Tenkiller_Bridge_AM0001_12_18_24.pdf
PDF 12 MB Posted
- Attached to
- Tenkiller Spillway Bridge Replacement Federal contract opportunity
- Solicitation number
- W912BV25R0001
About this file
This file is Amendment 0001 to a solicitation for the Tenkiller Spillway Bridge replacement project, which includes revisions to several sections including the Crane Placement Plan and Quality Control specifications, along with new attachments. The amendment adds significant technical documentation including a Tenkiller Main Spillway Bridge Inspection Report from November 2022, a Critical Findings Report, a Lead Containing Paint Survey, and revised material properties specifications changing concrete strength from 3,000 to 2,500 psi and reinforcing steel from 40,000 to 36,000 psi structural grade.
The amendment provides detailed requirements for crane operations, quality control procedures, and lead paint remediation. Key changes include requirements for the QC Manager to have 10 years of relevant experience (increased from 5 years), specific qualifications for structural specialists, and detailed procedures for crane placement planning and testing. The included bridge inspection report documents serious structural deficiencies, with the bridge currently load-posted at 16 tons. The lead paint survey from November 2020 identified multiple areas of lead-containing paint on the catwalk, girders and other bridge components that will require remediation during construction. The amendment also includes revised catwalk framing details showing kickplate modifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Am-0004_W912BV25R0001_Issued 27 January 2025.pdf | ||
| Am-0003_W912BV25R0001_Issued 23 January 2025.pdf | ||
| Tenkiller Bridge AM0002 1.21.25.pdf | ||
| Am_0001_W912BV25R0001_Issued_18_Dec_2025.pdf | ||
| Tenkiller Bridge AM0004 1.24.25.pdf | ||
| Am-0002_W912BV25R0001_Issued 22 January 2025.pdf | ||
| Site Visit Sign in Sheet 12.6.2024_Tenkiller Bridge Replacement.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0001 Continuation Sheet
Tenkiller Spillway Dam Replace Main Spillway Bridge
Date: 12/18/2024
Standard Form (SF) 30, Block 14 (continuation). Change the solicitation documents as follows.
The revised/new sections/appendices, listed below, are hereby added to, or revised, and made a part of the solicitation.
Revised sections/appendices:
SPECIFICATIONS
Revised or added/ deleted information can be located, in the specifications, by searching for an asterisk and amendment number (i.e., *AM0001).
SECTION DESCRIPTION OF CHANGE
01 11 01.00
Crane Placement Plan REPLACE section with the REVISED section of the same number.
01 11 01.00
Crane Placement Plan ADD attachment: Tenkiller Main Spillway Bridge Inspection Report Nov2022
01 11 01.00
Crane Placement Plan ADD attachment: Tenkiller Main Spillway Critical Findings Report
01 45 00.00 Quality Control REPLACE section with the REVISED section of the same number.
02 83 00 Lead Remediation ADD attachment: Lead Containing Paint Survey
DRAWINGS
Changes are identified with a revision triangle # 1.
SHEET DESCRIPTION OF CHANGE
S-562 Catwalk Framing Details REPLACE sheet with the REVISED sheet of the same number.
Clarification of Catwalk kickplate thickness.
FY23 Tenkiller Spillway Bridge Replacement Solicitation #: W912BV24R0108 December 18, 2024 Amendment 0001
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 01.00 47
CRANE PLACEMENT PLAN
SWT 06/23
PART 1 GENERAL
1.1 REFERENCES
1.2 SYSTEM DESCRIPTION
1.3 SUBMITTALS
1.4 GOVERNMENT INFORMATION PROVIDED TO THE CONTRACTOR
1.5 ENGINEER of Record QUALIFICATIONS
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 TENKILLER (MAIN) SPILLWAY BRIDGE EVALUATION AND CRANE PLACEMENT
PLAN
3.2 PROOF LOAD PERFORMANCE TEST
3.3 ENGINEERING SUPERVISION
ATTACHMENTS:
Tenkiller (Main) Spillway Bridge Inspection Report
Tenkiller (Main) Spillway Bridge Critical Findings Report
-- End of Section Table of Contents --
C23BRGSTENKILLER SECTION 01 11 01.00 47 Page 1
SECTION 01 11 01.00 47
CRANE PLACEMENT PLAN
SWT 06/23
"Revised by Amendment 0001"
PART 1 GENERAL
This section describes requirements for the development of crane placement plans required before performing crane lifts on the existing spillway bridge , and adjacent structures (e.g. concrete monoliths). Multiple crane placement plans may be necessary for this construction contract.
Crane placement plans must conform to the criteria included in this section.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
LRFD BRIDGE DESIGN SPECS (2020; R 2021) LRFD Bridge Design Specifications, 9th Edition
MANUAL FOR BRIDGE EVALUATION (2018; R 2022) Manual for Bridge Evaluation, 2nd Edition
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety and Occupational Health (SOH)Requirements
1.2 SYSTEM DESCRIPTION
The Engineer of Record is required to perform a load rating analysis for each bridge span and/or adjacent structures for all respective construction sequences (e.g. demolition activities, construction activities requiring crane(s) located on the bridge or adjacent structures, etc.) to ensure the existing spillway bridge, new spillway bridge , and adjacent structures are not subject to loads greater than allowed by LRFD BRIDGE DESIGN SPECS and MANUAL FOR BRIDGE EVALUATION LRFR procedures of analysis in the references cited within this section. Each span is to be considered separately, to ensure safe operation and travel of cranes, with special consideration given to damaged girders on the existing bridge.
If a crane, suitable for performing demolition and construction activities, without setting up on the bridge , is utilized, an evaluation of the adjacent structures, where the crane is set up, in accordance with LRFD BRIDGE DESIGN SPECS, and the requirements of this specification section is to be performed by an Engineer of Record.
C23BRGSTENKILLER SECTION 01 11 01.00 47 Page 2
The Engineer of record is required to evaluate the access hatches located on the concrete monoliths as needed depending on crane placement, crane travel and pick location.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Engineer of Record Qualifications ; G, Crane Placement Plan ; G, DO
Load Analysis ; G, DO
1.4 GOVERNMENT INFORMATION PROVIDED TO THE CONTRACTOR
The following information is provided to the Contractor for development of the Crane Placement Plan:
1. Tenkiller (Main) Spillway Bridge Inspection Report, November 2022 (signed/approved 08-JUN-2023). Attached to the end of this section.
2. Tenkiller (Main) Spillway Bridge Critical Findings Report.
Attached to the end of this section.
(*AM0001) 3. Existing Bridge & Adjacent Structures Material Properties:
a) Existing Bridge Material Properties. Attached to the end of this section.
b) Perform replacement Spillway bridge properties as specified in contract documents.
4. Adjacent Structures Material Properties
a. Concrete - f'c = 3,000 2,500 psi
b. Reinforcing Steel: Intermediate grade, 40,000 Structural grade, 36,000 psi
c. ASTM A36/A36M Structural Steel : Fy = 33 psi and Fu = 66 ksi
(*AM0001)
1.5 ENGINEER of Record QUALIFICATIONS
The Crane Placement Plan and bridge evaluation is to be performed by a licensed professional engineer with a minimum of 10 years experience in bridge design and/or bridge load rating. Submit the following information to the Contracting Officer before starting any work:
a. Name of Professional Engineer
b. State of licensure, license number, and expiration date
c. Resume showing 10 years of relevant experience
C23BRGSTENKILLER SECTION 01 11 01.00 47 Page 3
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 TENKILLER (MAIN) SPILLWAY BRIDGE EVALUATION AND CRANE PLACEMENT PLAN
1. Select a crane that is safe to traverse and operate on the existing structures. The Government will take ownership and possession of all crane analysis and plans developed by the Contractor for future use.
2. Verify existing conditions. Report any variations or change of conditions from Government-provided documents immediately to the Contracting Officer for transmittal and review by the Tulsa District Bridge Safety Program Manager. Coordinate all site investigations with the Contracting Officer.
3. Coordinate all traffic control operations and notifications with the Oklahoma Department of Transportation (ODOT). Road closures must conform to awarded contract specifications.
4. Retain, on site, copies of all annual inspections for the crane(s) used. Annual inspections are to be performed by a qualified, independent party or the crane manufacturer. Crane annual inspection records are to be in accordance with OSHA, 29 CFR 1926 Subpart CC, "Cranes and Derricks in Construction," Section 1926.1412 - Inspections. Copies of all inspection reports are to be furnished to the Government upon request.
5. Utilize the services of a licensed professional engineer registered in the United States to analyze structures for the Contractor's proposed crane placement plan(s).
6. Crane placement plan(s) are to consider the transport of all materials to the structure(s) on Contractor-provided equipment as well as logistics and positioning of said equipment with respect to the crane and operational loading of the analyzed structure.
7. The analysis is to consider the effects of the crane and all other ancillary equipment present throughout crane operation on the structure for the proposed crane placement plan(s) as well as dynamic loads imposed by the crane during execution of the crane placement plan(s).
8. Analysis is to consider crane loads while driving as well as crane loadings from the lift set up.
9. All load ratings (including for permit loads) are to be in accordance with Load and Resistance Factor Rating (LRFR) methods in Section 6A of the MANUAL FOR BRIDGE EVALUATION, including all subsequent revisions and errata. Ratings using Load Factor Design (LFD) and Allowable Stress Design (ASD) will not be accepted.
Depending on the structure being analyzed, other industry standards or codes may be used if approved in advance by the Contracting Officer.
10. Live Load effects are to consist of actual axle weights and
C23BRGSTENKILLER SECTION 01 11 01.00 47 Page 4 spacing configurations.
11. All resistance factors (i.e. phi factors) are to be selected based on each individual structure's characteristics and condition.
12. If the planned outrigger configuration is not based on published manufacture configurations (i.e. fully extended, partial extension, or combination of fully and partial extension), provide manufacture written approval of alternative outrigger configurations for all planned lift configurations as well as the corresponding outrigger reactions for each configuration utilized.
13. The source of the crane outrigger reactions during all phases of each lift are to be clearly documented. Determination of reactions via crane manufacturer software, tables, or charts is acceptable. Any deviations from the crane lift charts are to be verified and approved by the crane manufacturer with written correspondence provided to the Government.
14. Provide outrigger padding to prevent damage or scarification of the concrete surfaces.
15. For reinforced concrete and prestressed concrete components, both the Strength II and Service I limit states are to be investigated.
16. Load factors for outrigger reactions are to be as follows: 1.35 (Strength II), 1.00 (Service I).
17. All USACE owned structures, be considered " critical or essential."
18. Submit to the Contracting Officer, for approval, the Load Analysis including all engineering calculations, schematics, and drawings, and the complete crane placement for all phases of placement and retrieval of all loads. All submitted calculations, schematics, drawings, and the placement plan are to be stamped by the licensed professional engineer. The Government is allowed 30 days to review each submitted plan and each re-submission. All schematics and drawings submitted for approval are to be prepared using Computer Aided Drafting (CAD) methods in accordance with A/E/C CAD Standard Release 6.0.
19. The Contractor's Crane Placement Plan is to include, as a minimum:
a. Written certification letter stamped by the licensed professional engineer stating all assumptions, references, analysis approach and procedures, limitations, conclusions and approval of the proposed crane placement plan. The conclusions and certification portion of the certification letter is to include, for bridges, the determined inventory rating factor and the operating rating factor.
b. Drawings showing precise locations of crane outriggers and floats relative to existing structure, maximum lift radii, operating slew angles, and boom lengths. Swing angle limitations are to be provided in the procedure. Indicate any lifting radius limitations during pick-up and lay-down operation(s). See ENGINEERING SUPERVISION paragraph.
c. Clearly specify the delivery and placement of any counterweights.
C23BRGSTENKILLER SECTION 01 11 01.00 47 Page 5
d. The location and configuration of trailer(s) and additional vehicle(s) on the bridge during crane operation is to be identified in the crane placement plan/drawing. Verify that the location and orientation of trailer(s) and additional vehicle(s) are placed strictly in accordance with the established lifting radius and swing angle limitations.
20. The Contractor's Crane Placement Plan is required to be in accordance with EM 385-1-1 .
21. The number of Crane Placement Plans required depends on means and methods of the Contractor. Provide and organize each plan into its own chapter or appendix within the Crane Placement Plan submittal.
Clearly indicate the title of the chapter or appendix (e.g. "Crane Placement Plan for Existing Spillway Bridge "). Allow the Government 30 days to review the Crane Placement Plan. If additional plans (chapters or appendices) are deemed necessary, revise and re-submit the Crane Placement Plan with the new chapter or appendix for approval; allow 30 days for Government review of each new chapter or appendix.
3.2 PROOF LOAD PERFORMANCE TEST
Prior to initial use and following any modification, alteration, or repair of any component, perform a Load Performance Test in an approved staging area and in the presence of the Contracting Officer. Include lifting, swinging, and brake holding a load of 100% of the load chart rating for a specific configuration and load radius is the load test. Use configuration, load radius, and test weight to prove the crane's capability and load chart accuracy for its anticipated use.
3.3 ENGINEERING SUPERVISION
Prior to the first lift performed for each approved crane placement plan, the professional engineer of Record is to be present to mark and/or verify marked locations for crane travel and pontoon/outrigger placement.
Provide at least three working days advanced notice to the Contracting Officer prior to execution of any crane placement plan.
-- End of Section --
C23BRGSTENKILLER SECTION 01 11 01.00 47 Page 6
Tenkiller (Main) Spillway Bridge
Critical Finding Report
CRITICAL FINDINGS REPORT
Bridge Number: CEPSWTOKTENKILL Date of Critical Finding: March 2011
Bridge Name: Tenkiller (Main) Spillway Bridge Time: 1000
State: Oklahoma County: Sequoyah Level of Critical Finding: Level 3
Description of Critical Finding
Describe the location, extent, and nature of the Critical Finding. Attach photos and sketches.
Nov 17, 2022 Critical Finding Update
The Tenkiller (Main) Spillway Bridge is a fracture critical bridge. A fracture critical bridge is a bridge containing a fracture critical member which is a steel member in tension, or with a tension element, whose failure would probably cause a portion of or the entire bridge to collapse. The main load carrying elements of the Tenkiller Bridge are two steel (welded, built-up) girders that are fracture critical members.
Defect #1: A crack (4” long surface crack with surface rust) has been noted in the November 2022 hands-on visual inspection on the bottom flange of the DS Girder, Span 4, between FB #3 & FB #4. The crack occurs adjacent to the end of a tapered cover plate. This crack was documented in the NDT Report of 2011 and in previous bridge inspection reports, but neither the extent (NDT) was documented nor was a repair method recommended. The crack is likely the result of a rolling flaw. The extent of the crack should be determined via non-destructive testing (NDT). Once the degree of the defect is assessed, a repair method (i.e. bolted splice plate) should be considered. In the meantime, a new load rating, fracture analysis, and fatigue analysis should be prepared. A load posting of 16 tons is implemented until a fracture analysis is completed.
Nov 2019 Bridge
Inspection
Dec 2020 Bridge
Inspection
Nov 2021 Bridge
Inspection
Nov 2022 Bridge
Defect #2: Rolling flaw and delamination concentration in the bottom flange of the US Girder of Span 3, between FB #3 & FB #4. Although no cracking was visible during the Bridge Inspection, the NDT (Ultrasonic Examination) report, prepared during the NDT of 2011, revealed that the depth of these cracks range from 0.125 to 0.150”, which is about 20% of the bottom flange thickness. Although it was recommended to grind out as much as 1/8” of the flange to remove these flaws, no action has been taken since their discovery. A repair method (i.e. bolted splice plate) should be considered. In the meantime, a new load rating, fracture analysis, and fatigue analysis should be prepared so that (if needed) revised load posting can be implemented. A load posting of 16 tons is implemented until a fracture analysis is completed. The concentration of anomalies covers 24” of the girder bottom flange.
Mar 2011 Weld
Nov 2017 Bridge
Inspection Nov 2013 Bridge
Inspection
Nov 2019 Bridge
Inspection
Nov 2021 Bridge
Defect #3: Rolling flaws (2” – 4” long each) in the bottom flange of the US Girder of Spans 8 and 9. No cracking was visible during the bridge inspection. The NDT (Ultrasonic Examination) report, prepared during the NDT of 2011, revealed that there is 0.63” of bottom flange thickness through the gouges (about 20% of thickness loss).
No action has been taken since the discovery of this section loss. A repair method (i.e. bolted splice plate) should be considered. In the meantime, a new load rating, fracture analysis, and fatigue analysis should be prepared so that (if needed) revised load posting can be implemented. A load posting of 16 tons is implemented until a fracture analysis is completed.
860/851
Nov 2013 Bridge
Inspection
Nov 2021
Span 8
Nov 2021
Span 9
Nov 2022
Span 9
Nov 2022
Span 8
Defect #4: Missing weld (1” long) in the connection of the east end of the cover plate to the D/S girder on Span 3 and 4. The weld discontinuity has rust forming in the abrupt ending. This was not found during the 2011 NDT report. A repair method (i.e. grind and re-weld) should be considered. In the meantime, a new load rating, fracture analysis, and fatigue analysis should be prepared so that (if needed) revised load posting can be implemented or repair made. A load posting of 16 tons is implemented until a fracture analysis is completed.
Nov 2013 Bridge
Inspection
Nov 2018 Bridge
Inspection
Dec 2020
Inspection
Nov 2022 Bridge
Inspection, Span 3
Nov 2022 Bridge
Inspection, Span 4
Nov 2017 Bridge
Inspection, Span 3
Dec 2020 Bridge
Inspection, Span 4
Nov 2021 Bridge
Inspection, Span 4
CRITICAL FINDINGS REPORT (Cont.)
Contacts
List the names of individuals contacted for this Critical Finding.
Name Responsibility Date & Time Response
Jennifer Butler District Bridge PM November 4, 2022
Kathryn White Chief, E&C Division November 4, 2022
David Jarvis MSC Bridge PM November 4, 2022
Michael Malone Chief, Infrastructure Support November 4, 2022
David Sconyers Chief, Infrastructure Branch November 4, 2022
Chris Westbrook HQ Bridge PM November 4, 2022
Actions Taken
List the action(s) taken and provide a brief description of each action.
Type Description
Partial Closure
Full Closure
Load Restrictions Load Post Bridge at 16 tons for all vehicles (Load Rating underway in 2023)
Temporary Support 35% Design for new bridge is complete.
Temporary Repairs
Permanent Repairs Funding for new design and construction to replace bridge was provided in IIJA. This will remain on SWT priority list until design is complete and construction is underway.
Monitoring
The Critical Finding report was created to make everyone in the contact list aware of the safety concern that the damaged bridge girder presents, so that funding can be allocated for the repairs.
- Consider NDT to determine the extent of the rolling flaw.
- Continue inspecting the Fracture Critical Structure at a 12-mo frequency.
- Prepare new load rating, fatigue & fracture analysis that model the defect(s), until appropriate repairs can be funded.
Level 3, Needed Response Action: A Level 3 Critical Finding is used to report a potentially hazardous condition, which, if left unattended beyond the next anticipated inspection, would likely become dangerous to persons or property. A re-inspection or repair should be scheduled.
CRITICAL FINDINGS REPORT (Cont.)
Description of Repairs
Describe each repair, cost of repair and date the repair was completed or is scheduled for.
Type Cost Completion
Non-Destructive Testing $25,000 Not complete
Critical Action Follow-Up
Describe each action (repair, load restriction, etc.), date re-inspected or followed-up, and whether the action is Complete or Overdue. The Critical Findings Report is finished following completion of the routine inspection after completion of all actions.
Action Date of Follow-up Overdue Complete
Load Posting Feb. 1, 2014 Complete
Non-Destructive Testing Nov. 1, 2014 Overdue
Fatigue Analysis Nov. 1, 2014 Overdue
Fracture Analysis Nov. 1, 2014 Overdue
Load Rating Nov. 1, 2014 Overdue Ongoing
December 16, 2024 Amendment 0001
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 00.00
QUALITY CONTROL
08/23, CHG 1: 05/24
PART 1 GENERAL
1.1 REFERENCES
1.2 PAYMENT
1.3 SUBMITTALS
1.4 GENERAL REQUIREMENTS
1.5 QUALITY CONTROL (QC) PROGRAM REQUIREMENTS
1.5.1 Meetings
1.5.1.1 Quality Control Plan Meeting
1.5.1.2 Coordination and Mutual Understanding Meeting
1.5.1.2.1 Purpose
1.5.1.2.2 Coordination of Activities
1.5.1.2.3 Attendees
1.5.1.3 Quality Control (QC) Meetings
1.5.2 Contractor Quality Control (CQC) Plan
1.5.2.1 Content of Contractor Quality Control (CQC) Plan
1.5.3 Acceptance of the Quality Control (QC) Plan
1.5.4 Notification of Changes
1.6 QUALITY CONTROL (QC) ORGANIZATION
1.6.1 Personnel Requirements
1.6.2 Quality Control (QC) Manager
1.6.2.1 Duties
1.6.2.2 Qualifications
1.6.2.3 Construction Quality Management Training
1.6.3 Organizational Changes
1.6.4 Alternate Quality Control (QC) Manager Duties and
Qualifications
1.6.5 Quality Control (QC) Specialists
1.7 SUBMITTAL AND DELIVERABLES REVIEW AND APPROVAL
1.8 THREE PHASES OF CONTROL
1.8.1 Preparatory Phase
1.8.2 Initial Phase
1.8.3 Follow-Up Phase
1.8.4 Additional Preparatory and Initial Phases
1.8.5 Notification of Three Phases of Control for Off-Site Work
1.8.6 Deficiency/Rework Items List
1.9 TESTING
1.9.1 Laboratory Accreditation Authorities
1.9.2 Capability Check
1.9.2.1 Capability Recheck
1.9.2.2 Onsite Laboratory
1.9.3 Test Results
1.10 COMPLETION INSPECTIONS
1.10.1 Punch-Out Inspection
1.10.2 Pre-Final Inspection
1.10.3 Final Acceptance Inspection
C23BRGSTENKILLER SECTION 01 45 00.00 Page 1
1.11 QUALITY CONTROL (QC) CERTIFICATIONS
1.11.1 Contractor Quality Control (CQC) Report Certification
1.11.2 Completion Certification
1.12 DOCUMENTATION AND INFORMATION FOR THE CONTRACTING OFFICER
1.12.1 Construction Documentation
1.12.2 Quality Control Activities
1.12.3 Verification Statement
1.12.4 Reports from the Quality Control (QC) Specialist(s)
1.12.5 Quality Control Validation
1.12.6 Testing Plan and Log
1.12.7 As-Built Drawings
1.13 NOTIFICATION ON NON-COMPLIANCE
1.14 DELIVERY, STORAGE, AND HANDLING
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
C23BRGSTENKILLER SECTION 01 45 00.00 Page 2
SECTION 01 45 00.00
QUALITY CONTROL
08/23, CHG 1: 05/24
"Revised by Amendment 0001"
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D3740 (2019) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction
ASTM E329 (2023) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety and Occupational Health (SOH)Requirements
1.2 PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable Bid Schedule item.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan ; G
SD-06 Test Reports
Verification Statement
1.4 GENERAL REQUIREMENTS
Establish and maintain an effective quality control (QC) system that complies with FAR 52.246-12 Inspection of Construction. QC is comprised of plans, procedures, and organization necessary to produce an end product
C23BRGSTENKILLER SECTION 01 45 00.00 Page 3 that complies with the Contract requirements. The QC system covers all construction operations, both onsite and offsite, and must be keyed to the proposed construction sequence. The Quality Control Manager, Superintendent, Site Safety and Health Officer (SSHO), and all on-site supervisors are responsible for the quality of work and are subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the Contract. The Quality Control Manager must maintain a physical presence at the work site at all times and is the primary individual responsible for all quality control.
1.5 QUALITY CONTROL (QC) PROGRAM REQUIREMENTS
Establish and maintain a QC program as described in this section. The QC program consists of a QC Organization, QC Plan, QC Plan Meeting(s), a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, testing, completion inspections, QC certifications, and documentation necessary to provide materials, equipment, workmanship, fabrication, construction and operations that comply with the requirements of this Contract. The QC program must cover on-site and off-site work and be keyed to the work sequence. No construction work or testing may be performed unless the QC Manager is on the work site. The QC Manager must report to an officer of the firm and not be subordinate to the Project Superintendent or the Project Manager. The QC Manager, Project Superintendent and Project Manager must work together effectively. Although the QC Manager is the primary individual responsible for quality control, all individuals will be held responsible for the quality of work on the job.
1.5.1 Meetings
1.5.1.1 Quality Control Plan Meeting
Prior to submission of the QC Plan, the Contractor may request a meeting with the Contracting Officer to discuss the QC Plan requirements of this Contract.
The purpose of this meeting is to develop a mutual understanding of the QC Plan requirements prior to plan development and submission and to agree on the Contractor's list of Definable Feature of Work (DFOW).
1.5.1.2 Coordination and Mutual Understanding Meeting
After the Preconstruction Conference, before start of construction, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer and discuss the Contractor's quality control system.
During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the QC Manager and signed by the Contractor and the Government. Provide a copy of the signed minutes to all attendees and include in the QC Plan. At a minimum the Coordination and Mutual Understanding Meeting must be repeated when a new QC Manager is appointed. There can be other occasions when subsequent conferences will be called by either party to reconfirm mutual understandings or address deficiencies in the CQC system or procedures which can require corrective action by the Contractor.
C23BRGSTENKILLER SECTION 01 45 00.00 Page 4
1.5.1.2.1 Purpose
The purpose of this meeting is to develop a mutual understanding of the QC details, including documentation, administration for on-site and off-site work, design intent, environmental requirements and procedures, coordination of activities to be performed, and the coordination of the Contractor's management, production, and QC personnel. At the meeting, the Contractor must explain in detail how three phases of control will be implemented for each DFOW, as well as how each DFOW will be affected by each management plan or requirement as listed below:
a. Waste Management Plan.
b. Procedures for noise and acoustics management.
c. Environmental Protection Plan.
d. Environmental regulatory requirements.
1.5.1.2.2 Coordination of Activities
Coordinate activities included in various sections to assure efficient and orderly installation of each component. Coordinate operations included under different sections that are dependent on each other for proper installation and operation.
1.5.1.2.3 Attendees
As a minimum, the Contractor's personnel required to attend include an officer of the firm, the Project Manager, Project Superintendent, QC Manager, Alternate QC Manager, Assistant QC Manager, Environmental Manager, and subcontractor representatives. Each subcontractor who will be assigned QC responsibilities must have a principal of the firm at the meeting.
1.5.1.3 Quality Control (QC) Meetings
After the start of construction, conduct weekly QC meetings led by the QC Manager at the work site with the Project Superintendent, and the other personnel as necessary. The QC Manager is to prepare the minutes of the meeting and provide a copy to the Contracting Officer within 2 working days after the meeting. The Contracting Officer may attend these meetings. As a minimum, accomplish the following at each meeting:
a. Review the minutes of the previous meeting.
b. Review the schedule and the status of work and deficiencies/rework.
Review the most current approved schedule (in accordance with schedule specification) and the status of work and deficiencies/rework.
c. Review the status of submittals and Request For Information (RFIs).
d. Review the work to be accomplished in the next 3 weeks as defined by the schedule section paragraph WEEKLY PROGRESS MEETINGS in Section 01 32 01.00 10 PROJECT SCHEDULE and all documentation required for that work.
e. Review Testing Plan and Log including status of tests performed since last QC Meeting.
C23BRGSTENKILLER SECTION 01 45 00.00 Page 5
f. Resolve QC and production problems. Discuss status of pending change orders.
g. Address items that may require revising the QC Plan.
h. Review Accident Prevention Plan (APP) and effectiveness of the safety program.
i. Review environmental requirements and procedures.
j. Review Environmental Management Plan.
k. Review Waste Management Plan.
l. Review the status of training completion.
1.5.2 Contractor Quality Control (CQC) Plan
Submit no later than 30 days after receipt of notice to proceed , the CQC Plan proposed to implement the requirements FAR 52.246-12 Inspection of Construction. Construction will be permitted to begin only after acceptance of the CQC Plan and other Contract requirements
1.5.2.1 Content of Contractor Quality Control (CQC) Plan
Provide a CQC Plan, prior to start of construction that includes a table of contents, with major sections identified, pages numbered sequentially, and that documents the proposed methods and responsibilities for accomplishing quality control during the construction of the project. The CQC Plan must at a minimum include the following sections:
a. A description of the quality control organization and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified.
b. An organizational chart showing the quality control organization with individual names and job titles and lines of authority up to an executive of the company at the home office.
c. NAMES AND QUALIFICATIONS: Names and qualifications, in resume format, (including position titles and durations for qualifying experiences) for each person in the QC organization. Include the Construction Quality Management (CQM) for Contractors course certifications for the QC personnel as required by the paragraph CONSTRUCTION QUALITY
MANAGEMENT TRAINING.
d. DUTIES, RESPONSIBILITY AND AUTHORITY OF QC PERSONNEL: Duties, responsibilities, and authorities of each person in the QC organization.
e. OUTSIDE ORGANIZATIONS: A listing of outside organizations, such as architectural and consulting engineering firms, that will be employed by the Contractor and a description of the services these firms will provide.
f. APPOINTMENT LETTERS: Letters signed by an officer of the firm appointing the QC Manager and Alternate QC Manager, and stating that they are responsible for implementing and managing the QC program as described in this Contract. Include in this letter the responsibility
C23BRGSTENKILLER SECTION 01 45 00.00 Page 6 of the QC Manager and Alternate QC Manager to implement and manage the three phases of control, and their authority to stop work that is not in compliance with the Contract. Letters of direction are to be issued by the QC Manager to the Assistant QC Manager and all other QC Specialists or quality control representatives outlining their duties, authorities, and responsibilities. Include copies of the letters in the QC Plan.
g. SUBMITTAL PROCEDURES AND INITIAL SUBMITTAL REGISTER: Procedures for reviewing, approving, scheduling, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents. Provide the name(s) of the person(s) in the QC organization authorized to review and certify submittals prior to approval. Provide the initial submittal of the Submittal Register as specified in Section 01 33 00 SUBMITTAL PROCEDURES.
h. TESTING LABORATORY INFORMATION: Testing laboratory information required by the paragraph ACCREDITATION REQUIREMENTS, as applicable.
i. TESTING PLAN AND LOG: A Testing Plan and Log that includes the tests required, associated feature of work required, referenced by the specification paragraph number requiring the test, the frequency, and the person responsible for each test.
j. Procedures to complete construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected. This phase is performed prior to beginning work on each definable feature of work, after all required plans, documents, materials are approved, and after copies are at the work site.
k. Reporting procedures, including proposed reporting formats.
l. Procedures for submitting and reviewing design changes/variations prior to submission to the Contracting Officer.
m. LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task that is separate and distinct from other tasks and has control requirements and work crews unique to that task. A DFOW is identified by different trades or disciplines, or it is work by the same trade in a different environment. A DFOW is by definition any item or activity on the construction schedule, and the schedule specification provides direction regarding how the DFOWs are to be structured. Include in the list of DFOWs for all activities on the Construction Schedule.
Although each section of the specifications can generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. Identify the specification section number and schedule activity ID for each DFOW listed. The DFOW list will be reviewed in coordination with the construction schedule and agreed upon during the Coordination of Mutual Understanding Meeting.
n. PROCEDURES FOR PERFORMING AND TRACKING THE THREE PHASES OF CONTROL:
Identify procedures used to ensure the three phases of control to manage the quality on this project. For each Definable Feature of Work (DFOW), a Preparatory and Initial phase checklist will be filled out during the Preparatory and Initial phase meetings. Conduct the Preparatory and Initial Phases and meetings with a view towards obtaining quality construction by planning ahead and identifying
C23BRGSTENKILLER SECTION 01 45 00.00 Page 7 potential problems for each DFOW.
1.5.3 Acceptance of the Quality Control (QC) Plan
The Contracting Officer's acceptance of the Contractor QC Plan , or interim plan applicable to the particular feature of work to be started, is required prior to the start of construction. The Government will consider an interim plan for the first 7 days of operation. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work. The Contracting Officer reserves the right to require changes in the QC Plan and operations as necessary, including removal or addition of personnel, to ensure the specified quality of work. The Contracting Officer reserves the right to interview any member of the QC organization at any time to verify the submitted qualifications. All QC organization personnel are subject to acceptance by the Contracting Officer. The Contracting Officer may require the removal of any individual for non-compliance with quality requirements specified in the Contract.
1.5.4 Notification of Changes
Notify the Contracting Officer, in writing, of any proposed changes in the QC Plan or changes to the QC organization personnel. Proposed changes are subject to acceptance by the Contracting Officer.
1.6 QUALITY CONTROL (QC) ORGANIZATION
1.6.1 Personnel Requirements
The requirements for the CQC organization are a Site Safety and Health Officer (SSHO), QC Manager, and enough qualified personnel to ensure safety and Contract compliance. The SSHO reports directly to a senior project (or corporate) official independent from the QC Manager. The SSHO will also serve as a member of the CQC Staff Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly. The CQC staff always maintains a presence at the site during progress of the work and have complete authority and responsibility to take any action necessary to ensure Contract compliance. The CQC staff will be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC organization. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules, and all other project documentation to the CQC organization. The CQC organization is responsible for always maintaining these documents and records at the site, except as otherwise acceptable to the Contracting Officer.
1.6.2 Quality Control (QC) Manager
1.6.2.1 Duties
Provide a QC Manager at the work site to implement and manage the QC program. The only duties and responsibilities of the QC Manager are to manage and implement the QC program on this Contract. The QC Manager must attend the Coordination and Mutual Understanding Meeting, perform the three phases of control except for those phases of control designated to be performed by QC Specialists, perform submittal review and approval, ensure testing is performed and provide QC certifications and documentation required in this Contract. The QC Manager is responsible
C23BRGSTENKILLER SECTION 01 45 00.00 Page 8 for managing and coordinating the three phases of control and documentation performed by testing laboratory personnel and any other inspection and testing personnel required by this Contract. The QC Manager is the manager of all QC activities.
1.6.2.2 Qualifications
The QC Manager must be an individual with a minimum of (*AM0001) 5 10(*AM0001) years combined experience in the following positions: Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction Contracts which included the major trades that are part of this Contract. The individual must have at least 27 years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification, safety compliance, and sustainability.
(*AM0001) The QC Manager must possess at least a Bachelor's degree in engineering, architecture, or construction management, with a current professional engineer registration in a US State or Territory and a minimum of 10 years construction experience as a Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction Contracts which included the major trades that are part of this Contract. The individual must have at least 2 years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification, safety compliance, and sustainability.
(*AM0001)
The QC Manager and all members of the QC organization must be capable of reading, writing, and conversing fluently in the English language.
1.6.2.3 Construction Quality Management Training
In addition to the above experience and education requirements, the QC Manager and all members of the QC team must have completed the CQM for Contractors course. If the QC Manager does not have a current certification, obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the Naval Facilities Engineering Systems Command and the Army Corps of Engineers.
Contact the Contracting Officer for information on the next scheduled class.
The Construction Quality Management Training certificate expires after 5 years. If the QC Manager's certificate has expired, retake the course to remain current.
1.6.3 Organizational Changes
Maintain the QC staff with personnel as required by the specification section at all times. When it is necessary to make changes to the QC staff, revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer for acceptance.
1.6.4 Alternate Quality Control (QC) Manager Duties and Qualifications
Designate an alternate for the QC Manager at the work site to serve in the event of the designated QC Manager's absence. The qualification requirements for the Alternate QC Manager must be the same as for the QC Manager.
C23BRGSTENKILLER SECTION 01 45 00.00 Page 9
(*AM0001) 1.6.5 Quality Control (QC) Specialists
Provide a separate QC Specialist at the work site for each of the areas as listed in the Matrix listed below, who must assist and report to the QC Manager and who[ may perform production related duties but must be allowed sufficient time to perform][ must have no duties other than] their assigned quality control duties. These individuals or specialized technical companies[ are directly employed by the Prime Contractor and cannot be employed by a supplier or subcontractor on this project][ are employees of the Prime or subcontractor]. A single person can cover more than one area provided that the single person is qualified to perform quality control activities in each designated and that workload allows.
QC Specialists must be physically present at the work site with frequency as indicated in the Experience Matrix below, to participate in the QC Meetings, perform the three phases of control, including participation in Preparatory and Initial Phase meetings, and to perform and document Follow-up inspections as an extension of the QC Manager for each definable feature of work in their area of responsibility. QC Specialist must assist and be present for training events, and Critical System Acceptance inspections by the Government. Qualification, experience, Area of Responsibility, and frequency of QC surveillance are provided in Matrix listed herein.
Experience Matrix
1. Area 2.1 Qualification 3.1 Experience
Structural 2-1. Graduate Civil Engineer (with Structural Track or Focus) or Construction Manager with a professional engineer registration in any US state or territory.
2-2. 10 years of related field experience and 5 years of experience supervising structural features of similar work
(*AM0001)
1.7 SUBMITTAL AND DELIVERABLES REVIEW AND APPROVAL
Procedures for submission, review and approval of submittals are described in Section 01 33 00 SUBMITTAL PROCEDURES. Procedures must include field verification of relevant dimensions and component characteristics by the QC organization prior to submittal being sent to the Contracting Officer.
The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the Contract.
1.8 THREE PHASES OF CONTROL
CQC enables the Contractor to ensure that the construction, including that of subcontractors and suppliers, complies with the requirements of the Contract. At least three phases of control must be conducted by the QC Manager to adequately cover both on-site and off-site work for each definable feature of the construction work as follows:
C23BRGSTENKILLER SECTION 01 45 00.00 Page 10
1.8.1 Preparatory Phase
Document the results of the preparatory phase actions by separate minutes prepared by the QC Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required to meet Contract specifications.
Notify the Contracting Officer at least 2 business days in advance of each preparatory phase meeting. The meeting will be conducted by the QC Manager and attended by the QC Specialists, the Project Superintendent, and the foreman responsible for the DFOW. When the DFOW will be accomplished by a subcontractor, that subcontractor's foreman must attend the preparatory phase meeting. This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. Perform the following prior to beginning work on each DFOW:
a. Review each paragraph of the applicable specification sections, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.
b. Review the Contract drawings.
c. Verify that field measurements are as indicated on construction or shop drawings or both before confirming product orders, to minimize waste due to excessive materials.
d. Verify that appropriate shop drawings and submittals for materials and equipment have been submitted and approved. Verify receipt of approved factory test results, when required.
e. Review the testing plan and ensure that provisions have been made to provide the required QC testing.
f. Examine the work area to ensure that the required preliminary work has been completed and complies with the Contract and ensure any deficiencies/rework items in the preliminary work have been corrected and confirmed by the Contracting Officer.
g. Review coordination of product/material delivery to designated prepared areas to execute the work.
h. Examine the required materials, equipment and sample work to ensure that they are on hand and conform to the approved shop drawings and submitted data and are properly stored.
i. Check to assure that all materials and equipment have been tested, submitted, and approved.
j. Discuss specific controls to be used, construction methods, construction tolerances, workmanship standards, and the approach that will be used to provide quality construction by planning ahead and identifying potential problems for each DFOW. Ensure any portion of the plan requiring separate Contracting Officer acceptance has been approved.
C23BRGSTENKILLER SECTION 01 45 00.00 Page 11
k. Review the APP and appropriate Activity Hazard Analysis (AHA) to ensure that applicable safety requirements are met, and that required Safety Data Sheets (SDS) are submitted.
l. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.
m. Discuss schedule and execution of the initial control phase and confirmation or construction quality compliance.
1.8.2 Initial Phase
Notify the Contracting Officer at least 2 business days in advance of each initial phase. When construction crews are ready to start work on a DFOW, conduct the initial phase with the Project Superintendent, and the foreman responsible for that DFOW. Observe the initial segment of the DFOW to ensure that the work complies with Contract requirements. Document the results of the initial phase in the daily CQC Report and in the Initial Phase Checklist. Repeat the initial phase for each new crew to work on-site when acceptable levels of specified quality are not being met.
Indicate the exact location of initial phase for definable feature of work for future reference and comparison with follow-up phases. Perform the following for each DFOW:
a. Check work to ensure that it is in full compliance with Contract requirements. Review minutes of the preparatory meeting.
b. Verify adequacy of controls to ensure full Contract compliance.
Verify required control inspection and testing comply with the Contract.
c. Establish level of workmanship and verify that it meets the minimum acceptable workmanship standards. Compare with required sample panels as appropriate.
d. Resolve any workmanship issues.
e. Ensure that testing is performed by the approved laboratory.
f. Check work procedures for compliance with the APP and the appropriate AHA to ensure that applicable safety requirements are met.
g. Review project specific work plans (i.e., HAZMAT Abatement, Stormwater Management) to ensure all preparatory work items have been completed and documented.
1.8.3 Follow-Up Phase
Perform the following for on-going DFOW daily, or more frequently as necessary, until the completion of each DFOW. The Final Follow-Up for any DFOW will clearly note in the daily report the DFOW is completed, and all deficiencies/rework items have been completed in accordance with the paragraph DEFICIENCY/REWORK ITEMS LIST. Each DFOW that has completed the Initial Phase and has not completed the Final Follow-up must be included on each daily report. If no work was performed on that DFOW for the period of that daily report, it must be so noted. Document all Follow-Up activities for DFOWs in the daily CQC Report:
C23BRGSTENKILLER SECTION 01 45 00.00 Page 12
a. Ensure the work including control testing complies with Contract requirements until completion of that particular work…