W912BU-17-B-0006_Specs-AM0002.pdf

PDF 177 KB Posted

Attached to
Beachfill - Brigantine Inlet to Great Egg Harbor Inlet, Brigantine Island, Atlantic County, New Jersey
Solicitation number
W912BU-17-B-0006
Issued by

About this file

Amendment 2 W912BU-17-B-0006 Specs

View the file

Other files

File Type Posted
Brigantine_-_Formal_Abstract.pdf PDF
BrigInlet_Inlet_9_2016_XYZ.csv CSV file
W912BU-17-B-0006_Dwgs-AM0002.pdf PDF
W912BU-17-B-0006_Specs-AM0001_6-20-2017.pdf PDF
W912BU-17-B-0006_Dwgs.pdf PDF
W912BU-17-B-0006_Specs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers XX is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or

(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) as Amendment No. 0002. Failure to acknowledge all amendments may be cause for rejection of the bid.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

Beachfill - Brigantine Inlet to Great Egg Harbor Inlet, Brigantine Island, Atlantic County

This amendment extends the bid opening date from 30 June 2017 to 12 July 2017 at 11:00 A.M. EST. The RFI Period is not extended. This amendment modifies the borrow area restrictions and provides responses to RFI's.

E5CT9RH9

US ARMY ENGINEER DISTRICT, PHILADELPHIA

WANAMAKER BUILDING, 100 PENN SQUARE EAST

PHILADELPHIA, PENNSYLVANIA 19107-3390

US ARMY ENGINEER DISTRICT, PHILADELPHIA

POC: LEONARD BUHROW

WANAMAKER BUILDING, 100 PENN SQUARE EAST

PHILADELPHIA, PENNSYLVANIA 19107-3390

9A. AMENDMENT OF SOLICITATION

NO.

W912BU-17-B-0006

06/27/2017

9B. DATED (SEE ITEM 11)

05/31/2017

1 1

Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD)

X

This page was intentionally left blank for duplex printing.

Amendment No. 0002

IFB W912BU-17-B-0006

14. DESCRIPTION OF AMENDMENT (continued)

a. REQUESTS FOR INFORMATION (RFI) WITH RESPONSES: RFI’s with responses, annotated Amendment No. 0002, are attached to this amendment.

b. CONTRACT DRAWINGS:

Please delete the drawing C-402 in its entirety and substitute the revised drawing, of the same drawing number, with the latest revision date of 26 June 2017, attached hereto:

c. Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment No. 0002. Failure to acknowledge all amendments may be cause for rejection of the bid.

Amendment No. 0002

IFB W912BU-17-B-0006

RFI# Request for Information Response

Drawing C-402 shows Borrow Area Access Limits. Is the access limit shown for all access to the borrow area including the submerged pipeline? Or is the access limit only for the dredge to access the borrow area? Where is the Contractor allowed to lay submerged pipeline to access the borrow area? Are anchors allowed to be placed outside the borrow area limits? What is the purpose of the borrow area access limits?

The borrow access area is an area outside of the approved borrow area that may be dredged to the same depth shown on the plans to allow safe access to the borrow area. Any material dredged from the access channel can be pumped on the beach at the applicable pay rates.

There are no restrictions on placement of submerged pipeline to access the borrow area. Anchors are allowed outside of the borrow area.

The Base Bid quantity for beachfill is 405,000 CY and all options add another 410,000 CY of beachfill for a maximum of 815,000 CY of beachfill. In calculating the amount of material in the borrow area there will not be enough material to perform the base bid plus all options. How much material is available in the borrow area? What is the Corps’ plan if the Contractor runs out of material in the borrow area before the contract is complete? Can the Corps please provide the XYZ survey data of the borrow area

See amendment 0002 for revisions to the borrow area.

The government estimates sufficient quantity to complete the base plus all options. Options will not be exercised until a review of the BD surveys is complete and a final determination is made on the sand requirements. XYX data of the borrow area will be provided. See Amendment No. 0002.

REQUESTS FOR INFORMATION with RESPONSES Solicitation No. W912BU-17-B-0006

SF30
AMENDMENT DESCRIPTION
REQUESTS FOR INFORMATION AND RESPONSES