W912BV20R0001 Amendment 0012 Bidder Inquiry Response.pdf
PDF 380 KB Posted
- Solicitation number
- W912BV20R0001
About this file
This document provides responses to bidder inquiries for solicitation number W912BV20R0001 for the Building 1020 Repair Tech Training project at Sheppard Air Force Base. Work includes replacing HVAC, electrical, and plumbing systems, upgrading controls, replacing exterior siding and doors, and refinishing interior spaces. Inquiries addressed include confirming floor drain sizes, quantities and locations for various restrooms. The contracting office is the Department of the Army Corps of Engineers Engineering District Tulsa, with proposals due by 2:00 PM Central Time on August 14, 2020.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
REPAIR TECH TRAINING BUILDING 1020 SHEPPARD AIR FORCE BASE - WICHITA COUNTY, TEXAS.
This amendment is hereby executed to provides a response to ProjNet Bidder Inquiry 8332051.
Proposals are due at 2:00 PM Central Time on 14 AUG 2020.
Contract Specialist: Chris Wright (Christopher.T.Wright@usace.army.mil) Off ice (918)669-7277
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Aug-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912BV20R0001
X 9B. DATED (SEE ITEM 11)
06-Dec-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Aug-2020
CODE
CONTRACTING DIV
US ARMY CORPS OF ENGINEERS, TULSA DISTRICT
2488 E. 81ST STREET
TULSA OK 74137-4290
W912BV 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912BV20R0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION 00 11 00 - SF 1442 AND CLIN SCHEDULE
SUMMARY OF CHANGES
SECTION 00 72 00 - CONTRACT CLAUSES
The following have been added by reference:
52.204-26 Covered Telecommunications Equipment or Services--
Representation.
DEC 2019
(End of Summary of Changes)
The following items are applicable to this modification:
SECTION 00 73 10 - SUPPLEMENTAL CONTRACT REQUIREMENTS
ProjNet Question 8332051 Please verify the size, quantity and locations of the floor drains to be installed. In addition to the floor drains shown on the plans, provide 2” floor drains for the following restrooms (Women C235, Men D235 and Men C133).
Room C133 (Men) shows 1 each 2" Floor Drain located @ the end of the drain line serving the 10 Urinals. The floor drain appears to be located in the plumbing chase or wall? The referenced 2” floor drain is incorrectly shown. Provide one (1) floor drain near the middle of the room.
Very large Restroom to have 1 Floor Drain located in the corner of the room? The room will have only one (1) floor drain.
Room D132 (Women) shows a 2" Floor Drain located in the main entrance to the restroom? Install floor drain as shown. Room D133 (Men) shows a 2" Floor Drain located in the Plumbing Chase? No floor drains will be installed in Men D133 or in the plumbing chase.
Room C235 (Women) does not show any Floor Drains? Provide room C235 with a 2” floor drain.
Room C236 (Women) shows 2 Floor Drains with one of them located in the middle of the closet door entry? The floor drain shown in the closet entry is not to be installed.
Room D235 (Men) shows 1 Floor Drain located in the middle of the room @ the bank of urinals. Large Restroom to only have one floor drain? Floor drain quantity and location are correct.