SPECS-Wister_Expansion_Joint_Seal_Replacement_Specs_W912BV-16-R-0016_dated_6-10-16.pdf

PDF 821 KB Posted

Attached to
INSTALLATION EXPANSION JOINTS WISTER LAKE
Solicitation number
W912BV-16-R-0116
Issued by

About this file

SPECS-Wister Expansion Joint Seal Replacement Specs W912BV-16-R-0016 dated 6-10-16

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. W912BV-16-R-0016

US Army Corps of Engineers Tulsa District Arkansas River Watershed Wister Lake, Oklahoma

Expansion Joint Seal Replacement

Specifications

June 10, 2016 rsl

TABLE OF CONTENTS

SOLICITATION NO. W912BV-16-R-0016

EXPANSION JOINT SEAL REPLACEMENT

WISTER LAKE, OKLAHOMA

MAY 4, 2016

00 01 10-1

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 11 00 SF 1442 AND CLIN SCHEDULE

00 21 00 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

00 22 00 SUBMISSION REQUIREMENTS

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 72 00 CONTRACT CLAUSES

00 73 00 SPECIAL CONTRACT REQUIREMENTS

00 73 46 WAGE DETERMINATION SCHEDULE

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 SUMMARY OF WORK

01 22 00 MEASUREMENT AND PAYMENT

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00 QUALITY CONTROL

01 46 00 QUALITY CONTROL SYSTEM (QCS)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20 ENVIRONMENTAL PROTECTION

01 58 00 BULLETIN BOARD, PROJECT SIGN, AND SAFETY SIGN

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

DIVISION 03 - CONCRETE

03 15 00 EXPANSION JOINT SEAL REPLACEMENT SYSTEM

DIVISION 05 - METALS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

APPENDIX A – PHOTO REPORT

-- End of Project Table of Contents --

Wister Conduit Expansion Joint Seal Replacement FY16 WISTERCNDUITFY16

SECTION 01 00 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 GENERAL PROJECT INFORMATION

This project will be a total turn-key contract with all work being performed by the Contractor. The Contractor shall provide all plant, materials, equipment, labor, instruments, tools, subcontractors, supervision, management, and travel necessary to complete all work in accordance with this summary of work, the attached drawings, the specifications, and all other contract documents and requirements. Where contract documents and criteria appear to be in conflict, the Contractor shall consult the Contracting Officer (CO) or Administrative Contracting Officer (ACO), as applicable, for clarification.

In general, the Contractor shall construct and install expansion joint systems at Wister Lake, Oklahoma. See other contract documents, specifications sections, and drawings for detailed requirements.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1926 Safety and Health Regulations for Construction

1.3 SAFETY

All work shall be performed in accordance with the requirements of EM 385-1-1, 29 CFR 1910, and 29 CFR 1926, latest editions, and all subsequently issued interim changes and errata. Matters of interpretation of the standards shall be submitted to the CO or ACO for resolution before starting work. Where the regulations conflict, the most stringent requirements shall apply. The Government stresses the importance of safety on all U. S. Army Corps of Engineers (USACE) job sites. When safety violations arise, all work shall be stopped immediately and shall not resume until violations are corrected to the exclusive satisfaction of the ACO. Stoppages of work due to safety violations shall not be considered for contract time extensions and the Contractor shall be not be reimbursed for any costs due to these work stoppages.

1.4 PERMIT REQUIRED CONFINED SPACES

All conduits at Wister are permit required confined spaces until proven

SECTION 01 00 00 Page 1 otherwise or made safe to enter by the Contractor.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Traffic Control Plan; G

Traffic Control Plan shall be submitted to and approved by the Administrative Contracting Officer (ACO) and the Oklahoma Department of Transportation (ODOT). The Contractor shall be responsible for direct coordination with ODOT.

Detailed Work Plan; G

A detailed work plan shall be submitted and shall include, as a minimum, details for construction and installation of the expansion joint systems.

1.6 SITE VISIT

An authorized Contractor representative in conjunction with the CO and/or the ACO and technical representatives shall conduct a site visit at the proposed construction site. The Contractor shall provide ten working days advance notice to the CO to arrange and schedule government personnel to meet with the Contractor at the site prior to field data collection. The Contractor shall review all data and information provided by the Government prior to making the site visit. Government personnel shall meet with the Contractor to discuss the scope of work and provide a walk-through of the site. The Contractor shall be responsible for obtaining all required measurements, dimensions, etc. and verifying the data and information provided by the Government. In addition, the Contractor shall collect all information necessary to provide the Work Plan that details all construction activities. All Contractor personnel shall bring and properly use personal protective equipment (hard hat, eye protection, flashlight, rubber boots, and/or hip waders) in order to enter the conduits/work sites. No exceptions to this requirement will be granted.

1.7 VERIFICATION OF SITE CONDITIONS

The Contractor shall be responsible for verifying the accuracy of all drawings and existing site conditions. The Contractor shall review the existing documents pertaining to the site and shall visit the site and vicinity to evaluate observable existing conditions. The Contractor shall obtain all required information, measurements, dimensions, etc. necessary to field verify all existing conditions and dimensions and provide the specified Detailed Work Plan and other required submittal information. If there are existing conditions that appear to affect the proposed construction or are different from the contract documents, the Contractor shall inform the CO in writing before proceeding with any construction processes, including ordering materials. Work outside the original scope shall be accomplished only at the direction of the Contracting Officer through subsequent contract modifications.

SECTION 01 00 00 Page 2

The Contractor shall photograph the site and structures in connection with the project to portray the initial conditions affecting the Work Plan. One copy of all pictures taken shall be furnished to the CO with the Work Plan before any on site work will be allowed to begin. Photographs shall include 5"x7" hard copies on photograph quality paper and digital files on CD with a minimum resolution of 5 megapixels each.

1.8 RESERVOIR INFORMATION AND HISTORICAL DATA

Wister Lake reservoir and pool information may be viewed at http://www.swt-wc.usace.army.mil/WIST.lakepage.html/. Any conclusions drawn by the Contractor from this data are done so at the Contractor's risk.

1.9 LAKE DRAWDOWN

The reservoir and pool will not be drawn down or otherwise altered to accommodate work under this contract.

1.10 WATER RELEASES

The Government's normal operations of facilities will not be altered or compromised to accommodate any work under this contract. Normally, the Government will give 24 hours advance notice to the Contractor when water releases and/or gate changes are made. In flood release emergencies, 24 hours notification of flow increases and gate changes may not be possible.

The Contractor's superintendent shall be the point of contact and shall be accessible to communications from the Government at all times for notification of gate changes by the Government.

The Contractor shall develop a plan to remove all construction equipment in less than 24 hours. The Contractor shall constantly monitor weather conditions and forecasts and be prepared for potential emergency conditions. The Contractor shall be constantly prepared to secure and protect personnel, equipment, and work areas from flood releases.

1.11 EQUIPMENT HANDLING CAUSED BY EMERGENCY CONDITIONS & FLOOD CONTROL

If the Contractor is directed to remove construction equipment because of high water, flood control, or other emergency operation not otherwise required for the normal execution of the work as shown and specified, an equitable adjustment in the contract price will be made in accordance with the paragraph "CHANGES" for the contract.

1.12 GOVERNMENT FURNISHED UTILITIES

None.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 WORK SCHEDULE

Work hours shall be 7 a.m. to 6:00 p.m. Monday through Friday unless requested otherwise in writing by the Contractor and approved in writing by the ACO.

SECTION 01 00 00 Page 3

3.2 UTILITY OUTAGE COORDINATION

3.2.1 Approval

The Contractor shall obtain written permission/approval from the ACO 21 days prior to performing any work which will close any street or interrupt any utility service. The proposed outage request shall indicate the proposed work and length of outage.

3.2.2 Government Right to Delay

The Government reserves the right to postpone for seven days any scheduled outages. There shall be no outages when the outside temperature is expected to be below 35 degrees F.

3.2.3 Government Performance

Government personnel shall perform all shutting off and turning on of valves and switches necessary to accomplish scheduled outage.

3.3 DEWATERING/CONTROL OF WATER

The Contractor shall be fully responsible for dewatering the conduits and continuous control of water through the life of this contract in order to perform the work and meet quality control requirements. Other than setting the emergency gates, the Government will not assist in dewatering/control of water. The Contractor shall given the Government 72 hours advance notice for the Government to set the emergency gates.

3.4 LEAKAGE OF EXISTING GATES AND STRUCTURES

The Contractor is advised that a significant amount of water may leak through the Wister Lake expansion joints after the existing seals are removed. The Contractor is also advised the existing service/emergency gates leak varying amounts of water at varying times and will cause difficulty in completing the work in this contract. Leakage at Wister Lake is approximately 100 gallons per minute at normal conservation pool elevation of 478.0. Leakage at Wister Lake will cause the Contractor to expend significant effort to control the leakage.

3.5 REMOVAL OF EQUIPMENT/SHUTDOWN DUE TO WATER RELEASES

Water releases may impact the Contractor's operations. Releases will be made as necessary to perform flood control, water quality, water supply, and all other authorized project purposes. No project purposes will be altered or compromised to accommodate any work under this contract. The Government will give 24 hours advance notice to the Contractor when water releases and/or gate changes are made.

Flood releases will be made as required for flood damage reduction. The Contractor shall develop a flood release plan to remove all construction equipment, scaffolding, machinery, etc. within 24 hours and re-assemble all gate hoist equipment and facilities in order for the Government to operate the gates and outlet works for flood damage reduction purposes. The Contractor shall implement the flood release plan upon direction of the ACO. Costs to implement the flood release plan shall be as addressed in the Changes Clause of the contract.

The Contractor's on-site superintendent shall be accessible to

SECTION 01 00 00 Page 4 communications from the Government at all times and will be notified of gate changes by the Government. In flood release emergencies, every effort will be made to give the Contractor a minimum of 24 hours notification of gate changes. The Contractor shall constantly monitor weather conditions and forecasts and be prepared for potential emergency conditions. The Contractor shall be continuously prepared to move, secure, and protect work areas, marine plant, equipment, and personnel from flood releases.

3.6 VENTILATION AND CONFINED SPACE

Providing adequate ventilation and conforming with all applicable permit required confined space requirements shall be the Contractor's responsibility.

3.7 PROTECTION OF GOVERNMENT PROPERTY

The Contractor shall take all measures necessary for protection of the existing structures, grounds, concrete surfaces, equipment, and machinery.

Any damage caused by the negligence of the Contractor shall be repaired with new materials at no additional cost to the Government. The Contractor shall not drill holes or otherwise alter or deface any existing structure unless requested in writing with proposed repair methods and approved in writing by the ACO.

3.8 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the ACO. Submit a view location sketch indicating points of view. Submit with the monthly invoice two sets of digital photographs each set on a separate CD-R, cumulative of all photos to date. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch. The view location sketch shall also be provided on the CD as digital file. All file names shall include a date designator. Cross reference submittals in the appropriate daily report.

Photographs shall be provided for unrestricted use by the Government.

3.9 CLEAN UP

After completion of construction, the Contractor shall clean all Contractor-generated blast media and construction debris from Government property. The Contractor shall ensure that all drain holes are completely open.

-- End of Section --

SECTION 01 00 00 Page 5

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

Payment items for all work in this contract for which payments will be made are listed on the PROPOSAL SCHEDULE and described below. All costs for items of work which are not specifically mentioned to be included in a particular payment item price shall be included in the listed payment item price most closely associated with the work involved.

Payment for the items listed below shall constitute full compensation for furnishing all plant, materials, equipment, labor, instruments, tools, subcontractors, supervision, and management and performing all associated Contractor quality control, environmental protection, safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1 EXPANSION JOINT SYSTEM

MEASUREMENT

Work pertaining to the expansion joint system shall not be separately measured.

PAYMENT

Payment for the expansion joint system will be made at the contract job price for the items "Expansion Joint System - Left Upstream Joint", "Expansion Joint System - Right Upstream Joint", "Expansion Joint System - Left Downstream Joint", and "Expansion Joint System - Right Downstream Joint", as applicable, which prices shall be full compensation for furnishing all plant, materials, equipment, labor, instruments, tools, subcontractors, supervision, and management required to perform all work as required in the contract documents

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

SECTION 01 22 00 Page 1

SECTION 01 32 01

PROJECT SCHEDULE

PART 1 GENERAL

Project schedule shall be in accordance with the contract clause SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984) in Section 00 72 00 - CONTRACT

CLAUSES.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

SECTION 01 32 01 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates of insurance Surety bonds List of proposed Subcontractors List of proposed products Construction progress schedule Submittal register Health and safety plan

SECTION 01 33 00 Page 1

Work plan Quality Control(QC) plan Environmental protection plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

SECTION 01 33 00 Page 2

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

Interim "DD Form 1354" with cost breakout for all assets 30 days prior to facility turnover.

1.2.2 Approving Authority

Office or designated person authorized to approve submittal.

1.2.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G

SECTION 01 33 00 Page 3

1.4 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.4.1 Government Approved G

Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.

Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings."

1.4.2 Information Only

Submittals not requiring Government approval will be for information only.They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.5 PREPARATION

1.5.1 Transmittal Form

Use transmittal form ENG Form 4025 for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms are included in the QCS software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.6 QUANTITY OF SUBMITTALS

1.6.1 Number of Copies of SD-02 Shop Drawings

Submit six copies of submittals of shop drawings requiring review and approval only by QC organization and seven copies of shop drawings requiring review and approval by Contracting Officer.

1.6.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions

Submit in compliance with quantity requirements specified for shop drawings.

1.6.3 Number of Samples SD-04 Samples

a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.

b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.

c. Submit one sample installation, where directed.

d. Submit one sample of non-solid materials.

SECTION 01 33 00 Page 4

1.6.4 Number of Copies SD-05 Design Data and SD-07 Certificates

Submit in compliance with quantity requirements specified for shop drawings.

1.6.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports

Submit in compliance with quantity and quality requirements specified for shop drawings other than field test results that will be submitted with QC reports.

1.6.6 Number of Copies of SD-10 Operation and Maintenance Data

Submit five copies of O&M Data to the Contracting Officer for review and approval.

1.6.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals

Unless otherwise specified, submit three sets of administrative submittals.

1.7 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.

The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;

and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.8 VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.

1.8.1 Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

1.8.2 Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the

SECTION 01 33 00 Page 5

DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.

Clearly mark the proposed variation in all documentation.

Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.

The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

1.8.3 Warranting That Variations Are Compatible

When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.8.4 Review Schedule Is Modified

In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.

1.9 SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and

(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 46 00 QUALITY CONTROL SYSTEM (QCS). The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.

Column (c): Lists specification section in which submittal is required.

Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.

Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.

Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.

1.9.1 Use of Submittal Register

Submit submittal register. Submit with QC plan and project schedule.

Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:

SECTION 01 33 00 Page 6

Column (a) Activity Number: Activity number from the project schedule.

Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.

Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.

Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.

1.9.2 Contractor Use of Submittal Register

Update the following fields with each submittal throughout contract.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.

Column (l) List date of submittal transmission.

Column (q) List date approval received.

1.9.3 Approving Authority Use of Submittal Register

Update the following fields.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (l) List date of submittal receipt.

Column (m) through (p) List Date related to review actions.

Column (q) List date returned to Contractor.

1.9.4 Copies Delivered to the Government

Deliver one copy of submittal register updated by Contractor to Government with each invoice request.

1.10 SCHEDULING

Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals. An additional 10 calendar days will be allowed and shown on the register for review and approval of submittals for HVAC control systems.

a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.

b. Submittals called for by the contract documents will be listed on the

SECTION 01 33 00 Page 7 register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."

c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.

d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."

1.11 GOVERNMENT APPROVING AUTHORITY

When approving authority is Contracting Officer, the Government will:

a. Note date on which submittal was received.

b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

c. Identify returned submittals with one of the actions defined in paragraph entitled, "Review Notations," of this section and with markings appropriate for action indicated.

Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. Five copies of the approved submittal will be retained by the Contracting Officer and one copy of the submittal will be returned to the Contractor. If the Government performs a conformance review of other Designer of Record approved submittals, the submittals will be so identified and returned, as described above.

1.11.1 Review Notations

Contracting Officer review will be completed within 30 calendar days after receipt of submittal by the Government. Submittals will be returned to the Contractor with the following notations:

a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.

b. Submittals marked "approved as noted" "or approved except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.

c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.

d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an

SECTION 01 33 00 Page 8 explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.

1.12 DISAPPROVED SUBMITTALS

Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.

Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.13 APPROVED SUBMITTALS

The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory.

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work.

After submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.14 APPROVED SAMPLES

Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.

Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those which may be damaged in testing, will be returned to the Contractor, at his expense, upon completion of the contract. Samples not approved will also be returned to the Contractor at its expense, if so requested.

Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.

SECTION 01 33 00 Page 9

Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals.

Contractor to replace such materials or equipment to meet contract requirements.

Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract.

1.15 WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained.

1.16 STAMPS

Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements is to be similar to the following:

SECTION 01 33 00 Page 10

| CONTRACTOR |

| (Firm Name) | | _____ Approved | | _____ Approved with corrections as noted on submittal data and/or | | attached sheets(s) |

| SIGNATURE: __________________________________________________________ |

| TITLE: ______________________________________________________________ |

| DATE: _______________________________________________________________ |

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 33 00 Page 11

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 3 PAGES

RFP

Wister Conduit Expansion Joint Seal Replacement FY16

01 00 00 SD-01 Preconstruction Submittals GTraffic Control Plan;

GDetailed Work Plan;

01 33 00 SD-01 Preconstruction Submittals

1.9 GSubmittal Register

01 35 26 SD-01 Preconstruction Submittals

1.5 GAccident Prevention Plan (APP)

1.6 GActivity Hazard Analysis (AHA)

1.5.1 GCrane Critical Lift Plan

1.4.1.2 GCrane Operators

SD-06 Test Reports 1.10Notifications and Reports

1.10.2 GAccident Reports

1.10.3Crane Reports

SD-07 Certificates 1.7Confined Space Entry Permit 1.7Hot work permit 1.12License Certificates

01 45 00 SD-01 Preconstruction Submittals

3.2 GContractor Quality Control (CQC)

Plan SD-06 Test Reports

3.9Verification Statement 01 50 00 SD-01 Preconstruction Submittals

1.3 GConstruction Site Plan

01 57 20 SD-01 Preconstruction Submittals

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 3 PAGES

Wister Conduit Expansion Joint Seal Replacement FY16

01 57 20 1.7 GEnvironmental Protection Plan 01 78 00 SD-03 Product Data

GAs-Built Record of Equipment and Materials

GSpare Parts Data SD-11 Closeout Submittals

1.3.1 GRecord (As-Built) Drawings

02 41 00 SD-01 Preconstruction Submittals

1.9 G EC-DExisting Conditions

SD-07 Certificates

1.2.1 G EC-DDemolition Plan

GNotification

SD-11 Closeout Submittals GReceipts

03 15 00 SD-02 Shop Drawings G EC-DSeals and Sealant Systems

SD-03 Product Data G EC-DPreformed Expansion Joint Filler G EC-DExpansion Joint Seals G EC-DAdhesives and Epoxys

SD-04 Samples G EC-DLubricant for Preformed

Compression Seals G EC-DSplicing Compression Seals G EC-DCompression Seals G EC-DExpansion Joint Filler Sealant

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 3 PAGES

Wister Conduit Expansion Joint Seal Replacement FY16

03 15 00 G EC-DInjection Packers SD-07 Certificates Preformed Expansion Joint Filler

EC-DC

G EC-DSealant 05 50 13 SD-02 Shop Drawings

G EC-DWork Plan G EC-DExpansion joint covers

SD-03 Product Data G EC-DExpansion joint covers

Anchors and Fasteners

EC-DC

SD-04 Samples G EC-DExpansion joint covers G EC-DAnchors and Fasteners

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SECTION 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)

ASSE/SAFE A10.32 (2012) Fall Protection

ASSE/SAFE A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites

ASSE/SAFE Z359.1 (2007) Safety Requirements for Personal Fall Arrest Systems, Subsystems and Components

ASME INTERNATIONAL (ASME)

ASME B30.22 (2010) Articulating Boom Cranes

ASME B30.3 (2012) Tower Cranes

ASME B30.5 (2014) Mobile and Locomotive Cranes

ASME B30.8 (2010) Floating Cranes and Floating Derricks

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2013) Standard for Portable Fire Extinguishers

NFPA 51B (2014) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work

NFPA 70E (2015; ERTA 1 2015) Standard for Electrical Safety in the Workplace

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

10 CFR 20 Standards for Protection Against Radiation

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.146 Permit-required Confined Spaces

SECTION 01 35 26 Page 1

29 CFR 1926 Safety and Health Regulations for Construction

29 CFR 1926.1400 Cranes and Derricks in Construction

29 CFR 1926.16 Rules of Construction

29 CFR 1926.500 Fall Protection

CPL 2.100 (1995) Application of the Permit-Required Confined Spaces (PRCS) Standards, 29 CFR 1910.146

1.2 DEFINITIONS

a. High Visibility Accident. Any mishap which may generate publicity or high visibility.

b. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.

c. Recordable Injuries or Illnesses. Any work-related injury or illness that results in:

(1) Death, regardless of the time between the injury and death, or the length of the illness;

(2) Days away from work (any time lost after day of injury/illness onset);

(3) Restricted work;

(4) Transfer to another job;

(5) Medical treatment beyond first aid;

(6) Loss of consciousness; or

(7) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in

(1) through (6) above.

d. "USACE" property and equipment specified in USACE EM 385-1-1 should be interpreted as Government property and equipment.

e. Weight Handling Equipment (WHE) Accident. A WHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment; two-blocking; overload;

or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in

SECTION 01 35 26 Page 2 damage to other components (e.g., dropped boom, dropped load, roll over, etc.) Any mishap meeting the criteria described above shall be documented in both the Contractor Significant Incident Report (CSIR) submitted within five days both as provided by the Contracting Officer.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Accident Prevention Plan (APP); G

Activity Hazard Analysis (AHA); G

Crane Critical Lift Plan; G

Proof of qualification for Crane Operators; G

SD-06 Test Reports

Notifications and Reports

Submit reports as their incidence occurs, in accordance with the requirements of the paragraph, "Notifications and Reports."

Accident Reports; G

Crane Reports

SD-07 Certificates

Confined Space Entry Permit

Hot work permit

License Certificates

1.4 SITE QUALIFICATIONS, DUTIES AND MEETINGS

1.4.1 Personnel Qualifications

1.4.1.1 Site Safety and Health Officer (SSHO)

The SSHO must meet the requirements of EM 385-1-1 section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one (1) person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/alternate shall be at the work site at all times to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.

SECTION 01 35 26 Page 3

A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the the Contracting Officer for acceptance in consultation with the Safety Office.

1.4.1.1.1 Contractor Quality Control (QC) Person:

The Contractor Quality Control Person cannot be the SSHO on this project, even though the QC has safety inspection responsibilities as part of the QC duties.

1.4.1.2 Crane Operators

Meet the crane operators requirements in USACE EM 385-1-1, Section 16 and Appendix I. In addition, for mobile cranes with Original Equipment Manufacturer (OEM) rated capacitates of 50,000 pounds or greater, designate crane operators as qualified by a source that qualifies crane operators (i.e., union, a government agency, or an organization that tests and qualifies crane operators). Provide proof of current qualification.

1.4.2 Personnel Duties

1.4.2.1 Site Safety and Health Officer (SSHO)

The SSHO shall:

a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily quality control report.

b. Conduct mishap investigations and complete required reports. Maintain the OSHA Form 300 and Daily Production reports for prime and sub-contractors.

c. Maintain applicable safety reference material on the job site.

d. Attend the pre-construction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings.

e. Implement and enforce accepted APPS and AHAs.

f. Maintain a safety and health deficiency tracking system that monitors outstanding deficiencies until resolution. Post a list of unresolved safety and health deficiencies on the safety bulletin board.

g. Ensure sub-contractor compliance with safety and health requirements.

h. Maintain a list of hazardous chemicals on site and their material safety data sheets.

Failure to perform the above duties will result in dismissal of the superintendent, QC Manager, and/or SSHO, and a project work stoppage.

This is the start of the file's text. The full file is on GovTribe.