QUESTIONS AND ANSWERS.pdf

PDF 926 KB Posted

Attached to
18 NIPR DROPS BLDG 9098 CDC
Solicitation number
W912CN25Q0005
Issued by

About this file

This document is a Questions and Answers file related to a federal contract opportunity for the installation of 18 NIPR drops in Building 9098 at Schofield Barracks, HI. The key details are:

The contract opportunity is a solicitation (W912CN25Q0005) for a firm-fixed-price contract to provide personnel, equipment, and services to install 18 NIPR drops in the CDC building at Schofield Barracks. A site visit is scheduled for October 28, 2024. The government is seeking quotes from small businesses. Pricing is requested for materials/equipment and labor. The technical capability of the offeror will be evaluated, as well as the overall price. Award will be made to the lowest priced, technically acceptable offeror. The questions and answers provide clarification on various installation details such as the nature of the new drops, cabling requirements, and availability of existing infrastructure.

View the file

Other files

File Type Posted
PWS for CDC SCHOFIELD BKS 18 NIPR DROPS - 8-8-24.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Are these NIPR drops intended as replacements for existing ones, or will they be entirely new installations?

New Installations

2. If they are replacements, will the existing drops need to be removed?-N/A

3. Could you provide some context for the provided photos, including the names of the rooms shown? TR Room # is 110, Manager’s Office is 162 – Front desk and copy machine area is not labeled

4. Are the walls drywalls or concrete?-Drywall

5. If these are new drops, are there existing sleeves available to run the cabling from the data rack to the destination points? YES COMING OUT OF TR ROOM THEN VIA J-HOOKS OVER TO ROOM

Front room entrance has exposed cable from ceiling to termination points. Flex Conduit will be used for that and new cable runs.

6. Is there adequate capacity on the current patch panels?- 12 AVAILABLE-CUSTOMER WILL USE

EXISTING BY REMOVING UNNECESSARY CABLEING BASED ON CABLES REMOVED FROM SWITCH.

FOR THE ADDITIONAL 6

7. Will we be required to install a new patch panel, and if so, is there a preferred brand?

NO

8. Will a new switch be needed for this installation, and if so, who will be responsible for providing it? NO NEW SWITCH, CUSTOMER IS REMOVING UNUSED CABLES

9. Will there be new ceiling tiles available to ensure a professional finish where cables penetrate the ceiling? THIS REQUIREMENT HAS NOT BEEN ADDRESSED, CUSTOMER OR CONTRACTOR CAN

SUPPLY

10. If possible, could you supply additional photos? Specific images of the rack, the data closet, and desired jack locations would be especially helpful.

Existing Switch for 18 drops prior to removing un-need drops to accommodate for 18 new

Over cable route of cable leaving TR to Front desk area via j-hooks

FRONT DESK NEW CABLE JACK LOCATION FOR 10 DROPS

TR CABLE SLEEVE FEEDING TO NEW CABLE AREAS

Cables from TR Room entering Front Desk Area (will be placed in conduit)

Cable above ceiling Area.

Copy Room Area for 2 new drops near printer.

Current building TR Room and building data drops are non-compliant. We are not addressing any of that based on customer’s budget. I have addressed this policy with my manager and am trying to determine if, in non-compliant areas should we install new drops/equipment or insist customers pay for remediation. There are many locations this applies to that have not been remediated .