13R0037-SPECS-AM1.pdf
PDF 84 KB Posted
- Solicitation number
- W912BU-13-R-0037
About this file
13R0037-SPECS-AM1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912BU-13-R-0037_Amendment0002.pdf | ||
| 13R0037_RTA_SPECS.pdf | ||
| 13R0037_RTA_Dwgs.pdf | ||
| Site_Visit_Request_Letter_(English).doc | DOC document | |
| Copy_of_IAA_DBIDS_Form.xls | XLS spreadsheet | |
| Emirati_Security_Declaration_Form.pdf | ||
| Al_Dhafra_Site_Visit_Request.docx | DOCX document | |
| DBIDS_Registrations-_(Form_Info).pdf | ||
| Blue_Badge_Temporary_Spreadsheet.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
THIS AMENDMENT DOES NOT EXTEND THE 20 AUGUST 2013 PROPOSAL DUE DATE AT 2:00 P.M. EST
(Continued)
1. CONTRACT ID CODE PAGE OF PAGES
J 1
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU-13-R-0037
X 9B. DATED (SEE ITEM 11)
19-Jul-2013
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required) Design/Build Fire Protection Water Storage, Al Dhafra Air Base (ADAB), Abu Dhabi, United Arab Emirates
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
07-Aug-2013
CODE
US ARMY ENGINEER DISTRICT, PHILADELPHIA
CONTRACTING DIVISION – ROOM 643
WANAMAKER BUILDING, 100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
W912BU 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
US ARMY ENGINEER DISTRICT, PHILADELPHIA
POC: EMILY M. ACEDO-MALANEY
WANAMAKER BUILDING, 100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
FACILITY CODE CODE
EMAIL: TEL:
W912BU
THIS PAGE HAS BEEN INTENTIONALLY LEFT BLANK
Amendment No. 0001
RFP W912BU-13-R-0037
14. DESCRIPTION OF AMENDMENT (continued)
a. SPECIFICATIONS:
(1) Section 01 80 00.12 10 – TECHNICAL REQUIREMENTS – FIRE PROTECTION WATER STORAGE: Please delete pages 01 80 00.12 10- 23, 24, 25 and 29 in their entirety and substitute revised pages 01 80 00.12 10- 23, 24, 25 and 29, annotated Amendment No. 0001, attached hereto.
b. Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment No. 0001. Failure to acknowledge all amendments may be cause for rejection of the bid.
This page was intentionally left blank for duplex printing.
2.20.3 Water Storage Tank
Provide two (2) 300,000 gallon water storage tanks located at the locations shown on the conceptual Site Plan.
The Contractor shall provide potable bolted steel ground water storage tanks with liner (GST) according to section 33 16 15(edit by contractor).
This tank will store treated water. The storage facility shall be located above drainage areas and locations subject to flooding as approved by the Contracting Officer. The storage facility shall be located on the higher elevations of the site to promote gravity flow and reduce pumping requirements. Contractor shall construct a pump house in accordance to the requirements contained herein, to deliver design flow pressure to meet the fire protection requirements of the system..
PART 3 ARCHITECTURAL
3.1 General Pump House Requirements
Provide a pre-fabricated pre-engineered building (PEB) to completely enclose all equipment required to pump water to the fire protection facilities in accordance with the requirements contained herein. Provide a concrete slab designed to support the weight of the fire pump house including the equipment within, Including but not limited to, the diesel fuel storage tank, water mains, pumps, etc. required for the system.
The design shall be performed and documents signed by professional engineers and/or a registered architect. License shall be administered by one of the fifty United States or equivalent recognized international body. Documentation of equivalency shall be provided to the Contracting Officer for evaluation.
3.1.1 Design Objectives and Considerations
Design and construction shall comply with the requirements contained herein. All facilities will have a life expectancy of not less than 25 years. This document establishes minimum standards for design and construction quality. Floor plans, elevations and building sections have been included in this document, but improvements to these plans are encouraged, as are innovative, creative, or cost saving proposals which meet or exceed these requirements. The enclosed floor plans are provided primarily to communicate desired space relationships and establish approximate room sizes. Appropriate room sizes shall be determined based on functional requirements. Select materials, equipment and construction methods that provide overall economy consistent with functional and aesthetic requirements, reasonable comfort and sound architectural and engineering practice. The level of local technology shall be considered with respect to construction, operation and maintenance of the facility.
Conflicts between this document and local standards shall be brought to the attention of the Contracting Officer’s representative for resolution.
3.1.1.1 Finished Floor Elevation
Set finished ground floor elevations with respect to the finished grades.
Place the finished floor no less than 200 mm (8 inches) above the finished grade for slab-on-grade construction, 350 mm (18 inches) for frame construction. The finished grade is defined as the final grade elevation.
Section 01 80 00.12 10 Page 23
3.1.1.2 Orientation
Orientation of the building(s) shall be coordinated with the civil engineer to insure that placement of building features such as primary entrances and service entrances are logically considered with respect to adjacent site characteristics such as pedestrian circulation routes, roads, parking areas and other buildings.
3.1.1.3 Exterior Appearance
Buildings shall be designed to enhance or compliment the visual environment of the installation. Exterior building materials, roof forms, finishes and colors shall be compatible with those of existing adjacent buildings of similar construction. Mechanical or electrical equipment located outside of the building shall be shielded from view. All exterior attached piping, wiring, etc., shall have a metal accessible metal covering to match adjacent finish.
3.1.1.4 Corrosion
Exposed metals must be carefully selected and appropriately protected against corrosion. Paint all exposed metal steel surfaces or use galvanized metal. Insure all edges are either galvanized or treated against corrosion. The project site may have corrosive soils, constant winds and limited rainfall resulting in windblown chloride containing dust which can lodge in joints and welds and result in condensation on metal surfaces.
3.1.2 Demolition
Contractor shall examine the site and construction and verify with the government provided design. If any demolition is needed, the contractor shall obtain authorization from the Government. Comply with host nation hauling and disposal regulations and comply with ANSI A10.6. Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal or demolition work performed under this contract.
Do not disturb existing construction beyond the necessary for installation of new construction. Hazardous materials shall be identified and disposed of in an appropriate manner. Prevent the spread of dust and debris and avoid the creation of a nuisance in the area surrounding the work site.
3.1.3 Life Safety
The designer shall perform a life safety analysis to include a narrative and supporting floor plans addressing building occupancy classification, construction type classification, egress capacity, travel distance, allowable areas, fire separation requirements, etc. The designer shall follow the guidelines as set forth in UFC 1-200-01 General Building Requirements. This documentation shall be included in the design submittal package. The use and occupancy classification shall be as defined in Section 302 and the construction type classification shall be as defined in section 602 of the International Building Code (IBC).
3.1.4 Accommodation of Individual with Physical Disabilities
ACCESSIBILITY REQUIREMENTS
Design the facility to comply with the requirements of "Architectural Barriers Act Accessibility Standard Department of Defense Facilities" found
Section 01 80 00.12 10 Page 24 at http://www.access-board.gov/ada%2Daba/aba-standards-dod.cfm.
These buildings will be occupied by only able-bodied personnel and are therefore not required to meet the Americans with Disabilities Act Accessibility Guidelines. (ADAAG).
3.1.5 Leadership in Energy and Environmental Design (LEED)
While these buildings are not required to achieve LEED certification, features which conserve energy, improve livability, utilize recycled materials, etc. are encouraged.
3.1.6 DELETED
3.1.6.1 DELETED
3.1.6.2 DELETED
3.1.7 Applicable Criteria
3.1.3 Applicable Criteria
The following is a list of applicable architectural design and construction criteria. The latest edition, as of the date of the RFP, of any criteria listed shall be applicable. In the event of conflict between criteria, the most stringent requirement shall apply unless noted otherwise in the contract. Comparable recognized standards other than those listed may be acceptable provided the minimum requirements identified herein are satisfied and the Contractor submits documentation supporting the equivalency to the Contracting Officer’s representative for approval.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 318 (2011; Errata 2011; Errata 2012) Building Code Requirements for Structural Concrete and Commentary
Section 01 80 00.12 10 Page 25
ACI 318M (2011; Errata 2011; Errata 2012) Building Code Requirements for Structural Concrete & Commentary
ACI 347 (2004; Errata 2008; Errata 2012) Guide to Formwork for Concrete
ACI 437R (2003) Strength Evaluation of Existing Concrete Buildings
ACI 440.3R (2012) Guide Test Methods for Fiber-Reinforced Polymer (FRP) for Reinforcing or Strengthening Concrete Structures
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
AISC 341 (2010) Seismic Provisions for Structural Steel Buildings
AISC 360 (2010) Specification for Structural Steel Buildings
AISC DESIGN GUIDE 10 (1997) Erection Bracing of Low-Rise Structural Steel Buildings
AMERICAN IRON AND STEEL INSTITUTE (AISI)
AISI SG03-3 (2002; Suppl 2001-2004; R 2008) Cold-Formed Steel Design Manual Set
BUILDERS HARDWARE MANUFACTURERS ASSOCIATION (BHMA)
ANSI/BHMA A156.1 (2006) Butts and Hinges
ANSI/BHMA A156.10 (2011) Power Operated Pedestrian Doors
ANSI/BHMA A156.11 (2010) Cabinet Locks
ANSI/BHMA A156.115 (2006) Hardware Preparation in Steel Doors and Steel Frames
ANSI/BHMA A156.12 (2005) Interconnected Locks & Latches
ANSI/BHMA A156.13 (2012) Mortise Locks & Latches Series 1000
ANSI/BHMA A156.16 (2008) Auxiliary Hardware
ANSI/BHMA A156.17 (2004; R 2010) Self Closing Hinges & Pivots
ANSI/BHMA A156.18 (2006) Materials and Finishes
ANSI/BHMA A156.2 (2011) Bored and Preassembled Locks and Latches
ANSI/BHMA A156.20 (2006) Strap and Tee Hinges, and Hasps
ANSI/BHMA A156.21 (2009) Thresholds
Section 01 80 00.12 10 Page 26
- UFC 1-200-01 General Building Requirements, with Change 1
- UFC 3-110-03 Roofing
- UFC 3-190-02FA Design: Builders’ Hardware
- UFC 3-190-06 Protective Coatings and Paints
- UFC 3-230-08A Water Supply: Water Treatment
- UFC 3-240-02N Wastewater Treatment Systems; Augmenting Handbook
- UFC 3-600-01Fire Protection Engineering for Facilities, with Change 1
- UFC 4-010-01 DoD Minimum Antiterrorism Standards for Facilities, with Change 1
- U.S. Army Corps of Engineers (USACE) EM 385-1-1 Safety and Health Requirements
- U.S. National Archives and Records Administration (NARA) 29 CFR 1910.27 Fixed Ladders
DELETED
3.2 Building Description
The pump house building shall be as described herein and on the attached drawings with specific information relating to building systems and components listed below. See Drawings in attached Appendices.
3.2.1 Pump House (Fire Protection)
The fire water pump house shall consist of a single story pre-engineered metal building (PEB) structure with reinforced CMU and insulated metal panel exterior walls with adequate access for maintenance and replacement of equipment. Building shall incorporate applicable antiterrorism and force protection requirements per the Unified Facility Criteria. The building shall be water-tight and provided with electrical power, lighting, plumbing, heating, cooling, ventilation, power generation, and a fire alarm system. Contractor shall review the concept drawings provided and provide and install the items according to his approved design to complete the construction of the facility. Batched concrete is required. Hand mixed concrete shall not be allowed.
3.2.2 Pre-Engineered Buildings (PEBS)
Provide factory finished insulated metal panels for the exterior walls of the fire pump house. Exterior finish color to match surrounding facilities. Provide insulated metal panels for the roof. Provide minimum R-19 insulation in walls and ceiling. Provides minimum six fluorescent lighting fixtures throughout interior of fire pump house. Provided minimum two sets of double doors to access interior of the fire pump house.
Provide exterior flood lights at exit doors (70 watt high pressure sodium). Provide minimum 6 square meters concrete pavement adjacent to each exterior door. Provide all electric components pre-wired at the factory. Provide bituminous asphalt road to the fire pump house such that the concrete pavement and the paved road intersect. Provide continuous paved surface for the delivery of equipment to the fire pump house. See drawing for additional details. See Structural section for specific requirements.
3.3 BUILDING SYSTEMS AND COMPONENTS
3.3.1 Concrete
Concrete work shall be coordinated with the STRUCTURAL section of this document.
Section 01 80 00.12 10 Page 29
3.3.2 Exterior Enclosure
This system consists of the exterior shell of the facility, which includes all vertical and horizontal exterior closure such as exterior walls, and exterior doors. Roofing is discussed in Paragraph titled Roofing.
3.3.2.1 Insulated Steel Wall Panels
All exterior walls and roof panels shall be steel factory-fabricated units with insulating core between metal face sheets securely fastened together and uniformly separated with rigid spacers. Panels shall have a factory color finish. Insulation shall be polystyrene or polyisocyanurate foam and be compatible with adjoining materials and capable of retaining its R-value for the life of the metal facing sheets; and unaffected by extremes of temperature and humidity. The assembly shall have a flame spread rating not higher than 25, and smoke developed rating not higher than 50 when tested in accordance with ASTM E84. Panels shall be not less than 200 mm wide and shall be in one piece for unbroken wall heights.
Wall panels shall have edge configurations with interlocking ribs for securing adjacent panels. System shall use factory fabricated corners and trim pieces at intersections with other materials. Wall panels shall be fastened to framework using concealed fasteners. Installation shall be in accordance with Designer of Record (DOR)-approved shop drawings and manufacturer's recommendations.
3.3.2.1.1 Vapor Barrier
Continuous vapor barrier or equivalent shall be provided between the inside finished wall surface and the insulation.
a. A vapor barrier of clear polyethylene sheeting, 0.152 millimeter 6-mil, conforming to ASTM D2103 and ASTM D4397 shall be provided on grade under raised floors, between exterior building skins and exterior wall framing, below concrete slabs, and where indicated on the Drawings.
b. Vapor barrier shall be uninterrupted. Seams shall be sealed using a pressure sensitive waterproof tape. Contractor shall avoid cutting or puncturing the vapor barrier during construction.
3.3.2.2 Insulation Systems
Vertical and horizontal polystyrene insulation conforming to ASTM C578 or rigid polyisocyanurate board wall insulating products conforming to ASTM C591 or mineral-fiber blanket insulation conforming to ASTM C 665 shall be provided.
3.3.2.2.1 Insulating R-value
Wall insulating product shall have a minimum R-value to meet the code and the energy design of the facility.
a. Exterior walls shall be insulated to provide an R-19 value as minimum.
b. The ceilings/roofs shall be insulated to provide an R-30 value as minimum.
Section 01 80 00.12 10 Page 30