Control Number _______________
SOLE SOURCE JUSTIFICATION
FOR PROPOSED ACTION NOT EXCEEDING THE
SIMPLIFIED ACQUISITION THRESHOLD (SAT)
1. CONTRACTING AGENCY - Department of Army U.S. Army Corps of Engineers Philadelphia District (NAP) Contracting Division Philadelphia, Pennsylvania
2. Description of Action:
Nature: New Requirement Follow-on Requirement
Mod to Existing Purchase Order/Delivery Order/Task Order/ Contract Number
Pricing: Firm-Fixed Price Time and Materials Cost Labor Hours
3. Describe the supplies or services required (including the estimated value).
4. Authority (select one):
FAR 13.106-1(b)(1)(i): The contracting officers may solicit from one source if the contracting officer determines that the circumstances of the contract action deem only one source reasonably available (e.g. urgency, exclusive licensing agreements, brand name, or industrial mobilization).
FAR 13.106-1(b)(1)(ii): This documentation only covers the portion of the acquisition that is brand-name. A single source has been identified to provide a portion of a purchase because that portion of the purchase specifies a particular brand-name item.
5. Reasons for Authority Cited (including the qualifications of the proposed contractor to meet the requirements):
6. Describe the market research conducted and the results, or a statement for the reason market research was not conducted.
7. A listing of other sources, if any, which expressed, in writing, an interest in the acquisition.
8. A statement of the actions, if any, the agency may take to remove or overcome any barriers to competition before any subsequent acquisition for the supplies or services required, if necessary.
9. TECHNICAL PERSONNEL CERTIFICATION: I certify that the information provided herein recommending “other than full and open competition,” as presented to the contracting officer, is accurate and complete to the best of my knowledge. Further documentation, if needed, may be obtained from the undersigned technical representative.
Signature: Date:
Name: Phone Number:
Title:
10. APPROVAL STATEMENT: I hereby determine this justification is accurate and complete to the best of my knowledge and belief. The estimated cost to the Government is fair and reasonable.
IAW FAR 13.106-1(b)(1), I hereby determine that the circumstances of the contract action deems only one source is reasonably available; provided that the services and property herein described have otherwise been authorized for acquisition and funds are available.
Signature: Date:
Name: Phone Number:
Contracting Officer
| Control Number: |
| Enter the contract number of your action in this box: |
| Group9: Choice1 |
| Text10: New Radars, ECDIS (Electronic Chart Display and Information System) and GMDSS (Global Maritime Distress and Safety System) for Dredge McFARLAND. All the components to be procured under this contract shall be manufactured by Furuno. Estimated value is $149,115.00 |
| Text11: All the components to be procured under this contract shall be manufactured by Furuno in order to properly interface with each other and to properly interface with existing Furuno components that are not being replaced. |
The new radars and new GMDSS being procured are to replace existing radars and GMDSS on the ship. All are over 10 years old and parts are becoming difficult, and sometimes impossible, to procure new. And the frequency of breakdowns of the radars has been increasing as of late, further necessitating replacement.
Furthermore, the U.S. Coast Guard is also requiring the Dredge McFARLAND be fitted with ECDIS by January 2017. The old radars will not work with the new ECDIS, hence the need for all new equipment.
All of the other bridge equipment that will remain in place, including the AIS, GPS, VDR, Fathometer and Doppler Speed Log, is manufactured by Furuno and will properly interface with the new equipment being procured.
It is essential that the new equipment interface properly not only with each other but with the aforementioned existing equipment and the only way to ensure that is to procure new Furuno equipment. The ramifications of incorrect or erratic data transmission between components/systems would jeopardize the safety of the McFARLAND, its crew and any vessels operating nearby.
Experience on the McFARLAND trying to integrate multiple manufacturers of similar equipment, either when new or mating new to existing, has and continues to cause problems. All the original voltage regulators had to be replaced due to not working properly with the new switchgear installed in 2011, the interface with the propulsion controls manufactured by MCR Engineering and the propulsion system designed by Rolls Royce Naval Marine has lead to troubleshooting problems, and the recent installation of a new tank level indicating system by EMS Marcon required the replacement of numerous electrical components due to incorrect data transmission.
It is for all of the aforementioned reasons that only Furuno components should be sourced.
Text12: Market research was done by getting a cost estimate for radars and ECDIS maufactured by JRC. The cost of these components alone was $113K, not including the GMDSS, which would cost an estimated $30K. The total procurement using JRC components would be close to $140K, and this does not include replacing any other existing Furuno components (AIS, GPS, etc.) that may not be compatible with JRC components.
The total cost savings, if any, by using JRC components is estimated to be 6% at best, and this is only if everything works together, which as stated above is a major safety concern. Replacement of any other existing Furuno components would quickly negate any potential cost savings, not to mention the increased time and expense, both on the contractual side and lost dredging time, of diagnosing and correcting any problems.
| Text13: Furuno components are available from numerous distributors throughout the USA. |
| Text14: Furuno components are available from numerous distributors throughout the USA. |
| Text17: |
| Text18: |
| Text19: |
| Text20: |
| Text21: |
| Text22: |
| Text23: |
| Group10: Choice4 |
| Group11: Choice9 |
File details come from the government source that posted it. Updated .