US ARMY ENGINEER DISTRICT, PHILADELPHIA

CONTRACTING DIVISION

WANAMAKER BUILDING

100 PENN SQUARE EAST

PHILADELPHIA PA 19107-3390

UNDER DPAS (15 CFR 700)

11. DELIVERY FOR FOB

RFQ

SEE SCHEDULE

14. METHOD OF SOLICITATION

IFB RFP

CODE

SEE ADDENDUM

BLOCK IS MARKED

DESTINATION UNLESS

12. DISCOUNT TERMS

(No Collect Calls)

1,000

13b. RATING

13a. THIS CONTRACT IS A RATED ORDER

X

CODE

W912BU-09-T-0035 11-May-2009

b. TELEPHONE NUMBER

215-656-6786

8. OFFER DUE DATE/LOCAL TIME

03:00 PM 19 May 2009

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV 3/2005)

Prescribed by GSA

FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER) 31c. DATE SIGNED

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

22. UNIT 23. UNIT PRICE 24. AMOUNT21. QUANTITY

CODE 10. THIS ACQUISITION IS

UNRESTRICTED

FAX: NAICS:

TEL:

CODE 18a. PAYMENT WILL BE MADE BYOFFEROR

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TEL.

W912BU

SIZE STD:

9. ISSUED BY

FACILITY

CODE

17a.CONTRACTOR/

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

15. DELIVER TO CODE 16. ADMINISTERED BY

SEE SCHEDULE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

EDWARD A BODDIE

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

19. ITEM NO. 20. SCHEDULE OF SUPPLIES/ SERVICES

SEE SCHEDULE

336611

TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS

SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL SHEETS

SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN.

SB

HUBZONE SB

SET ASIDE: 100 % FOR

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

W25PHS91054599A

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

TEL: EMAIL:

2 COPIES

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

.OFFER DATED YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 29. AWARD OF CONTRACT: REFERENCE

X

8(A)

SVC-DISABLED VET-OWNED SB

EMERGING SB

X X

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

SEE SCHEDULE

19. ITEM NO. 20. SCHEDULE OF SUPPLIES/ SERVICES 21. QUANTITY 22. UNIT 24. AMOUNT

PAGE 2 OF

23. UNIT PRICE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT 41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV 3/2005) BACK

Prescribed by GSA

FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

pd2B

Printed:5/12/2009@10:51:10 AM

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lump Sum

DONLON REPAIRS 2009

FFP

The contractor will complete work in accordance with the statement of work, to include:

1. Drydocking & providing utilities and services

2. hull painting

3. fuel tank cleaning

4. propulsion shaft inspection

5. repairs to watertight doors

6. hydrostatic testing of the keel coolers

7. modifications to the navigation lights/mast

Place of Performance: TBD [range between Atlantic City, NJ and Baltimore, MD.]

PERIOD OF PERFORMANCE: Twenty-Four (24) Calendar Days after NTP

FOB: Destination

MILSTRIP: W25PHS91054599

PURCHASE REQUEST NUMBER: W25PHS91054599A

NET AMT

LINE ITEMS

DONLON DRYDOCKING LINE ITEMS

LINE

ITEM

LINE ITEM DESCRIPTION QTY UNIT OF

ISSUE

UNIT PRICE TOTAL

0001 REPAIRS TO WORKBOAT DONLON 1 VSSL

0001AA DRYDOCKING AND REPAIRS (The submittals required for "Drydocking and Repairs” are listed in contract clause H02.) This item is initiated only by a Notice To Proceed issued by the Contracting Officer's Representative after satisfactory completion of Item 0001A. The contractor may not start this item until he receives a Notice To Proceed for this item.

1 JB

0001AB H-101 Drydocking 35 DY 0001AC H-102 Utilities and Services 35 DY 0001AD H-201 Hull Painting 1 JB 0001AE H-202 Anode Replacement 1 JB 0001AF H-203 Audiogaging (If Directed) 150 EA 0001AG H-204 Sounding Tube 1 JB 0001AH H-205 Pilot House Doors 1 JB 0001AJ H-206 Pilot House Heaters 1 JB 0001AK H-207 Air Horn 1 JB 0001AL H-231 Inspect Sea Valves 1 JB

Printed:5/12/2009@10:51:10 AM

DONLON DRYDOCKING LINE ITEMS

0001AM H-701 Mastlights 1 JB 0001AN H-801 Tank Inspections 1 JB 0001AP H-901 Rudder Inspections 1 JB 0001AQ M-101 Propulsion Engines 1 JB 0001AR M-701 Propulsion Shafts 1 JB 0001AS M-901 Misc Maintenance - LABOR (IF DIRECTED) 120 HRS

0001AT M-901 Misc Maintenance - MATERIALS (IF DIRECTED) 120 HRS

0001AU M-901 Misc Maintenance - Burden Charge

(INSERT % RATE HERE:____________)

1 JB

0001AV M-902 Windshield Wiper 1 JB 0001AW M-903 Bilge Pump 1 JB

TOTAL FOR ITEM 0001 1 VSL

INSERT THE LOCATION OF THE SHIPYARD WHERE THE WORK WILL BE PERFORMED:

In accordance with FAR 15-404 (g) (3), an offer may be rejected and the offeror considered unresponsive if the contracting officer determines that the lack of balance poses an unacceptable risk to the Government.

Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly over or understated as indicated by the application of cost or price analysis techniques.

Printed:5/12/2009@10:51:10 AM

Section C - Descriptions and Specifications

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

TP TECHNICAL PROVISIONS

TP-1 SCOPE OF WORK

The contractor shall furnish all engineering, design, labor, services, equipment, parts and materials and perform the drydocking and repairs to the Workboat EVANS listed in this contract.

Drawings, equipment or materials to be furnished by the Government will be specifically listed in the appropriate contract clause. Unless specifically listed, the contractor shall assume no drawings; equipment or materials will be furnished by the Government and shall bid accordingly.

TP-2 DEFINITIONS

The following definitions are applicable to phrases and acronyms used throughout this contract:

• Contracting Officer (KO) - A person with authority to enter into, administer, and/or terminate contracts and make related determinations and findings.

• Contracting Officer's Representative (COR) - A member of the Philadelphia District contract management and quality assurance team authorized by the Contracting Officer to perform administrative and managerial duties. A copy of the COR's authority letter will be furnished to the Contractor at the time of award.

• Government Furnished Equipment (GFE) - Equipment, materials, parts, supplies, or components furnished by the Government to the contractor for installation on the vessel.

• USACE - Acronym for the U.S. Army Corps of Engineers.

• PSBr - Acronym for the Physical Support Branch of the Philadelphia District Corps of Engineers.

• QC - Quality Control. Quality Control is a function of the contractor. Refer to E03.

• QA - Quality Assurance. Quality Assurance is a function of the Government.

• ABS - Acronym for the American Bureau of Shipping

• USCG - Acronym for the U.S. Coast Guard.

Printed:5/12/2009@10:51:10 AM

• CFR - Acronym for the Code of Federal Regulations.

• ANSI - Acronym for American National Standards Institute

• OSHA - Acronym for Occupational Safety and Health Administration

• NFPA - Acronym for National Fire Protection Association

TP-3 STANDARDS

All design, engineering, modifications and repairs to the vessel shall be performed in accordance with the criteria set forth in the latest issues of the following standards:

• U.S. Army Corps of Engineers, Publication No. EM 385-1-1, "Safety and Health Requirements Manual." Dated 03 November 2003.

• American Bureau of Shipping (ABS) "Guide for Building and Classing High Speed

Craft."

• American Boat and Yacht Council (ABYC) - “Standards and Recommended Practices for Small Craft”

• 46 CFR Subchapter T – “Rules and Regulations for Small Passenger Vessels (Under

100 Gross Tons)” [46 CFR 175 - 185].

• 46 CFR Subchapter S – “Subdivision and Stability Regulations” [46 CFR 170 - 171].

• United States Public Health Service (USPHS), Publication No. 393 "Handbook on Sanitation of Vessel Construction".

• USCG, Navigation Rules - Inland/International.

• Institute of Electrical and Electronic Engineers Standards, Publication No. IEEE-45 -

Recommended Practice for Electrical Installation on Shipboard.

• Illuminating Engineering Society, "Recommended Practice for Marine Lighting."

• National Electric Code (NEC).

Note that these standards apply only to the engineering, design and workmanship performed by the contractor as part of this contract including removals, accesses and other work performed by the contractor incidental to the work required by the contract.

TP-4 CERTIFICATION AND CLASSIFICATION

The Tugboat MIKE DONLON has a Certificate of Classification with the ABS, which expires 7 June 2009. It is recorded by ABS as a Class A1 Towing Vessel River & Intercoastal Waterway Service, AMS. The main purpose of this Shipyard and Drydock availability is to renew the certification for another 5 years.

The vessel is not certified by the USCG.

TP-5 INSPECTIONS, TESTING AND TRIALS

The contractor shall provide and maintain inspection systems covering the work specified in this contract in accordance with the requirements

The contractor shall perform Tests, Trials and other operational performance demonstrations as required in Section E – ‘‘INSPECTION AND ACCEPTANCE’’ of this contract.

The contractor shall provide reasonable advance notice (not less than one full working day) to the COR prior to any testing or trials. If the COR, after having received such notification, is not present at the designated time and place for the inspection or test, the contractor shall proceed with the inspection or test. Untimely notification will result in postponement or repetition of the test. Lack of notification will require retesting. All delays caused by improper notification are the responsibility of, and to the account of, the contractor.

The contractor shall furnish a competent and authorized individual to witness and document the results of all inspections or tests.

TP-6 WORKMANSHIP AND CONSTRUCTION STANDARDS

A GENERAL REQUIREMENTS FOR ACCESS

After careful planning and subject to the approval of the COR, the Contractor may cut and/or remove plating or framing members from the vessel for access to machinery, piping, wiring and equipment.

Under the same conditions, the Contractor may also remove piping, wiring, fixtures, fittings, etc., for access and clearance to perform required work.

At the completion of required work, all removals shall be replaced. Replacement shall consist of returning the removed equipment, piping, wiring, structural members and plating to their original locations and reinstallation. Where parts, components or equipment are damaged because of the removals, the contractor shall replace them in kind. Installations shall be in accordance with the original construction drawings or the referenced standards (Refer to TP-3). Fit and finish shall be restored and damaged paint shall be renewed. All removed equipment shall be tested as part of the Tests and Trials required in Section E of this contract. Any removals for access shall be temporarily supported if lack of such support could cause failure or damage to adjacent systems, distortion of adjacent framing or plating, or result in a safety hazard.

B GENERAL REQUIREMENTS FOR HULL WORK

All new hull plating and shapes shall be fabricated from ABS Structural Steel or ASTM

A36, “Specification for Structural Steel”.

Due regard shall be paid to details in both the design and construction of all new and/or modified structures, to prevent structural discontinuities and other stress concentrations. Where openings must be provided in the structure, the contractor shall provide adequate compensation.

Watertight integrity of all bulkheads and decks shall be maintained. Openings created by permanent removal or addition of piping, wiring or other materials shall be closed by means of watertight penetrations or insert plates of equal thickness flush-welded to the bulkheads.

All welds shall be ground flush and smooth.

Sections of stiffeners, beams, girders, etc., shall be welded to the bulkheads to maintain continuity of structure.

Openings cut into decks and bulkheads shall be adequately compensated by bounding bar to maintain original strength.

All watertight, oil tight and weather tight work shall be tested for tightness prior to painting. Testing procedures, other than hydrostatic testing, shall be submitted to the COR for approval. Submittals shall include complete particulars on the testing procedure(s) proposed and, if air testing is used, the method of controlling the air pressure. Water used for testing shall be potable quality to prevent contamination of the compartments and piping.

C GENERAL REQUIREMENTS FOR FOUNDATIONS AND SUPPORTS

Suitable foundations shall be provided under all new units of machinery.

Foundations shall be built up of plates and structural shapes to the dimensions required for satisfactory support, and shall assure rigidity, freedom from vibration and designed for secure containment of the equipment in event of crash stops.

Where dripping water or oil can be expected, the top plates of foundations shall project beyond the edges of the bedplates or bases of units being supported and formed into spill containment/drip pans. Flat bars welded around the edges of the top plates may be used to retain any leakage. Valved drains shall be provided at the ends or corners of the pans to facilitate fluid removal or recovery.

Foundations shall extend beyond the equipment fore and aft or transversely to distribute the load and to avoid excessive weight concentrations.

Doublers insert plates, girders, headers and stanchions shall be fitted and under-deck framing shall be reinforced to support units mounted on deck.

D GENERAL REQUIREMENTS FOR MATERIALS

All materials provided by the contractor shall be suitable for marine applications and shall be subject to approval of the COR.

All new hull plate and hull-framing members shall be mild steel suitable for marine use.

All fasteners used shall be made of AISI type 304 or type 316 series stainless steel.

E GENERAL REQUIREMENTS FOR PIPING

All piping required in these specifications shall be designed and installed to obtain optimum operating conditions, and shall be compatible with the machinery or equipment serviced.

All piping, valves and fittings shall comply with material specifications of the design standards for that particular service.

Piping shall be led as directly. Piping shall include valves, unions and fittings.

Unions and flanges shall be provided to facilitate installation and subsequent removal.

Flexible connections to machinery components shall be provided where vibration may be anticipated.

Piping shall not pass over switchboards and be kept clear of switchgear, wiring, etc.

All work shall be templated from the vessel.

Piping shall be secured by supports and hangers so as to avoid excessive strains;

avoid the weight of the piping being transmitted to valves and fittings; minimize the effects of vibration, shock, pitching and rolling of the vessel; and permit proper thermal expansion and contraction. Provision may be made for expansion and contraction by changes in direction of pipe runs or by use of expansion bends, joints, loops or offsets.

Exhaust piping shall be welded for all sizes.

All burrs shall be removed from the ends of all piping after any cutting or threading. Pipe ends shall be dressed with a reamer before installation.

Valve type shall be consistent with the service. All valve materials shall be stainless steel.

An aluminum label plate shall be attached to the hand-wheel of all new valves to indicate its function.

Where pipes are carried through watertight bulkheads, decks or tank tops, the watertight integrity of the structure shall be maintained.

Heat sensitive materials shall not be used in piping systems that penetrate watertight subdivisions.

All fastenings used to connect valves to shell connections shall be of stainless steel.

Where dissimilar metals occur, the contractor shall insulate to prevent electrolytic action.

F GENERAL REQUIREMENTS FOR MACHINERY SYSTEMS

Where new machinery and equipment is to be installed, or when existing machinery and equipment is relocated, the contractor shall mount the items on foundations as specified elsewhere herein.

All fastenings, bolts, (fitted or otherwise) studs, nuts, washers, gaskets, etc., shall be installed using anti-seize compound furnished by the contractor unless otherwise specified.

Any defective or missing fasteners shall be renewed at Contractor's own expense.

Where detailed disassembly, assembly, or installation procedures appear in this specification, they are presented for the contractor's information and convenience in estimating the possible extent of the work to be done. The inclusion of these detailed procedures does not relieve the contractor of responsibility for doing all work necessary and in the proper manner for satisfactorily accomplishing the specified ultimate objective.

G GENERAL REQUIREMENTS FOR ELECTRICAL SYSTEMS

All electrical installations as set forth elsewhere in these specifications shall be in compliance with the referenced rules, regulations and standards, especially with regard to ambient and working temperature requirements.

Electric cable shall be capable of handling the required amperage.

Electrical installations shall be such so as to eliminate the possibility of mechanical injury or damage from the accumulation of dust, oil, vapors, steam, dripping liquids, etc.

New cable runs shall be supported at intervals of not more than 18" apart where vertical and 14" apart where horizontal. Straps, hangers, and standoffs shall be aluminum with stainless steel fasteners. Plastic type straps are permitted only behind sheathing/paneling. No cable runs will be permitted below the deck-plates, except for bilge pump wiring. Cable penetrations, where required to be watertight, shall have approved kick-plates, stuffing tubes, etc.

All electrical supplies and/or installations to meet CFR 46, Subchapters J and T, as well as all applicable NEMA, NEC and ANSI standards.

H GENERAL REQUIREMENTS FOR HOT WORK

Prior to any hot work commencing in any compartment, the compartment shall be pumped dry, cleaned, and gas-freed in accordance with 29 CFR 1915, Occupational Safety and Health Standards for Shipyard Employment, and other applicable standards.

The COR shall be furnished a certificate stating that each compartment gas-freed by the contractor has been tested by an approved certified chemist or competent person and that the space is safe for burning and/or welding.

The contractor shall provide proper ventilation of spaces in which work is required or men are required to enter. Disposal of material accumulated during gas-freeing work shall be the responsibility of the contractor and shall be in accordance with all federal, state and local laws.

The contractor shall post and maintain a fire watch whenever any hot work is being performed. If work is being performed on a bulkhead, a fire watch shall be posted on both sides of the bulkhead.

I GENERAL REQUIREMENTS FOR WELDING

Only welders who have successfully passed the qualifications test of the ABS, the USN or the USCG for steel welding shall do all welding under this contract.

The contractor shall bear the expense of conducting these tests, and shall certify by name to the COR those welders who have successfully passed the prescribed tests.

The contractor shall require any welder to repeat these tests when, in the opinion of the COR or his appointed representative, the work of the welder indicates a reasonable doubt of his efficiency. In such cases, the welder shall be recertified as above.

The electrodes used throughout the work shall be suitable for use with the parent metal at each weld. Electrodes shall be received on the job in unbroken packages bearing the manufacturers' label or be otherwise marked. Certified statements shall accompany each shipment of electrodes to the effect that sample pieces, representative of each kind and size in each shipment, have satisfactorily passed the tests required by the ABS, the USCG, and/or the USN for welding on the parent material.

The COR shall be provided with documentation that certifies compatibility of electrode with parent material.

Welding procedures, where welding to a casting or a forging, shall be submitted to the COR for approval prior to welding. The procedure shall cover the type of weld process, welding electrode, pre-heat, welding sequence and stress relief required.

All welding shall be smooth, tight and free from undercuts, porosity, craters and gas inclusions.

Shell and deck butts and flush seams shall be back chipped or gouged to sound metal from the closing side before welding.

All sharp and/or rough edges shall be ground smooth and all weld splatter shall be removed.

All welds for temporary dogs used during modifications or to secure plate in place while welding shall be ground flush with the surrounding metal.

Assembly of all welded joints before welding shall be such as to secure proper gaps in butt welds and metal contact in fillet welds.

Welding shall not be used to close openings larger than stipulated for each plate thickness by the ABS.

All watertight seal welds shall be of a “bead” type. No “weave” welding is permitted.

Welding procedures, as to direction, length, number, temperature and sequence, shall be carefully planned to minimize distortion and locked-in stresses.

Any welding to or of hull shell plating, watertight and/or oil-tight bulkheads shall be inspected by the ABS. This includes the removal of existing plate, examination of the remaining surrounding plate, examination of the fit-up, and examination of the final welding.

The contractor shall maintain a log of all welders who worked on the vessel throughout the repair period, their certification and the repair Clauses on which they worked.

This log shall be made accessible to the COR at any time during normal business hours.

Testing of welds, where required, shall be addressed under the individual repair Clauses.

The contractor shall provide a certified statement from the manufacturer for each shipment of electrodes used. Documentation shall also be provided stating that the electrode is compatible with the parent/base metal.

J GENERAL REQUIREMENTS FOR WORKMANSHIP

All parts of the work intended to join or bear upon others shall be cut or trimmed to fit neatly.

All faying surfaces shall be clean and smooth before bolting up. Shims or liners shall not be used for the purpose of overcoming a bad fit.

Lightening holes may be punched, sawn or sheared and all burrs and cutting slag shall be removed.

Weld spatter shall be removed from all plating and stiffeners.

All mounting holes shall be drilled and reamed. Holes in members having sharp curvature shall be avoided whenever possible.

All frames and longitudinals shall have limber holes and/or snipes of adequate size to allow water to flow to the lowest point of each compartment and to allow air to escape.

All joints or areas of connection between aluminum and dissimilar metals shall be properly insulated by gasket material.

All fastenings used for connecting aluminum shall be made of AISI type 304 or type 316 series stainless steel.

All labor shall be especially skilled for each kind of work, thorough, first-class in every respect and under competent direction.

Where work of one trade joins, passes through or is on other work, there shall be no discrepancy or misfit when completed. In engaging one kind of work with another, marring or damaging of previously acceptable construction shall be cause for rejection.

K GENERAL REQUIREMENTS FOR PAINTING

The contractor shall seal off all ventilation, antennas, engine room, exhaust, tank and fan vents or openings, and all other intake or exhaust venting/piping and cover all zinc anodes, transducers, windows, propellers, propeller shafts, shaft bearings, rudders stocks, and other fixtures that could be damaged or introduce contamination into the vessel from the high pressure water washing, sandblasting, or painting.

All areas contaminated with grease, oil, lubricants or other foreign matter shall be cleaned with a solvent similar to DEVOE Devprep #88, 788-T-000.

Defective shell plate discovered during sandblasting shall be reported to the COR immediately.

The paint system shall be applied in strict accordance with the manufacturer's guidelines and recommendations, including time between coats, proper application equipment, thinning and disposal of excess paint and thinner and cleaning of equipment.

All painting underwater surfaces shall be completed and accepted by the COR prior to refloating the vessel.

The contractor shall furnish the COR with a thickness gauge suitable for use on aluminum to verify proper wet/dry film thickness.

All paints used in the performance of this work shall be within the manufacturer’s specified closed container and “pot” shelf life.

All overspray of any new paint onto existing finished surfaces shall be removed and all surface repaired to original condition.

Colors shall conform to Federal Standard 595, in accordance with the following schedule:

AREA COLOR AND FS595 NUMBER

Hull Exterior Black/17038 Deckhouse Exterior Old Ivory/13695 Decks & Housetop Deck Red/10076 Hull & Deckhouse Interior White/27880 Deck Fittings Yellow/13655 Hull Markings White/27880 Exterior Deck Coaming Striping Red/11136 Handrails & Stair Rails Black/17038 Antifouling 1st Coat Manufacturer Contrasting Color Antifouling 2nd Coat Manufacturer’s Red

L GENERAL REQUIREMENTS FOR DISPOSAL OF FLUIDS

All fluids, including, but not limited to, diesel fuel, lubricating oil, hydraulic fluid, antifreeze/coolant, bilge wastes, battery acid, penetrating and cutting oils, dye penetrants, and paint thinners removed from the vessel or generated by the contractor in the course of performing the required work shall be disposed of by the contractor in accordance with all Federal, State, Regional and Local laws, rules, regulations, and guidelines for the disposal of hazardous materials.

This also applies to any rags, clothing, equipment or other materials exposed or contaminated with such fluids.

M GENERAL REQUIREMENTS FOR CONFINED SPACES

The contractor shall comply with all requirements of Federal Law contained in 29

CFR 1910 and 29 CFR 1915 for entry into, monitoring of, rescue from and closure of confined spaces during the performance of the repair work performed as a part of this contract.

The contractor shall have a competent person on-site whenever any work is being performed in a confined space and shall post required certificates in the immediate vicinity of the confined space and maintain a log of all inspections and certificates.

The COR shall be provided with copies of the Gas-Free certificates and all competent persons logs as part of the overhaul record at the conclusion of the contract.

N GENERAL REQUIREMENTS FOR SAFETY

The contractor shall comply with the requirements of EM 385-1-1, “U.S. Army Corps of Engineers Safety and Health Requirements Manual” throughout the contract period. It can be found online at http://140.194.76.129/publications/eng-manuals/em385-1-1/2008_English/toc.html

The contractor shall maintain Safety, Fire, and Security programs as required by

Section H of this contract throughout the contract period.

HULL HULL SECTION ITEMS

HULL-101 DRYDOCKING

References: Drawing No. 533-D170-03; “Docking Plan” Drawing No. 533-D170-02; “Lifting Gear” MIL-STD-1625; “Safety Certification Program for

Drydocking Facilities and Shipbuilding Ways for US Navy Ships”

NAVFAC DM-29.1; “Graving Docks, Design Manual 29.1”

Provide all labor, services and materials and perform the work required in this clause.

Provide a certified marine railway, or a certified synchronic-lift, etc. and qualified personnel and necessary equipment to dock the vessel.

The DONLON is 53-foot steel tugboat with a beam of 19’-2”. The loaded draft of the vessel is 5’ – 0” aft and 4’ – 0” forward. Gross tonnage is 50 tons loaded.

Proposals from bidders requesting the use of non-NAVSEA certified drydocking facilities should be accompanied by the following requirements:

• A current independent detailed engineering evaluation and analysis (within one calendar year) of the proposed facility supporting its structural integrity and verifying that it is structurally and operationally safe.

• A certificate signed by a person authorized to sign offers, verifying that the facility is presently safe

• Engineering stability calculations in accordance with the above references verifying that the facility is presently safe

• Use of a certified dock master, and a trained docking crew in accordance with the above references is required when using an uncertified docking facility

Provide and set blocks to support and distribute the weight of the vessel while out of water and to prevent movement of vessel. Blocks should provide for a minimum of 40-inches clearance under the hull.

Haul the vessel out of the water and set on the blocks/cradles. The vessel is keel cooled.

Do not place blocks or boat jacks in way of keel coolers. The keel coolers in no way shall be used to support the weight of the vessel.

Participate in the joint docking inspection.

Immediately after drydocking the vessel, and before the hull and any marine growth has had a chance to dry, the entire hull from the keel to the top of the bulwarks shall receive a fresh water high pressure wash at no less than 5000 psi.

Upon completion of all underwater-related repairs and following the joint undocking inspection, return the vessel to the water.

All lay days, demurrage and other dock costs, including the costs of weekends and holidays, necessary to perform the repair work listed in this contract shall be included in the cost of this Line Item.

Estimate on 35 calendar days for dry-docking. Price per day.

HULL-102 UTILITIES AND SERVICES (UNIT PRICE)

The contractor shall provide all labor, materials, and equipment and provide, adjust and maintain the drydock and pier side utilities and services specified in this clause for the duration of the contract.

Services shall be connected and operating within 2 hours after arrival of the vessel at the contractor’s facility and shall continue until the COR. accepts the vessel.

Payment shall be made only for the actual number of days the vessel remains and utilizes services at the contractor’s facility.

Unit price shall cover all costs incidental to and charged direct to the job, and not otherwise included as overhead.

Services and utilities shall consist of the following:

• WATER: Furnish fresh potable water for filling water tank and deck wash down.

Potable water shall be lead-free and meet local municipal water standards. Provide certificate to COR indicating water to be safe for human consumption.

• SHORE POWER: Provide necessary labor to connect, maintain and disconnect shore power service for initial hook-up, re-blocking and moving vessel to pier side.

Provide electrical service for the duration of the repair period.

Shore power service to be 50 amps (minimum), 120/240 VAC, 60 Hz, single phase.

The vessel contains a number of components and systems that are sensitive to voltage fluctuations. The contractor shall be responsible for removal, repair or replacement, reinstallation and testing of electrical equipment that fails while the ship is in the contractor’s possession due to voltage surge or fluctuation.

The vessel shall be grounded to earth via a grounding conductor when operating on shore power. Ensure the vessel is galvanically isolated from the shore (earth), using a galvanic isolator or an isolation transformer. Application and installation of this device shall be in accordance with ABYC E-8.20.

• TRASH REMOVAL: Provide receptacles, equipment and labor to collect and remove garbage and trash from the vessel. The trash bins shall be located near the gangway.

• GANGWAY: Provide a gangway with safety net or ladder for access to and from the vessel.

Install (on opposite side of vessel from gangway) and maintain a separate ladder from the bottom of the drydock to the main deck for emergency egress during the docking period.

Estimate on 35 calendar days. Price per day.

HULL-201 HULL PAINTING

Reference Drawing: 533-D205-01; “Outboard Profile”

The contractor shall furnish all necessary labor, materials, services and equipment, prepare, sandblast, and paint the hull of the vessel in accordance with the following specifications.

A SURFACE PREPARATION AND INSPECTION

Immediately after drydocking the vessel, and before the hull and any marine growth has had a chance to dry, the entire hull from the keel to the top of the bulwarks shall receive a high-pressure wash.

The high-pressure wash shall be performed with fresh water only and shall be no less than 5000 psi. All washing to be performed shall be done from above (i.e. from the top of the drydock, scaffolds, etc.) with the nozzles pointed down to the floor of the dock to prevent the spread of water to the upper portion of the vessel and into any interior spaces.

Any areas contaminated with grease, oil, dirt, rubber streaks or other foreign matter shall be cleaned with DEVOE “Devprep # 88”, 788-T-000 and washed clear with the high pressure wash.

After the hull has dried and within 24 hours after drydocking the vessel, a joint inspection shall be conducted with the COR and the contractor.

The entire hull from the keel to the deep load line shall be surveyed. All areas where the anticorrosive system (primers) have been disturbed or removed shall be identified and clearly marked. A written condition report with recommendations shall be submitted by the contractor to the COR within 24 hours after performing the joint inspection. The report shall include a summary of the hull's condition, including an estimate of the total square-footage of the hull that requires a renewal of the anticorrosive system.

All of the manufacturer's and USACE preparation and environmental conditions must be met prior to beginning any operation. Surface temperature, humidity, wind conditions, dew point and wet-bulb readings shall be checked and recorded at least twice daily.

B BLASTING

All blasting shall be done from above with the nozzles pointed down toward the floor of dock to prevent the spread of sand or shot to the upper portion of the vessel and into the quarters and machinery spaces.

Sand and dust on decks resulting from sand or shot blasting shall be removed from the vessel daily by broom sweeping.

Scaffolds, cherry pickers or other means shall be provided for use of personnel in blasting and painting. The use of extension pipes for blasting or painting of the vessel from the deck of the drydock is unacceptable and will not be permitted.

As an option, hydro blasting, at a minimum of 30,000 psi, may be used in lieu of sand blasting.

Artificial illumination shall be used on any area specified to be cleaned and painted, which can not be clearly seen with eyes of normal vision at any time the work is being performed.

This work shall be coordinated in writing in advance with the COR.

Prior to abrasive blasting, precautions shall be taken to protect the hull and machinery from flying sand, dust and water discharge. This also applies to blasting on other ships in the vicinity. All the main deck scuppers shall be equipped with half pipes or dammed to keep water off the hull during abrasive blasting.

All open fans, vents, doors, hatches, air conditioner, antennas and wiring, windows, name boards, castle, ship’s bell, electrical outlets, navigation lights, wipers, spot light, machinery and deck gear shall be sealed with plastic film or a suitable substitute prior to blasting and painting operations. As an option, equipment may be removed prior to blasting and reinstalled after the last coat of paint has dried.

Abrasive blasting shall not be carried out while the engines, propellers, hydraulic system, etc., are exposed. If propeller shafts, hydraulic actuators, etc., are off the vessel during the blasting, all openings must be securely protected against contamination. It is of the utmost importance to insure that these systems are not contaminated.

Special care shall be taken to mask and fully protect the transducers, shafts, zinc anodes, propellers, and other underwater equipment against abrasion, damage, and painting.

Any damage to the vessel or its components due to lack of or improper painting/blasting protection shall be repaired to original by the Contractor at no additional cost to the Government. The Contractor shall contact the COR to inspect and approve the blasting/painting protection prior to the start of the blasting process. It shall be the responsibility of the Contractor to maintain the blasting/painting protection for the duration of the blasting/painting process. At no time shall this be a cause for extension of contract time or additional cost to the Government.

The designated areas of the underwater hull and freeboard, as determined by the joint inspection, shall be blasted clean using dry sand, hydro blast or shot blast to a brush-off blast in accordance with Steel Structures Painting Council Specification SSPC-SP-7. Completely remove all oil, grease, dirt, rubber streaks, loose paint and foreign matter. All remaining and paint should be tight and the surface should be sufficiently abraded to provide good adhesion and bonding of paint. Blast overspray shall be kept to minimum so as to reduce the total amount of coatings to be renewed.

Any overspray of new paint onto the sides and upper deck of the house shall be removed and all paint repaired to the original color scheme at no additional cost to the Government using the DEVOE paint system. The contractor shall monitor wind conditions to ensure that no sandblast or paint spray damages nearby vehicles or vessels;

the Government will not be responsible for any damages incurred due to improper scheduling and monitoring of the blasting/painting process. The paint system applied in accordance with the manufacturer’s guidelines and recommendations.

C PAINTING (Deep Load Line to Top of Bulwarks)

The hull from the deep load line to the top of the bulwarks shall be prepared and painted in accordance with the following specifications:

• After pressure washing the hull as required in Part A, SURFACE PREPARATION preceding, conduct a visual inspection of the hull and identify areas that require blasting due to the anticorrosive system (primers) being disturbed or foreign material not removed by pressure washing.

• Blast these areas and apply 1 spot coat of AMERON “Amercoat 385”, Red, 6 mils wet/4 mils dry. Apply 1 spot coat of AMERON “Amercoat 450HS”, Black, 3.5 mils wet/2 mils dry on any affected area from the deep load line to the top of the bulwarks. Any blasting shall be performed as outlined in Part

B, BLASTING.

Estimate on 25% of total surface area above the waterline for spot coating and

100% for final coat.

Lines shall be cut with brush or roller, remainder may be sprayed.

Paint all draft marks, legends, ABS load line and plimsoll marks with one coat of white color paint, similar to AMERON “Amercoat 450HS”, White, 3.5 mils wet/2 mils dry.

D PAINTING (Keel To Deep Load Line)

The contractor shall proceed with preparing and painting the hull from the keel to the deep load line in accordance with the following specifications:

• The designated areas from the keel to the deep load line shall be blasted clean using dry sand, hydro blast or shot blast to a brush-off blast finish in accordance with Steel Structures Painting Council Specification SSPC-SP-7 as required in Section B, General Requirements for BLASTING.

• A visual inspection shall be conducted by the COR and the contractor to identify areas that will require additional primer/antifoulant. The areas identified shall receive the following to restore primer/antifoulant system:

1 spot coat of AMERON “Amercoat 385 Gray”, 6 mils wet/4 mils dry 1 spot coat of AMERON “Amercoat 385 Red”, 6 mils wet/4 mils dry 2 full coats AMERON Devran ABC #3 antifoulant, Red

Estimate on 25% of total surface area from the keel to the waterline for spot coating and 100% total surface area for anti-foulant.

E PAINTING (House Proper, Main Cabin, Stack, and Decks)

The entire house proper exterior, main cabin and main deck shall be prepared and painted in accordance with the following specifications:

• After preparing the designated areas as required, blast the house proper, main cabin and main deck using dry sand, hydro blast or shot blast to a brush-off blast finish in accordance with Steel Structures Painting Council Specification SSPC-SP-7 as required in Section B, General Requirements for BLASTING.

• Apply 1 spot coat of AMERON “Amercoat 385”, Red, 6 mils wet/4 mils dry to the house proper, main cabin and decks.

• Apply 1 full coat of AMERON “Amercoat 450HS1024”, Ivory, 3.5 mils wet/2 mils dry to the bulkheads.

• Apply 1 full coat of heavy-duty epoxy non-skid coating to all walking deck areas. The coating shall be similar to Devoe Devgrip 237C, Red.

All hatches shall be painted in accordance with the following: Apply one coat of

AMERON “Amercoat 450 HS”, Black, 3.5 mils wet/2 mils dry. All hatch trim and cleat tips shall be painted Safety Yellow.

HULL-202 ANODE REPLACEMENT

Reference Drawing: 533-D170-03; “Docking Plan”

The contractor shall provide all labor, materials and equipment and accomplish the following:

Replace the 12 welded anodes on the perimeter of the hull with new contractor provided bolt-on type hull anodes. All new anodes shall be zinc and be 6” x 12”.

Remove all welded anodes and install welded threaded studs, lockwashers, and nuts. All new hardware shall be stainless steel and be contractor provided. Coordinate installation of anodes with Line Item HULL-202, Hull Painting.

HULL-203 AUDIOGAGING (IF-DIRECTED)

Reference Drawing: 533-D309-02-1; “Frame Construction, Sht 1” 533-D309-02-2; “Frame Construction, Sht 2”

Intent: The intent of this section is to perform ultrasonic thickness testing aboard the vessel when required by the Government Technical Representative or ABS.

Reference Drawings: Reference drawings will be furnished to the contractor for the areas to be audiogaged. These drawings will be used as basis for % wastage.

Description of Work: Provide the services of an ABS-approved ultrasonic thickness testing laboratory (subject to the approval of the Government Technical Representative) to perform ultrasonic thickness testing aboard the vessel as directed by the Government Technical Representative.

NOTE: A copy of the testing certification and equipment calibration and documentation showing ABS approval shall be provided to the Government Technical Representative prior to start of work.

NOTE: Cost of staging areas not currently staged will be handled separately from this Clause.

Prep the areas to be audiogaged. Measure the plate or pipe thickness at these spots.

Record the thickness found at each spot, compare to original plate thickness and record percentage of deterioration.

Furnish to the Government Technical Representative two copies of a detailed report of the ultrasonic thickness reading, the original thickness, the percentage wastage and drawings indicating spot locations. Highlight all areas in excess of 25% wastage in red and 15-25% wastage in orange.

Estimate on 150 test spots. Price per spot. Payment will be made on the total number of spots recorded.

HULL-204 SOUNDING TUBE

Reference Drawing: 533-D670-01; “Vents, Fills and Soundings”

Replace the 2” ballast sounding tube and vent from the ballast tank located forward of the house.

Cut the vent pipe 6” above the deck and replace with a “Y”, a threaded cap, and vent.

The vent shall have a flame arrester, a manual hinged weather shield, and a ball float. The threaded cap shall be attached by a chain when not in use.

HULL-205 PILOT HOUSE DOORS

Reference Drawing: 533-D233-01; “Pilot House Arrangement” following:

Crop out and replace the deteriorated steel around both pilot house door frames and the CO2 cylinder storage compartment on the starboard side.

Inspect and realign both pilot house doors.

Perform a hose test on both pilot house doors to determine the entry point for water.

Once located, seal to prevent future water intrusion.

HULL-206 ELECTRIC HEATERS

Procure and replace the 6 Patton heaters throughout the vessel.

Four heaters are 110VAC, 1500 Watts, and two heaters are 220VAC, 2000 Watts. The blower cover is 14” x 18”.

HULL-207 AIR HORN

Troubleshoot and repair the electric Grover Air horn. The entire air horn system is located in the overhead console in the main cabin.

Remove the overhead panel mid-ship for access. Near the control valve, procure and install an electric push button to operate the air horn.

Upon satisfactory completion of repairs and operation, restore all removals.

HULL-231 INSPECT SEA VALVES

Intent: It is the intent of this Clause to inspect the sea valves in the presence of the Government and the USCG, have them repaired or replaced, then tested and reinstalled on vessel as part of the Drydock Exam.

Description of Work: The contractor shall provide all labor, services, material and equipment to perform and complete the work listed below.

NOTE: All valves, whether new or repaired existing, shall be hydrostatically tested by the contractor to the required test pressure in the presence of the Government Technical Representative. The contractor shall also perform a separate, Final Acceptance, hydrostatic test in the presence of the Government Technical Representative and the USCG.

Remove all sea valves and transport to shop for inspection and repairs.

Identify each removed valve with a brass or aluminum stamped tag showing the location and service.

Clean all valves internally. Examine valves for holes in flange fillet area, eroded discs and seats, bent or damaged valve stems and any other defects. Mark defective areas prior to inspection.

Provide Condition Report to Government Technical Representative listing condition of each valve. Replacement of defective valves will be handled under Modification of Contract.

Of those valves having passed the initial inspection, grind in valve discs and seats.

Replace all gaskets and any defective fastenings and repack valve stems, and leave valves in satisfactory operating condition.

Coat the inside of each valve with 2 coats of Apexior No. 2. New valves shall also be coated.

Hydrostatically test repaired and new valves. Valves failing test due to improper repair or those new valves that are defective from the manufacturer shall be repaired or replaced, and tested at no additional cost to the Government.

CHECKPOINT - Inform Government Technical Representative and USCG that the valves are ready for hydrostatic test. Provide Condition Report to Government Technical Representative listing results of tests.

Replacement of defective valves will be handled under Modification of Contract.

Reinstall accepted valves on the vessel. Furnish and install new gaskets, stainless steel bolts, nuts, and lock washers during reinstallation.

Check valves and connections for leakage during Dock Trial Period. Any leakage at flange due to conditions not previously submitted by Condition Report to Government Technical Representative, or any leakage of accepted valve, shall be corrected at no additional cost to the Government.

Final acceptance constitutes acceptance of valves by USCG and leak-free operation during Dock Trial period.

NOTE: Contractor may elect to replace any existing valve with new prior to the initial inspection at no additional cost to the Government. The new valves shall be of the same construction and pressure rating as existing and shall be coated and hydrostatically tested as detailed above.

HULL-701 MASTLIGHTS

The contractor shall provide all labor, materials and services and procure and install new mastlights.

Procure and install the three 32 pt. all-round lights indicating restricted ability to maneuver which provide a 2 nautical mile visibility range similar to Perko model 1154, with bulbs. The color scheme for restricted maneuverability is red-white-red.

Modify the mast by welding an extension to the mast, and foundations as required to mount the lights. For visibility of the lights, the lower red light shall be above the radar unit.

Extend or re-wire the wires/cables for the existing antennas and lights to accommodate the modified mast.

Wire the lights to the spare breaker in the 12 volt breaker panel in the pilothouse. Wiring from the lights shall be run inside the mast. Ensure a watertight penetration with kick pipe.

Prime and paint the affected areas.

Test the lights in the presence of the COR

HULL-801 TANK INSPECTIONS

A. Intent

The intent of this clause is for the accomplishment of the tank inspection relative to renewing the Donlon ABS certification.

B. Reference:

533-C205-01 General Arrangement 533-D320-01 Fuel Tank Construction 533-D415-02 Doors, Windows, Hatches & Manholes

C. Safety Requirements:

All confined space safety requirements in EM385-1-1 must be adhered to.