This is a Performance Work Statement (PWS) for material delivery services at Panama Pacifico International Airport (PPIA) in support of U.S. Army engineer operations.
The contractor shall transport and deliver construction materials to a single designated work area covering approximately 4.22 acres (17,000 square meters). Required deliverables include 4,400 loose cubic yards of ¾"-0 angular crushed stone aggregate (Aggregate Base Course equivalent), 3,700 loose cubic yards of drainage stone sized 2.5"-4", 34,000 square meters of geotextile (17,000 square meters woven and 17,000 square meters non-woven, both 130 g/m²), and 1,250 meters of pre-assembled silt fencing. The contractor is responsible solely for material transportation and delivery; all installation and placement activities will be performed by U.S. Government or designated onsite personnel. The contract is a Firm Fixed Price engagement with performance period from November 30, 2026 through final delivery, with aggregate material delivery commencing on or about December 1, 2026 and concluding no later than December 18, 2026. The contractor must deliver a minimum of 541 loose cubic yards per day beginning December 1 until all aggregate materials are delivered. All deliveries must occur between 08:00 a.m. and 5:00 p.m., with rescheduled deliveries within eight hours of requested time. The contractor must comply with all Panamanian labor laws, obtain and maintain required insurance (including third-party damage, worker's compensation, general liability, and automobile liability), conduct background checks on all employees, provide key personnel including a Contract Manager and Project Superintendent with specified qualifications, and adhere to extensive safety, environmental, and security requirements including FAR 52.236-13 (Accident Prevention) and EM 385-1-1 safety standards. Critical deliverables with 24-hour submission deadlines include background check notifications, gravel delivery receipts, product data sheets, petroleum spill reports, and delivery delay notifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - W912CL27QA006.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
Version 2
November 2026
4PWS Ver 1 2025-12
[PPIA JSCG-P RLB Site Development– Materials]
Part 1
General Information
1. General: This is a non-personal services contract under which the personnel rendering the services are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees. The United States (U.S.) Government shall not exercise any supervision or control over the Contractor’s employees performing the tasks herein. Such contract employees shall be accountable solely to the Contractor who, in turn shall be responsible to the U.S. Government.
1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the delivery of construction material at Panama Pacifico International Airport (PPIA) as defined in this Performance Work Statement (PWS) except for those items specified as government furnished property (GFP) and government furnished services (GFS). The contractor shall perform to the standards in this contract.
1.2 Background: The project site is located at PPIA near the southeastern boundary of the airport. U.S.
Army troops will conduct construction activities at one (1) designated work area identified in Technical Exhibit A. One (1) gravel pad will be built on approximately 17,000 m². Materials delivered under this contract will support construction activities performed by on-site personnel. This effort will enable U.S.
forces to conduct required construction tasks at Panama Pacifico International Airport (PPIA).
1.3 Objectives: The objective of this requirement is the delivery of geotextile, gravel, and the performance of waste disposal in support of U.S. Army engineer operations at Panama Pacifico International Airport (PPIA). The objective of this project is to transport and deliver all gravel and drainage material needed to support the development of one (1) gravel pad location totaling 4.22 acres. The Contractor is responsible solely for the transportation and delivery of materials; all installation, placement, and construction activities will be performed by Government or designated- onsite personnel.
1.4 Scope: : The contractor shall provide services to transport and deliver aggregate materials and associated deliverables, including 4,400 loose cubic yards of ¾”–0 angular crushed stone mixed with aggregate blend (crushed run equivalent), 3,700 loose cubic yards of drainage stone sized (2.5”-4” mixed stone), and 17,000 sq meters of woven and 17,000 sq meters of Non-woven geotextile 130 g/m2. The contractor shall accomplish all tasks required to acquire, transport, and deliver materials in accordance with this PWS and technical exhibits herein. The project aims to ensure compliance with all applicable Panama and local regulations while prioritizing safety and environmental protection.
1.5 Period of Performance: The period of performance for this contract is from 30 November 2026 and ends upon final delivery of all required materials. Aggregate material delivery shall begin on or about 1 December with a final delivery no later than 18 December 2026. If a Contractor’s or Subcontractor’s certification or permit expires, and this causes the firm to not be allowed to perform any work until the certification or permit is reissued, then requests for extension of time for any delay to the completion of the project due to an inactive certification or permit will not be considered and liquidated damages will apply.
Notify the Contracting Officer of any change in Contractor certification or permit status.
1.5.1 Recognized Holidays:
New Year’s Day 1-JAN Shrove (Carnival) Day 17-FEB Good Day 3-APR
November 2026
Labor Day 1-MAY Separation Day From Colombia 3-NOV Colon Day 5-NOV Los Santos Uprising Day 10-NOV Independence Day from Spain 28-NOV Mother’s Day 8-DEC Christmas Day 25-DEC
1.6 General Information:
1.6.1 Quality Control Plan (QCP): RESERVED
1.6.2 Quality Assurance (QA): The government shall evaluate the contractor’s performance under this contract in accordance with (IAW) the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed IAW the performance standards and contract quality requirements are met. Contract quality requirements mean the technical requirements in the contract relating to the quality of the product or service and those contract clauses prescribing inspection, and other quality controls incumbent on the contractor, to ensure the product or service conforms to the contractual requirements. It defines how the performance standards will be applied, the frequency of surveillance, the performance threshold, and deductions, if applicable.
1.6.3 Hours of Operation: The contractor is responsible for conducting business between the hours of 8:00am through 5:00pm Monday through Friday, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must, at all times, maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons.
1.6.4 Place of Performance: The work to be performed under this contract will be performed in vicinity of Panama Pacifico International Airport bordered by Avenue Continental to the north a hardball street to Veracruz on the southern border and to the west by wood line. Location is shown in Technical Exhibit A.
1.6.5 Type of Contract: The Government plans to award a Firm Fixed Price contract for this project.
1.6.6 Access and General Protection Policy and Procedures:
1.6.7.1 FPCON: RESERVED
1.6.7.2 Physical Security: The Contractor shall be responsible for safeguarding all government equipment, information, and property provided for contractor use.
1.6.7.3 Escorts: The Contractor and all associated sub-contractor employees performing services under this contract shall be escorted by Army Personal onsite working. Escort availability must be coordinated; delays due to unavailable escorts shall be resolved through COR.
1.6.7.4 Personnel Security Clearance Requirements: RESERVED
1.6.7.5 Background Checks: The Contractor shall ensure contractor employees and subcontractor employees performing services under this contract have passed a security check conducted by the Host Nation Police Department of their residence or the State Police Department of their U.S. residence.
Security checks that have been completed as part of a personnel security clearance background investigation, or a previous background check that was a condition of employment, meet this requirement.
Documentation of these checks will be made available to the KO or COR within 10 days of request. The Government retains the right to exclude any employee from performance of duties under this contract if a background security check reveals an employee is a security risk. The exclusion of an employee for security reasons will not relieve the Contractor from performance of services required under this contract.
If the Government determines additional background checks are required, at a minimum, and upon request
November 2026 from the Government, the Contractor shall provide to the KO or COR, the following information on any contractor or subcontractor employee performing services under this contract:
• Full Birth Name
• Married name (if applicable)
• SSN or local equivalent (ID card number)
• Date of birth
• Place of birth (city, country)
1.6.7.5.1 Background Check Notification Requirements: If a background check on any employee or subcontractor employee performing services under this contract, whether the check was conducted as a condition of employment or as part of the contract with the Government, reveals any information from any source (including host country law enforcement) of criminal activity by Contractor employees, subcontractors, or subcontractor employees, the Contractor shall notify the KO and COR of that information within 24 hours {Deliverable A.002}. The Contractor shall make notification of:
(1) Traffic violations, other than parking, will be reported to the KO or COR only if the contract is for drivers for the Government;
(2) Any suspicious activity by Contractor employees, subcontractors, or subcontractor employees the Contractor believes may pose a risk to U.S. or host nation national security or imminent risk of deadly bodily harm to any person; and
(3) Any actions taken against Contractor employees, subcontractors, or subcontractor employees pursuant to this requirement.
1.6.7.5.2 Remedies: In addition to other remedies available to the Government, the Contractor’s failure to comply with the requirements of this paragraph my result in requiring the Contractor to remove a contractor employee or employees from the performance of the contract.
1.6.7.5.3 Subcontracts: The Contractor shall include the substance of this paragraph and the preceding paragraph in all subcontracts.
1.6.7.6 Uncleared Contractor Common Access Card (CAC) Credentialing and Access Procedures
1.6.7.6.1 Contractor Common Access Card (CAC) Eligible Requirements: RESERVED
1.6.7.6.1.1 Federal Installation/Facility Access: Contractor and all associated sub-contractor employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The employee performing services under this contract shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services, Security Office or the host nation equivalent.
1.6.7.6.2. Contractor Non CAC Eligible Requirements for DOD Facility and Installation Access:
RESERVED
1.6.7.7 Employment Eligibility: The Contractor shall ensure that all Contractor employees and sub-contractor employees performing services under this contract shall be employed in compliance with Panamanian labor laws and regulations. Verification of the eligibility check will be made available to the KO or COR within 30 days of request.
1.6.7.8 Access to Government Information Systems: RESEVED
1.6.7.9 Key Control: RESERVED
November 2026
1.6.7.10 Lock Combinations: RESERVED
1.6.8 Post Award Conference/Contract Periodic Progress Meetings: The Contractor shall attend the post award conference convened by the contracting activity or contract administration office IAW Federal Acquisition Regulation (FAR) Subpart 42.5. The KO, COR, with other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the KO will apprise the contractor of how the government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.
1.6.9 Contracting Officer Representative (COR): The COR will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: ensure the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor Contractor's performance and notifies both the KO and Contractor of any deficiencies; coordinate availability of government furnished property; and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
1.6.10 Key Personnel: The following are considered as key personnel to the government: The Project Superintendent/Foreman, Project Manager, and Project Safety Officer. The Contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate, who shall act for the Contractor when the manager is absent, shall be designated in writing to the Contracting Officer within 3 days. Contract Manager and alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The Contract Manager or alternate shall be available between the hours reflected in paragraph 1.6.4. Contractor shall provide a roster with all key personnel no later than ten (10) workdays prior to commencing the work. {Deliverable A.003}
1.6.10.1 Minimum qualifications for all key personnel are listed below:
1.6.10.1.1 Project Superintendent/Foreman: CV must demonstrate an engineer degree related to the task being performed, at least have three (3) years of experience or three (3) projects of experience with a project of a similar type or magnitude.
1.6.10.1.2 All Project Managers and Supervisors shall be able to speak, read, write, and understand English at the high school graduate level. A translator will be provided in case of not being able to speak, read, write, and understand English.
1.6.10.1.3 Safety Officer must have three (3) years of experience in related projects.
1.6.10.1.4 Contract Manager and/or Alternate Contract Manager: At least four (4) years of experience within the past six (6) years, working as a Project Manager. The Contract Manager and/or Alternate Contract Manager shall be able to speak, read, write, and understand English. A translator will be provided in case of not being able to speak, read, write, and understand English.
1.6.10.1.5 All key personnel shall submit their personal CV to demonstrate compliance with the position requirements within fifteen (15) days after project is awarded {Deliverable A.004}.
1.6.11 Special Qualifications or Certifications: RESERVED
1.6.11.1 IA/IT Training Certification: RESERVED
November 2026
1.6.12 Identification of Contractor Employees: Appearance of Personnel. The Contractor shall ensure that Contractor personnel present a neat and professional appearance at all times. At all times during contract performance Contractor personnel shall wear as outer wear a shirt or vest with the company logo and name. This includes shirts with sleeves (short or long sleeves). Contractor personnel shall wear long pants, safety shoes, and hard hats in designated areas as required by Occupational Safety and Health Administration (OSHA) requirements and Army regulations. Offensive pictures, sayings, tank tops, tee shirts, and spandex or similar fabric worn as outerwear are strictly prohibited.
1.6.12.1 Badging of Contractor Employees: RESERVED
1.6.12.2 Uniform: The Contractor shall provide a standard uniform for all Contractor and subcontractor employees performing services under this contract, and ensure they wear the uniform during appointed duty hours. The uniform may consist of the same type and color shirt and slacks for all workers.
1.6.13 Contractor Travel: RESERVED
1.6.14 Other Direct Costs (ODC): RESERVED
1.6.15 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.6.16. Non-Disclosure Requirements: Performance under this contract may require the Contractor to access data and information proprietary to a Government agency, another Government Contractor, or of such nature that its dissemination or use other than as specified in this work statement would be adverse to the interests of the Government or others. Neither the Contractor, nor Contractor personnel, shall divulge, nor release data or information developed, or obtained under performance of this work statement, except to authorized Government personnel or upon written approval of the KO. The Contractor shall not use, disclose, or reproduce proprietary data, which bears a restrictive legend, other than as specified in this PWS. All documentation showing individual names or other personal information shall apply, and shall be controlled and protected under the provisions of the Privacy Act of 1974, Public Law 93-579, 5 United States Code (U.S.C.) Section 552a.
1.6.16.1 Non-Disclosure Statements: The Contractor shall provide signed non-disclosure agreements to the Government prior to commencement of work under the contract. Disclosure of information by Contractor personnel may result in Contractor personnel removal from performance of duties under this contract.
1.6.16.2 Advertisement and Social Media: The Contractor shall NOT post information to public websites or social media locations, personal or professional, that in any way disclose names, locations, hotel data, participants, discussions, pictures, etc. before, during or after the contract period of performance without the express consent of the Government. The use of propaganda violates DOD Commercial Use of Imagery Guidelines stated at (www.dimoc.mil/resourcess/limitations/). The Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any marketing tools to include its company website.
1.6.16.3 Information Assurance: At no time will the Contractor or associated sub-contractor employees transmit government documents or information over using methods that do not meet the security requirements specified in the National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171, "Protecting Controlled Unclassified Information in Nonfederal Information Systems and Organizations" such as personal electronic mail accounts, public digital data storage sites (cloud storage), http://www.dimoc.mil/resourcess/limitations/
November 2026 social media platforms or instant messaging. Approved government sites such as U.S. Army Aviation and Missile Research Development and Engineering Center (ARMDEC) Safe Exchange at https://safe.amrdec.army.mil/SAFE/About.aspx, or All Partners Access Network (APAN) at https://community.apan.org/, or other transmission means determined by the government must be used.
1.6.17 Organizational Conflict of Interest (OCI): Contractor and subcontractor personnel performing work under this contract may receive, have access to, or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.6.18 Phase-in/Phase-Out (PIPO) Period: RESERVED
1.6.19 General Training Requirements:
1.6.19.1 Anti-Terrorism (AT) Level I Training: RESERVED
1.6.19.2 OPSEC Awareness: RESERVED
1.6.19.3 Information Assurance (IA) Training: RESERVED
1.6.19.4 Information Assurance (IA)/Information Technology (IT) Training: RESERVED
1.6.19.5 Threat Awareness Reporting Program (TARP Training): RESERVED
1.6.19.6 iWATCH Training: RESERVED
1.6.19.7 OPSEC Training: RESERVED
1.6.20 Overseas Training Requirements:
1.6.20.1 Antiterrorism (AT) Awareness Training for Contractor Personnel Traveling: RESERVED
1.6.20.2 SERE Training: RESERVED
1.6.21 Foreign (OCONUS) Requirements: RESERVED
1.6.21.1 Theater and Country Clearance Requirements: RESERVED
1.6.21.2 Vetting: RESERVED
1.6.21.3 Installation Access to DOD Facility or Host Nation Installation: Contractor and all subcontractor employees performing services under this contract shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) (U.S. citizen and residents only), and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and areas commander installation/facility access and local security policies and procedures (provided by the COR or KO), and status of forces agreements or other diplomatic agreements. The employee performing services under this contract shall provide all information required for background checks to meet installation access requirements to the installation Provost Marshal Office, Director of Emergency Services, Security Office, or host nation equivalent.
November 2026
1.6.21.4 Host Nation Installation Access with No DOD Facility: Contractor and all associated subcontractor employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures. The employee performing services under this contract shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, Security Office or the host nation equivalent.
1.6.21.5 Deoxyribonucleic Acid (DNA) Samples: RESERVED
1.6.21.6 Medical Travel Requirement: RESERVED
1.6.22 Synchronized Pre-deployment and Operational Tracker (SPOT): RESERVED
1.6.23 Safety: The following provides information pertaining to Safety and Accident Prevention:
1.6.23.1 (Host Nation) Safety Laws and Regulations: The Contractor shall comply with FAR 52.236-13, Accident Prevention (November 1991), the references contained therein (e.g. U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1)), and applicable Host Nation Safety Laws and Regulations.
The requirements under FAR 52.236-13 and specifically of the EM 385-1-1 include, but are not limited to the following:
(a) Before initiation of work at the job site, an Accident Prevention Plan, written by the Contractor for the specific work and hazards of the contract and implementing in detail the pertinent requirements of EM 385-1-1; will be reviewed for acceptance by designated Government personnel {Deliverable A.005}.
Specific requirements for development of the Accident Prevention Plan are found in 01.A and Appendix A of EM 385-1-1. EM 385-1-1 is available online at www.usace.army.mil.
(b) Before beginning each activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work, activity hazard analysis (AHA) shall be prepared by the Contractor performing the work activity (See paragraph 01.a.09 of
EM 385-1-1);
(c) The Contractor shall require subcontractors to submit their plan of operations showing methods they propose to use in accomplishing major phases of work;
(d) The Contractor shall discuss the plans in conferences convened by the Contracting Officer prior to starting work on each major phase of operation. Plans shall include all pertinent information such as layout of haul roads, access roads, storage areas, electrical distribution lines, methods of providing minimum exposure to overhead loads, and methods of access to work areas. The plan for accomplishing the initial work phase shall be submitted within ten (10) calendar days after award of the contract. Plans for subsequent major phases of work shall be submitted no later than ten (10) calendar days prior to initiation of work on each major phase; and
(e) In all areas where construction, demolition, alteration, building, or similar related activities take place, the Contractor shall have the following minimum personal protective clothing and equipment requirements in place for any person working on or visiting the site:
(i) Short sleeve shirt;
(ii) Long trousers;
(iii) Steel-toed safety boots;
http://www.usace.army.mil/
November 2026
(iv) Hard hat.
1.6.23.1.1 In addition to other requirements for accident prevention specified in this contract, the Contractor shall comply with all Federal and State requirements governing safety and health protection on construction sites and other applicable occupational safety codes.
The Contractor shall indicate its plan for compliance considering conditions of the work described by the design, technical proposal, operational activities of the Government or others in the area of the work, identification of the coordinator, and implementation of all other accident prevention provisions of this contract. For the compliance with host nation laws and regulations, the Contractor shall comply with the non-exclusive list of duties described in this paragraph. If the Contractor determines that additional activities are required to fully comply, the Contractor shall ensure that compliance with the laws is complete.
1.6.23.1.2 The Contractor shall complete and provide safety notifications required by Panama and will provide documented proof to the Contracting Officer via the COR, no later than ten (10) days that such notifications were made.
1.6.24 Environmental Compliance: The following provides information on Environmental Compliance.
1.6.24.1 Environmental Compliance Plan and Program: The Contractor shall ensure that all of its operations and activities conform to the environmental policy requirements. The Contractor shall ensure that all contract personnel have received appropriate levels of training in the handling, use, storage, and disposal of hazardous material. In addition, the Contractor shall ensure that all Contractor controlled activities on Panama Pacifico International Airport are conducted in accordance with the Spill Prevention and Response Plan, Solid Waste Policy, Final Governing Standards, and applicable Panama environmental laws/standards.
If contract requires the use of hazardous materials/substances, the Contractor shall, prior to mobilization, inform the Contracting Officer (KO)/Contracting Officer Representative (COR) of the types and amount of hazardous materials needed to be brought onto the Garrison in order to fulfill their contractual requirements. The Contractor shall also provide the Safety Data Sheets, storage requirements and proposed storage locations for the hazardous material.
Prior to contract completion, the Contractor shall remove all hazardous materials and dispose of all hazardous waste (HW) generated in accordance with the Government of Panama environmental laws/standards. A copy of the HW disposal documents must be forwarded to the Contracting Officer (KO) and Contracting Officer Representative (COR).
The Contractor shall clean up at its own expense any contamination, including soil and ground water contamination caused by hazardous materials/substances brought onto the garrison, or by his activities. The Contractor must immediately report any hazardous substance spills to the nearest fire department.
1.6.25 Marking of Work Zones: The Contractor shall mark all work zones using two lines of plastic yellow security ribbon. Yellow security ribbons shall be 8 cm wide and supported on stable wood stakes.
Likewise, the project excavation or high accident risk zones shall be signaled with warning signs or fences as protective measurements by the Contractor.
1.6.26 Construction Operations and Storage Areas:
1.6.26.1 Confinement to Authorized Areas: The Contractor shall confine all operations (including storage of materials) to areas authorized or approved by the COR from information received by local authorities.
U.S. Government agencies shall have access to the premises for official fire, safety, and security inspections and/or to conduct site visits as authorized by the COR.
November 2026
1.6.26.2 Access to Contractor Storage Yard: The Contractor shall store all materials, tools, and equipment for this project only within the designated storage or laydown area approved by the COR. The Contractor is responsible for securing all contractor‑owned equipment and materials to prevent unauthorized use or safety hazards.
1.6.27 Contractor Vehicles:
1.6.27.1 Vehicular Access: The Contractor shall, and in accordance with any regulations specified by the municipal, local country authorities and, PPIA use only established site entrances and roadways at both worksite locations. The Contractor and all associated sub-contractor employees performing services under this contract shall be escorted. Escort availability must be coordinated; delays due to unavailable escorts shall be resolved through COR.
1.6.28.2 Vehicle list: The Contractor shall provide a list of all vehicles used in the performance of this contract to include vehicle description, valid vehicle registration number, and identification ID card numbers to the COR and KO within fifteen (15) days after contract award and update as the changes occur {Deliverable A.006}. ID information will be used by the site to verify credentials and issue access permits.
Contractor shall coordinate local security office to access sites.
1.6.29 Unforeseen Conditions: The Contractor shall conduct aerial, surface, underground or embedded interference survey to avoid damage to pipes, boxes, cables, utility poles, hoses, wells or other elements in the work area. If a potential interference is found, the Contractor shall give written notice within three (3) working days to the KO/COR in accordance with FAR Clause 52.236-2 and prepare information for possible alternatives.
THIS SECTION INTENTIONALLY LEFT BLANK
November 2026
PART 2
DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1. Definitions:
2.1.1 Area of Responsibility. The U.S. Southern Command (USSOUTHCOM) area of responsibility (AOR) includes the geographic areas of Antigua and Barbuda, Argentina, Aruba, Barbados, Belize, Bolivia, Brazil, British Virgin Islands, Cayman Islands, Chile, Colombia, Costa Rica, Cuba, Curacao, Dominica, Dominican Republic, Ecuador, El Salvador, Falkland Islands, French Guiana, Grenada, Guadeloupe, Guatemala, Guyana, Haiti, Honduras, Jamaica, Martinique, Mayotte, Montserrat, Nicaragua, Panama, Paraguay, Peru, Saint Barthélemy, Saint Martin, Saint Kitts and Nevis, Saint Lucia, Saint Vincent and the Grenadines, Saint Maarten, Suriname, Trinidad and Tobago, Turks and Caicos Islands, Uruguay, and Venezuela.
2.1.2. Contractor. The total contractor organization or a separate entity of it; such as an affiliate, division, or plant that performs its own purchasing.
2.1.3. Contracting officer (KO). A person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings.
2.1.4. Contracting Officer’s Representative (COR). An individual designated and authorized in writing by the contracting officer to perform specific technical or administrative functions.
2.1.5. Defective Service. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.6. Deliverable. Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.
2.1.7. Foreign National. A foreign national is not a U.S. citizen. Green card holders are also identified as foreign nationals. A foreign national is further categorized as either a third country national or a local national based on the person’s citizenship and location of performance of duty.
2.1.8. Key Personnel. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.9. Local National. Local nationals are foreign nationals who are citizens of the country where the performance of duty will occur.
2.1.10. Performance Work Statement (PWS). A statement of work for performance-based acquisitions that describes the required results in clear, specific, and objective terms with measurable outcomes.
2.1.11. Physical Security. Protection of the perimeter area, government property, and assets that prevent the loss or damage of Government property.
2.1.12. Quality Assurance. The various functions, including inspection, performed by the government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.
2.1.13. Quality Assurance Surveillance Plan (QASP). A plan describing how the agency will survey, observe, test, sample, evaluate and document the Contractor’s performance in meeting critical performance standards identified in the contract.
November 2026
2.1.14. Quality Control (QC). Tasks performed by the Contractor to improve the quality of the organization’s output.
2.1.15. Shall. An imperative command; has a duty to or is required to. Denotes that a regulation must be followed unless the contracting officer has obtained a deviation.
2.1.16. Subcontractor. Any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime contractor or another subcontractor.
2.1.17. Third Country National. Third country nationals are foreign nationals who are not citizens of the country where the performance of duty will occur.
2.1.18. Workday. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.19. Work Week. Monday through Friday, unless specified otherwise.
2.2 Acronyms:
AFFSSIR Armed Forces Repository of Specimen Samples ALMS Army Learning Management System ANSI American National Standards Institute AOR Area of Responsibility AR Army Regulation ATCTS Army Training Certification Tracking System AT Anti-Terrorism CAC Common Access Card CFR Code of Federal Regulations CI Counter Intelligence CLIN Contract Line Item Number CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative DD Form 254 Department of Defense Contract Security Requirement List DNA Deoxyribonucleic Acid (DNA) DOD Department of Defense DODD Department of Defense Directive DODI Department of Defense Instruction FAR Federal Acquisition Regulation FHP Force Health Protection FCG Foreign Clearance Guide FN Foreign National FY Fiscal Year GFE Government Furnished Equipment GFP Government Furnished Property GFS Government Furnished Services IA Information Assurance IAW In Accordance With IT Information Technology JPAS Joint Personnel Adjudication System JTR Joint Travel Regulation KO Contracting Officer LN Local National LOA Letter of Authorization NCIC-III National Crime Information Center Interstate Identification Index
November 2026
NIST National Institute of Standards and Technology ODC Other Direct Costs OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs OSHA Occupational Safety and Health Administration OPSEC Operation Security PIPO Phase In/Phase Out PRS Performance Requirements Summary PPE Personal Protective Equipment PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QCP Quality Control Program RA Requiring Activity SCR Service Contract Reporting SOP Standard Operating Procedures SPOT Synchronized Predeployment and Operational Tracker TCN Third Country National TE Technical Exhibit TSDB Terrorist Screening Data Base U.S.C. United States Code USSOUTHCOM United States Southern Command
November 2026
THIS SECTION INTENTIONALLY LEFT BLANK
November 2026
PART 3
Government Furnished Equipment (GFE), Government Furnished Property (GFP), and Government Furnished Services (GFS)
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
3.1. Services: RESERVED
3.2 Facilities: RESERVED
3.3 Utilities: RESERVED
3.4 Equipment: RESERVED
3.5 Materials: RESERVED
November 2026
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
4.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3. The Contractor shall comply with special considerations, safety program, required insurance and any host nation facility regulations.
4.2 Facility Security Clearance: RESERVED
4.3. Materials: The Contractor shall deliver ¾”-0 angular crushed stone mixed with smaller aggregate equivalent to FLBC (Fine Lime Base Course) and ABC (Aggregate Base Course) Gravel (Crusher Run aggregate composition) , drainage stone, and geotextile woven and non-woven (130 g/m2) . Contractor to submit product data sheets to COR for review and acceptance.
4.3.1 Aggregate Material: The Contractor shall deliver 4,400 loose cubic yards of ¾”–0 angular crushed stone mixed with stone dust (crush and run equivalent).
• Aggregate shall meet the performance characteristics of Aggregate Base Course (ABC) as described in UFGS 32 11 23 – Aggregate Base Course, including applicable stone type and sieve gradation requirements.
• Materials shall comply with WBDG and UFGS criteria for ABC performance
4.3.2 Drainage Stone: The Contractor shall provide 3,700 loose cubic yards of drainage stone sized (2.5”- 4” mixed stone)
• Aggregate Type: No. 1 Blend, 2.5" to 4", ~50–100 mm, large riprap, erosion control, large drainage
4.3.3 Geotextile: The contractor shall provide geotextile 130 g/m² Woven and 130 g/m² Non-woven (17,000 square meters of each).
• Materials shall be consistent with typical USACE and NAVFAC SWPPP practices.
• Woven 17,000 square meters and Non-Woven 17,000 square meters
4.3.4 Silt Fencing: The contractor shall provide 1,250 meters silt fencing: 36 in, woven polypropylene geotextile fabric with wire fabric backing, galvanized metal posts (1.5” x 1.5” x 42”), and pre-assembled with posts attached from vendor/supplier.
• Materials shall be consistent with ASTM D461.
4.4. Equipment: The contractor shall provide all required equipment to support transportation of materials to Panama Pacifico International Airport.
4.5 Insurance: All insurances required by the Panamanian government to operate within the country shall be obtained and maintained as required by the Panamanian government. Insurance requirements include but are not limited to Third Party Damage, First Person Fatality, Additional person Fatalities, Criminal court representation and Civil Representation.
4.5.1 Worker’s Compensation and Employers Liability Insurance as required by law except that if the contract is to be performed in a country which does not require or permit private insurance, then compliance with the statutory or administrative requirements for the Panamanian government. The required Worker’s Compensation insurance shall extend to cover employer’s liability for accidental bodily injury or death and for occupational disease with a minimum liability limit as required by the Panamanian government.
November 2026
4.5.1.2 General Liability Insurance: Bodily injury liability insurance, in the minimum limits as established by the Government of Panama, per occurrence shall be required on the comprehensive form of policy.
4.5.1.3 Automobile Liability Insurance for Contractor Owned/Leased Vehicles. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles used in connection with the performance of the contract.
At least the minimum limits as established by the Panamanian government shall be required.
4.5.1.4 Payment of Wages/Salaries: The contractor shall be responsible for payment of all employee salaries, vacations, social security, medical insurance, family subsistence and all other entitlements required by Panamanian labor laws. At a minimum, the Contractor shall adhere to applicable wages established by the GOC. Additionally, the Contractor will make a good faith attempt to provide reasonable wages to maintain stability in the workforce.
4.6 Contractor Vehicles and Passes: All contractor employees’ and Contractor’s subcontractor vehicles used for the performance of this contract shall comply with all Panamanian Government Regulations. In addition, all vehicles described above must be registered through the Government of Panama. The contractor is responsible to provide maintenance or fuel for contractor vehicles.
4.7 RESPONSIBILITIES OF CONTRACTOR.
4.7.1 Insurance Damage to Persons or Property: The Contractor shall be responsible for all damages to persons or properties at the worksite that occur as a result of the Contractor's own fault or negligence. The Contract shall take proper safety and health precautions to protect the work sites, the workers, the public, and the property of others. All insurances required by the Government of Panama to operate within the country shall be obtained and maintained as required by the Government of Panama Insurance requirements include but are not limited to Third Party Damage, First Person Fatality, Additional person Fatalities, Criminal court representation and Civil Representation.
4.7.2 Responsibility for Work Performed: The Contractor shall be responsible for all materials delivered and work performed until final completion and acceptance of the entire project, except for any completed unit of work which may have been accepted in writing under the contract.
4.8 Contractor Records/ Progress Reports: RESERVED
4.9 Contractor Work Schedule: RESERVED
4.9 Procedure Plan: RESERVED
4.10 Product Data Submittal: RESERVED
4.11 Progress Meetings: RESERVED
4.12 Testing Reports: RESERVED
4.13 As Built Drawings: RESERVED
4.14 Project and Equipment Warranty: RESERVED
4.15 Final Report: RESERVED
4.16 Operation and Maintenance Course: RESERVED
November 2026
4.17 Repair/Restoration: The Contractor shall repair/restore any damage to the existing grounds, facilities or property incurred during the course of the clearing to their original pre-existing conditions. Contractor shall always comply with special considerations, safety program, required insurance and the Government of Panama regulations.
4.18 Safety: The Contractor is responsible for the safety of workers and visitors to the work sites. The Contractor shall ensure that all personnel wear appropriate safety gear at all times in compliance with all Panama Occupational Safety & Health regulations and ensure all local safety regulations are followed at all times. The Contractor shall provide sanitation for workers IAW the latest edition of Corps of Engineers Safety and Health Manual EM 385-1-1 and Panama safety and health laws. Contractor shall comply with safety and health requirements as established by EM 385-1-1. Information about how to obtain electronic and/or hard copies of this manual is located at the following website:
http://www.usace.army.mil/CESO/Pages/EM385-1-1.aspx
4.19 Utilities Connections and Excavations: RESERVED
4.20 Utility Service Interruption: RESERVED
4.21 Defense Base Act (DBA) Workers' Compensation Insurance: RESERVED
4.22 Contractor’s Personnel: The Contractor shall provide sufficient number of personnel, properly trained and qualified to perform the requirements of this contract at the worksite location.
4.22.1 Contractor Vehicles and Passes: RESERVED
http://www.usace.army.mil/CESO/Pages/EM385-1-1.aspx
November 2026
PART 5
SPECIFIC TASKS
5. Specific Tasks: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to deliver 4,400 loose cubic yards of ¾”–0 angular crushed stone mixed with aggregate blend (crushed run equivalent), 3,700 loose cubic yards of drainage stone sized (2.5”-4” mixed stone), 17,000 square meters of Woven and 17,000 square meters of Non-Woven geotextile 130 g/m², and 1250 meters of silt fencing to support troop construction activities at PPIA. Installation, placement, and compaction of aggregate materials will be performed by U.S. personnel or designated onsite personnel.
Editing of the specifications shall not be used to reduce quality standards. If adjustments to the specifications are required, then these recommendations must be approved by the KO prior to making the change.
5.1 Materials:
5.1.1 ABC Gravel: The Contractor shall provide 4,400 cu yds of ¾”–0 angular crushed stone mixed with smaller aggregate equivalent to FLBC and ABC (crush and run type composition). All material shall meet U.S. Government standards and will be inspected by the Joint Security Cooperation Group – Panama Engineer Cell. Material certification documents shall be submitted to the COR prior to purchase and delivery.
(a) Standard: Gravel shall be ¾”–0 angular crushed stone mixed with stone dust, durable, compactable, and free of clay, organic matter, or debris. Material shall provide a stable, level surface under operational use, IAW UFGS 32 11 23 – Aggregate Base Course.
AQL: 100% compliance
(b) Standard: The Contractor shall produce receipts detailing the volume of gravel delivered each day (in loose cubic yards). Receipts shall be provided to the COR within one (1) day of delivery {Deliverable A.007}.
AQL: 100% compliance
(c) Standard: The contractor shall submit product data sheets to the COR for review no later than ten (10) days prior to delivery of aggregate materials {Deliverable A.008}: Submittals shall include the following:
• Aggregate Base Course (ABC): Equivalent aggregate materials described in specification DIV 32 Exterior Improvements, Aggregate Base Course 32 11 23, including the required stone type and sieve gradation of applicable stone.
• Whole Building Design Guide (WBDG) and Unified Facilities Guide Specifications (UFGS) documentation that provides the description of ABC materials and performance expectations of aggregate materials.
AQL: 100% compliance
(d) Standard: Aggregate material delivery shall begin on or about 1 December 2026.
AQL: 100% compliance
5.1.2 Drainage Stone. The Contractor shall provide 3,700 loose cubic yards of drainage stone to Panama Pacifico International Airport starting on 1 December 2026. The Contractor shall coordinate with the COR 24 hours prior to delivery.
5.1.3 Geotextile: The contractor shall deliver 17,000 square meters of Woven and 17,000 square meters of Non Woven geotextile 130 g/m² (34,000 square meters in total) to Panama Pacifico Airport, Panama on the 30 November 2026. The contractor shall coordinate with the COR 24 hours prior to delivery.
PERFORMANCE WORK STATEMENT (PWS)
Version 2
November 2026
5.1.4 Silt Fencing: The contractor shall provide 1,250 meters silt fencing: 36 in, woven polypropylene geotextile fabric with wire fabric backing, galvanized metal posts (1.5” x 1.5” x 42”), and pre-assembled with posts, including wire spools, attached according to Technical Exhibit 2 to Panama Pacifico Airport, Panama on 30 November 2026. The contractor shall coordinate with the COR 24 hours prior to delivery.
AQL: 100% compliance
5.1.5 Delivery: The Contractor shall deliver gravel to one (1) construction site on Panama Pacifico Airport, Panama using contractor-supplied transportation. The Contractor shall provide sufficient transportation to deliver all materials, excepting aggregate, on 30 November 2026. The Contractor shall provide sufficient transportation to deliver minimum 541 loose cubic yards per day beginning 1 December 2026 until all aggregate material is delivered. The COR will provide delivery locations and times no later than 24 hours prior to the required delivery. The Contractor shall deliver materials to the locations designated by the
COR.
a. Standard: The Contractor shall accomplish all deliveries to the specific locations on the work site between 08:00am and 5:00pm, as directed by the COR. Rescheduled deliveries shall occur within eight (8) hours of the requested delivery time, subject to weather or other impacts to the delivery schedule. The Contractor shall deliver gravel to the locations designated by the COR.
AQL: 100% compliance
b. Standard: The Contractor shall comply with all site access requirements, gate procedures, escort needs, and safety rules.
AQL: 100% compliance
(c) Standard: The Contractor shall not stockpile material unless directed by the COR. Stockpiles shall not block roadways or facility access.
AQL: 100% compliance
(d) Standard: The Contractor shall ensure all personnel wear appropriate PPE, including helmets, reflective vests, and safety footwear. Delivery operations shall comply with local safety regulations.
AQL: 95% compliance
(e)…