responsibility of the Contractor.

12. The Contractor and the Contracting Officer’s Representative will agree on temporary storage areas in the general location of the project. Request for storage area shall be submitted with the proposal package. The contractor will be responsible for security and tidiness of the storage area.

13. Submittal Schedule:

Submittal Description Due Construction Schedule With Quote OPSEC Training Certificate: (See item 10)

2 Days Post Award

Product data on expansion joint sealant 2 Days Post Award Reinforcement Steel Data 2 Days Post Award

8. The Construction period is 60 days after issuance of NTP. The NTP will be issued 10 days after the date the contract is awarded. The construction period includes material procurement and equipment delivery times.

9. Security Requirement. All contractor and all associated sub‐contractor employees shall comply with applicable installation, facility and area commander installation/ facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.

Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

10. All new contractor employees, to include subcontractor employees, requiring access to Department of Defense installations, facilities, and controlled access areas shall complete initial Operations Security (OPSEC) training or provide proof (Certificate) of current annual OPSEC training. All contractor employees will complete annual refresher training as required by the length of the contract. The required training is available at: https://securityawareness.usalearning.gov/opsec/. The contractor shall maintain certificates of completion for each employee and subcontractor employee upon employment.

11. The contractor's employees are not to divulge anything they may see or hear with regards to the activities and operations of units within the workplace or anywhere else on and off the installation. Employees are not to discuss anything they are doing on the installation to anyone that does not need to know.

ATTACHMENTS:

Work site photographs

Project: CHP-16010-6J & DPW-17139-7J
Move Sign and Replace Sidewalks
Building 4107
SCOPE OF WORK
(30 August 2018)