Amendmemnt 1 W912BU20Q0012 Questions - Answers.pdf
PDF 554 KB Posted
- Attached to
- Pedestal Knuckle Marine Crane Replacement
- Solicitation number
- W912BU-20-Q-0012
About this file
This document contains an amendment to a solicitation for a pedestal mounted knuckle boom marine crane. Key details include that the U.S. Army Corps of Engineers, Philadelphia District is seeking to replace an existing Link Belt HC-218 crane for the Seattle District. The new crane must be manufactured to API 2C standards with monogram and include independent third party verification and ABS certification. The response date for the solicitation is 24 February 2020 and the contract is anticipated to be approximately $1,000,000 to $3,000,000 with a duration of 420 calendar days. The solicitation will be set aside 100% for small businesses and issued on or around 20 February 2020 under number W912BU-20-Q-0012. Offers must be submitted electronically to the identified contracting officer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 4 W912BU20Q0012.pdf | ||
| Amendment 3 20Q0012.pdf | ||
| Amendment 2 20Q0012.pdf | ||
| Solicitation W912BU20Q0012 with Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
6 Questions and Answ ers Attached
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 02-Apr-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912BU20Q0012
X 9B. DATED (SEE ITEM 11)
18-Mar-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-Apr-2020
CODE
US ARMY ENGINEER DISTRICT, PHILADELPHIA
CONTRACTING DIVISION
WANAMAKER BUILDING
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
W912BU 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912BU20Q0012
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 1 Q&A'S
AMENDMENT 1
W912BU20Q0012
Q&A for 20Q0012
Q-1 Can the U.S. Army Corps of Engineers make an exception to the API monogram requirement if the crane is designed and built to API 2C Standards?
A-1 No. The API Monogram must remain as a requirement. We seek this on all cranes built for USACE. The requirement is also called out in EM385.
Q-2 Please help us understand why the specification includes an overturning moment limitation with no load, as the common method, is for overturning limitations to be specified with loads, due to vessel stability considerations.
A-2 Due to the narrow beam of the vessel onto which this crane will be placed, a very unique load chart will be determined upon delivery. This load chart will be de-rated from the manufacturer's issued floating service load charts into an azimuth based floating service load chart based on the stability of the vessel. As a result, the contract language as it stands now was the clearest way to communicate the performance requirements for the crane as will stand as written.
Q-3 Would a hinged door be acceptable in place of a sliding door?
A-3 Hinged door will be acceptable in lieu of a sliding door
Q-4 The way this is stated makes it a little confusing, first line says "shall be stainless steel" but the second line says " all hydraulic and other protected by tape". I don't believe you would install tape on stainless.
Are galvanized fittings with Densyl tape acceptable?
A-4 Galvanized fittings will not be accepted. Fittings shall be as per the contract.
Q-5 Our cranes do not have foot pedals for braking, dynamic braking is done by slewing in the opposite direction. The swing brake is a parking brake activated with a push button on the joysticks. Will this be acceptable?
W912BU20Q0012
A-5 Crane braking - the brakes shall be as per the contract requirements. A foot brake is required.
Q-6 For E under C003 Performance Requirements, is the value of 170,000 ft-lbs correct?
A-6 : 170,000 ft-lbs is the correct value for the deadweight moment of the machine with the boom/arm fully extended.
(End of Summary of Changes)