Text version
W912BV20Q0159
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 72 00 - CONTRACT CLAUSES
The following have been added by full text:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 days. *The time stated for completion shall include final cleanup of the premises.
(End of clause)
The following have been deleted:
| 52.211-10 |
| Commencement, Prosecution, and Completion of Work |
| APR 1984 |
SECTION 00 73 00 - SPECIAL CONTRACT REQUIREMENTS
The following have been modified:
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $329.57 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
(End of Summary of Changes) image1.wmf
File details come from the government source that posted it. Updated .