Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
W912BU
Maintenance Dredging, Delaware River, Philadelphia, PA to Trenton, NJ
THIS AMENDMENT DOES NOT EXTEND THE 3 SEPTEMBER 2015 BID OPENING DATE AT 11:00 A.M.
E5CTCSGF
US ARMY ENGINEER DISTRICT, PHILADELPHIA
WANAMAKER BUILDING, 100 PENN SQUARE EAST
PHILADELPHIA, PENNSYLVANIA 19107-3390
US ARMY ENGINEER DISTRICT, PHILADELPHIA
POC: SANDI FLETCHER
WANAMAKER BUILDING, 100 PENN SQUARE EAST
PHILADELPHIA, PENNSYLVANIA 19107-3390
W912BU-15-B-0010
08/14/2015
08/04/2015
This page was intentionally left blank for duplex printing.
Amendment No. 0001
IFB W912BU-15-B-0010
14. DESCRIPTION OF AMENDMENT (continued)
a. INSIDE PAGE: Please delete this page in its entirety and substitute the revised inside page, annotated Amendment No. 0001, attached hereto.
b. BIDDING SCHEDULE: Please delete the Bidding Schedule in its entirety and substitute the revised Bidding Schedule, annotated Amendment No. 0001, attached hereto.
c. TECHNICAL SPECIFICATIONS:
(1) Section 35 20 23 – DREDGING: Please delete page 35 20 23-12 in its entirety and substitute revised page 35 20 23-12, annotated Amendment No. 0001, attached hereto.
d. CONTRACT DRAWINGS: Please delete the following drawings in their entirety and substitute revised drawings of the same numbers, with the latest revision date of 14 August 2015, attached hereto.
C-001 C-105 C-110 C-101 C-106 C-111 C-102 C-107 C-112 C-103 C-108 C-301 C-104 C-109 C-302
e. Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment No. 0001. Failure to acknowledge all amendments may be cause for rejection of the bid.
4 AUGUST 2015
INVITATION NO. W912BU-15-B-0010
PHILADELPHIA DISTRICT
CORPS OF ENGINEERS
INVITATION FOR BIDS
FOR
MAINTENANCE DREDGING
DELAWARE RIVER
PHILADELPHIA, PENNSYLVANIA TO TRENTON, NEW JERSEY
I. NOTE THE AFFIRMATIVE ACTION REQUIREMENT OF THE EQUAL OPPORTUNITY CLAUSE
WHICH MAY APPLY TO THE CONTRACT RESULTING FROM THIS SOLICITATION.
II. BIDDERS ARE REQUIRED TO COMPLETE THE REPRESENTATION AND CERTIFICATIONS
PORTION OF SECTION 00 45 00 OF THIS SOLICITATION AND SUBMIT THIS WITH THEIR
BID.
III. PROSPECTIVE BIDDERS ARE INVITED TO VISIT THE DISPOSAL AREA TO ACQUAINT
THEMSELVES WITH THE SITE CONDITIONS AND ANY PROBLEMS INCIDENT TO THE
PROSECUTION OF THE WORK. AN ADDITIONAL SITE VISIT WILL BE HELD ON 28 AUGUST
2015. THE SITE VISIT WILL BEGIN AT 11:00 AM. IT IS REQUESTED THAT YOU CALL
MR. CHARLES MYERS AT 215-656-6736 WITH ANY QUESTIONS INCLUDING LOCATION AND
DIRECTIONS CONCERNING THIS SITE VISIT.
00 10 00-3
BIDDING SCHEDULE
(To be attached to SF 1442)
Item Estimated Unit Estimated No. Description Quantity Unit Price Amount
1. Mobilization & Demobilization 1 JOB L.S. $____________
2. Removal and Satisfactory
Disposal of Material 126,808 CY $______ $____________
TOTAL ESTIMATED AMOUNT $_____________________
NOTE:
Bidders must bid on all items.
times of sampling, on the Daily Report of Operations forms required in Paragraph "CONTRACTOR QUALITY CONTROL" of this section. Fax the hydrometer readings (expressed in Grams/Liter) daily to the US Army COE Philadelphia District Office, Operations Division, at 215-656-6922 or provide them directly to the Government Representative in the field. Collect each sample at the sluice from the mixture flowing over the discharge box interior weir as shown on the attached figure. Make a composite sample by partially filling, without overflow, a one-quart container for five or six consecutive intervals such that a total of about 1 gallon is collected and combined in a bucket or other suitable container. Determine the composite sample density by the hydrometer method, no more than 5 minutes after collecting the first one-quart container sample, otherwise discard the sample and make up a new one.
a. Hydrometer Method: The hydrometer used to determine the composite sample density shall be a soil hydrometer conforming to ASTM E100, Hydrometer No. ASTM 152H, -5 to +60 grams per liter. This specified hydrometer reads density directly in grams per liter, so no other computations are required to determine density. Submit the proposed hydrometer brand and model for approval prior to commencing dredging operations. Use the hydrometer as specified by the manufacturer.
b. Weight-Volume Method: When the weight-volume method is used for density determination, measure the total sample to obtain volume in liters and weight in grams. Measurements shall be made with a 1,000 c.c. laboratory cylinder and a scale or balance capable of weighing the sample and cylinder to the nearest gram. Obtain the unit weight by dividing the net weight of the sample in grams (total weight minus the weight of cylinder) by the total volume in liters.
3.3.4 Records
Submit records of disposal area effluent measurements and corrective action taken daily to the Contracting Officer.
3.3.5 Timber Flashboards
Prior to commencement of pumping, provide a sufficient number of flashboards for the sluice as required for the retention of dredged material under this contract and ensure that the entire sluice length is effective. Brush applied preservative treatment shall be available at the site and all cut surfaces shall be heavily brushed as specified in AWPA M4.
3.3.6 Continuing Effluent Control
Upon completion and acceptance of a work assignment, provide continuing, intermittent labor to ensure that effluent control is continued beyond the completion of dredged discharge into the disposal area. Continue the control, including the removal of flashboards, until water impoundment is reduced to that which existed prior to the commencement of disposal into this area. The time required for effluent control beyond completion and acceptance of the work assignment will not be considered part of the completion time for the contract.
3.4 OVERDEPTH AND SIDE SLOPES
3.4.1 Overdepth
Material removed from within a work assignment area, to a depth of not more
Section 35 20 23 Page 11 than 1 foot below the required depth, limited by a vertical plane through the required depth contour, will be estimated and paid for at the contract unit price for removal and disposal of material.
3.4.2 Side and End Slopes
No side or end slopes are specified for this contract. Dredging limits shall be box cut.
3.4.3 Excessive Dredging
Material taken from beyond the limits specified in the Paragraphs "Overdepth" and "Side and End Slopes", will be deducted from the total amount dredged as excessive dredging for which payment will not be made.
Nothing herein shall be construed to prevent payment for the removal of shoals performed in accordance with the applicable requirements of the Special Clauses "FINAL EXAMINATION AND ACCEPTANCE" and "SHOALING".
3.5 ESTIMATED QUANTITIES
The total estimated quantity of material necessary to be removed within the specified limits as shown on the contract drawings, including allowable overdepth and areas outside the turning basin limits as previously specified, is as follows:
Acceptance Station Req'd Dredging Overdepth Total Section to Station to 40' (CY) 40' to 41'(CY) Available (CY) 1 14+300 to 15+100 625 473 1,098 2 23+200 to 24+877 4,799 2,800 7,599 3 31+000 to 33+000 5,189 2,890 8,079 4 42+800 to 43+800 6,000 2,222 8,222 5 59+700 to 61+563 13,309 5,208 18,517 6 63+800 to 66+700 24,408 8,683 33,091 7 67+300 to 68+100 2,110 2,268 4,378 7A 69+500 to 70+500 6,000 3,000 9,000 8 72+000 to 74+300 10,000 6,600 16,600
9 DELETED 0 0 0
10 81+800 to 83+503 14,364 5,860 20,224
TOTALS 86,804 40,004 126,808
3.6 LIMIT OF DREDGING
3.6.1 General
The areas to be dredged are within the contract limits as indicated on the contract drawings, and as specified in the Special Clause entitled: FINAL EXAMINATION AND ACCEPTANCE, and as defined by dredging prism indicated in the Paragraphs "OVERDEPTH AND SIDE SLOPES" and "MEASUREMENT AND PAYMENT", of this section.
3.6.2 Quantity Acceptance
Clear each acceptance section in its entirety to the required depth prior to acceptance of the work by the Government. If after-dredging surveys of a portion of an acceptance section indicate dredging is required, and it was indicated by the before-dredging surveys, remove required material found to be remaining above the required depth, unless such dredging is waived by the Contracting Officer. Material removed as a result of
Section 35 20 23 Page 12
| SF30 |
| AMENDMENT DESCRIPTION |
| INSIDE PAGE |
| 03 15 00 REVISED BIDDING SCHEDULE |
| 35 20 23 PAGE 12 |