Fort Sill SHORAD Market Intelligence Survey - Fillable.pdf

PDF 1 MB Posted

Attached to
IFPC/M-SHORAD Instructional Facility
Solicitation number
W912BV27SSH01
Issued by

About this file

This document is a Market Research Questionnaire issued by the U.S. Army Corps of Engineers, Tulsa District, seeking industry feedback to inform the optimal project delivery method and contracting vehicle for the IFPC/M-SHORAD Instructional Facility at Fort Sill, Oklahoma. Responses must be submitted to Julie.S.Hill@usace.army.mil by 2:00 PM CST on August 28, 2026.

The project involves construction of a 75,930 square foot Automation-Aided Instruction Building with a target budget of $84 million under MILCON funding and a performance period of approximately 720 days, with construction award anticipated in FY28. The facility will consolidate training for two new Army air defense systems—the Indirect Fire Protection Capability (IFPC) and Maneuver-Short Range Air Defense (M-SHORAD)—and will include automation-aided classrooms, simulator training rooms, vehicle bays for applied instruction, administrative spaces, arms vaults, secure storage for classified items, FEMA safe rooms, tactical vehicle hardstands, and outdoor training areas. The Government is evaluating three primary delivery approaches: Accelerated Design-Build to Budget (DBtB), Construction Manager at Risk (CM@Risk) under OTA, and Progressive Design-Build (PDB) under OTA. The questionnaire requests detailed industry input across five sections covering company information and bidding intent, delivery method feasibility and risk assessment, budget and cost driver analysis, collaboration priorities and financial incentives, and overall delivery recommendations. The Government also seeks specific feedback on the applicability of industrialized construction methodologies—including volumetric modular construction, panelized/pre-cast systems, pre-engineered metal buildings, and 3D printed structures—aligned with Army policy to deliver facilities 50% faster at 30% lower cost. Additionally, respondents are asked to provide recommendations on evaluation criteria, contract incentive structures, stipend expectations, and commercial best practices to optimize project success.

View the file

Other files

File Type Posted
Fort Sill SHORAD Market Intelligence Survey.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Market Research Questionnaire | Project Delivery & Acquisition Strategy

Comprehensive Market Research Questionnaire

Project Delivery & Acquisition Strategy

Originating Agency U.S. Army Corps of Engineers / Tulsa District

Document Type Sources Sought / Request for Information (RFI)

Target Audience Project Delivery Teams (PDTs) & Industry Partners

Classification Unclassified / Pre-Solicitation

Table of Contents

Table of Contents

1. Project Information Packet (PIP)

Project Overview & Constraints

2. Industry Questionnaire

Part I: Company Information & Bidding Intent

Part II: Delivery Method Feasibility & Risk

1. Design Control vs. Single-Point Responsibility

2. Feasibility of Early Price Certainty

3. Rationale

4. Relevant Delivery Experience

Part III: Budget, Cost Drivers & Schedule

5. Budget Realism

6. Primary Cost Drivers

7. Schedule/Supply Chain Risk

Part IV: Defining Value, Collaboration & Financial Drivers

8. Collaboration Priorities

9. Industry Engagement & Proprietary Meetings

10. Stipends (Honorariums) & Proposal Costs

11. Contract Incentives

12. Program Capability/Interest

Part V: Overall Delivery Recommendation

13. Recommended Project Delivery Path

14. Basis of Recommendation & Contracting Vehicle

15. Evaluation Strategy

16. Industrialized Construction Methodologies

17. Commercial Best Practices & Concerns

1. Project Information Packet (PIP)

Project Overview & Constraints

Project Name & Location IFPC/M-SHORAD Instructional Facility | Fort Sill, OK

Mission Statement The U.S. Army requires a new instructional facility at Fort Sill to serve as a cornerstone for the modernization and enhancement of its air defense capabilities. Its core mission is to provide soldiers with the critical skills and doctrinal knowledge necessary to operate and maintain two of the Army's newest and most advanced air defense weapon systems: the Indirect Fire Protection Capability (IFPC) and the Maneuver-Short Range Air Defense (M-SHORAD). This facility represents a vital investment in the readiness and lethality of the force, directly supporting the strategic initiative to field one Divisional Air Defense Battalion per Division.

This project is especially significant because both the IFPC and M- SHORAD systems are new additive capabilities for the Air Defense Artillery Branch. Currently, there are no existing facilities at the institutional training base dedicated to these platforms. The construction of this dual-use training center will fill that critical gap, consolidating training for both systems under one roof and creating a synergistic learning environment.

Ultimately, the mission of this facility is to serve as the institutional crucible for forging the next generation of Air Defense Artillery soldiers.

It will provide a state-of-the-art environment for hands-on, realistic training that transforms recruits into proficient operators and maintainers. The soldiers trained here will depart Fort Sill prepared to deploy globally, equipped with the skills to ensure the Army's dominance of the airspace and the protection of its ground forces and assets against modern aerial threats.

Facility Type & Scale Automation – Aided Instruction Building | 75,930SF

Primary Functional Spaces

1. Automation Aided Instruction Classrooms (Classrooms XXI)

2. Simulator Training Rooms

3. Applied Instruction Area (Vehicle Bay)

4. Administrative Staff Space

5. Arms Vault

6. Secure Storage for Classified Training Items

7. FEMA Safe Rooms

8. Tactical Vehicle Hardstands

9. Outdoor Training Area

Funding Type MILCON

Target Budget (CCL) $84M

Period of Performance ~720 Days

Critical Milestones Construction Award in FY28

2. Industry Questionnaire

Purpose: The Government seeks your expert feedback to select the optimal project delivery method and contracting vehicle (FAR-based or OTA) for the above facilities. Please email your response to Shay Hill at Julie.S.Hill@usace.army.mil, U.S. Army Corps of Engineers, Tulsa District (CECT-SWT), no later than 2:00PM CST 28 August 2026.

Accelerated Design-Build to Budget (DBtB) Project delivery approach where the Government develops sufficient project definition to competitively establish a Firm-Fixed-Price before collaborative design development.

Construction Manager at Risk (CM At Risk) - OTA Project delivery method where a construction manager acts as a consultant to the owner during the design phase and transitions to a general contractor role during construction.

Progressive Design-Build (PDB) – OTA Single design-build agreement. Phase 1 collaboratively matures the design and negotiates a Guaranteed Maximum Price before the Government decides whether to proceed with construction.

Part I: Company Information & Bidding Intent

Company Name & CAGE Code

Point of Contact [Name, Email, Phone]

Socioeconomic Status (Check all that apply)

☐ Large Business ☐ Small Business (SB) ☐ 8(a) Business Development Program ☐ HUBZone Small Business ☐ Service-Disabled Veteran-Owned (SDVOSB) ☐ Women-Owned Small Business (WOSB)

Bonding Capacity Single Project Limit:

Aggregate Limit:

Intent to Propose ☐ Yes as Prime ☐ Yes as Sub ☐ No ☐ Undecided

Anticipated Teaming ☐ Standalone Prime ☐ Joint Venture (JV) ☐ Mentor-Protégé ☐ Subcontractor/Designer Only

Part II: Delivery Method Feasibility & Risk

1. Design Control vs. Single-Point Responsibility

Given the projects scale and complexity described in Section 1, which foundational approach poses the least risk to cost and schedule?

☐ Owner-Controlled Design: The Government should retain the design team but hire a builder early for constructability/pricing (CM@Risk).

☐ Single-Point Responsibility: The Government should shift design-completion risk to a single Design- Build entity (DBtB or PDB).

2. Feasibility of Early Price Certainty

For the projects listed above, is it feasible to propose a reliable fixed-price early in the process (e.g., DBtB), or are the scopes too undefined, requiring progressive design development (e.g., PDB)?

☐ Yes, a reliable price is achievable early based on the provided requirements.

☐ No, there is too much risk. We would need the design to reach completion before offering a Guaranteed Maximum Price (GMP).

3. Rationale

Please briefly explain the top 1–2 factors driving your answers to Questions 1 and 2:

4. Relevant Delivery Experience

Has your firm successfully executed projects of similar size/complexity using your recommended delivery method in the last 5 years?

☐ Yes ☐ No

If yes, please provide 1 brief project name/location:

Part III: Budget, Cost Drivers & Schedule

5. Budget Realism

Based on current market data, does the target budget appear realistic for these facility types and scale?

6. Primary Cost Drivers

What specific mission needs or functional requirements do you anticipate driving the most cost?

7. Schedule/Supply Chain Risk

What systems or trades present the most significant schedule risk (e.g., long-lead MEP, local labor)?

Part IV: Defining Value, Collaboration & Financial Drivers

8. Collaboration Priorities

Please rank the areas that would benefit most from early builder involvement during the design phase of the above projects (1 = Greatest Benefit, 5 = Least Benefit).

Area of Collaboration Rank (1–5)

Cost Certainty & Real-Time Estimating [ ]

Schedule Certainty & Phasing [ ]

Constructability & Quality Control [ ]

Innovation & Scope Betterments (Getting more for the money) [ ]

Overall Risk Reduction / Site Mitigations [ ]

9. Industry Engagement & Proprietary Meetings

If the Government utilizes a delivery method that allows for confidential, one-on-one proprietary meetings during the solicitation phase to collaboratively discuss innovative solutions, would your firm participate?

☐ Yes ☐ No

10. Stipends (Honorariums) & Proposal Costs

In highly collaborative procurement methods (like DBtB), offerors will incur design and proposal development costs. Would the Government's offer of a stipend significantly influence your decision to compete?

☐ Yes ☐ No

If yes, what is a commercially reasonable stipend amount for a project of this scale?

[Insert Amount/Percentage Here]

11. Contract Incentives

What specific contract incentives would best drive innovation and maximize your firm's interest in these projects?

☐ Shared Cost Savings (e.g., within a GMP structure)

☐ Award Fee for Quality / Innovation

☐ Other:

12. Program Capability/Interest (Tinker AFB)

Considering the project listed in Section 1 for Fort Sill with an estimated value of approximately $84M:

a) Would your firm be interested in proposing as a prime contractor for this project?

☐ Yes ☐ No

b) If yes, does your firm have the necessary bonding capability to cover the value of the project ☐ Yes ☐ No

Part V: Overall Delivery Recommendation

13. Recommended Project Delivery Path

Considering all factors, which project delivery path is optimal for this specific project? (Provide a response for each project listed in Section 1 above)

☐ Design-Bid-Build (DBB): Scope is simple and fully defined (closer to 30-35%); traditional FAR Part 36 and FAR 15 is sufficient.

☐ Design-Build (DB): Government establishes performance requirements and a baseline design (typically 10-35% complete); traditional FAR Part 36 and FAR 15 is sufficient.

☐ CM@Risk: Government needs to control the design but needs early builder collaboration.

☐ Design-Build to Budget (DBtB): Requirements are understood enough to drive a competitive (10- 15%), fixed-price solution, use of proprietary meetings to advance design solutions (highly collaborative).

☐ Progressive Design-Build (PDB): Scope is highly complex/undefined. Requires a single contract to collaboratively mature the design before locking in a GMP.

14. Basis of Recommendation & Contracting Vehicle

Please explain your selections above for each project. Indicate if you recommend executing this via a standard FAR-based contract or an Other Transaction Authority (OTA):

15. Evaluation Strategy

For these specific projects, what evaluation criteria do you believe the Government should weigh most heavily to ensure success? (Rank top 3: 1 being most important) ☐ Past Performance ☐ Technical Approach/Design ☐ Price/GMP ☐ Key Personnel & Team Integration ☐ Other:

16. Industrialized Construction Methodologies

In alignment with the Assistant Secretary of the Army for Installations, Energy, & Environment (ASA IE&E) policy memo, "Facility Construction Policy Implementing Installation Resilience through Industrialized Construction (IC) Methodologies," the Army is transitioning to modern construction methods to deliver facilities 50% faster and at a 30% lower cost. This policy directs the use of IC to accelerate the delivery of critical infrastructure, reduce initial capital costs, and increase the flexibility of the Army's real property portfolio.

Considering the mission and functional spaces of the IFPC/M-SHORAD Instructional Facility - a facility comprised of classrooms, simulator bays, an applied instruction area (vehicle bay), and administrative spaces - please provide your detailed assessment on the applicability of the following Industrialized Construction methods:

• Volumetric Modular Construction

• Kit of Parts (Panelized) / Pre-Cast Concrete Systems

• Pre-Engineered Metal Buildings (PEMB)

• 3D Printed Structures

In your response, please address the following:

1. Applicability and Suitability: Which of these methods are most suitable for this project?

Please specify which functional areas of the facility (e.g., classrooms, vehicle bay, entire structure) are best suited for each method.

2. Opportunities: What are the primary opportunities (e.g., schedule acceleration, cost savings, quality improvements, enhanced durability, supply chain resilience) that could be realized by implementing these technologies on this project?

3. Risks and Challenges: What are the potential risks, challenges, or limitations (e.g., design constraints, local labor availability, transportation logistics, long-term maintenance, adherence to DoD standards) associated with using these methods for an instructional facility of this type at Fort Sill?

17. Commercial Best Practices & Concerns

Please provide any additional comments, overly prescriptive constraints to avoid, or commercial best practices the Government should consider:

Table of Contents
1. Project Information Packet (PIP)
Project Overview & Constraints
2. Industry Questionnaire
Part I: Company Information & Bidding Intent
Part II: Delivery Method Feasibility & Risk
1. Design Control vs. Single-Point Responsibility
2. Feasibility of Early Price Certainty
3. Rationale
4. Relevant Delivery Experience
Part III: Budget, Cost Drivers & Schedule
5. Budget Realism
6. Primary Cost Drivers
7. Schedule/Supply Chain Risk
Part IV: Defining Value, Collaboration & Financial Drivers
8. Collaboration Priorities
9. Industry Engagement & Proprietary Meetings
10. Stipends (Honorariums) & Proposal Costs
11. Contract Incentives
12. Program Capability/Interest (Tinker AFB)
Part V: Overall Delivery Recommendation
13. Recommended Project Delivery Path
14. Basis of Recommendation & Contracting Vehicle
15. Evaluation Strategy
16. Industrialized Construction Methodologies
17. Commercial Best Practices & Concerns
Insert Name CAGE:
Insert Name Email Phone:
Large Business: Off
Small Business SB: Off
8a Business Development Program: Off
HUBZone Small Business: Off
ServiceDisabled VeteranOwned SDVOSB: Off
WomenOwned Small Business WOSB: Off
Yes as Prime: Off
Yes as Sub: Off
No: Off
Undecided: Off
Standalone Prime: Off
Joint Venture JV: Off
MentorProtégé: Off
SubcontractorDesigner Only: Off
Yes a reliable price is achievable early based on the provided requirements: Off
No there is too much risk We would need the design to reach Insert completion before offering: Off
Insert Response Here:
delivery method in the last 5 years: Off
Insert Response Here_2:
Insert Response Here_3:
Insert Response Here_4:
Insert Response Here_5:
compete: Off
Shared Cost Savings eg within a GMP structure: Off
Award Fee for Quality Innovation: Off
Other: Off
b If yes does your firm have the necessary bonding capability to cover the value of the project: Off
DesignBuild DB Government establishes performance requirements and a baseline design: Off
DesignBuild to Budget DBtB Requirements are understood enough to drive a competitive 10: Off
Progressive DesignBuild PDB Scope is highly complexundefined Requires a single contract to: Off
Insert Response Here_6:
Insert Response Here_7:
Text28:
Text29:
Text30:
Text31:
Text32:
Text33:
Text34:
Text35:
Text37:
17 Commercial Best Practices Concerns:
Insert Response Here_8:
participate: Off
DesignBidBuild DBB Scope is simple and fully defined closer to 3035 traditional1: Off
CMRisk Government needs to control the design but needs early builder collaboration: Off
b If yes does your firm have the necessary bonding capability to cover the value of the project1: Off
Text38:
Text39:
Text40:
Text41:
Text42:
Text43:
Text44:
OwnerControlled Design The Government should retain the design team but hire a builder early for: Off
OwnerControlled Design The Government should retain the design team but hire a builder early for1: Off

File details come from the government source that posted it. Updated .