This file is an Industry Day presentation for the Cape May Delaware Avenue Revetment project, a Section 14 Continuing Authority Program (CAP) shoreline erosion protection initiative conducted by the U.S. Army Corps of Engineers, Philadelphia District. The presentation was delivered on September 2, 2026, to solicit feedback from potential contractors on project scope and requirements prior to formal solicitation.

The project involves constructing a firm fixed-price construction contract valued between $5-15 million with a 165-calendar-day period of performance to address severe, ongoing shoreline erosion along Delaware Avenue in Cape May, New Jersey. The primary objective is to protect the county-owned roadway, which serves as the critical supply route for the USCG Training Center and local residential buildings, and to safeguard an 8-inch underground sanitary sewer force main that was previously exposed during hurricanes. The scope includes removal and relocation of approximately 1,000 cubic yards of existing riprap, excavation and disposal of 5,900 cubic yards of excess soil, placement of 13,700 tons of R-7 riprap, 3,800 cubic yards of imported sand fill, geotextile and soil stabilization mat placement totaling 14,400 square yards, and installation of 6,250 square yards of Spartina Alterniflora plantings. The formal Invitation for Bid (IFB) under FAR Part 14 procedures is anticipated to issue on October 30, 2026, with contract award anticipated by February 10, 2027. Key stakeholders include the City of Cape May (utility owner/operator), Cape May County (road owner), and the USCG (utility customer). Written questions and comments were requested by September 10, 2026, submitted electronically to Contract Specialist Molly Gallagher.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cape may Delaware ave

CAPE MAY, NJ

Industry Day

SEPTEMBER 2, 2026

Nick Cosenza Project Manager Planning Division

Connor Struckmeyer Contracting Officer Contracting Division

Molly Gallagher Contract Specialist Contracting Division

Cheryl Keiser Design Manager Engineering and Construction Division

Scott Sanderson Chief, Planning Division

Introductions Cape May Delaware Ave Overview Scope Review Meeting Agenda

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

CONTRACTING’S BRIEFING

The Government assumes no responsibility for any conclusions or interpretations made by the prospective Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of any contract, unless that understanding or representation is expressly stated in a contract.

The information in these slides are subject to change prior to Solicitation.

Firm Fixed-Price Construction Contract

Disclosure of Magnitude of the Proposed Construction Project: Between $5-15M

Total Period of Performance: 165 Calendar Days

Anticipated Solicitation issuance : 30 October 2026

Anticipated Award by 10 February 2027

Invitation for Bid (IFB); FAR Part 14 procedures

Slides and Attendance listed to be published on SAM.gov

Comments and questions are encouraged, but we also ask they are submitted electronically via email to Contract Specialist, Molly Gallagher at Molly.Gallagher@usace.army.mil no later than close of business on 10 September 2026.

During the Solicitation period, there will be another Request for Information (RFI) period.

Project authorization Authority to design and implement this Continuing Authority Program (CAP) project is provided under Section 14 of the 1946 Flood Control Act (33 U.S.C. 701r), as amended. The purpose of the Section 14 authority is to protect public works and non-profit public facilities from streambank and shoreline erosion. Federal funding for each Section 14 project is limited to $15,000,000 (as amended by Section 1030 of the Water Resources Reform and Development Act of 2014, P.L. 113-121).

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

Cape may Delaware ave OVERVIEW North Jetty

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

TRAFFIC CONTROL AND DETOUR PLAN

Cape may Delaware ave OVERVIEW North Jetty

CAPE MAY DELAWARE AVE

GEOTECHNICAL DATA

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

Subsurface exploration

Five Hand Augers to 5 feet Two SPT Borings and Five CPT Soundings to 76 feet

Subsurface profile

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

PROJECT OVERVIEW / STAGING & ACCESS

PERMANENT STAGING AREA

TEMPORARYSTAGING AREA

EASTBOUND LANE OF DELAWARE AVENUE MUST REMAIN OPEN

PROJECT OVERVIEW

Focus AreaKey Details
Primary ObjectiveAddress severe, ongoing shoreline erosion along Delaware Avenue (City of Cape May, NJ).
Roadway & AccessProtect Delaware Ave (county-owned), the primary supply route for the USCG Training Center and local residential buildings.
Utility VulnerabilitySafeguard a shallow, 8-inch underground sewer force main previously exposed by historic storms (e.g., Hurricane Sandy).
Operational ImpactMaintain critical sewer operations for ~75 multi-family residential buildings and ~50 USCG facilities.
Key StakeholdersCity of Cape May (Utility Owner/Operator), Cape May County (Road Owner), and USCG (Utility Customer).

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

EXISTING CONDITIONS AND DEMOLITION

WETLANDS TO BE PROTECTED

Existing conditions and demolition

Plan – station 0+00 to station 6+00

Plan – station 6+00 to station 13+27

Plan –station 13+27 to station 20+54

Plan –station 20+54 to station 26+77

TYPICAL SECTION

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

Nature center access ramp

R-7 RIPRAP

SAND FILL

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

Plantings – station 0+00 to station 13+27

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

Plantings – station 13+27 to station 26+77

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

Cape May Delaware AVE

Scope of Work SummaryEstimated Quantity
Removal and relocation of existing riprap1,000± CY
Removal and satisfactory disposal of debris3,630± Tons
Excavation and satisfactory disposal of excess soil5,900± CY
Geotextile Placement11,800± SY
R-7 Riprap Placement13,700± Tons
Imported Sand Fill Placement3,800± CY
Soil Stabilization Mat Placement2,600± SY
Spartina Alterniflora Placement6,250± SY

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

DISCLAIMER: Information discussed today is subject to change prior to Solicitation.

CONTACT INFORMATION

Please contact Molly Gallagher with any questions: molly.gallagher@usace.army.mil

This is a Special Notice and is for planning purposes only as defined by FAR 15.201. This is not a solicitation announcement, nor is it an Invitation for Bid (IFB), Request for Proposal (RFP), or Request for Quote (RFQ). No solicitation is currently published. Participation in this conference by any party does not obligate the Government in any contract award. The Government will not pay for the provision of any information, nor will it compensate any respondents for the development of such information. The Government is not responsible for any costs associated with reviewing the Draft Documents, preparing and submitting comments, or any other efforts towards participation in this conference. Furthermore, the Government is not obligated to compensate respondents for any information received, even if the Draft Documents are revised as a result of a respondent’s comment or question. Respondents should refrain from providing proprietary information in the course of the conference, since any information acquired by the Government in this forum will not be treated as proprietary. The information gathered will be used by the Government to make appropriate acquisition decisions. Replies to responses, comments, or suggestions will not be provided or published.

Closing image4.png image8.png image9.png image10.png image11.png image12.png image13.png image14.png

Block

- 1193 Lot - 1

- 1194 Lot - 3

Lot - 13

Block -

Lot - 2

- 1204

Lot - 15

Block - 1195

Block - 1206

Lot - 1.01

Block - 1206

Lot - 23

Lot - 24

Lot - 20

Lot - 21

Lot - 16

- 1183

Lot - 17

Lot - 18

Lot - 19

Block - 1205 Lot

- 1

- 1184

Lot - 9

Lot - 8Block -

Lot - 7

Block - 1216

Block - 1217 Lot - 1.02

Block - 1195 Lot

- 1.01

Lot - 14

Lot - 12

Lot - 11

Lot - 10

Lot - 22

Lot - 6

Block - 1184

Lot - 5

Lot - 4

- 1160

Lot - 90

Pennsylvania Ave

Delaware Ave

Chicago Ave

Brooklyn Ave

Wilmington Ave

Cape May New Jersey - Delaware Avenue Section 14 - Emergency Shoreline Erosion Protection

0 150 300 450 600 Feet

³ Notes:

1 - All wetlands are coastal wetlands.

No freshwater wetlands are located on the project site.

2 - Sand will be placed around the existing wetlands to avoid impacts

Impacts to Existing Coastal Wetlands

Document Path: E:\Planning_Projects2\Cape_May\MXD\CM_Map1_Wetlands_Impacts.mxd

¬«A

¬«1

Project Limits

Existing Coastal Wetlands

Project Sand Fill Area

Riprap Area Wetlands Impacted By Excavation and Rip-Rap Placement Wetlands from NJDEP 2012 LULC Wetlands Parcels

¬«2

¬«A Impacted Wetlands By

Area in Feet - 3,862 sq ft Area in Acres - 0.1 ac

Excavation and Rip-Rap Placement image15.emf image16.png image17.emf image18.png image19.png image20.png image21.png image22.png image23.png image24.png image25.png image26.png image27.png image28.png image29.png image30.png image31.png image32.png image33.png image34.png image35.png image1.png image2.png image3.png image7.png

File details come from the government source that posted it. Updated .