Amendment 4 W912BU24B0013.pdf
PDF 485 KB Posted
- Attached to
- W912BU24B0013 -Summit Bridge Repair
- Solicitation number
- W912BU24B0013
About this file
This document is Amendment 0004 to Solicitation W912BU24B0013 for the Summit Bridge Repair project. The amendment addresses remaining requests for information (RFI) and makes changes to the bid schedule and technical specifications. Key details include:
The bid schedule has been revised, with a new line item added for a "Work Access Platform." The technical specifications for the work access platform have been updated, including requirements for the platform design, debris shielding, and removal. The bid opening date has not been extended. RFI responses are provided, clarifying that a plan holders list is not available, water collection is not required, and past performance experience requirements remain unchanged for this invitation for bid (IFB) solicitation. Overall, this amendment provides final clarifications to the solicitation prior to bid submission.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 0004 is hereby issued to address the remaining RFI questions. This includes an adjustment to the bid schedule that reflects in the platform section. This amendment w ill also answ er any final RFIs submitted. Please indicate receipt of this amendment on the Standard Form 1442, (Solicitation, Offer, and Aw ard) as Amendment 0004. Failure to acknow ledge all Amendments may be cause for rejection of the bid. With this amendment, this solicitation is considered to be clear.
********************THIS AMENDMENT DOES NOT EXTEND THE BID OPENING DATE*******************************
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912BU24B0013
X 9B. DATED (SEE ITEM 11)
10-Sep-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
07-Oct-2024
CODE
US ARMY ENGINEER DISTRICT, PHILADELPHIA
POC: MOLLY GALLAGHER, CONTRACTING DIVISION, 1
TREET, 4TH FLOOR MAIL ROOM.
PHILADELPHIA PA 19103-2004
W912BU 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912BU24B0013
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The following have been modified:
RFI QUESTIONS AND ANSWERS
RFI QUESTION AND ANSWERS
1.Will a plan holders list be available for the following solicitation, W912BU24B0013 -Summit Bridge Repair 2.Will the water be required to be collect in areas to be cleaned by ( SSPC WJ-4/NACEWJ-4 locations?
3.Will the USACE be open to make the painters platform separate bid item from the painting. The painting is a square foot item and the access or platforms to the areas is necessary, this will lead to many months waiting to get paid for work completed prior to the platform being removed.
4.Would you consider limiting the past performance to the cleaning/painting of bridges as the major scope item as requiring 9 projects from one subcontractor and will it also limit competition and increase the government’s cost?
5.We would like the government to consider allowing a prime to use a subcontractor’s past performance as allowed in the FAR.
RFI Answers
1. The plans were made available to the public through SAM.gov – there is no list of plan holders.
2. The water is not required to be collected. Solid debris must be contained and collected.
3. The Work Platform to the bid schedule is address in this Amendment. This will make painting platform it’s own bid line item.
4. No changes are made to the experience required; all bidders must satisfy the experience requirements required in the solicitation.
5. This is an IFB and not a source selection solicitation. There’s no Past performance experience evaluation.
(End of Summary of Changes)
IFB W912BU24B0013
Amendment No. 0004
14. DESCRIPTION OF AMENDMENT (continued)
a. BIDDING SCHEDULE: Please delete the Bidding Schedule in its entirety and replace it with the revised Bidding Schedule, annotated Amendment No.
0004, attached hereto.
b. TECHNICAL SPECIFICATIONS:
(1) SECTION 01 60 00 – WORK ACCESS PLATFORM: Please delete this section in its entirety, and substitute the revised section 01 60 00, annotated Amendment No. 0004, attached hereto.
c. Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment No. 0004. Failure to acknowledge all amendments may be cause for rejection of the Bidder.
00 10 00-3
BIDDING SCHEDULE
(To be attached to SF 1442)
Item Estimated Unit Estimated No. Description Quantity Unit Price Amount
BASE BID
1. Traffic Control 1 JOB LS $ ___________
2. State Police Support 1 JOB LS $ ___________
3. Concrete Deck Topside Spall Repairs 47 SF $______ $ ___________
4. Steel Repair Detail “A” 160 EA $______ $ ___________
5. Steel Repair Detail “B” 96 EA $______ $ ___________
6. Steel Repair Detail “D” 1 EA $______ $ ___________
7. Steel Repair Detail “F” 62.5 LF $______ $ ___________
8. Steel Repair Detail “G1” 1 EA $______ $ ___________
9. Steel Repair Detail “G2” 1 EA $______ $ ___________
10. Steel Repair Detail “H” 1 EA $______ $ ___________
11. Steel Repair Detail “J” 1 EA $______ $ ___________
12. Steel Repair Detail “K1” 2 EA $______ $ ___________
13. Steel Repair Detail “K2” 2 EA $______ $ ___________
14. Steel Repair Detail “Q” 3 EA $______ $ ___________
15. Steel Repair Detail “T1” 6 EA $______ $ ___________
16. Steel Repair Detail “T2” 2 EA $______ $ ___________
17. Steel Repair Detail “U1” 2 EA $______ $ ___________
18. Steel Repair Detail “U2” 1 EA $______ $ ___________
19. Steel Repair Detail “U3” 1 EA $______ $ ___________
20. Steel Repair Detail “V” 1 EA $______ $ ___________
21. Steel Repair Detail “W” 1 EA $______ $ ___________
22. Steel Repair Detail “X” 1 EA $______ $ ___________
23. Steel Repair Detail “Y1” 1 EA $______ $ ___________
24. Steel Repair Detail “Y2” 2 EA $______ $ ___________
25. Steel Repair “SPAN 5 PPLO'E” 1 EA $______ $ ___________
26. Steel Repair “SPAN 4 PPL12W” 1 EA $______ $ ___________
27. Bearing Grout Pad Repair Detail “C” 3 EA $______ $ ___________
28. Parapet Base Grout Repair Detail “P" 468 LF $______ $ ___________
29. Parapet Replacement Detail “S" 1 JOB LS $ ___________
30. Utility Support Steel Repair Detail "I" 1 EA $______ $ ___________
00 10 00-4
31. Fastener Replacement 145 EA $______ $ ___________
32. Drainage Repairs 1 JOB LS $ ___________
33. Painting 126,281 SF $______ $ ___________
34. Work Access Platform 1 JOB LS $ ___________
TOTAL BASE BID AMOUNT $ ___________________
OPTION 1
35. Concrete Spall Repairs 407 SF $______ $ ___________
36. Concrete Deck Underside/Edge Spall Repairs 78 SF $______ $ ___________
37. Joint Steel Armor Replacement Detail “L" 133 LF $______ $ ___________
38. Joint Seal Replacement Details “M” and “R" 592 LF $______ $ ___________
TOTAL OPTION 1 AMOUNT $ ___________________
TOTAL BASE BID AND ALL OPTIONS AMOUNT $ ___________________
NOTES: Bidders must bid on all items.
SECTION 01 60 00
WORK ACCESS PLATFORM
PART 1 GENERAL
1.1 SCOPE OF SECTION
The work covered by this section consists of furnishing all labor, materials, and performing all operations required for the construction of a temporary work access platform and temporary debris control shield.
Minimum clearances for marine traffic shall be as specified in Section
01 57 60 PROTECTION OF MARINE NAVIGATION.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Work Access Platform; G, DO.
Submit a work access platform plan that describes the platform, temporary debris control shield, and details. Included shall be all structural analysis and design calculations for the platform, debris control shields, and associated support system. Include in the plan detailed erection plans and drawings for the platform indicating minimum clearance for marine traffic. The system shall be designed in accordance with EM 385-1-1, OSHA, and AASHTO requirements and to support all environmental loads and those loads imposed in carrying out the Contractor's work plan. Provide calculations to verify that the bridge will not be overstressed by construction activities including debris from blasting operations, work access platforms, construction equipment exceeding 80,000 lbs, and containment structure. The plan shall outline all heavy equipment and storage of materials on the bridge that will occur during construction. The design, drawings, and calculations shall be approved by a Professional Engineer licensed in the State of Delaware.
Section 01 60 00 Page 1
PART 2 PRODUCTS
2.1 WORK ACCESS PLATFORM
Provide an approved solid floor debris shield and platform system. Debris shields shall be provided to protect all locations where overhead work poses a hazard to the traveling public or marine vessels.
2.1.1 Platform Design
The design of the work access platform shall specifically address any necessary strengthening of existing bridge members required during platform construction or connection to the bridge. The design shall also specifically detail all connections to the bridge.
PART 3 EXECUTION
3.1 WORK ACCESS PLATFORM
Provide and erect a work access platform required for access and construction for this contract. During all operations of this contract, the Contractor is not permitted to drop material or debris from the bridge. Protective shields shall be used to catch falling material and shield the area below the work. If the Government determines that adequate protective shields are not being provided, the work shall be suspended until adequate protective shields are employed at no additional cost to the Government.
The Contractor must not modify, damage, or attach the work access platform system to any existing bridge member to construct or operate the platform system without approval from the Government. Any modification to the bridge shall be detailed in the erection drawings and approved by a Delaware -registered Professional Engineer. Any damage to the existing structure and its appurtenances occurring during work access platform installation shall be repaired by the Contractor at no expense to the Government.
3.1.1 Inspection
The work access platform shall be inspected in person and certified by the manufacturer or registered PE when initially assembled and each time thereafter when the work access platform is reassembled at a new location on the bridge.
3.1.2 Platform Removal
Remove and properly dispose of all temporary apparatuses and work access platform systems used throughout the project, as soon as they serve their intended purpose. The Contractor shall bring any disturbed element surrounding the temporary apparatus and/or support systems to its original condition, subject to the Government's approval.
3.2 MEASUREMENT AND PAYMENT
The work specified in this section will not be measured for payment and all costs in connection therewith shall be included in the contract lump sum price for Bid Item titled "Work Access Platform".
-- End of Section --
Section 01 60 00 Page 2
| SF30 AND REQUESTS FOR INFORMATION AND RESPONSES |
| AMENDMENT DESCRIPTION |
| BID SCHEDULE |
| 01 60 00 WORK ACCESS PLATFORM |