S P E C I F I C A T I O N S
LAKE TEXOMA
OKLAHOMA & TEXAS
CXT SHOWER BULDING INSTALLATION
FOR
PRESTON BEND PUA
PART 1 – GENERAL
1.1 SCOPE OF WORK
These specification and drawings covers requirements for contractor to furnish all materials, labor, and equipment necessary to demo and remove the existing restroom, and install a new CXT Navajo shower building located at Preston Bend Public Use Area approximately 10 miles north of Pottsboro, Texas in Grayson County, Texas.
1.1.1 (CLIN 0001) – All materials, labor, and equipment necessary to construct pad, install electric plumbing, and sewer stub ups, install new sewer pipe from stub ups to trash tank, install new sewer holding tanks, install new sewer pipe from trash tanks to lateral field, install new electric service from meter base to restroom, and install new light pole prior to placement of restroom.
1.1.2 (CLIN 0002) - All materials, labor, and equipment necessary to purchase, deliver, and install one CXT Navajo Restroom.
1.1.3 (CLIN 0003) - Provide all materials, labor, and equipment to make final connections of electric, plumbing and sewer utilities, place concrete sidewalks, place concrete parking area, and landscape after placement of restroom.
1.1.4 (CLIN 0004 – OPTION) - All materials, labor, and equipment necessary to demolish the existing shower building and remove and dispose of debris off government property.
1.2 REFERENCES
ACI 318, ACI 301 and ACI 306
TCEQ
NEC
1.3 BASIS FOR PAYMENT
Partial and Full Payment.
1.4 WORK HOURS
Regular work hours will be from 8:00 am – 4:30 pm Monday through Friday, excluding federal holidays. Any proposed changes to the work hours must be approved by the Contracting Officer.
1.5 COMPLETION TIME
Work shall be completed within 90 calendar days after receipt of the notice to proceed.
1.7 SAFETY REQUIREMENTS
The contractor shall comply with the Corps of Engineers Safety and Health Requirements anual, EM 385-1-1 dated 15 Sept 2008, and all applicable Federal, State, and local safety codes and practices. It is the contractor’s responsibility to insure public safety during the entire duration of the contract. Necessary signs, barriers, warning devices, etc. shall be operated and maintained by the contractor at contractor expense. Contractor employees shall comply with the minimum dress requirements as stated in Chapter 7 of EM 385-1-1.
1.8 EQUIPMENT
All equipment used to perform work under this contract shall be in good operating and mechanical condition and shall comply with Section 18 of EM 385-1-1. Equipment shall be inspected by the contractor and the inspection reports shall be submitted to the Contracting Officer prior to utilization of such equipment to accomplish work on this contract.
1.9 WEATHER LIMITATIONS
Work shall not be done during adverse weather conditions that would cause damage to Government Property.
1.10 SUBMITTALS
The contractor may be required to furnish certain submittals. These submittals may be certifications of materials, safety plans, drawings, training certifications, work plans, etc.
These will be specifically listed and shall be furnished to the Contracting Officer.
Submittals requiring Government approval shall be formally prepared and approval granted prior to proceeding with work involving these submittals. FIO (For Information Only) submittals do not require Government approval.
1.11 PREWORK CONFERENCE
A prework conference will be held with the Contracting Officer and contractor prior to the commencement of any work. The contractor’s responsible person and necessary administrative staff will be required to attend this meeting. Procedures for proper invoicing and payment, schedule, etc., will be covered at this time.
1.12 ENVIRONMENTAL CLEANUP
The contractor shall maintain a clean work area at all times. The contractor shall be responsible for the protection of the environment and will be required to restore all damages subject to the approval of the contracting officer. The contractor shall remove and dispose of all debris off Government property in a state approved disposal site unless specified otherwise. The contractor will be required to comply with all Federal and State environmental requirements.
1.13 COORDINATION OF WORK
Dusty Pollard Civil Engineering Tech. – Phone: (903) 465-4990 X 7825
Cell: (580) 230-8826 Joe Custer Lake Manager - Phone: (903) 465-4990 X 7814 Tommy Holder, Asst. Lake Manager - Phone: (903) 465-4990 X 7810 Fax (903) 465-6571
1.14 INVOICES
Invoices shall be submitted to the Lake Texoma Project Office for processing at:
Attn. Dusty Pollard Lake Texoma Project Office 351 Corps Rd Denison, TX 75020
1.5.Weather Delays. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
(OCT 1989) (ER 415-1-15)
1.5.1. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled “Default: (Fixed Price Construction)”. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.
1.5.2. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations.
The contractor’s progress schedule must reflect these anticipated adverse weather delays in all-weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
4 4 4 5 5 4 4 4 4 3 4 4
1.5.3. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily Contractor Quality Control (CQC) report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent of more of the contractor’s scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 1.10.2, above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work day, and issue a modification in accordance with the contract clause entitled “Default (Fixed Price Construction)”.
1.6 Liquidated Damages.
Refer to basic contract Section 00800, clause 52.211-12, Liquidated Damages— Construction, $98.00 per day.
1.7 Antiterrorism and Operations Security Requirements. The Contractor shall be responsible for ensuring all personnel, to include sub-contractor personnel, comply with the training requirements and procedures identified on the document titled “Antiterrorism/Operations Security Requirements” in Section H, Special Contract Requirements. When items for which training is identified, the Contractor shall ensure that all personnel complete acknowledgement for the specified training; the Contractor is responsible for ensuring all training acknowledgments, when applicable, are submitted to the COR or Contracting Officer within 10 calendar days of contract award (or NTP for construction contracts). In no event shall any contractor or sub-contractor personnel be onsite prior to completion of any applicable training and submission of training verification. Training materials and verification forms will be provided by the Contracting Officer upon written request.
PART 2 – PRODUCTS
2.1 MATERIALS
All materials shall be new and undamaged as follows.
2.1.1 - Concrete shall be 3500 psi.
2.1.2 - Rebar shall be #3 and #4 in diameter as specified in the execution portion of this specification.
2.1.3 - Water supply shall be 2 inch PEX tubing.
2.1.4 - Waste pipe shall be SCD 40 PVC sized to the specifications outlined in the CXT drawings.
2.1.5 - Vent pipe shall be SCD 40 PVC sized to the specifications outlined in the CXT drawings.
2.1.6 - Road bore sleeve shall be SCH 11 HDPE sized to allow for installation of 2” PEX pipe.
2.1.7 - Electric wire shall be copper underground and sized in accordance with the NEC
2.1.8 - Gray, electrical conduit sized to accommodate all buried electric service.
2.1.9 - 200 amp outdoor fused disconnect.
2.1.10 – Light pole shall be a CREE catalog number PSRV25CTBZ round tapered pole.
2.1.11 – Lights for light pole shall be CREE LEDway series photo sensor controlled LED light, catalog number STR-LWY-3M-HT-10-E-UL-SV-700-R-40K.
2.1.12 – 1000 gallon septic tanks shall be concrete.
2.1.13 – 500 gallon septic tanks shall be concrete.
2.1.14 – CXT Inc. Navajo restrooms shall meet the requirements and have the options outlined in this specification.
2.1.15 – Fill dirt shall free of foreign debris and rocks larger than 2 inches in diameter.
2.1.16 – Top soil shall free of any foreign debris and all rocks.
2.1.17 – Aggregate base material shall be 3/4 inch crushed stone suitable for compaction.
2.1.18 – Sod shall be Bermuda grass.
2.1.19 – Handrail material for stairs shall be 1 1/4" .120 wall round pipe.
2.2 DELIVERY AND STORAGE
Materials shall be delivered to the site undamaged and stored out of contact with the ground. Materials that are damaged during the delivery or improper storage shall be replaced at no cost to the government
2.3 GOVERNMENT FURNISHED PROPERTY
The government will provide potable water for watering of sod.
PART 3 - EXECUTION
3.1 ACCOMPLISHMENT OF WORK SHOWER BUILDING
All work shall be accomplished in a safe, workmanlike manner and in accordance with standard industry practices. Plumbing work shall comply with the National Plumbing Code. Electrical work shall comply with the National Electrical Code. Concrete work shall comply with American Concrete Institute. These specification and drawings covers requirements for contractor to demolish and remove an existing shower building, construct a pad for a CXT Navajo shower building, plumb sewer and water stub ups, install electrical stub ups, make final connections of sewer, water, and electrical stub ups, place sidewalks, landscape, install new sewer pipe from stub ups to newly installed septic tanks, connect new sewer pipe to existing lateral field, and grade, compact , and place concrete for parking area. The contractor shall provide Quality Control (QC) of all work.
The government will conduct Quality Assurance (QA).
3.1.2 Demolition and Removal of Existing Shower Building The contractor shall demolish and remove all remanence of the existing shower building.
All debris to include but not limited to concrete, masonry materials, rebar, roofing material, wood, electrical wiring or components, plumbing fixtures and components, or insulation shall be disposed of off government property in accordance with state and local law. The contractor is responsible for disconnecting and capping all existing utilities.
After removal and disposal of the existing shower building the contractor shall back fill and grade the disturbed area to allow for adequate drainage or run off of rain water. The contractor shall then spread top soil a minimum of 4 inches thick over the entire disturbed area and place Bermuda grass sod to cover the entire area with no gaps.
The contractor shall water the sod for a minimum of 1 hour per day after placement of the sod for a minimum of 7 days.
3.1.3
SITE PREPARATION
The exact location of the newly installed restroom will be marked in the field. The contractor shall place fill material free of foreign debris and rocks larger than 2 inches in diameter to raise the existing elevation where the new restroom will be placed a minimum of 2 feet from the lowest point of the footprint of the new CXT restroom. The contractor shall place and compact the fill material in 6 inch lifts to a minimum compaction rate of 95% maximum density. The contractor shall slope the fill material away from the restroom at a maximum of 4 to 1 slope.
The base area for the building shall extend beyond the floor by at least 6 inches in each direction. Water, sewer, electrical etc. lines need to be placed before base material is added and compacted. See drawings for placement of utilities. A minimum of 6 inches of a compacted ¾” minus angular gravel material (i.e. road base) shall be used as the base material. The material shall be placed level and compacted to support a minimum of 1500 pounds per square foot. The base shall be confined to prevent washout erosion or any other undermining. This base will provide support, leveling and drainage.
The base area shall be prepared for a 6 foot wide by 4 inches thick with a 1 ½ inch fall away from building for concrete sidewalks at the same time as it is prepared for the building.
Sidewalks shall be added shortly after installation of the facility itself. The contractor may stockpile any excavated materials in area designated onsite, but must remove excess sub soil not being reused from site to a designated site provided by the government before work is accepted. The contractor shall be responsible for loading and hauling materials.
3.1.4
PLUMBING STUB UPS
Except for bury depths plumbing stub ups shall be placed in accordance with CXT drawings and recommendations and tie in to existing lines by a licensed plumber. Bury depths shall be in accordance with code for this area. The contractor shall install new 2 inch PEX pipe to supply water to the restroom. The distance from the existing water pipe to the new restroom is approximately 110 feet. The water pipe shall not travel under the parking area or parking area access. The contractor shall install a new underground shut off valve where the water line branches off the water main to service the restroom with a valve box to allow for access to the valve. The contractor shall make final connections of plumbing after restroom has be placed. The contractor will be responsible for locating the existing water supply main and determining the size and type of connection needed.
The contractor shall bore under the existing roadway to install the new water pipe. The contractor will not be allowed to trench the roadway. The PEX pipe shall be sleeved in SCH 11 HDPE pipe.
3.1.6
INSTALLATION OF SEWER PIPE
The contractor shall install new sewer pipe from the sewer stub ups to each newly installed septic tank and connect to the existing lateral field. The length of sewer pipe the contractor will install from the north end of the restroom to the lateral field is approximately 150 feet. The contractor shall place two 1000 gallon, concrete septic tanks immediately past the edge of the newly installed parking lot. The contractor shall place a 500 gallon, concrete septic tank directly adjacent to the existing lateral field to ensure fall in elevation of the sewer pipe from the 500 gallon tank to the lateral field will not cause damage to the lateral field. The contractor shall place one sewer cleanout on each side of the restroom and one sewer cleanout half the distance from the first clean out to the first 1000 gallon septic tank. The sewer cleanouts will be installed in the concrete sidewalk and concrete parking area. The cleanout caps shall be cast iron and flush with the top of the newly placed concrete.
The pipe shall be schedule 40 PVC and shall be installed according to local code. A layer of bedding sand four inches deep shall be placed in the trench prior to installation of the pipe and another layer of bedding sand shall be placed after installation of pipe to extend six inches above the top of the pipe. Random fill, free of debris and any rocks larger than two inches in diameter, shall be used to fill the remainder of the trench and shall be compacted to a rate of 95% maximum density. The trench shall be smoothed and graded to match the existing elevation of the surrounding earth. Metallic marking tape shall be installed one foot below surface elevation. Prior to covering the pipe and compacting the earth, the trench shall be inspected by a designated government official.
A drawing diagram of a typical trench is included.
3.1.7
ELECTIRCAL STUB UPS
Electrical stub ups shall be placed in accordance with CXT drawings and recommendations and connect to an existing electrical service by a licensed electrician.
The contractor shall install new electrical service wire from an existing transformer approximately 130 feet from the proposed location of the new restroom that is sized according to the NEC cased in gray, SCH 40 electrical conduit and a 200 amp, single phase, fused disconnect directly after the meter base to allow government to de-energize the restroom electrical service. The contractor shall make final connections of electrical service after restroom is placed.
The contractor shall place a light pole on the west side of the parking area annotated in the attached drawings. The light pole shall have a concrete base a minimum of 16 inches in diameter and 4 feet deep. The light pole shall be a round, steel, tapered pole 25 feet in length with a 7 inch base. The lights shall be a CREE LEDway series LED light. The contractor shall install two specified LED lights using an approved tenon designed for use with the specified light pole and LED lights 180 degrees apart to supply light for the new restroom parking lot and the adjacent roadway. The contractor shall supply electric service for the light pole from the 200 amp panel box install in the restroom. The electric wire and breaker shall be sized in accordance with NEC and placed in gray, schedule 40 PVC electrical conduit. The distance from the panel box inside the restroom to the light pole is approximately 85 feet.
3.1.8
RESTROOM PUCHASE, DELIVERY, AND INSTALLATION
The contractor shall purchase, deliver and install one new CXT Navajo restroom. A list of all options required for the building can be found in the references section of this specification. The contractor will be responsible for the transportation of the CXT restroom. The restroom shall be delivered to the worksite without damage. The restroom is constructed in two pieces and must be connected at the work site. The contractor will be required to set the restroom and connect the two halves together in accordance with CXT specifications. The contractor shall connect the utilities of the two pieces together and shall grout all floor drains after final connection of all utilities. Attached are reference drawings of the Navajo restroom. Full size drawings can be obtained from CXT’s website at http://www.cxtinc.com/.
3.1.9 SIDEWALKS, PARKING LOT, and STAIRS
a. Forms.
1. Forms shall be constructed and place to provide sidewalks as shown on attached drawing. The sidewalks shall be constructed on a compacted sand base prepared by the contractor. Sidewalks shall be constructed around the entire perimeter of the newly placed CXT building and tie into the existing sidewalk approaching the building. Sidewalks shall be 4” thick by 6’ wide.
The Government Inspector before placement shall approve forms. Forms to be constructed shall be grout tight and sufficiently anchored to prevent displacement during placement of concrete. Prior to placement of concrete, form surfaces in contact with concrete must be either wetted or oiled. When oil is used, it must be applied prior to the placement of reinforcing steel. The final grade of the concrete shall be flush with the top of CXT shower building slab grade with a 1 ½ inch fall away from building. Form placement shall be approved by the government inspector.
2. The contractor shall supply fill material and aggregate base to grade and compact for placement of concrete parking area. The approximate area of the parking lot including approaches and handicap space is 5,200 square feet. The elevation of the parking handicap parking spot shall match the elevation of the sidewalks around the restroom. The elevation of the parking lot where meets the restroom on the south side will be dependent on the required elevation of the parking lot to allow for drainage away from the restroom. The contractor shall grade the sub base and aggregate base of the parking lot to allow for drainage of rain water away from the restroom and to the east where able. The drainage shall not be diverted to allow flow onto or into the existing lateral field. The contractor shall compact the subbase and aggregate base to a minimum of 95% maximum density. The subbase shall be compacted in 6 inch lifts to achieve desired grade. The aggregate base shall be a minimum of 6 inches thick and compacted as specified. The concrete parking area shall be a minimum of 6 inches thick with thickened edges. A drawing of the parking area in relationship to the bathroom and access roadway is attached.
3. The contractor shall place a concrete stairway to access the restroom sidewalk from the parking area. The stairway shall be 4 feet wide and have handrails on each side that meet ADA standards. The length of the stairway will be dependent on the 4 to 1 slope specifications for fill around restroom and the elevation difference between the restroom sidewalk and the parking lot.
b. Concrete Reinforcement.
Concrete shall be reinforced with #3 rebar for the sidewalks and stairway and #4 rebar for the parking area. Rebar shall be placed on 18” centers longitudinally and transversely. Dowels shall be placed in the concrete foundation of the CXT restroom to prevent heaving or settling of the sidewalks. Rebar ends shall overlap a minimum of 6” and be wired securely together. Fabricate and place concrete reinforcing in accordance with ACI 318.
c. Cast in Place Concrete.
The contractor shall provide 3500-PSI concrete. Delivery tickets shall be furnished with each delivery and a copy made available to the government inspector. The contractor shall saw the sidewalks and parking area to allow for expansion cracks.
The saw marks shall not extend deep enough to cut the rebar reinforcing the concrete.
The contractor shall place concrete in accordance with ACI 301 and ACI 306.
d. Concrete Finishing.
Concrete shall be finished in a matter to provide a smooth surface in accordance with ACI 301. The concrete shall be placed and finished so as to provide a surface that is free of defects such as low places (Bird baths) or high ridges, etc. The finish surface shall be tested for straightness. The maximum allowable deviation shall be ¼ inch in five feet. The surface of the concrete shall receive the equivalent of a steel trowel finish, but while still sufficiently wet to be worked; the surface of the concrete shall be lightly broom finished.
e. Curing and Protection.
All concrete shall be cured by approved method for three days. During the curing period the concrete shall be protected from physical damage.
f. Form Removal.
Forms may be removed after 24 hours and must be accomplished in a matter that prevents damage to the concrete.
3.1.10
PARKING LOT STRIPING AND WHEEL STOPS
The contractor shall place concrete wheel stops at each parking space. The wheel stops shall be a minimum of 6 feet in length, 5 inches high and 8 inches wide reinforced with #3 rebar. The wheel stops shall be secured to the parking area using #4 rebar drilled and driven into the concrete parking area. The wheel stops shall be centered in the parking spots and be 12 inches from the end of the parking spot.
The contractor shall stripe the parking lot to delineate each parking space. The handicap parking space shall be indicated with a handicap emblem and have diagonal striping on each side. The parking lot will have 7 parking spots including the handicap parking spot.
3.1.11 Landscaping and cleanup After all construction work has been completed, the contractor shall place and grade top soil free of all foreign debris a minimum of 4 inches thick to match the elevation of the sidewalks, parking area, and undisturbed surrounding grounds. All exposed top soil shall be sodded with Bermuda grass sod. The contractor shall water the sod for a minimum of one hour per day for a minimum of 7 days. All foreign debris shall be removed from construction site to complete work.
3.2 TESTING
1. All plumbing, sewer, and electrical utilities shall be tested for proper operation prior to final approval of work.
2. Contractor shall test the subbase for the restroom pad using nuclear density testing and provide test results to the contracting officer’s representative (COR). If the test results do not meet the minimum standards of these specifications, the contractor shall scarify and compact the sub base to reach the required compaction rate.
3. Contractor shall test the aggregate base for the restroom using a plate load test and provide the test results to the COR. If the test results do not meet the minimum standards of these specifications, the contractor shall scarify and compact the base to reach the required compaction rate.
4. Contractor shall test the sub base and aggregate base of the parking area using nuclear density testing and provide the results to the COR. If the test results do not meet the minimum standards of these specifications, the contractor shall scarify and compact the sub base and/or aggregate base to reach the required compaction rate.
3.3 TREE REMOVAL
The contractor may be required to remove or trim trees to allow enough room for installation of the restroom. . The contractor is responsible for removing the trees and associated stump and root ball. The cavity left by the root ball shall be filled and compacted with top soil to achieve a proper working grade necessary for construction to continue. All associated tree parts shall be removed from Government property.
3.3 WARRANTY
None
3.4 REFERENCE MATERIAL
DRAWINGS AND MAPS
PARKING AND RESTROOM LAYOUT
PARKING LOT STRIPING LAYOUT
EXISTING AND NEW FACILITY LOCATIONS
Navajo Restroom Stub Up Diagram
Navajo Restroom Pad Diagram
Navajo Restroom Dimensions Drawing
| S P E C I F I C A T I O N S |
| LAKE TEXOMA |
| OKLAHOMA & TEXAS |
| CXT SHOWER BULDING INSTALLATION |
| FOR |
| PRESTON BEND PUA |
| PART 1 – GENERAL |
| PART 2 – PRODUCTS |
| PART 3 - EXECUTION |
| Navajo Restroom Stub Up Diagram |
| Navajo Restroom Pad Diagram |
| Navajo Restroom Dimensions Drawing |