C04 - Abstract of Offers - W912BU26BA002 Franklin Slag - 10 FEB 2026.xlsx
XLSX spreadsheet 30 KB Posted
- Attached to
- Franklin Slag Pile Superfund Remediation Project
- Solicitation number
- W912BU26BA002
About this file
This is an Abstract of Offers document for a firm fixed-price construction contract to remediate the Franklin Slag Pile Superfund Site located at the northeast corner of Castor and Delaware Avenues in Philadelphia, PA. The solicitation (W912BU26BA002) was issued on November 13, 2025, by the U.S. Army Corps of Engineers, Philadelphia District, with an offer opening date of February 5, 2026. Four offers were received, all acknowledging four amendments to the solicitation. The Independent Government Estimate (IGE) totaled $58,647,529.50, with actual bids ranging from $17,977,777.00 (Sevenson Environmental, 69.35% below IGE) to $38,891,797.74 (EQM Services, 33.69% below IGE). The other two offerors were Lucianos Excavation Inc. ($24,320,533.07, 58.53% below IGE) and Cape Environmental ($22,150,875.00, 62.23% below IGE).
The contract work comprises 22 line items covering environmental remediation activities including general conditions, environmental protection, site security, workplan development, traffic control, air monitoring, clearing and grubbing, selective demolition, benchscale testing, stabilization of 61,500 cubic yards of slag materials at unit prices ranging from $51.48 to $321.02 per cubic yard, excavation of 8,500 cubic yards of native soils, reprocessing of 2,000 cubic yards of slag, waste loadout and transportation of 120,000 tons, closeable liner bags, waste classification analytical testing (260 samples), supplemental TCLP lead analytical testing (35 samples), metals and chemicals of concern sampling and analytical work (225 samples), geotextile installation, fill materials (13,000 cubic yards), aggregate cover (6,000 cubic yards), groundwater monitoring, and final disposal of 120,000 tons of material. The contracting officer is Brandon R. Mormello.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Abstract of Offers
| ABSTRACT OF OFFERS - CONSTRUCTION |
| ISSUING OFFICE: |
US Army Corps of Engineers, Philadelphia, PA 1650 Arch Street Philadelphia, PA 19107-3390 NAME & TITLE OF CERTIFYING OFFICIAL:
Brandon R. Mormello
| Contracting Officer | I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. | SIGNATURE: | |
| PROJECT TITLE: Franklin Slag Pile Superfund Remediation Project | |||
| SOLICITATION NO.: W912BU26BA002 | |||
| DATE ISSUED: 13 NOV 2025 | |||
| DATE OPENED: 05 FEB 2026 | |||
| NO. OF AMENDMENTS: 4 |
| IGE | OFFEROR NO. 1 | OFFEROR NO. 2 | OFFEROR NO. 3 | OFFEROR NO. 4 |
| Independent Government Estimate | Name: LUCIANOS EXCAVATION INC | Name: CAPE ENVIRONMENTAL | Name: EQM SERVICES, LLC | Name: SEVENSON ENVIRONMENTAL |
| Address: 41 Taunton Green Suite 102 | Address: 500 Pinnacle Ct #100 | Address: 1800 Carillon Blvd. | Address: 2749 Lockport Road | |
| Address: Taunton, MA 02780 | Address: Norcross, GA 30071 | Address: Cincinnati, OH 45240-2788 | Address: Niagara Falls, NY 14305 | |
| UEI/CAGE: KMKAHKFB79M3 / 6NNB5 | UEI/CAGE: GG88Z283HTH3 / 0JAF5 | UEI/CAGE: YZCLNX5DTCM4 / 8B4V6 | UEI/CAGE: VHPJR3MJWV49 / 0LT07 | |
| AMENDMENT(S) ACKNOWLEDGED: YES | AMENDMENT(S) ACKNOWLEDGED: YES | AMENDMENT(S) ACKNOWLEDGED: YES | AMENDMENT(S) ACKNOWLEDGED: YES |
| ITEM NO. | DESCIPTION OF OFFERED ITEM | ESTIMATED QUANTITY | UNIT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT |
| 0001 | General Conditions | 1 | Job | LS | $5,425,691.00 | LS | $1,200,000.00 | LS | $3,416,866.54 | LS | $5,100,197.13 | LS | $1,604,790.00 |
| 0002 | Environmental Protection | 1 | Job | LS | $725,873.00 | LS | $300,000.00 | LS | $5,309.38 | LS | $870,897.78 | LS | $102,157.00 |
| 0003 | Site Security | 1 | Job | LS | $1,444,234.00 | LS | $100,000.00 | LS | $50,213.13 | LS | $521,562.84 | LS | $59,874.00 |
| 0004 | Workplan Development | 1 | Job | LS | $216,867.00 | LS | $125,000.00 | LS | $107,816.39 | LS | $69,367.34 | LS | $144,845.00 |
| 0005 | Maintenance and Protection of Traffic | 1 | Job | LS | $817,871.00 | LS | $133,000.00 | LS | $196,458.04 | LS | $1,474,826.73 | LS | $120,015.00 |
| 0006 | Perimeter Air Monitoring | 1 | Job | LS | $413,163.00 | LS | $400,000.00 | LS | $193,933.04 | LS | $1,014,001.62 | LS | $177,351.00 |
| 0007 | Clearing and Grubbing | 1 | Job | LS | $82,400.00 | LS | $125,000.00 | LS | $5,611.12 | LS | $216,124.55 | LS | $33,629.00 |
| 0008 | Selective Demolition | 1 | Job | LS | $415,588.00 | LS | $125,000.00 | LS | $5,611.12 | LS | $90,431.42 | LS | $16,649.00 |
| 0009 | Benchscale and Demonstration | 1 | Job | LS | $47,119.00 | LS | $1,200,000.00 | LS | $214,950.02 | LS | $315,100.40 | LS | $42,300.00 |
| 0010 | Stabilization of Slag Materials | 61,500 | Cubic Yard | $321.02 | $19,742,730.00 | $55.00 | $3,382,500.00 | $95.82 | $5,892,930.00 | $149.01 | $9,164,115.00 | $51.48 | $3,166,020.00 |
| 0011 | Excavation of Native Soils | 8,500 | Cubic Yard | $252.45 | $2,145,825.00 | $30.00 | $255,000.00 | $10.56 | $89,760.00 | $75.36 | $640,560.00 | $20.52 | $174,420.00 |
| 0012 | Reprocessing of Slag Materials | 2,000 | Cubic Yard | $425.35 | $850,700.00 | $65.00 | $130,000.00 | $31.01 | $62,020.00 | $111.41 | $222,820.00 | $27.67 | $55,340.00 |
| 0013 | Waste Loadout and Transportation | 120,000 | Actual Tons | $92.40 | $11,088,000.00 | $35.00 | $4,200,000.00 | $34.79 | $4,174,800.00 | $48.64 | $5,836,800.00 | $24.74 | $2,968,800.00 |
| 0014 | Closeable Liner Bags | 5,750 | Each | $137.00 | $787,750.00 | $30.00 | $172,500.00 | $94.80 | $545,100.00 | $349.25 | $2,008,187.50 | $125.90 | $723,925.00 |
| 0015 | Waste Classification Analytical | 260 | Each | $3,807.30 | $989,898.00 | $1,300.00 | $338,000.00 | $1,511.46 | $392,979.60 | $3,409.35 | $886,431.00 | $1,424.00 | $370,240.00 |
| 0016 | Supplemental TCLP Lead Analytical | 35 | Each | $25,894.00 | $906,290.00 | $275.00 | $9,625.00 | $114.26 | $3,999.10 | $548.82 | $19,208.70 | $330.00 | $11,550.00 |
| 0017 | Metal Chemicals of Concern Sampling & Analytical | 225 | Each | $5,141.50 | $1,156,837.50 | $250.00 | $56,250.00 | $376.79 | $84,777.75 | $551.24 | $124,029.00 | $112.00 | $25,200.00 |
| 0018 | Geotextile | 1,000 | Square Yard | $25.83 | $25,830.00 | $9.00 | $9,000.00 | $2.57 | $2,570.00 | $36.92 | $36,920.00 | $2.60 | $2,600.00 |
| 0019 | Fill | 13,000 | Cubic Yard | $32.55 | $423,150.00 | $45.00 | $585,000.00 | $62.79 | $816,270.00 | $70.04 | $910,520.00 | $55.06 | $715,780.00 |
| 0020 | Aggregate Cover | 6,000 | Cubic Yard | $7.71 | $46,260.00 | $65.00 | $390,000.00 | $84.61 | $507,660.00 | $92.59 | $555,540.00 | $78.50 | $471,000.00 |
| 0021 | Groundwater Monitoring | 1 | Job | LS | $947,453.00 | LS | $275,000.00 | LS | $65,297.84 | LS | $140,556.73 | LS | $357,692.00 |
| 0022 | Disposal | 120,000 | Actual Tons | $82.90 | $9,948,000.00 | $72.00 | $8,640,000.00 | $62.38 | $7,485,600.00 | $71.98 | $8,673,600.00 | $55.28 | $6,633,600.00 |
TOTAL ESTIMATED BID AMOUNT TOTAL $58,647,529.50 TOTAL $22,150,875.00 TOTAL $24,320,533.07 TOTAL $38,891,797.74 TOTAL $17,977,777.00
PERCENT DIFFERENCE FROM IGE -62.23% -58.53% -33.69% -69.35%
Attendee List
| NAME | ORGANIZATION |
| Eric Leach | USACE |
| Brandon Mormello | USACE |
| Stephen Pindale | USACE |
| Scott Seufert | USACE |
| Eric Frisbie | USACE |
| Dom Franchi | USACE |
| Brain Duffy | USACE |
| Chelsea | USACE |
| Juan Carlos Corona | USACE |
| John Zacheiss | USACE |
| Kim DiBartolomeo | USACE |
| Steve Glazier | USACE |
| Sterling Johnson | USACE |
| Andrew Haeiko | EPA |
| Paul Feroni - 1189 | CAPE ENVIRONMENTAL MANAGEMENT INC |
| Chuck Peters - 1575 | TERA MATERIALS |
| Nick Tomkins | SEVENSON ENVIRONMENTAL SERVICES, INC. |
| Sarah Kiefer | EQM SERVICES, LLC |
| Gerard Nelson - 8601 | MAVIRO |
| Matt Ednie | J. CARPENTER ENVIRONMENTAL |
| Bob Knapp | EQM SERVICES, LLC |
| Eric Mangasarina - 7911 | LUCIANOS |
| Landon Mckenny - 0724 | CAPE ENVIRONMENTAL MANAGEMENT INC |
| Richard Moorey | MOREY METAL INDUSTRIES |
| Andrew Wright | SEVENSON ENVIRONMENTAL SERVICES, INC. |
| Bob Stank | |
| GK | |
| 678-428-4043 | |
| 609-462-3719 | |
| 732-588-3653 | |
| 215-990-3291 |