FY27_NIPR-SIPR_Installation_BPA_PWS_Tracked_Changes Revised (22Oct26) - Clean.pdf
PDF 246 KB Posted
- Attached to
- MULTIPLE AWARD LAN/DLAN SIPR-NIPR BPA
- Solicitation number
- W912CN27RA005
About this file
This Performance Work Statement (PWS) governs a Blanket Purchase Agreement (BPA) for inside plant (ISP) structured cabling design, installation, testing, and repair services supporting NIPRNET and SIPRNET infrastructure across U.S. Army installations in Hawaii (Schofield Barracks, Fort Shafter, Wheeler Army Airfield, Tripler Army Medical Center, Camp Smith) and Alaska within the USINDOPACOM Area of Responsibility. The contractor shall provide all personnel, management, tools, materials, transportation, and engineering services on a 100% Contractor-Furnished Material (CFM) basis with no Government-furnished equipment. Work is strictly limited to interior cabling installations terminating at Building Entry Points or demarcation points within Telecommunications Rooms; outside plant work, inter-building campus cabling, exterior trenching, and duct bank rodding are explicitly excluded and managed under separate contracts.
The BPA establishes a base period of twelve months from award with four consecutive twelve-month option periods exercisable at Government discretion. The contractor must maintain local technical support resources on Oahu and other designated regions with 24/7 emergency response capability (2-4 hours for critical outages; 8 hours for routine repairs). Key deliverables include native electronic test data (Fluke .flw files for copper; .sor/.flw OTDR traces for fiber), as-built CAD/MicroStation drawings within fifteen business days of acceptance, Engineering Installation Plans with itemized Bills of Materials, Quality Control Plans, and weekly status reports. All personnel must hold active SECRET security clearances for SIPRNET work; the Project Engineer must maintain mandatory BICSI RCDD certification. The contract requires compliance with UFC 3-580-01, ANSI/TIA standards, CNSSI No. 7003 for Protective Distribution Systems, and 30th Signal Battalion labeling standards; all cabling must be machine-labeled per Pacific Labeling Guide with zero hand-written labels permitted. The contractor warrants all installations for twelve months from Government acceptance, covering labor, parts, shipping, and travel at no additional cost, with OEM warranty pass-through to the Government.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
NON-SECURE INTERNET PROTOCOL ROUTER NETWORK (NIPRNET) / SECURE
INTERNET PROTOCOL ROUTER NETWORK (SIPRNET) INSIDE PLANT (ISP)
INSTALLATION BLANKET PURCHASE AGREEMENT (BPA)
30TH SIGNAL BATTALION, 516TH SIGNAL BRIGADE
1.0 GENERAL INFORMATION AND SCOPE OF WORK
1.1 Mission and Physical Demarcation. The contractor shall provide all personnel, management, supervision, tools, testing apparatus, materials, Contractor-Furnished Material (CFM), transportation, and engineering services necessary to perform Inside Plant (ISP) structured cabling design, horizontal cable distribution, and fiber/copper installation, diagnostic troubleshooting, and repair across NIPRNET and SIPRNET physical layer infrastructure.
The overarching operational objective is to modernize and sustain Department of Defense Information Network (DoDIN) physical transport architecture across US Army installations supported by the 30th Signal Battalion, Network Enterprise Center (NEC).
1.1.1 Exclusively Inside Plant (ISP) Scope. The previous draft contained ambiguous language regarding inter-building links: The scope of this BPA is strictly restricted to Inside Plant (ISP) structured cabling. Inter-building outside plant runs, manhole duct bank rodding, and exterior campus cabling are strictly excluded and handled under separate command OSP vehicles. Outside Plant (OSP) infrastructure—including exterior underground conduit duct banks, manholes, handholes, aerial poles, direct buried cable, exterior campus raceways, rodding, and exterior digging/trenching—is strictly excluded and managed under separate command contracts. Contractor activities under this BPA shall terminate at the interior side of the facility Building Entry Point (BEP) sleeve or at the incoming demarcation busbar/enclosure within the designated Telecommunications Room (TR). Inter-building campus cabling pulls are strictly prohibited under this vehicle.
1.1.2 Strict Non-GFE Mandate (100% Contractor-Furnished Material). Original draft specification: The contractor shall furnish all materials, equipment, patch panels, cabling, and services... This is an absolute Non-GFE BPA. All items shall be Contractor-Furnished Materials (CFM) itemized in the contractor's proposal BOM and approved by the COR. In accordance with command policy, the Government will not furnish tools, installation materials, consumables, patch cords, jacks, patch panels, raceways, or mounting hardware. All materials, supplies, and system components required for project execution shall be Contractor-Furnished Materials (CFM). The contractor shall detail all CFM in a granular, fully itemized Bill of Materials (BOM) submitted with each individual Task Order proposal for Contracting Officer's Representative (COR) validation and approval prior to procurement.
1.1.3 Remediation as an Installation Enabler (Safety and Hazard Clause) [NEW CLAUSE]: Section 3.1.2 Remediation as an Installation Enabler (Safety & Hazard Clause): While this BPA is dedicated to active cable plant installation, the contractor shall inspect the immediate installation path and telecommunication space for critical safety, physical, or electrical hazards. If the contractor identifies deficiencies (such as compromised firestopping barriers, absent or non-compliant equipment bonding/grounding, or hazardous environmental obstructions) that physically prevent code-compliant and safe cable installation: 1. The contractor shall immediately issue written notification to the COR. 2. Upon written COR approval, the contractor is authorized to remediate these localized deficiencies in strict adherence to the 30th Signal TR Remediation Checklist solely to the extent necessary to facilitate a safe, code-compliant network installation. The contractor shall immediately halt affected work and issue written notification to the COR within twenty-four (24) hours. Upon written COR review and authorization, the contractor is empowered to remediate these localized physical, bonding, or fire-barrier deficiencies in strict adherence to the 30th Signal TR Remediation standards, solely to the extent necessary to facilitate a code-compliant, safe, and fully certified cable plant installation under the active Task Order.
1.2 Work Locations. Work locations include military installations, administrative buildings, operational complexes, command headquarters, and satellite support facilities within the State of Hawaii (including Schofield Barracks, Fort Shafter, Wheeler Army Airfield, Tripler Army Medical Center, Camp Smith, and associated garrison envelopes), the State of Alaska, and other designated locations within the U.S. Indo-Pacific Command (USINDOPACOM) Area of Responsibility (AOR). Work outside the defined geographic area of a specific task order requires formal written modification issued by the Contracting Officer (KO).
1.3 Local Technical Support and Readiness. The contractor shall maintain local technical support resources on the island of Oahu, Hawaii, and other operational regions as identified in individual task orders, sufficient to respond to site surveys, engineering walkthroughs, routine service calls, and emergency restoration tasks. The contractor shall maintain and provide to the KO and COR an up-to-date roster of all local technical support personnel, including employee legal names, operational roles, technical certifications, clearance verification, and 24/7 contact information. This roster shall be submitted within five (5) business days of award and updated within twenty-four
(24) hours of any personnel reassignment. Local support personnel must be capable of fulfilling the emergency response requirements in Section 1.9.2 and the diagnostic repair requirements in Section 4.6.
1.4 Transportation, Travel, and Lodging. The contractor is exclusively responsible for all transportation, vehicle assets, shipping, specialized transport, lodging, meals, per diem, and commercial travel expenses associated with executing work under this BPA. Transportation and mobilization expenses must be fully accounted for within the firm-fixed price (FFP) quote submitted for each Task Order. The Government will not provide government vehicles, flight arrangements, or commercial logistics support.
1.5 Contractor Points of Contact and Electronic Communications. 1.5.1 Contractor Point of Contact: The contractor shall establish and provide to the KO and COR, at the post-award conference, a centralized local toll-free telephone number accessible from all supported locations within the USINDOPACOM AOR. The contractor shall designate Primary Point of Contact (POC) and an Alternate POC authorized to receive delivery orders, dispatch technicians, schedule surveys, and manage operational milestones. The contractor shall deliver detailed after-hours emergency contact procedures, including an escalation matrix and continuously monitored 24/7/365 phone numbers.
Any change to designated contact personnel or numbers must be reported in writing to the KO and COR within twenty-four (24) hours.
1.5.2 Electronic Communications and Timelines: The contractor shall maintain continuous electronic communication capabilities (e.g., enterprise email, mobile communications, secure messaging). Written notification from the Government transmitted to the contractor's official email address or designated telephone number constitutes official delivery. The contractor shall acknowledge receipt and respond within the following strict timeframes based on criticality: Routine Inquiries: Within twenty-four (24) hours; Urgent Operational Matters:
Within four (4) hours; Emergency Outages or Hazardous Conditions: Within two (2) hours.
1.6 Period of Performance. The overall Blanket Purchase Agreement period of performance shall consist of a base period of twelve (12) months from the date of award, with four (4) consecutive twelve-month option periods, exercisable at the discretion of the Government in accordance with FAR 52.217-9. Each individual Task Order issued against this BPA shall specify its own discrete period of performance and milestone completion schedule.
1.7 Material Receipts and Accounting. The contractor shall submit complete documentation validating the procurement, shipping, receipt, and physical delivery of all materials and assemblies required for Task Order execution. Contractor proposals and invoices must present fully itemized costs, cleanly separating labor, hardware, cabling, and ancillary supplies. Submissions must include manufacturer shipping invoices, Bills of Materials (BOM), packing slips, and receiving inspection reports showing compliance with specified part numbers and DoDIN Approved Products List (APL) status.
1.8 System and Workmanship Warranty. The contractor shall warrant all installation workmanship, physical cabling, terminations, patch panels, raceways, grounding infrastructure, and repair actions for a minimum period of twelve (12) months from the date of formal Government acceptance. The contractor shall submit a formal Warranty Management Plan defining precise procedures for warranty claims, including a dedicated ticketing portal, points of contact, and escalation paths. Upon official defect notification from the COR, the contractor shall provide an on-site technical response within forty-eight (48) hours to diagnose and initiate repairs. If a defect involves a physical security breach or mechanical failure within a SIPRNET Protected Distribution System (PDS), the contractor shall respond on-site within four (4) hours. The contractor shall guarantee the pass-through and formal transfer of all Original Equipment Manufacturer (OEM) component warranties (including 20- to 25-year structured cabling system performance warranties from certified manufacturers) to the Government upon project completion. The warranty coverage shall be comprehensive, covering all costs of labor, replacement parts, shipping, test certification, and travel at no additional cost to the Government. The warranty period begins upon formal signature of the DD Form 250 (Material Inspection and Receiving Report) or official COR Acceptance Memorandum.
1.9 Operational Hours and Emergency Response. 1.9.1 Normal Operating Hours: The contractor shall execute engineering design, site surveys, physical installation, and testing functions during normal garrison duty hours: 0730 to 1630 Hawaii Standard Time (HST), Monday through Friday, excluding Federal holidays and Government-directed closures pursuant to 5 U.S.C. 6103. Work outside normal duty hours must be coordinated with and approved in writing by the COR at least forty-eight (48) hours in advance. 1.9.2 Emergency Service After Normal Operating Hours: Emergency service calls involving critical physical cable plant outages, life-safety hazards, or structural damage impacting DoDIN transport will be authorized by the COR. The contractor shall maintain after-hours emergency capability and arrive on-site within two (2) to four (4) hours of emergency notification, depending on priority: Monday through Friday: 1630 to 0730 HST; Weekends: 1630 Friday through 0730 Monday HST;
Federal Holidays: 24-hour continuous coverage.
2.0 ROLES, RESPONSIBILITIES, AND QUALITY OVERSIGHT
2.1 Demarcation of Operational Responsibilities. To ensure operational efficiency, protect Government manpower, and eliminate contractual ambiguity, a strict demarcation between contractor physical installation responsibilities and Government logical/enterprise network engineering responsibilities is enforced.
2.1.1 Contractor Responsibilities (Layer 1 Physical Only): The contractor is exclusively responsible for physical Layer 1 engineering, installation, testing, and mechanical labeling. The contractor shall not perform Layer 2 or Layer 3 logical configurations. Specific contractor duties include: Performing pre-installation physical site surveys and engineering path validation; Supplying and installing physical containment, conduits, raceways, J-hooks, and cable trays; Installing, dressing, terminating, and certifying copper (Category 6A) and single-mode/multimode optical fiber cabling; Furnishing and mounting equipment racks, cabinets, cable management, patch panels, and faceplates; Performing localized TR installation-enabling remediation (bonding, FRT backboards, raceway dressing) upon COR authorization; Conducting non-configurative physical-layer testing, including 100% Level IIIe/2G copper certification and Tier 1 / Tier 2 OTDR fiber testing; Applying standardized machine-printed mechanical labels to cables, faceplates, patch panels, and cabinets; Submitting native electronic test files (.flw, .sor) and CAD/MicroStation as-built drawings; Correcting physical layer, labeling, or structural deficiencies identified during Government Quality Assurance inspections.
2.1.2 Government Responsibilities (Layer 2/3 Logical and Enterprise Network): The 30th Signal Battalion NEC Networking Branch and designated Government engineering entities retain exclusive legal and operational authority over all network devices, logical routing, and cybersecurity policies. The contractor shall not touch, configure, or administer these functions. Specific Government responsibilities include: Network switch-port activation, port configuration, and port security assignments; VLAN assignments, 802.1Q trunking, routing protocol provisioning, and IP address management (IPAM); Power over Ethernet (PoE/PoE+) policy administration and power budgeting on active switches; Staging, configuring, provisioning, updating firmware, and managing all active switches, routers, and cryptographic equipment; Enterprise network integration and DISA Security Technical Implementation Guide (STIG) compliance validation; Initiating and securing CTTA, TEMPEST, and PDS accreditation approvals from command authorities prior to Task Order issuance; Service ticketing and port activation scheduling via the Army Enterprise Service Management Platform (AESMP).
2.1.3 Infrastructure Branch Oversight: The 30th Signal Battalion Infrastructure Branch (IB) serves as the primary technical oversight authority for all physical installations executed under this BPA. Infrastructure Branch personnel shall: Review and approve all physical engineering packages, cable routing designs, and BOM submissions prior to task order execution; Conduct independent Government Quality Assurance (QA) surveillance and physical inspections; Validate that all cable certification test data meets required parameters using native testing software;
Provide formal technical sign-off and recommendation for project acceptance as the COR(s).
2.2 Contractor Quality Control Program. 2.2.1 Quality Control Plan (QCP): The contractor shall establish and maintain a comprehensive Quality Control Program to ensure all NIPRNET and SIPRNET infrastructure installation, testing, and documentation strictly meet the requirements of this PWS. The contractor shall submit a written QCP to the KO and COR for formal review and approval no later than thirty (30) calendar days after BPA award. Physical work shall not commence until the Government has formally approved the QCP.
2.2.2 Subcontractor Quality and Security Compliance: The prime contractor maintains sole legal and operational responsibility for ensuring that all subcontractors, across all tiers, strictly satisfy the security clearance, technical certification, and quality requirements of this PWS. No subcontractor personnel shall access telecommunication spaces or handle SIPRNET infrastructure without active SECRET security clearances, verified investigation documentation, and prior COR authorization.
2.3 Government Quality Assurance (QA) and Surveillance. The Government will evaluate contractor performance in accordance with the Government's Quality Assurance Surveillance Plan (QASP). The Government reserves the right to conduct unannounced physical inspections, witness testing procedures, and audit 100% of QC logs and native electronic test data. Contractor failure to maintain acceptable standards or correct deficiencies within specified timeframes may result in the issuance of formal Corrective Action Requests (CARs), payment withholding pursuant to FAR 52.246-4, or adverse CPARS reporting.
3.0 DELIVERABLES AND REPORTING REQUIREMENTS
3.1 Deliverables Matrix.
Deliverable
ID
Deliverable Title Frequency Due Date Distribution Delivery Method
A001 Technical & As- Built Drawings
Per TO 15 business days post-acceptance
COR, NEC Electronic (CAD/MicroStation &
PDF)
A002 Information Security & Facility Clearances
Per TO 10 business days prior to site work
COR, S2,
NEC
Encrypted Email / DoD
SAFE (CUI)
A003 Engineering Installation Plans
(EIP) & BOM
Per TO With initial design submission
COR, NEC Electronic (PDF, Excel
BOM)
A004 Native Copper Cable Test Data
Per TO 5 business days prior to final acceptance
COR, NEC Native Electronic Format (Fluke .flw)
A005 Reports, Narratives, and Hazard Notices
As needed Within 24 hours of occurrence
COR Electronic (MS Word /
PDF)
A006 Weekly Project Status & Progress Reports
Weekly Every Friday by
1630 HST
COR, KO Electronic (PDF)
A007 Contractor QC Inspection Reports
Per inspection
Within 48 hours of inspection
COR Electronic (PDF)
A008 Native Optical Fiber Test Data & OTDR Traces
Per TO Submitted concurrently with A004
COR, NEC Native Electronic Format (.flw / .sor)
A009 Task Order Engineering Proposals & Quotes
Per TO RFP 15 business days post-RFP issuance
KO, COR Electronic (PDF & Excel)
A010 Quality Control Plan
(QCP)
Once 30 calendar days post-award
KO, COR Electronic (PDF)
A011 Warranty Management Plan
Per TO 10 business days post-acceptance
COR Electronic (PDF)
3.2 Native Electronic Test Data Delivery (Deliverables A004 and A008). Original draft language: Deliverable A004 & A008 Native Testing Data Submission: The contractor shall provide comprehensive, native electronic test results for 100% of installed links prior to final acceptance: Copper Certification: Level IIIe/2G (or higher) test results submitted in native tester format (e.g., Fluke LinkWare .flw). • Fiber Certification: Tier 1 optical attenuation loss measurements and Tier 2 OTDR trace profiles submitted in native format. Traces must clearly display link attenuation, backscatter characteristics, reflectance, optical return loss, and precise distance measurements to all events (connectors, splices, patch panels). PDF or printed summary reports are accepted as secondary reference only; native raw files are mandatory for technical acceptance. Scanned PDFs, printouts, or summary text documents are strictly unacceptable for technical sign-off and will result in deliverable rejection. Traces must clearly display link attenuation, backscatter coefficient, reflectance, optical return loss (ORL), and precise distance markers for all events, including splices, patch panels, and connectors.
3.3 As-Built Drawings and Technical Submittals (Deliverable A001). The contractor shall prepare and submit complete engineering installation drawings and final as-builts using current commercial versions of AutoCAD or MicroStation SE. Drawings must strictly conform to the A/E/C CADD Standard Manual published by the USACE CADD/GIS Technology Center (CGTC). As-built packages must document exact horizontal cable routes, pathway envelopes, core penetrations, firestop locations, TR rack layouts, patch panel port assignments, and drop locations cross-referenced to machine-generated label IDs. Final as-builts shall be delivered within fifteen (15) business days following physical installation acceptance.
4.0 SPECIFIC TECHNICAL REQUIREMENTS AND PERFORMANCE
TASKS
4.1 Project Planning, Engineering, and Design. The contractor shall perform engineering to transform system requirements into fully deliverable physical infrastructure solutions in strict compliance with Unified Facilities Criteria (UFC) 3-580-01, ANSI/TIA standards, and current DISN-EN ICAN-DI architecture.
4.1.1 Engineering Installation Plans (EIP) and Design Reviews: For each Task Order, the contractor shall conduct thorough physical site surveys and develop an Engineering Installation Plan (EIP) encompassing cable pathway routes, floor plans, rack elevations, grounding diagrams, drop schedules, and a 100% itemized CFM Bill of Materials (BOM). Initial Design Review (IDR) and Final Design Review (FDR) are required. Formal Authority to Proceed (ATP) must be issued in writing by the Government prior to physical installation.
4.1.1.1 Subcontractor Compliance & Clearance Enforcement [NEW CLAUSE]: Section 4.1.1 Subcontractor Compliance & Clearance Enforcement: The prime contractor maintains sole legal responsibility for ensuring that all subcontractors, across all tiers, strictly satisfy the security clearance, technical certification, and safety requirements of this PWS. No subcontractor employee shall access classified spaces or handle SIPRNET infrastructure without active SECRET clearance verification and prior COR badging authorization.
4.1.2 Unified Capabilities Approved Products List (DoDIN APL): All components, connectors, patch panels, enclosures, and physical hardware furnished by the contractor shall be fully certified and listed on the Department of Defense Information Network Approved Products List (DoDIN APL) in compliance with DoDI 8100.04.
4.2 Project and Inter-Agency Coordination: Continuous coordination is required across designated technical and administrative entities: COR, NEC Technical Personnel, DPW, and S2.
4.3 Historic Preservation Compliance: Due to the historical significance of military installations on Oahu (including Palm Circle at Fort Shafter and historic aviation facilities at Wheeler Army Airfield), the contractor shall not execute structural wall penetrations, anchor mountings into historic masonry/timber, or exterior modifications without prior written approval. All mounting designs, pathway anchors, and penetrations affecting historic buildings must be submitted through the COR to DPW and the State Historic Preservation Division (SHPD) / local Historical Society prior to commencing work.
4.4 Physical Cable Plant Installation Specifications:
4.4.1 Interior Optical Fiber Cable Installation: Optical fiber splicing shall utilize active core-alignment fusion splicing methods only; mechanical splices are strictly prohibited on permanent backbone or horizontal plant.
4.4.2 Interior Copper Structured Cabling Installation: Horizontal copper cabling shall be Category 6A, 4-pair UTP or STP, tested to 500 MHz and capable of supporting 10GBASE-T transmission over 100 meters.
4.4.3 Cable Pathways, Containment, and Support Structures: Continuous support systems consisting of metallic conduits, enclosed raceways, or open pathway systems. Fill ratios shall not exceed 40% at installation.
4.4.4 Interior Cable Removal and Disposal: When tasked, contractor shall remove abandoned cable back to originating frames.
4.5 Telecommunications Room (TR) Installation-Enabling Work: 4.5.1 Equipment Racks and Enclosures:
Assemble, anchor, and ground standard 19-inch equipment racks. 4.5.2 Grounding, Bonding, and Busbars: All components bonded to TGB/PBB in strict compliance with ANSI/TIA-607-C, MIL-HDBK-419A, and NFPA 70 (<
0.1 ohms). 4.5.3 Dedicated Electrical Power Infrastructure: Dedicated L5-20R or L6-30R circuits installed by licensed electricians. 4.5.4 Fire-Retardant-Treated (FRT) Equipment Backboards: 3/4-inch interior-grade Class A FRT plywood with manufacturer rating stamp exposed.
4.6 Diagnostic Testing, Fault Isolation, and Repair: Diagnostic testing using OTDR, OLTS, VFL, and Level IIIe copper certifiers. Response within eight (8) working hours following notification.
4.7 Physical Layer Infrastructure Labeling. The original baseline cited generic standards: All horizontal cable drops, workstation faceplates, fiber distribution panels, patch ports, and riser cables shall be machine-labeled in strict compliance with the Pacific Labeling Guide (Version 3.0f or current) and the 30SIG-NEC - Standard ISP Labeling Matrix. Hand-written labeling is strictly prohibited. All labels must be machine-printed on permanent, self-laminating vinyl or thermal-transfer polyolefin stock designed for industrial network environments. Hand-written, embossed, or temporary labels are strictly prohibited and will result in physical inspection failure. Horizontal cables shall be labeled within twelve (12) inches of each termination end and at thirty (30) foot intervals within accessible ceiling or floor pathways. Workstation faceplates and patch panels must be labeled with standardized alphanumeric syntax (e.g., B104-1-TR01-A024).
5.0 SECURITY REQUIREMENTS
5.1 General Security and Facility Access: The contractor shall comply with all applicable garrison and installation security regulations, including AR 380-5 and AR 25-2. Employee rosters and base pass requests must be submitted at least ten (10) business days prior to commencing on-site activities.
5.2 Secure Internet Protocol Router Network (SIPRNET) Infrastructure.
5.2.1 Government-Provided Pre-Approved PDS Pathways: The original draft improperly assigned CTTA approval burdens to the contractor: The physical SIPR/PDS pathway (conduit, raceway, or secure enclosure) will be provided by the Government unless explicitly designated as contractor-installed within the specific Task Order.
Prior to task order issuance, the Government will ensure all required CTTA, TEMPEST, and PDS design approvals have been formally obtained. The contractor shall install SIPR cabling strictly within these pre-approved, Government-designated pathways in full accordance with the approved engineering package.
5.2.2 PDS Physical Installation and Security Integrity: Where tasked to install or modify PDS components, the contractor shall ensure that all mechanical joints, pull boxes, and lockboxes comply with CNSSI No. 7003 and current USAISEC SIPRNet Criteria. Tamper-evident seal logs tracking serial numbers, locations, and inspection dates must be maintained and delivered to the COR.
5.2.3 RED/BLACK Separation and TEMPEST Guidelines: The contractor shall enforce strict physical separation between RED and BLACK cabling and raceways in accordance with CNSSAM TEMPEST/1-13 and MIL-HDBK- 419A (minimum 39 inches unshielded separation or 2 inches enclosed in grounded metallic conduit; 90-degree crossings).
5.3 Cleared Personnel and Escort Protocols: Personnel requiring unescorted access to operational TRs with active SIPRNET infrastructure must possess a verified SECRET clearance. Uncleared personnel require formal written Escort Requests submitted at least five (5) business days in advance.
6.0 PERSONNEL QUALIFICATIONS AND ACCESS REQUIREMENTS
6.1 General Personnel Requirements: Fully qualified, certified personnel; contractor employees are not Government personnel.
6.2 Key Personnel Categories and Mandatory Qualifications: 6.2.1 Project Manager (PM): Minimum 5 years experience, technical bachelor’s degree, PMP/BICSI credential, active SECRET clearance.
6.2.2 Project Engineer (Key Personnel): Original draft qualification language: The Project Engineer shall be a current BICSI Registered Communications Distribution Designer (RCDD) in good standing. A Professional Engineer (PE) license is recognized but does not substitute for the mandatory RCDD credential. The RCDD shall review, approve, and stamp all engineering installation packages, cable routing plans, and as-built deliverables.
Minimum of five (5) years of documented engineering experience in telecommunications inside plant structured cabling design and implementation. Must hold and maintain an active SECRET security clearance.
6.2.3 Quality Assurance / Quality Control (QA/QC) Manager: Minimum 3 years experience, CMQ/OE or CQA certification, active SECRET clearance.
6.3 Subcontractor Compliance Enforcement: The prime contractor maintains sole legal responsibility for ensuring that all subcontractors, across all tiers, strictly satisfy the security clearance, technical certification, and safety requirements of this PWS. No subcontractor employee shall access classified spaces or handle SIPRNET infrastructure without active SECRET clearance verification and prior COR badging authorization.
6.4 Personnel Security Clearance and Access Matrix.
Labor Category
Key Personnel Status
Network Account Access
Security Clearance
Required Investigation
Professional Certification
Project Manager
Yes None (Physical Only)
SECRET T3 / T3R PMP or BICSI
Project Engineer
Yes None (Physical Only)
SECRET T3 / T3R Mandatory BICSI
RCDD
QA/QC
Manager
Yes None (Physical Only)
SECRET T3 / T3R ASQ CMQ/OE or
CQA
Lead Fiber / Cable Tech
No None (Physical Only)
SECRET T3 / T3R BICSI Installer 2 / Tech
Cable Technician
No None (Physical Only)
SECRET T3 / T3R Industry Cabling Cert
CAD
Draftsman
No None (Physical Only)
Unclassified Favorable Background
AutoCAD / MicroStation
Licensed Electrician
No None (Physical Only)
Unclassified (Escorted)
Favorable Background
State of Hawaii Journeyman
7.0 PERFORMANCE REQUIREMENTS SUMMARY (PRS)
7.1 Performance Standards and Acceptable Quality Levels.
PWS
Ref
Performance Requirement
Performance Standard Acceptable Quality Level
(AQL)
Surveillance Method
Incentive / Remedy
4.1 Engineering and
EIP Development
Designs comply with UFC 3-580-01, TIA standards, and DISN-EN ICAN-DI.
Complete BOM and drop schedules provided.
95% First-Pass Acceptance Rate
100% Review by Infrastructure Branch & COR
Re-performance within 5 days at contractor expense.
4.4.1 Fiber Installation
& Splicing
Optical fiber installed, fusion-spliced, and terminated with zero exceeding loss.
95% Compliant Links on First Test
100% Inspection of Native OTDR Traces (.flw/.sor)
Re-termination / re-splicing at contractor expense.
4.4.2 Copper
Installation & Certification
Category 6A cabling homerun without splices;
meets 500 MHz Level IIIe/2G test limits.
95% First-Pass Yield across all drops
100% Verification of Native Fluke .flw Files
Re-termination and re-testing at contractor expense.
4.6.3 Emergency and
Repair Response
Technicians arrive on-site within specified emergency (2-4 hrs) and repair (8 hrs) timelines.
95% Compliance with Arrival Timelines
COR Logged Times & Verification
Formal CAR issued; negative CPARS rating.
4.7 Physical
Infrastructure Labeling
All drops, patch panels, cables, and racks machine-labeled IAW Pacific Labeling Guide. Zero handwritten labels.
100% Compliant Machine Labels
Physical Government QA Walkthrough
Complete re-labeling of non-compliant items.
5.2.2 SIPRNET PDS
Integrity & Security
PDS installed with full tamper-evident compliance, mechanical locking, and RED/BLACK separation.
100% First-Pass Physical Security Pass Rate
100% Joint Inspection with S2 and COR
Immediate stop work, corrective remediation at contractor expense.
3.2 Native Electronic
Data Delivery
100% native electronic test files (.flw, .sor) delivered.
No reliance on PDF-only summaries.
100% Submittal of Native Electronic Data
Review by Infrastructure Branch Engineers
Rejection of deliverable;
withholding of invoice sign-off.
8.0 APPLICABLE PUBLICATIONS, CODES, AND TECHNICAL
DIRECTIVES
8.1 Order of Precedence: PWS takes precedence over technical references; FAR clauses govern overall contract.
8.2 Government and Commercial Technical Publications:
CNSSI No. 7003: Protective Distribution Systems (PDS), Committee on National Security Systems Instruction.
CNSSAM TEMPEST/1-13: Advisory Memorandum, RED/BLACK Installation Guidance.
MIL-HDBK-419A: Grounding, Bonding, and Shielding Practices and Procedures for Electronic Equipment
Facilities.
NFPA 70: National Electrical Code (NEC).
NFPA 101: Life Safety Code.
OSHA 29 CFR 1910 / 1926: Occupational Safety and Health Standards for General Industry and Construction.
ANSI/TIA-568.0-D / 568.1-D: Generic Telecommunications Cabling for Customer Premises.
ANSI/TIA-569-E: Telecommunications Pathways and Spaces.
ANSI/TIA-606-C: Administration Standard for Telecommunications Infrastructure.
ANSI/TIA-607-D: Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises.
ANSI/TIA-526-14-C: Optical Power Loss Measurement of Installed Multimode Fiber Cable Plant.
ANSI/TIA-526-7-A: Measurement of Optical Power Loss of Installed Single-Mode Fiber Cable Plant.
ASTM E84 / UL 723: Standard Test Method for Surface Burning Characteristics of Building Materials.
ASTM E814 / UL 1479: Standard Test Method for Fire Tests of Through-Penetration Fire Stops.
8.3 Department of Defense and Army Publications:
• UFC 3-580-01: Unified Facilities Criteria: Telecommunications Interior Infrastructure Planning and Design.
• DISN-EN ICAN-DI: Defense Information System Network - Enterprise Network Installation Campus Area Network Design and Implementation.
• AR 25-1: Army Information Technology.
• AR 25-2: Army Cybersecurity.
• AR 380-5: Department of the Army Information Security Program.
• AR 380-27: Control of Compromising Emanations (TEMPEST).
• DoDI 8100.04: DoD Unified Capabilities (UC).
• DoD 8140.03: Cyberspace Workforce Qualification and Management Program.
• USAISEC SIPRNet: Current SIPRNet Technical Implementation Criteria, US Army Information Systems Engineering Command.
• Pacific Labeling Guide: Version 3.0f, Headquarters, 311th Signal Command / 516th Signal Brigade.
• 30SIG-NEC: Standard ISP Labeling Matrix.
• USAG-HI 200-4: Installation Hazardous Waste Management Program.
9.0 LIST OF ACRONYMS AND ABBREVIATIONS
Acronym Definition
AESMP Army Enterprise Service Management Platform
ANSI American National Standards Institute
AOR Area of Responsibility
APL Approved Products List
AQL Acceptable Quality Level
AR Army Regulation
ASTM American Society for Testing and Materials
ATP Authority to Proceed
BEP Building Entry Point
Acronym Definition
BICSI Building Industry Consulting Service International
BOM Bill of Materials
BPA Blanket Purchase Agreement
CAD Computer-Aided Design
CADD Computer-Aided Design and Drafting
CAR Corrective Action Request
CFM Contractor-Furnished Material
CGTC CADD/GIS Technology Center
CMQ/OE Certified Manager of Quality/Organizational Excellence
CNSSAM Committee on National Security Systems Advisory Memorandum
CNSSI Committee on National Security Systems Instruction
COR Contracting Officer's Representative
CPARS Contractor Performance Assessment Reporting System
CQA Certified Quality Auditor
CTTA Certified TEMPEST Technical Authority
CUI Controlled Unclassified Information
DISA Defense Information Systems Agency
DISN Defense Information Systems Network
DoD Department of Defense
DoDI Department of Defense Instruction
DoDIN Department of Defense Information Network
DPW Directorate of Public Works
EIP Engineering Installation Plan
FAR Federal Acquisition Regulation
FDP Fiber Distribution Panel
FDR Final Design Review
FEWRS Facility Engineering Work Request System
FFP Firm-Fixed-Price
FRT Fire-Retardant-Treated
GFE Government-Furnished Equipment
HST Hawaii Standard Time
HVAC Heating, Ventilation, and Air Conditioning
IAW In Accordance With
ICAN Installation Campus Area Network
IDR Initial Design Review
IPAM Internet Protocol Address Management
ISP Inside Plant
KO Contracting Officer
LAN Local Area Network
MAC Media Access Control
MIL-HDBK Military Handbook
NEC Network Enterprise Center / National Electrical Code
NEMA National Electrical Manufacturers Association
NFPA National Fire Protection Association
NIPRNET Non-Secure Internet Protocol Router Network
OEM Original Equipment Manufacturer
OLTS Optical Loss Test Set
OSHA Occupational Safety and Health Administration
OSP Outside Plant
OTDR Optical Time-Domain Reflectometer
PBB Primary Bonding Busbar
PDS Protected Distribution System
PMP Project Management Professional
PRS Performance Requirements Summary
PWS Performance Work Statement
QA Quality Assurance
QASP Quality Assurance Surveillance Plan
QC Quality Control
QCP Quality Control Plan
RCDD Registered Communications Distribution Designer
RCO-HI Regional Contracting Office - Hawaii
RF Radio Frequency
RFP Request for Proposal
RU Rack Unit
SCIF Sensitive Compartmented Information Facility
SHPD State Historic Preservation Division
SIPRNET Secure Internet Protocol Router Network
STIG Security Technical Implementation Guide
TGB Telecommunications Grounding Busbar
TIA Telecommunications Industry Association
TO Task Order
TR Telecommunications Room
UFC Unified Facilities Criteria
UL Underwriters Laboratories
USACE United States Army Corps of Engineers
USAISEC United States Army Information Systems Engineering Command
USINDOPACOM United States Indo-Pacific Command
UTP Unshielded Twisted Pair
VLAN Virtual Local Area Network
WLAN Wireless Local Area Network