Amend_01_to_16-T-0132.pdf
PDF 67 KB Posted
- Attached to
- Electrical Installation Hawthorn Bluff Oologah Federal contract opportunity
- Solicitation number
- W912BV-16-T-0132
About this file
Amendment to original solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation_16-T-0132.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
ELECTRRICAL IINSTALLATIION FOR HAWTHORN BLUFF OLOOGAH LAKE, OKLAHOMA
This synopsis is being advertised as a small business set-aside. The SF 1442 issue date is 30 July 2016 and proposal are due on 1 September 2016 by 2:00pm. E-mail is the perferred receipt of proposals. The correct w age determination is attached to this amendment.
r
1. CONTRACT ID CODE PAGE OF PAGES
J 1 14
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-Jul-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BV-16-T-0132
X 9B. DATED (SEE ITEM 11)
26-Jul-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-Jul-2016
CODE
CONTRACTING DIV
USACE, TULSA 1645 S 101 E AVE
TULSA OK 74128-4609
W912BV 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912BV-16-T-0132
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 11 00 - SF 1442 AND CLIN SCHEDULE
The following have been modified:
INFORMATION TO OFFERORS
Instructions to Offers
1. OFFEROR’S QUESTIONS AND COMMENTS
Questions and/or comments relative to these documents should be submitted to the Contract Specialist identified below:
Contract Specialist – Primary POC U.S. Army Corps of Engineers, Tulsa District
ATTN: Diane Cianci Phone number: 918-669-7458
Email: diane.cianci@usace.army.mil
Please include the solicitation number, and project title with your questions. Oral explanations or instructions are not binding. Any information given to an offeror which impacts the solicitation and/or offer will be given the form of a written amendment to the solicitation.
2. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS
This Request for Quote (RFQ) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal.
3. SUBMISSION OF OFFERS SUBMITTALS
Submit signed and dated offers to the office and individual specified in this solicitation at or before the exact time specified in this solicitation by electronic means. Electronic/email quotes will be accepted and e-mail is the preferred method of submitting your proposal. Faxed quotes will not be accepted. Do not submit hard copies of your offeror.
HAND DELIVER
If your submission will be hand-carried, please provide notification to the Contract Specialist at least one working day in advance (918-669-4318) or veronica.p.freire@usace.army.mil, as unescorted visitors are not allowed in the Contracting Division offices. Please consider in your arrival that visitors must go through security check points.
Offerors can only submit their documents to the Contract Specialist or a Contracting Officer of the Tulsa District Office. The address of the Tulsa District Office is below:
TULSA DISTRICT CORPS OF ENGINEERS
1645 S. 101ST EAST AVE
TULSA, OK 74128-4609
This procurement is being conducted in accordance with FAR Part 13, Simplified Acquisition Procedures (SAP).
Any reference to offers or bids or offerors or bidders should be substituted with quotations or quoters. All reference to discussions shall not be interpreted under FAR Part 15, but rather indicates that the Government may communicate with quoters as allowed under simplified acquisition procedures.
The point of contact for this solicitation is:
Contract Specialist: Diane M. Cianci Telephone: 918-669-7458 E-MAIL: diane.cianci@usace.army.mil and brian.j.abel@usace.army.mil
Any questions pertaining to past or current contract information for any of the past or current contracts should be submitted to the Office of Counsel, Tulsa District Office in the form of a FOIA (Freedom of Information Act) request. Below is the contact information for the Office of Counsel, Tulsa District.
CESWT-OC
1645 South 101st East Ave
Tulsa, OK 74128-4609 foia-swt@usace.army.mil
Phone: 918-669-7593/7178 Fax: 918-669-7576
Guidance on how to submit a FOIA request can be found at http://www.usace.army.mil/FOIA.aspx. Please ensure your request is submitted in a timely matter to receive feedback before the solicitation closing date.
QUOTE PREPARATION CHECKLIST
DO NOT RETURN THIS CHECKLIST
Important items for you to check are included, but not limited to those listed below. This checklist is furnished only to assist you in submitting a proper quote. Do not return the checklist with your quote.
____ Have you obtained a DUNS number? Provide your Duns number on the first page or cover page.
A duns number can be obtained through the D&B D-U-N-S Request Service at http://fedgov.dnb.com/webform.
____ Have you registered in System For Award Management (SAM)?
The name you use to submit a quote must be the exact name you use to register in SAM. Do not delay returning a quote while processing your SAM entry.
http://www.sam.gov It does not cost to register into SAM.
_____ Have you completed the representations and certifications electronically when registering in SAM?
Complete 52.204-8 and select whether paragraph (d) applies or paragraph (d) does not apply.
If you have NOT filled out Representations & Certifications through http://www.sam.gov or select paragraph (d) does not apply, fill out 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL ITEMS paragraphs (c) through (o) in this solicitation. You can find this in the solicitation under Section K under paragraph 52.212-3. The first question starts out: “(1) Small business concern. The offeror represents as part of its offer that it ( ) is, ( ) is not a small business concern.” The questions cover about 10 pages in length. If anything does not apply write “N/A”.
_____ Is the NAICS code on the solicitation incorporated into your CCR/SAM profile?
This solicitation is being advertised under the North American Industrial Classification Systems (NAICS) Code 334112 (listed in Box 10 on Page 1 of the SF 1449). You must ensure this NAICS Code is incorporated into your current SAM Profile if your company can provide the type of product or service applicable to this NAICS Code. Failure to have this NAICS Code in your current SAM Profile may result in not being considered for award. NAICS Codes may be viewed at the U.S. Census Bureau website at http://www.census.gov/eos/www/naics.
____ Have you entered a unit price for each line item?
The quantity multiplied by the unit price equals the total amount. Ensure all prices on line items are filled in. All line items must be priced to be considered for award. Unit prices must be rounded to the nearest cent (hundredths).
$20.56 IS an acceptable price.
$20.564 IS NOT an acceptable price.
Do not round total amount numbers.
If your price exceeds $2,000 for construction work or $2,500 for services, you will be required to pay employees at least the wage rates specified in the applicable wage decision/determination.
____ NO cross outs or strike through marks. Submit a legible quote with no correction marks.
QUOTE PREPARATION CHECKLIST (CONT)
____ Did you sign the original solicitation?
Ensure to include the first page of the solicitation and fill out block 12, 17a, 30a, 30b, and 30c. A signature of an authorized individual is required for your quote.
____ Have you completed Block 12(on the first page), Discount for Prompt Payment?
A prompt payment discount is the amount your invoice will be discounted if the Government pays your bill early. For example: If your invoice is for $100 and you offer a discount of 1% within 20 days, and the Government pays you within 20 days, your payment would be $99. If this block is empty we will default Net 30 (total net amount paid within 30 days).
____ Have you acknowledged all amendments, if any have been issued?
Acknowledge amendments by signing and dating the first page of the amendment. Ensure to read the amendment to determine if further documents are required to be submitted and to see what changes have been made to the solicitation. Reference the solicitation number in the subject line when submitting.
____ Have you submitted all information to evaluate your offer?
Refer to the Important Information and section M, 52.212-2 Evaluation- Commercial Items. You may need to submit references, relevant work experience or past performance information for the government to evaluate your quote.
____ Have you completed and included Clause 252.209-7994 with your quote?
____ Does your offer have a .pdf file extension if submitting electronically?
____ Have you provided a telephone number you can be reached during the business hours of 8:00 a.m. to 4:30 p.m. CST?
____ Have you considered the amount of labor, equipment, mobilization, and materials needed to perform all the work required by the specifications? Are your figures legible?
_____ Have you allowed enough time to submit your quote before the due date and time?
_____ Do not return every page of the solicitation.
Only return pages that are providing information regarding your quote. If you did not provide any information on a page, do not include this page. Example. If you filled out page 1, 2, 6 and 10 of the solicitation only return pages 1, 2, 6 and 10. You may include a cover page or additional pages that provide information that is requested.
SECTION 00 73 46 - WAGE DETERMINATION SCHEDULE
The following have been added by full text:
REPLACE WAGE RATES
General Decision Number: OK160030 07/01/2016 OK30
Superseded General Decision Number: OK20150030
State: Oklahoma
Construction Type: Heavy
Counties: Creek, Okmulgee, Osage, Pawnee, Rogers and Wagoner Counties in Oklahoma.
HEAVY CONSTRUCTION PROJECTS (including sewer/water line construction; heavy construction projects on treatment plants and industrial sites) (excludes heavy dredging and water well drilling)
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/08/2016 1 07/01/2016
ELEC1002-005 06/28/2015
Rates Fringes
ELECTRICIAN......................$ 33.89 29%+5.00
* ENGI0627-014 06/01/2016
Rates Fringes
POWER EQUIPMENT OPERATOR:
Group 1.....................$ 28.05 12.58 Group 2.....................$ 26.35 12.58 Group 3.....................$ 25.80 12.58 Group 4.....................$ 25.05 12.58 Group 6.....................$ 24.10 12.58 Group10.....................$ 21.10 12.58
POWER EQUIPMENT OPERATOR
GROUP 1: All Crane Type Equipment 200 ton and larger and including 400 ton capacity cranes. All Tower Cranes.
GROUP 2: All Crane Type Equipment 100 ton capacity and larger cranes, and less than 200 ton capacity.
GROUP 3: All Crane Type Equipment 50 ton capacity and larger cranes, and less than 100 ton capacity. Crane Equipment (as rated by mfg.) 3 cu. yd. and over Guy derrick Whirley Power Driven Hole Digger (with 30' and longer mast).
GROUP 4: CRANES with Boom Incl. Jib less than 100 ft and less than 3 cu. Yd.; Overhead Monorail Crane
GROUP 6: ROLLER (ASPHALT AND DIRT)
GROUP 10:OILER
IRON0584-019 06/01/2015
Rates Fringes
IRONWORKER (Structural, Reinforcing, and Ornamental).....$ 24.00 13.53
SUOK2012-008 05/18/2012
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 14.00 3.95
FORM WORKER......................$ 11.77 0.00
LABORER: Common or General......$ 11.78 2.76
LABORER: Pipelayer..............$ 12.94 2.42
OPERATOR: Backhoe/Excavator.....$ 16.62 3.10
OPERATOR: Bulldozer.............$ 17.98 1.75
OPERATOR: Drill.................$ 17.15 0.78
OPERATOR: Grader/Blade..........$ 17.76 3.87
OPERATOR: Loader (Front End)....$ 14.01 0.00
OPERATOR: Mechanic..............$ 19.61 9.39
OPERATOR: Scraper...............$ 16.00 1.55
OPERATOR: Trackhoe..............$ 18.54 2.78
TRUCK DRIVER: Dump Truck........$ 14.64 1.71
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
The following have been deleted:
WAGE RATES
SECTION 01 10 00 - STATEMENT OF WORK
The following have been modified:
STATEMENT OF WORK
SPECIFICATIONS
INSTALLATION OF UNDERGROUND ELECTRIC PRIMARY CABLE
OOLOGAH LAKE, OKLAHOMA
PART 1 – GENERAL
1.1 SCOPE OF WORK
This specification covers requirements for contractor-furnished materials, equipment and labor necessary to install an underground electrical primary cable at Hawthorn Bluff Campground, Oologah Lake located in Rogers County, Oklahoma. Government will supply the primary electric conductor. All materials and installation shall be in accordance with these specifications and drawings in addition to the National Electric Code (NEC). All work shall be accomplished in a safe, workmanlike manner and in accordance with the Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, most current edition, all applicable Federal, State, and local safety codes and practices.
1.2 REFERENCES
National Electric Code – Current Edition EM 385-1-1 – Current Edition All applicable Federal, State and local safety codes, rules and regulations
1.3 BASIS FOR PAYMENT
Lump sum; Imvoices shall be sent to the Oologah Lake Office, Attn: BJ Parkey, 8400 E Hwy 88, Oologah, OK 74053
1.4 WORK HOURS
Regular work hours will be from 8:00 am – 4:30 pm Monday through Friday, excluding federal holidays. Any proposed changes to the work hours must be approved by the project manager.
1.5 COMPLETION TIME
Work shall be fully completed 60 days after award of contract.
1.6 SAFETY REQUIREMENTS
The contractor shall comply with the Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, most current edition, National Electric Code (NEC) all applicable Federal, State, and local safety codes and practices. It is the contractor’s responsibility to insure public safety during the entire duration of the contract. Necessary signs, barriers, warning devices, etc. shall be operated and maintained by the contractor at contractor expense. Contractor employees shall comply with the minimum dress requirements as stated in Chapter 7 of EM 385-1-1.
1.7 EQUIPMENT
All equipment used to perform work under this contract shall be in good operating and mechanical condition and shall comply with Section 18 of EM 385-1-1. Equipment shall be inspected by the contractor and the inspection reports shall be submitted to the project manager prior to utilization of such equipment to accomplish work on this contract.
1.8WEATHER LIMITATIONS
Work shall not be done during adverse weather conditions that would cause damage to Government Property or risk the safety of contract personnel.
1.9 SUBMITTALS
None
1.10 PREWORK CONFERENCE
A pre-work conference will be held with the Lake Manager and contractor prior to the commencement of any work. The contractor’s responsible person and necessary administrative staff will be required to attend this meeting. Procedures for proper invoicing and payment, schedule, etc., will be covered at this time.
1.11 ENVIRONMENTAL CLEANUP
The contractor shall maintain a clean work area at all times. The contractor shall be responsible for the protection of the environment and will be required to restore all damages subject to the approval of the contracting officer. The contractor shall remove and dispose of all debris off Government property in a state approved disposal site unless specified otherwise. The contractor will be required to comply with all Federal and State environmental requirements.
1.12 COORDINATION OF WORK
BJ Parkey - Lake Manager Phone (918) 443-2250 x 5606 Bobby.J.Parkey@usace.army.mil
PART 2 – PRODUCTS
2.1 MATERIALS
All materials shall be new, undamaged and meet or exceed the specifications as detailed in drawings in this scope of work and as required by the National Electric Code, all Federal, State and local building codes.
- Grey Schedule 40 non-metallic conduit that is appropriately sized to accommodate the primary cable.
- Rigid metallic conduit that is appropriately sized to accommodate the primary cable.
- Rigid weather head that is appropriately sized to accommodate the primary cable.
- Metallic detection tape to be installed in the trench.
- Cleaned bedding sand free from foreign debris.
- ODOT Type B Asphalt
- Asphaltic primer bonding agent
2.2 DELIVERY AND STORAGE
Materials shall be delivered to the site undamaged. Materials that are damaged during the delivery, improper storage or improper installation shall be replaced at no cost to the government.
2.3 GOVERNMENT FURNISHED PROPERTY OR MATERIALS
Government will be furnishing electrical primary cable of 1/0, 25kV .260 mil EPR direct burial primary in duct. Cable is a single strand that is 2,294 feet in length and wrapped on a wooden cable spool. There are no splices.
PART 3 - EXECUTION
3.1 ACCOMPLISHMENT OF WORK
This specification covers requirements for contractor-furnished materials, equipment and labor necessary to install an underground electrical primary cable at Hawthorn Bluff Campground, Oologah Lake located in Rogers County, Oklahoma. All materials and installation shall be in accordance with these specifications and drawings in addition to the National Electric Code (NEC).
All work shall be accomplished in a safe, workmanlike manner and in accordance with the Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, most current edition, all applicable Federal, State, and local safety codes and practices. Contractor shall coordinate with the local utility company in order to perform the disconnection of existing primary from the pole to the pad-mount transformer. After installation of the new primary, the contractor shall coordinate with the local utility company in order to connect the new primary to pad-mount transformer and to the primary electrical service. Any electrical repairs and/or connections shall be performed by a State licensed electrician. Any plumbing utility repairs and/or connections shall be performed by a State licensed plumber.
3.2 LOCATING UTILITIES
The contractor shall locate all utilities within the trenching area prior to any ground disturbance. It will be the contractor’s responsibility and expense to make repairs to any utility line that is damaged during the performance of this contract.
3.3 ELECTRICAL CABLE TRANSPORT
The primary cable that is identified in section 2.3 is located in a storage building about ½ mile away from the work site. It will be the contractor’s responsibility to transport this cable to the work site.
3.4 TRENCHING OF CABLE
Trench for new primary cable is approximately 2000 feet in length. It will be the contractor’s responsibility to verify all underground electrical utilities are disconnected and verified as “dead” prior to ANY ground disturbance. Lockout/Tagout procedures shall be in place during all electrical work. During trenching of new electrical primary, the contractor may strike the existing primary cable with their trenching equipment. When this occurs, the contractor shall removal all damaged cabling from the excavation areas and dispose of offsite in accordance with all Federal, State and local laws.
Trench shall be a minimum of 51 inches in depth and a minimum of 4 inches in width. See attached drawing titled “Primary Trench Diagram” for depths of bedding sand, placement of random fill and placement of metallic electrical tape.
Primary electrical cable shall NOT be spliced at any point. A single continuous run shall be made from the utility pole to the pad-mount transformer.
Primary electrical cable shall be ran through PVC electrical non-metallic conduit when underground.
All PVC joints shall be glued and seated firmly to not allow any moisture intrusion.
Care shall be taken when determining the most viable path for the new trench. No mature trees shall be removed to accommodate new primary trench.
At the point where the primary electrical cable makes a 90 degree turn underground and is ran up the utility pole, the cable shall be placed in metallic ridged conduit and terminated with a weather-head connection. The length of this rigid conduit shall be extended the entire length of the utility pole. The primary cable shall have a weather loop installed when connecting back to utility company power.
During trenching, it will be necessary for the contractor to cross asphalt roadways. The contractor will have the discretion to either perform under-road boring that shall not affect the roadway structure or integrity in any way or the contractor may trench across the asphalt roadway and backfill with ODOT Type B asphalt pavement. If trenching the roadway is the preferred method of crossing, the contractor shall place at minimum a 4” thick asphalt patch. A 15” gravel base shall be prepared and compacted to not less than a 95% of maximum density prior to the placement of asphalt. After density compaction is achieved, asphaltic bonding agent shall be applied and new asphalt patch shall be compacted as to prevent any standing water depressions “bird-baths” and match the existing roadway for height.
If crossing a dirt or gravel roadway, the contractor shall compact backfilled material to not less than a 95% of maximum density and match the existing roadway surface elevation. No depression shall be allowed to create a “bird-bath”.
During trenching, if the contractor strikes a water line or secondary electrical line, all repairs shall be made by licensed plumbers or licensed electricians. Repairs shall be verified by USACE personnel PRIOR to backfilling the trench.
3.5 SITE CONDITIONS
It is highly recommended that prospective bidder’s perform a site visit to understand the terrain and soil composition in order to submit a bid proposal. This area is extremely rocky with very little topsoil coverage.
3.6 TESTING
Testing of all electrical systems/circuits and plumbing fixtures shall be performed after installation and verified prior to final acceptance of work.
3.7 WARRANTY
The contractor warrants the materials and installation of materials meets or exceeds the National Electric Code requirements for install.
(End of Summary of Changes)