W912BU24B0018-Specs.pdf

PDF 957 KB Posted

Attached to
#3287 MAINTENANCE DREDGING DELAWARE RIVER, FORT MIFFLIN DOCKS & USS NEW JERSEY
Solicitation number
W912BU24B0018
Issued by

About this file

This document is an Invitation for Bids (IFB) for maintenance dredging of the Delaware River, Fort Mifflin Docks, and USS New Jersey in Camden, New Jersey. The contract will consist of a base bid for dredging approximately 81,000 cubic yards (cy) of material from the Fort Mifflin dock facility to depths ranging from 16 to 25 feet plus 1 foot of allowable overdepth. There is an option to dredge approximately 37,120 cy from the vicinity of the USS New Jersey to a depth of 37 feet plus 1 foot of allowable overdepth. All dredged material will be placed in the Fort Mifflin dredged material placement facility. The contractor must provide all required floating mechanical plant, personnel, and equipment to meet a minimum production rate of 2,500 cy per day. The contract is valued between $10,000,000 and $25,000,000 and the work must be completed by the US Army Corps of Engineers, Philadelphia District.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB W912BU24B0018

US Army Corps of Engineers Philadelphia District

Maintenance Dredging

Fort Mifflin Docks Philadelphia, Pennsylvania

USS New Jersey Camden, New Jersey

Construction Solicitation and Specifications

18 July 2024

This page was intentionally left blank for duplex printing.

18 July 2024

INVITATION NO. W912BU24B0018

PHILADELPHIA DISTRICT

CORPS OF ENGINEERS

INVITATION FOR BIDS

FOR

MAINTENANCE DREDGING

FORT MIFFLIN DOCKS

PHILADELPHIA, PENNSYLVANIA

USS NEW JERSEY

CAMDEN, NEW JERSEY

I. NOTE THE AFFIRMATIVE ACTION REQUIREMENT OF THE EQUAL OPPORTUNITY CLAUSE

WHICH MAY APPLY TO THE CONTRACT RESULTING FROM THIS SOLICITATION.

II. BIDDERS ARE REQUIRED TO COMPLETE THE REPRESENTATION AND CERTIFICATIONS

PORTION OF SECTION 00 45 00 OF THIS SOLICITATION AND SUBMIT THIS WITH THEIR

BID.

00 10 00-3

BIDDING SCHEDULE

(To be attached to SF 1442)

Item Estimated Unit Estimated No. Description Quantity Unit Price Amount_

Base Bid

1. Mobilization and 1 Job L.S. $_________ Demobilization

2. Removal & Satisfactory Disposal of Material – Fort Mifflin 80,900 C.Y. $______ $_________

3. Debris Removal, 30 CY Dumpster - Fort Mifflin 1 EA $______ $_________

Option 1

4. Mobilization and 1 Job L.S. $_________ Demobilization Between Base Bid and Option 1 Areas

5. Removal & Satisfactory Disposal of Material – USS New Jersey 37,120 C.Y. $______ $_________

6. Debris Removal, 30 CY Dumpster - USS New Jersey 4 EA $______ $_________

TOTAL ESTIMATED AMOUNT: $________

Note: Bidders must bid on all items.

SECTION 00 50 05

PRE-AWARD SURVEY SUBMITTAL REQUIREMENTS

PART 1 GENERAL

1.1 DEFINITIVE RESPONSIBILITY CRITERIA

Award of this Contract will be made as a whole to the lowest responsive and responsible Bidder whose bid conforms to all requirements of the specifications. Subsequent to the bid opening, the apparent low Bidder shall submit Pre-Award Survey Information that demonstrates compliance with the requirements set forth in this section as a precondition to receiving award.

1.2 GENERAL PRE-AWARD SURVEY INFORMATION

Complete the pre-award survey information sheets attached to this section, and submit to the Contracting Officer within 5 calendar days after bid opening.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

Section 00 50 05 Page 1

US ARMY CORPS OF ENGINEERS

PHILADELPHIA DISTRICT

PRE-AWARD SURVEY

A. GENERAL INFORMATION

1) Name of Firm: ___________________________________________________________________

Address: __________________________________________________________________________

Phone: _____________________________________ Fax:__________________________________

Email: ____________________________________________________________________________

CAGE CODE:

If your company has more than one CAGE Code, please list all that apply.

2) Location where accounts are kept (if different than item 1 above): ____________________________

3) Type of Firm (Please check one):

Sole Proprietorship [ ] Partnership [ ] Corporation [ ] Joint Venture [ ] Other

Date Organized: ____________________________________

Date Incorporated: __________________________________

State of Incorporation: _______________________________

4) Attach list of Name of Officers.

Please check "Yes" or "No" for each of the following:

Have current officers of your firm ever been indicted? Yes [ ] No [ ]

Are any of your officers currently under indictment? Yes [ ] No [ ]

If you have answered "Yes" to either of the above, please attach an explanation.

5) Has your firm been terminated for default on any contracts in the past six years? Yes [ ] No [ ] (If yes, please attach an explanation)

00 50 05 Page 2

B. PROPOSED SCHEDULE

Submit a preliminary schedule depicting your project plan from start to final completion. The schedule you submit will be used to determine your ability to successfully perform the project within the time frame stated in the specifications.

IAW FAR 52.236-15, Schedules for Construction Contracts, you will be required to submit a fully loaded schedule within five days after work commences on the awarded contract.

C. PERFORMANCE AND PAYMENT BOND INFORMATION

1) Performance & Payment Bonds will be furnished by:

Name of Company: _______________________________________________________________

Phone No: _____________________________________________________________________

2) Firm's bonding capacity as authorized by your Insurance Company:

Single Project: ___________________________________________________________________

Aggregate Basis: _________________________________________________________________

D. BANKING INFORMATION

Name of Bank: ___________________________________________________________________

Address: ________________________________________________________________________

Account Representative: ____________________________________________________________

Phone No: ________________________________ E-mail: _______________________________

Authorized Credit Line: ________________________________________________

If additional banks are utilized, please provide this information for each.

E. INSURANCE INFORMATION

Name of Insurance Company: ______________________________________________________

Type of Insurance Provided: _______________________________________________________

Insurance Agency: _______________________________________________________________

Address: _______________________________________________________________________

Agent: _________________________________________________________________________

Phone No: ______________________________ Email: _________________________________

If more than one insurance company is utilized, please provide this formation for each.

00 50 05 Page 3

F. FINANCIAL DATA

Please provide the last two certified public accountant's financial statements.

G. SAFETYDATA

Please check "Yes" or "No" for each of the following:

1. Does your firm have a Standard Operating Procedure for Safety?

Yes [ ] No [ ] If yes, please provide a copy.

Does your firm have a Policy Letter dealing with Safety?

Yes [ ] No [ ] If yes, please provide a copy.

2. What was your accident rate for last year? _____________________

3. What is your accident rate to date for this year? ____________________

H. QUALITY CONTROL DATA

Please check "Yes" or "No" for each of the following:

1. Does your firm have a Standard Operating Procedure for Quality Control?

Yes [ ] No [ ] If yes, please provide a copy.

2. Does your firm have a Policy Letter dealing with Quality Control?

Yes [ ] No [ ] If yes, please provide a copy.

I. EQUIPMENT DATA

Please provide the following data for each piece of construction equipment (including equipment you will rent or lease), intended to be used on the project. Do not include consumables.

Make Year Mfg.

Description Purchase Price (if equipment is owned) Size Book Value (if equipment is owned) Model Number Unpaid Balance (if equipment is owned)

J. EXPERIENCE DATA

1. Please provide the following data for all major projects in progress or completed with the past three years.

Also, provide the same data for Corps of Engineer projects completed within the last five years. Those projects containing work similar in nature to that involved under this solicitation are to marked with an asterisk (*).

Name and Address of Owner Point of Contact and Telephone Number Project Location Type of Work performed by your firm Indicate whether you performed as a prime or subcontractor Name of Architect/Engineer in charge for Owner Address of Architect/Engineer Contract or Subcontract Amount Approximate date completed or, if not completed provide percent complete

00 50 05 Page 4

Were time extensions necessary? Were penalties imposed? Were liens, claims or stop work orders filed?

2. How many years have you been in business as a contractor? ________________________________

3. How many years experience in the type of work involved in the subject solicitation do you have

a) as prime contractor? ___________________________________

b) as a subcontractor? ___________________________________

K. KEY PROJECT PERSONNEL

Please provide resumes for each of the following key personnel to be assigned to this project:

Project Engineer, Superintendent, Quality Control Manager/Technician, Safety Technician, Office Engineer

(Signature of Person Supplying Data)

(Print or Type Name and Title of Person Supplying Data)

(Phone No.)

(Email Address)

00 50 05 Page 5

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 50 DIVING SERVICES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 05 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

35 20 23.13 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM - SCOW

MONITORING PROFILE

35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM - PIPELINE

HYDRAULIC DREDGE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

33 CFR 88 ANNEX V: PILOT RULES

1.2 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Superintendent's Qualifications; G Evidence Of Insurance Notice To Mariners Movement Of Navigation Aids Placing Submerged Pipelines Across The Channel

SD-11 Closeout Submittals

Certified Labor Payrolls

1.3 SUPERVISION

1.3.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. Submit superintendent's qualifications prior to mobilization to the work site.

Section 01 30 00 Page 1

1.3.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.3.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.3.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.4 PRECONSTRUCTION CONFERENCE

Immediately after award, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference. The conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out.

Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.4.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.5 U.S. COAST GUARD COORDINATION MEETING

Prior to any work, contact U.S. Coast Guard, MSO/Group Philadelphia, 1 Washington Avenue, Philadelphia, PA 19147, to conduct a coordination meeting with U.S. Coast Guard, the Contractor, and USACE to facilitate safe marine traffic scheme for navigation.

Section 01 30 00 Page 2

1.6 PHYSICAL DATA (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (FAR 52.236-4)

a. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys. Samples of material to be dredged and dated as shown were obtained by using vibracores.

b. Tide Data. Tide tables and tidal current tables for the Delaware River may be obtained from the National Ocean Service, Distribution Division, 6501 Lafayette Avenue, Riverdale, MD 20840. The maximum velocity of the normal tidal current is approximately 1/3 mile per hour.

c. Weather Conditions. The site of the work is exposed conditions. It is believed that work can be performed during all seasons of the year except during winter months when ice conditions may interfere with dredging operations, subject to the seasonal time restrictions specified in Section 35 20 23 DREDGING. Complete weather records and reports may be obtained from the local U.S. Weather Bureau Office nearest to the work site. The Contractor shall satisfy himself as to the hazards likely to arise from weather conditions during the construction period.

d. Channel Traffic. Traffic in the work area consists of ocean going and coastwise vessels, tugs and barges, and pleasure craft. Passing vessels may interfere with dredging operations.

e. Obstruction of Channel. The Government will not undertake to keep the Delaware River channel free from vessels or other obstructions, except to the extent of such regulations if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor must to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such as extent as may be necessary to afford a practicable passage. The Contractor shall request the U.S. Coast Guard to issue a Notice to Mariners for each work assignment advising navigation interests that the Contractor's dredging plant will be operating in the area. The Contractor shall submit each such request to the U.S. Coast Guard, MSO/Group Philadelphia, 1 Washington Avenue, Philadelphia, PA 19147-4395. The Contractor shall furnish a copy of each request to the Contracting Officer not less than five days prior to the start of dredging. Each request shall contain the approximate time required for completion of dredging. Upon completion of dredging, the Contractor shall promptly remove his plant, including ranges, buoys, piles and other marks placed by him under the contract in navigable waters and on shore.

f. Navigation Aids. Do not relocate or move any aids to navigation that have been established by the U.S. Coast Guard. If it becomes necessary to have any aid to navigation moved in order to complete dredging operations under this contract, the Contractor shall notify the Fifth Coast Guard District (dpw) at least 45 days prior to the desired date for movement of navigation aids. To request a relocation, Contractors shall contact Waterways Management Section, Assistant Section Chief/NJ, DE, PA at

Section 01 30 00 Page 3

(757)398-6371 or e-mail cgd5waterways@uscg.mil at least 45 days before the desired date for movement of the aid. When making a request by telephone, Contractors must speak to the designated points of contact. The leaving of voicemail messages will not be acceptable. The Fifth CG District (dpw) will coordinate all temporary relocations or discontinuances. A copy of each request (including records of telephone conversations) shall be furnished to the Contracting Officer.

g. Laying of Submerged Pipelines and Obstruction of Channel. All discharge pipelines crossing the Delaware River navigation channel shall be submerged. Should it become necessary in the performance of this contract to use a submerged pipeline, the Contractor shall notify the Contracting Officer in advance of the schedule for placement of the pipeline. If the submerged line is to be placed across a navigable channel, the Contractor shall submit a request for approval, at least 3 working days (Sundays and holidays excluded) prior to the desired closure date, to the U.S. Coast Guard, Sector Delaware Bay, 1 Washington Avenue, Philadelphia, PA 19147-4395. A copy of each request to the USCG for placing submerged pipelines across the channel shall be furnished to the Contracting Officer. This request shall contain the following information:

(1) Location (Channel Centerline Stationing) and depth (over the top ofthe pipeline) at which the submerged line will be placed;

(2) The desired length of time the channel is to be closed;

(3) The date and hour placement or removal will commence;

(4) The date and hour of anticipated completion; and

(5) The name and telephone number of the person to be contacted for information and response to any emergency condition.

The Coast Guard has indicated that the requirements of navigation may make it necessary to establish times other than those requested. Coordinate plans with the Coast Guard sufficiently in advance of the planned closing to prevent delay to the dredging operations and comply with the Coast Guard requirements. The minimum depth to the top of any submerged pipe in the Delaware River shall not be less than 35 feet below mean lower low water

(MLLW).

h. Utility Crossings (Delaware River):

(1) The location and elevation of oil, gas, telephone and power lines crossing the Delaware river in the vicinity of Fort Mifflin are shown in the following table:

LOCATION DESCRIPTION ELEVATION

Opposite International 1-24 inch, submarine 60 ft. below MLW Airport, Phila., PA pipeline (Laurel across channel across Mifflin Range Pipeline Co.) and anchorage Sta. 65+550

Opposite International 1-8 inch, 1-12 inch, 55 ft. below MLW Airport, Phila., PA, submarine petroleum across channel and across Mifflin Range pipe lines anchorage Sta. 64+750 (Sinclair Pipe Line Co. & Gulf Oil Corps.)

Section 01 30 00 Page 4

(2) Take all necessary precautions to prevent damage to these utilities. The Contractor shall cause timely notice of the dredging to be given to the owners and, when in the opinion of the Contractor such action is necessary, he shall request that the said owner or owners mark the pipelines or move the cables so as to avoid interference with the dredging operations. Requests made by the Contractor shall be within 30 days following his receipt of the Notice to Proceed.

(3) The above information may not be complete and it is the Contractor's responsibility to investigate all utility crossings.

Before beginning the work the Contractor shall contact all utility companies to verify the location of all underground utilities. Submit copies of all Utility Company correspondence.

i. Bridge to Bridge Radio Telephone Equipment. In order that radio telephone communication may be made with passing vessels, all dredges engaged in work under the contract shall be equipped with and operate bridge-to-bridge radio telephone equipment. The radio telephone equipment shall operate on VHF Channel 13 (156.65 MHZ) with low power output having a communication range of approximately ten miles. The frequency has been approved by the Federal Communication Commission.

j. Disposal Areas: The following Government-furnished disposal areas shall be used for this contract:

Ft. Mifflin Area, Cell C.

k. The most recent maintenance dredging of the Fort Mifflin docks was completed by Norfolk Dredging Company in 2006 under a non-Government contract.

l. "Abstract of Bottom Samples" are included as APPENDIX B40 of this contract.

m. Survey Controls. Survey control description sheets are included in APPENDIX A30. Additional survey control may be found at https://usmart.sec.usace.army.mil/w/ but should be verified with the Philadelphia District Corps of Engineers Survey Section. Additional horizontal and vertical control may be established by the Survey Section in the vicinity of the project, after contract award and in coordination with the Contractor. Contact the Philadelphia District Survey Section at least 10 business days prior to the start of Contractor survey and/or layout operations, to determine the best locations for additional control points based on project requirements. The District Survey Section may establish project control points in locations that are mutually agreed upon by the Contractor and the Surveys Section. The points of contact in the District Survey Section are Jason Gray at Jason.m.gray@usace.army.mil, Stephen Farrell at Stephen.a.farrell@usace.army.mil and Angelica DeHoyos at angelica.dehoyosmolina@usace.army.mil.

n. Magnitude of the Contract Work. The estimated value of the contract is between $10,000,000 and $25,000,000.

1.7 LAYOUT OF WORK (DEC 1996)

The Contractor shall lay out its work from Government-provided channel coordinates and survey control points, furnished as part of each work assignment. The Contractor shall furnish, at its own expense, such stakes, Section 01 30 00 Page 5 templates, platforms, equipment, range markers and labor as may be required in laying out any part of the work, from the channel coordinates and surveying benchmarks furnished by the Government and shall be responsible for all measurements in connection therewith. If any Government control is found disturbed or destroyed, this must be communicated to the Philadelphia District Surveys Branch through the COR before any control is re-established. The Contractor shall be responsible for executing the work to such lines and grades as may be established or indicated by the Contracting Officer. (CENAP)

1.8 SIGNAL LIGHTS (FEB 1983)

The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working navigable channels, as approved by the Commandant, U.S. Coast Guard with respect to vessels in inland waters (33 CFR 88), as applicable. (CENAP)

1.9 CONTINUITY OF WORK (APR 1965 OCE)

No payment will be made for work done in any area designated by the Contracting Officer until the full depth required under the contract is secured in the whole of such area, unless prevented by ledge rock, nor will payment be made for excavation in any area not adjacent to and in prolongation of areas where full depth has been secured except by decision of the Contracting Officer. Should any such nonadjacent area be excavated to full depth during the operations carried on under the contract, payment for all work therein may be deferred until the required depth has been made in the area intervening. The Contractor may be required to suspend dredging at any time when for any reason the gages or ranges cannot be seen or properly followed. (CENAP)

1.10 SHOALING (1965 APR OCE)

If before the contract is completed, shoaling occurs in any section previously accepted, including shoaling in the finished channel, because of the natural lowering of the side slopes, redredging at contract price, within the limits of available funds, may be done if agreeable to both the Contractor and the Contracting Officer. (CENAP)

1.11 INSPECTION (DEC 1996)

The presence of the inspector shall not relieve the Contractor of responsibility for the proper execution of the work in accordance with the specifications. The Contractor will be required:

a. To furnish, on the request of the Contracting Officer or any inspector, the use of such boats, boatmen, laborers, a part of the ordinary and usual equipment and crew of the dredging plant as may be reasonably necessary in inspecting and supervising the work.

b. To furnish, on the request of the Contracting Officer or any inspector, suitable transportation from all points on shore designated by the Contracting Officer to and from the various pieces of plant and to and from

Section 01 30 00 Page 6 the disposal areas.

Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting officer, and the cost thereof will be deducted from any amounts due or to become due the Contractor. (CENAP)

1.12 PERFORMANCE EVALUATION OF CONTRACTOR (MAR 2014)

a. As a minimum, the Contractor's performance will be evaluated upon final acceptance of the work for contracts less than one year in duration.

Contracts in excess of one year will receive at a minimum, an annual interim evaluation in addition to the final evaluation. However, interim evaluation may be prepared at any time during contract performance when determined to be in the best interest of the Government. The evaluation will be entered into the Contractor Performance Assessment Reporting System

(CPARS).

b. CPARS is a web-enabled application that supports the completion, distribution, and retrieval of construction contract performance evaluations. CPARS is for UNCLASSIFIED use only. An evaluation assesses Contractor performance and provides a record, both positive and negative, on a given contract. Each evaluation is based on objective facts and supported by contract management data, such as contract performance elements that evaluate quality, timely performance, effectiveness of management, and compliance with contract terms, labor standards, and safety requirements. The Contractor will be rated either outstanding, above average, satisfactory, marginal, or unsatisfactory in the areas of Contractor Quality Control, Timely Performance, Effectiveness of Management, Compliance with Labor Standards, and Compliance with Safety Standards. The Contractor will be advised of any unsatisfactory rating, either in an individual element or in the overall rating, prior to completing the evaluation, and all Contractor comments will be made a part of the official record. Performance Evaluation Reports will be available to all DOD Contracting offices for their future use in determining Contractor responsibility, in compliance with ER 415-1-17.

c. Upon successful award of the contract, the Contractor will be notified by CPARS via email that access has been granted to a contract within the system. The email will contain instructions of how to log into the system.

(CENAP)

1.13 REQUIREMENT TO NOTIFY COAST GUARD OF RELEASE OF OBJECTS INTO THE

NAVIGABLE WATERS OF THE UNITED STATES

a. Requirement: As soon as a person has knowledge of any release from a vessel or facility into the navigable waters of the United States of any object that creates an obstruction prohibited under section 403 of this title, such person shall notify the Secretary and the Secretary of the Army, and the COR of such release.

b. Restriction on use of notification: Any notification provided by an individual in accordance with subsection (a) of this section may not be used against such individual in any criminal case, except a prosecution for perjury or for giving a false statement.

(Pub. L. 92–340, §15, as added Pub. L. 109–241, title VI, §602, July 11, 2006, 120 Stat. 553.)

Section 01 30 00 Page 7

1.14 INSURANCE REQUIREMENTS

Evidence of Insurance: Evidence of the following insurance shall be submitted to the Contracting Officer prior to commencement of work.

Insurance shall be maintained throughout the period of performance:

a. General Liability Insurance (Comprehensive form of policy): Bodily Injury Liability - $500,000 per occurrence.

b. Automobile Liability Insurance (Comprehensive form of policy): Bodily Injury Liability - $200,000 per person and $500,000 per accident. Property Damage Liability - $20,000 per accident.

c. Workmen's Compensation and Employer's Liability Insurance: Compliance with applicable workmen's compensation and occupational disease statutes is required. Employer's liability coverage in the minimum amount of $100,000 is also required."

d. Applicable Marine Casualty and Marine Workmen's Compensation Insurance:

As appropriate for this contract.

1.15 PARTNERING

To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

1.15.1 Team-Led (Informal) Partnering

a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.

b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-base or at the Contractor's temporary trailer.

c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.

d. The Partners will determine the frequency of the follow-on sessions.

e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.

1.16 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the

Section 01 30 00 Page 8 capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.

Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Section 01 30 00 Page 9

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.1.1 Submittal Information

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

1.1.2 Project Type

The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

1.1.3 Submission of Submittals

Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:

SD-01 Preconstruction Submittals

Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.

Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.

Section 01 33 00 Page 1

Certificates Of Insurance

Surety Bonds

List Of Proposed Subcontractors

List Of Proposed Products

Baseline Network Analysis Schedule (NAS)

Submittal Register

Schedule Of Prices Or Earned Value Report

Accident Prevention Plan (APP)

Work Plan

Quality Control (QC) plan

Environmental Protection Plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports

Daily logs and checklists

Section 01 33 00 Page 2

Final acceptance test and operational test procedure

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits

Text of posted operating instructions

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.2.2 Approving Authority

Office or designated person authorized to approve the submittal.

1.2.3 Work

As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or “S” classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Submittal Register; G,COR

Section 01 33 00 Page 3

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."

1.4.2 For Information Only (FIO)

Submittals not requiring Government approval will be for information only.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."

1.5 PREPARATION

1.5.1 Transmittal Form

Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. This form is included in the RMS CM software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.5.2 Submittal Format

1.5.2.1 Format of SD-01 Preconstruction Submittals

When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.

Provide data in the unit of measure used in the contract documents.

1.5.2.2 Format for SD-02 Shop Drawings

Provide shop drawings not less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.

Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.

a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.

b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.

Submit an electronic copy of drawings in PDF format.

Section 01 33 00 Page 4

1.5.2.2.1 Drawing Identification

Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph

IDENTIFYING SUBMITTALS.

Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.

Reserve a blank space, no smaller than 5 inches on the right-hand side of each sheet for the Government disposition stamp.

1.5.2.3 Format of SD-03 Product Data

Present product data submittals for each section. Include a table of contents, listing the page and catalog item numbers for product data.

Indicate, by prominent notation, each product that is being submitted;

indicate the specification section number and paragraph number to which it pertains.

1.5.2.3.1 Product Information

Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.

Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.

1.5.2.3.2 Standards

Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer.

State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.

1.5.2.3.3 Data Submission

Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of the construction effort.

Submit the manufacturer's instructions before installation.

Section 01 33 00 Page 5

1.5.2.4 Format of SD-04 Samples

1.5.2.4.1 Sample Characteristics

Furnish samples in the following sizes, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately the same size as specified:

a. Sample of Equipment or Device: Full size.

b. Sample of Materials Less Than 2 by 3 inches: Built up to 8 1/2 by 11 inches.

c. Sample of Materials Exceeding 8 1/2 by 11 inches: Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.

d. Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.

e. Sample Volume of Nonsolid Materials: Pint. Examples of nonsolid materials are sand and paint.

f. Color Selection Samples: 2 by 4 inches. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard unit.

g. Sample Panel: 4 by 4 feet.

h. Sample Installation: 100 square feet.

1.5.2.4.2 Sample Incorporation

Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples are to be in undamaged condition at the time of use.

Recording of Sample Installation: Note and preserve the notation of any area constituting a sample installation, but remove the notation at the final clean-up of the project.

1.5.2.4.3 Comparison Sample

Samples Showing Range of Variation: Where variations in color, finish, pattern, or texture are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range. Mark each unit to describe its relation to the range of the variation.

When color, texture, or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.

Section 01 33 00 Page 6

1.5.2.5 Format of SD-05 Design Data

Provide design data and certificates on 8 1/2 by 11 inch paper.

1.5.2.6 Format of SD-06 Test Reports

By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.

1.5.2.7 Format of SD-07 Certificates

Provide design data and certificates on 8 1/2 by 11 inch paper.

1.5.2.8 Format of SD-08 Manufacturer's Instructions

Present manufacturer's instructions submittals for each section. Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry, and technical-society publication references. If supplemental information is needed to clarify the manufacturer's data, submit it as specified for SD-07 Certificates.

Submit the manufacturer's instructions before installation.

1.5.2.8.1 Standards

Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer.

State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.

1.5.2.9 Format of SD-09 Manufacturer's Field Reports

By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.

1.5.2.10 Format of SD-11 Closeout Submittals

When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.

Provide data in the unit of measure used in the contract documents.

1.5.3 Source Drawings for Shop Drawings

1.5.3.1 Source Drawings

The entire set of source drawing files (DWG) will not be provided to the Contractor. Request the specific Drawing Number for the preparation of

Section 01 33 00 Page 7 shop drawings. Only those drawings requested to prepare shop drawings will be provided. These drawings are provided only after award.

1.5.3.2 Terms and Conditions

Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim, and waives to the fullest extent permitted by law any claim or cause of action of any nature against the Government, its agents, or its subconsultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities, or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic source drawing files are not construction documents.

Differences may exist between the source drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic source drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. The Contractor is responsible for determining if any conflict exists. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished source drawing files, the signed and sealed construction documents govern. Use of these source drawing files does not relieve the Contractor of the duty to fully comply with the contract documents, including and without limitation the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses,…

This is the start of the file's text. The full file is on GovTribe.