W912CH-24-Q-0086 (003).pdf

PDF 18 KB Posted

Attached to
NSN: 1005-01-592-1520, ELEVATING AND TRAVERSING MECHANISM
Solicitation number
W912CH-24-Q-0086
Issued by

About this file

This document is an Amendment (0003) to Solicitation W912CH-24-Q-0086 for the procurement of an Elevating and Traversing Mechanism for a Machine Gun, Caliber .50 M2 Series. The U.S. Army Contracting Command - Detroit Arsenal is seeking to award a Firm Fixed Price contract for 53 units with a 100% option for an additional 53 units, exclusively set aside for Small Businesses. The amendment extends the solicitation close date from 6 March 2025 to 14 March 2025 and adds critical sections including Basis for Award, Evaluation Factors, Evaluation Criteria, and Responsibility Determination.

The procurement requires a Technical Data Package (TDP) that is Export Controlled, Distribution D, and requires United States/Canada Joint Certification Program (JCP) certification to access. Proposals must be submitted electronically to specified email addresses by 14 March 2025. The government will evaluate proposals based on two primary factors: Technical Capability (most important) and Price, using a best value tradeoff process where they may accept a higher-priced proposal if the perceived benefits merit the additional cost. Contractors will be assessed on their ability to meet technical requirements, compliance with the Technical Data Package, and demonstration of production capacity and resources.

View the file

Other files

File Type Posted
W912CH-24-Q-0086 (004).pdf PDF
W912CH-24-Q-0086 Conformed Copy.pdf PDF
Attach A -- CUI 2024 (002).pdf PDF
W912CH24Q0086-0002.pdf PDF
W912CH24Q0086-0001.pdf PDF
Attachment 0001 - First Article Waiver Worksheet.pdf PDF
W912CH24Q0086.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of

2. Amendment/Modification No.

3. Effective Date

4. Requisition/Purchase Req No.

5. Project No. (If applicable)

6. Issued By Code 7. Administered By (If other than Item 6) Code

8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)

9A. Amendment Of Solicitation No.

9B. Dated (See Item 11)

10A. Modification Of Contract/Order No.

10B. Dated (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS

It Modifies The Contract/Order No. As Described In Item 14.

A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In

The Contract/Order No. In Item 10A.

B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set

Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).

C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.

14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name And Title Of Signer (Type or print)

16A. Name And Title Of Contracting Officer (Type or print)

15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed

By (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITIONS UNUSABLE

30-105-02 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

SEE SCHEDULE

X

Firm Fixed Price

W912CH

ACC-DTA

6501 E. 11 MILE RD.

DETROIT ARSENAL, MI 48397-5000

ASHLEY YOUNG

EMAIL: ASHLEY.A.YOUNG2.CIV@ARMY.MIL

W912CH-24-Q-0086

2024DEC20

X

X 2025MAR14 03:00pm

2 signed

SEE SECOND PAGE FOR DESCRIPTION

1 4

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SUPPLEMENTAL INFORMATION

Buyer Name: ASHLEY YOUNG

Buyer Office Symbol/Telephone Number: CCTA-APS-C/(571)588-8996

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

Weapon System: Machine Gun, Caliber .50 M2 Series w/Tri

*** End of Narrative A0000 ***

SOLICITATION: W912CH-24-Q-0086

AMENDMENT: 0003

1. The purpose of this Amendment 0003 to Solicitation W912CH-24-Q-0086 is to:

SF18:______

a) Extend solicitation close date FROM 6 March 2025 TO 14 March 2025. ____ __

Section M:__________ b)Add sections M.3 BASIS FOR AWARD, M.4 EVALUATION FACTORS, M.5 EVALUATION CRITERIA, and M.7 RESPONSIBLITY DETERMINATION.

c) Revised CONTRACTOR RESPONSIBILITY AND ELIGIBILITY FOR AWARD FROM M.3 TO M.6 as well as additional verbiage changes. ____ __

This concludes all sections affected by this Amendment.

2. The contractor shall acknowledge this Amendment 0003 in Section A.4 Acknowledgment of Amendments in its proposal submission.

3. Proposals shall be submitted electronically to email address: ashley.a.young2.civ@army.mil and elizabeth.l.levinewelhouse.civ@army.mil by 14 March 2025.

4. All other terms and conditions of Solicitation W912CH-24-Q-0086 remain unchanged.

*** END OF NARRATIVE A0004 ***

2 4

W912CH-24-Q-0086

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

EVALUATION FACTORS FOR AWARD

M.1 EVALUATION FACTORS FOR FIRST ARTICLE TEST REQUIREMENT

M.1.1 If the offeror submits a request for waiver of First Article Testing but fails to comply with the requirements of paragraph L.4

PROVISION FOR WAIVER, the requested waiver may not be granted. If the waiver is not granted, more favorable alternative offers of price or delivery, conditioned upon the granting of a waiver, will not be considered in the evaluation process.

M.1.2 DELIVERY EVALUATION FACTORS

M.1.2.1 As specified in this solicitation, the Government reserves the right to waive the requirement entitled FIRST ARTICLE APPROVAL

(52.209-3 or 52.209-4), and will require an accelerated delivery schedule if the successful offeror is granted such a waiver. However, in no case will a delivery schedule predicated upon waiver of the First Article Test requirement be considered as an evaluation factor for award, even if such a schedule would be more advantageous to the Government.

M.1.2.2 If an offeror requests waiver of First Article Testing but takes exception to the accelerated delivery schedule set forth in the

Section F clause entitled TIME OF DELIVERY (FAR 52.211-8) herein, such offeror is not eligible for the requested waiver. In consequence, any award to that offeror will reflect either (i) the Government-proposed delivery schedule shown in that same clause, or (ii) the contractor-proposed schedule in that clause, if the Government has accepted it.

M.1.3 PRICE EVALUATION FACTORS. As specified in this solicitation, the Government reserves the right to waive the requirement in Section

E entitled FIRST ARTICLE APPROVAL (52.209-3 or 52.209-4), and requests the price of the proposed First Article Test (at Section B, Item

0001AB) from offerors who elect to seek such a waiver. In the event that the offeror requests and receives a waiver of First Article

Test requirements, the price for such testing, as identified by the offeror in Section B, Item 0001AB, shall be deducted from the total price otherwise cited for the materiel herein solicited. The offer will then be evaluated for award at the resulting alternate price.

M.1.3.1 If the offeror requests a waiver of First Article Test requirements, but fails to separately identify the cost of First Article

Testing in Section B, Item 0001AB of this solicitation, the Government reserves the right to evaluate the offer based upon the price for

0001AB, and to require that offeror perform on the contract at such price whether or not the First Article Requirement is waived, at no additional cost to the Government.

M.1.3.2 If the offeror requests but is not granted a waiver of First Article Testing, evaluation for award will be based upon the full amount entered for 0001AB: the amount entered for item 0001AB will not be deducted by the Government.

M.2 EVALUATION OF INCOMPLETE OPTION PRICING

M.2.1 Per FAR 17.203(d), offerors may price the option CLIN in this solicitation incrementally, by entering different option unit prices that will apply to different subquantities or quantity ranges (in the event that the Government elects to exercise less than 100% of the option). Notwithstanding this fact, the provision entitled EVALUATION OF OPTIONS (FAR 52.217-5, located elsewhere in this Section M) indicates that the Government's evaluation for contract award will include each offeror's price for 100% of the option quantity.

M.2.2 In light of the above, if an offeror specifies unit prices that apply to one or more option quantity ranges, but does not specify a unit price for 100% of the option, we will evaluate that offer for award as follows. The option price for such offer shall be deemed to be the higher of the unit price that applies to the basic (non-option) quantity, or the highest unit price that is identified against any range or subquantity of the option CLIN.

M.3 BASIS FOR AWARD

M.3.1 This acquisition will be conducted using the Simplified Acquisition Procedures (SAP) under FAR Part 13. The Government intends to award a firm-fixed-price contract to the responsible offeror whose proposal represents the best value to the Government, considering both price and non-price factors. Best value will be determined using a tradeoff process, as described in FAR 13.106-1(a)(2), where the

Government may accept other than the lowest-priced proposal if the perceived benefits of a higher-priced proposal merit the additional cost. Award will be made to the offeror whose proposal conforms to the solicitation requirements, including the Technical Data Package

(TDP) and First Article Test (FAT) requirements, and provides the greatest overall benefit to the Government. Unsuccessful offerors will be notified within seven days of award.

M.4 EVALUATION FACTORS

M.4.1 Proposals will be evaluated based on the following factors, listed in order of importance:

1. Technical Capability

2. Price

M.5 EVALUATION CRITERIA

M.5.1 Technical Capability: The Government will evaluate the offerors ability to meet the technical requirements of the solicitation, 3 4

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

including compliance with the provided Technical Data Package (TDP) and successful completion of the First Article Test (FAT). The evaluation will assess:

M.5.1.1 Conformance to TDP: The offerors proposal must demonstrate that the proposed supplies fully meet the specifications, tolerances, and quality standards outlined in the TDP. The contractor is responsible for having all drawings and specifications. Failure to obtain the Government-provided TDP associated with this solicitation prior to proposal submission and prior to solicitation closing date may determine an offeror non-responsible and ineligible for award.

M.5.1.2 Capability to Perform: Pursuant to FAR 9.104-1, the offeror must demonstrate adequate technical knowledge, production capacity, and resources to deliver conforming supplies within the required timeframe.

M.5.2 Price: The Government will evaluate the total proposed price for reasonableness and realism, consistent with FAR 13.106-3(a).

Unrealistically low or unbalanced pricing may indicate a lack of understanding of the requirements and could result in a determination of nonresponsibility under FAR 9.104-1.

M.6 CONTRACTOR RESPONSIBILITY AND ELIGIBILITY FOR AWARD

M.6.1 The Government will award a contract to the offeror that:

M.6.1.1 submits the lowest evaluated offer if award is based on price only, or the offer that provides the best value to the Government if factors in addition to price are identified elsewhere in this solicitation, M.6.1.2 submits a bid or proposal that meets all the material requirements (including technical requirements of the specification, if applicable) of this solicitation, and

M.6.1.3 meets all the responsibility criteria at FAR 9.104.

M.6.2 To make sure that an offeror meets the responsibility criteria at FAR 9.104 the Government may:

M.6.2.1 arrange a visit to the offerors plant and perform a preaward survey;

M.6.2.2 ask the offeror to provide financial, technical, production, or managerial background information.

M.6.3 If the offeror does not provide the Government with the data requested within 7 days from the date the requested is received, or if the offeror refuses to have an onsite visit to the offerors facility, the Government may determine the offeror to be nonresponsible.

M.6.4 If the Government visits the offerors facility, please make sure that current certified financial statements and other data relevant to the bid or proposal available for Government personnel to review.

M.7 RESPONSIBILITY DETERMINATION

M.7.1 In addition to the evaluation factors above, the Government will determine the offerors responsibility in accordance with FAR

9.104-1 prior to award. This includes verifying that the offeror:

- Has adequate financial resources or the ability to obtain them (FAR

9.104-1(a));

- Can comply with the required delivery schedule (FAR 9.104-1(b));

- Has a satisfactory performance record (FAR 9.104-1(c));

- Has the necessary technical skills, production capacity, and quality controls to perform (FAR 9.104-1(e)); and

- Meets all other standards of responsibility outlined in FAR 9.104.

Offerors determined non-responsible will not be eligible for award.

*** END OF NARRATIVE M0001 ***

4 4

SUPPLEMENTAL INFORMATION
EVALUATION FACTORS FOR AWARD

File details come from the government source that posted it. Updated .