CLEAN & INSPECT SPILLWAY SUB-SURFACE DRAINAGE SYSTEM OAHE DAM AND LAKE
Solicitation number
W9128F22R0085
Issued by

View the file

Other files

File Type Posted
Amendment W912F22R0085 0001.pdf PDF
Exhibit_3-Tables_5.1-5.6.pdf PDF
Exhibit_4-ContractDrawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W9128F22R0085 15-Aug-2022

b. TELEPHONE NUMBER

0000000000

8. OFFER DUE DATE/LOCAL TIME

02:00 PM 30 Aug 2022

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W9128F9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

ROBERT J TURNER

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

W59XQG21224375

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 968821 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

COE OAHE PRJT OFC TECH SPT SEC

KRIS CLEVELAND

USAED, OMAHACENWO-OD-OA-T

28563 POWERHOUSE RD

PIERRE SD 57501

TEL: 605-945-3410 FAX:

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$17,000,000

NAICS:

541990

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF100

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

Section SF 1449 - CONTINUATION SHEET

PWS

PERFORMANCE WORK STATEMENT (PWS)

CLEAN & INSPECT SPILLWAY SUB-SURFACE DRAINAGE SYSTEM

OAHE DAM AND LAKE

PIERRE, SOUTH DAKOTA

US Army Corps of Engineers, Oahe Project Office 28563 Powerhouse Road

Pierre, South Dakota 57501-6174

TABLE OF CONTENTS

TABLE OF CONTENTS 1

PART 1 - GENERAL INFORMATION 2

PART 2 - DEFINITIONS AND ACRONYMS 11

PART 3 - GOVERNMENT FURNISHED PROPERTY, EQUIPMENT,

AND SERVICES 13

PART 4 - CONTRACTOR FURNISHED ITEMS AND SERVICES 14

PART 5 – SPECIFIC SERVICE TASKS 15

PART 6 – APPLICABLE PUBLICATIONS 23

PART 7 – ATTACHMENTS / TECHNICAL EXHIBITS 24

Exhibit 1 - Performance Requirements Summary

Exhibit 2 – Deliverables Schedule

Exhibit 3 – Tables 5.1 though Table 5.6

Exhibit 4 – Contract Drawing (8 total) (C-001 through FIO- 3)

PERFORMANCE WORK STATEMENT (PWS)

CLEAN & INSPECT SPILLWAY SUB-SURFACE DRAINAGE SYSTEM

OAHE DAM AND LAKE

PIERRE, SOUTH DAKOTA

US Army Corps of Engineers, Oahe Project Office 28563 Powerhouse Road

Pierre, South Dakota 57501-6174

PART 1

GENERAL INFORMATION

1. GENERAL: This is a services contract to clean and inspect the spillway sub-surface drainage system at Oahe Dam in Pierre, South Dakota.

1.1. Description of Services / Introduction: The sub-surface drainage system is an integral component of the spillway structure at Oahe Dam. Cleaning of this system and the visual inspection of the drains and collector pipes with remote-operated camera equipment is required to document the existing condition of the system.

The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and services necessary to clean and to inspect the spillway sub-drains and collector pipes as defined in this Performance Work Statement, except for those items specified as government furnished property and services. The Contractor shall perform to the standards in this Contract.

1.2. General Project and Spillway Structure Information:

1.2.1. Project Information: The Oahe Dam and Lake Project is a federally owned facility.

Oahe Dam is located in Hughes and Stanley Counties in central South Dakota on the Missouri River, approximately 6 miles upstream of the city of Pierre and approximately 1,072 river miles upstream of the mouth of the river. Oahe is the third dam (downstream) of a system of six mainstem Omaha District dams on the Missouri River. Vicinity and location maps for the Project are shown on Sheet C-001. The general location of the spillway with relation to local highways along with Contractor access routes is also provided on Sheet C-001.

1.2.2. Spillway Structure and Channel Information. The spillway for Oahe Dam is located in a narrow valley in the far right abutment of the dam, approximately one mile from the northwest end of the embankment as shown in Sheet C-001. The spillway consists of an unlined approach channel, a gated spillway structure, and a discharge channel. The use of the spillway was designed to be a rare occurrence. Since completion, the spillway has not been used for release of water. Small volumes of water have been released through the spillway during periodic exercising of spillway tainter gates and for other maintenance related reasons.

The spillway gate structure consists of an eight bay, flat-crested weir; a depressed stilling basin; and a downstream apron as shown on the general layout Sheet C-100. The weir crest and apron slab were constructed at elevation 1596.5 feet and the depressed stilling basin was constructed at elevation 1590.0 feet.

The spillway weir is comprised of seven monoliths and two end segments built integrally with each abutment. The weir has an overall length of 456 feet from abutment face to abutment face. Each monolith consists of an 8-foot wide center pier and 25 feet of weir on each side of the pier. The piers support the tainter gates, bridge, gate hoist machinery and auxiliary equipment. Eight tainter gates, each 50 feet wide by 23.5 feet high, are located between the piers. In a closed position, top of tainter gate elevation is 1620.0 feet. Each gate was retrofitted with a 1-foot high inclined splash plate to elevation 1621.0 feet. Non-overflow abutments on each side of the weir house auxiliary equipment and contain drainage galleries that collect water from the weir, backfill, and frost blanket drainage system.

The depressed basin of the spillway extends downstream from the weir approximately 100 feet to the end sill. The end sill is a gravity concrete block structure that is anchored to the shale foundation by reinforcing bars grouted into drilled holes. The apron slab extends approximately 209 feet downstream from the end sill. Both the depressed basin and apron slab are 18 inches thick and were constructed over a 5’-4” thick frost blanket layer and anchored to the shale foundation with reinforcing bars grouted 10 feet below the bottom of the frost blanket. The frost blanket together with the apron slab, serve to protect the foundation from frost action and facilitates drainage beneath the slab.

A discharge channel extends approximately two miles downstream from the spillway gate structure. Immediately downstream of the spillway structure cutoff wall, the channel bottom narrows to an approximate width of 334 feet and then remains constant. Between the cutoff wall and 140 feet downstream of the cutoff, the channel side slopes transition from 1V on 2.5H to 1V on 3H. The side slopes are armored with riprap in the transition area and the channel bottom is armored with riprap for 240 feet downstream of the cutoff wall. The remainder of the downstream channel is comprised of unprotected shale surfaces. The channel is straight except for one bend located approximately one-half of the distance to the downstream end of the channel. The downstream end of the channel directs flows into a valley allowing discharges to flow across the flood plain toward the river channel.

1.2.3. Spillway Structure Drainage System. An extensive system of drainage and collector pipes and foundation drains (over 8,400 feet) exist beneath the spillway weir; in the abutment galleries; beneath the stilling basin and apron slabs; behind the walls; and behind the apron blocks. The pipes range in diameter from 6 to 12 inches. Pipe material types include perforated vitrified clay pipe (VCP), solid cement asbestos pipe (CAP), solid cast iron pipe (CIP), perforated and solid plastic pipe (PP), perforated and solid galvanized standard steel pipe (GP) and solid corrugated metal pipe (CMP).

1.3 Objectives: The overall objective of this Contract is to clean and thoroughly document the existing condition of the sub-surface drains and collector pipes of the spillway structure.

1.4 Scope: The scope of work for this Contract generally consists of (1) cleaning the spillway structure drainage system pipes and drains by hydro-flushing them (flushing them with large quantities of water or jetting them), (2) visually inspecting the pipes with remote-operated camera equipment and (3) producing a detailed formal report that thoroughly documents the condition of these features. Deliverables for this work will include DVD(s) of the inspection footage and a report that summarizes the procedures and findings of all inspections and includes individual inspection logs that summarizes the condition each pipe segment and documents the location of any significant observation. The Contractor shall perform these services as noted in this PWS. All work shall be conducted in accordance with current professional standards, Corps of Engineers policies, regulations, and procedures. The Contractor is responsible for supplying all equipment, supplies, materials, and personnel necessary for the completion of this work.

1.5 Scope Period of Performance: The period of performance for the PWS shall be 180 days from the date of Notice to Proceed (NTP). Upon receipt of NTP, the Contractor shall submit a draft baseline schedule for completion of the tasks in this PWS for approval to meet the milestones as indicated below. The baseline schedule shall be based on calendar days and shall include milestones for completion of each task provided herein.

Schedule Milestones

ITEM

Duration

(Calendar Days) Draft Baseline Schedule & Work Plan 14 days after NTP Final Baseline Schedule & Work Plan 21 days after NTP Kick-Off Meeting Prior to start of work

On-Site Field Work Start 30 days after NTP

On-Site Field Work Complete 90 days after NTP

Field Work Documentation /Draft Inspection Reports Complete 120 days after NTP

Completion of all Work 180 Days after NTP

1.6 General Information:

1.6.1 Quality Control: The Contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the Contract. A QC Plan will be included in the Work Plan as indicated in Para 1.6.4 below.

1.6.2 Quality Assurance: At any time during the period of performance, representatives of the Contracting Officer may review: work progress; adherence to this PWS and the subsequent Work Plan; and work quality and adequacy. This may include oversight of field operations.

Such review shall not relieve the Contractor from performing all Contract requirements.

1.6.3 Safety: The Contractor shall be responsible for site safety of Contractor and subcontractor employees and any visitors to the work area. The Contractor shall supply the required safety equipment and shall ensure that all Contractor employees and subcontractor employees are properly equipped and trained in all safety procedures and precautions.

An Accident Prevention Plan (APP) shall be developed, maintained on-site during fieldwork and shall be available for review at any time during the period of performance. The APP shall be submitted as part of the Work Plan.

At a minimum, all work shall be conducted in accordance with OSHA requirements and the requirements in EM 385-1-1, (USACE, Nov 2014). This safety manual is available at the following internet site: https://www.usace.army.mil/Missions/Safety-and-Occupational- Health/Safety-and-Health-Requirements-Manual/. All other applicable local, state, and federal rules and requirements shall be adhered to.

It is anticipated that some, if not the majority, of the inspection work can be conducted from the spillway chute slab, top of the spillway walls, or ground surface without physical confined space entry. However, some confined space entry will be required as part of this Contract.

The spillway gallery is a non-permit required confined space and is equipped with a ventilation system. The ventilation system shall be operating at all times during work activities in the spillway gallery. The Contractor shall not enter the gallery without ventilating the work area for a minimum of 30 minutes. The access manholes on the outside of the spillway walls (wall manholes 1E through 3E and 1W through 3W) are permit required confined spaces for entry.

The depth of these manholes is up to 60 feet. The Contractor shall conduct his/her own investigations and make his/her own determination whether or not confined space entry is required to complete the inspection requirements for this Contract when considering his bid.

The Contractor shall abide by all Corps of Engineers and OSHA confined space requirements.

The Contractor shall not enter any manholes or other confined spaces without full coordination and prior approval of the Government Representative. The Contractor’s APP shall specifically address on-site confined space procedures.

Insects, rodents, snakes, and other wildlife could be encountered in the area of the manholes and pipe entrance and exit points. The Contractor shall take appropriate safety precautions and provide appropriate personnel protection equipment. The Contractor shall be responsible to submit to the Government Representative, Material Safety Data Sheets (MSDS) for any materials delivered to the work site.

1.6.3.1 Site Safety and Health Officer: Site Safety and Health Officer (SSHO) shall be designated at the work site at all times to assure adherence to the APP, perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The SSHO role and responsibilities may be assigned to one of the personnel working at the site.

1.6.3.2 Tailgate Safety Meetings: A tailgate safety meeting shall be held at the beginning of the project and daily thereafter for the duration of the project or any time the hazards associated with the work change significantly, whichever is more frequent. The Contractor shall document the occurrence of the safety meeting on a Tailgate Safety Meeting form. The Tailgate Safety Meeting form shall consist of the safety topics covered, date of the meeting, and printed names and signatures of all participants of the field team. In addition, emergency and Contractor POC phone numbers and the location, direction, and route to the nearest hospital shall be verified and discussed for situational awareness at the Tailgate Safety Meeting.

1.6.4 Work Plan: The Contractor shall develop and submit a Work Plan that details the Contractor’s plan for executing this PWS to include procedures for completing tasks and gathering relevant data. Fieldwork shall not commence until the Corps of Engineers reviews and approves the Work Plan. The Contractor shall submit for acceptance a written APP including an Activity Hazard Analysis (AHA) as part of the Work Plan. The APP and AHA shall be in accordance with the criteria described in EM 385-1-1, with reference to this manual in the APP (USACE, 2008). At a minimum and as applicable to task(s), the following information will be provided in the Work Plan.

Project Summary Project Management Baseline Project Schedule Accident Prevention Plan Including Activity Hazard Analysis Quality Control Plan Procedures and Equipment for Cleaning and Conducting Remote Camera

Inspections for Drainage System Pipes.

Points of Contact

1.6.5 Draft and Final Inspection Report: An Inspection Report shall be developed at the completion of the work. The Inspection Report shall contain all documentation and results specified in Paragraph 5.5 and delivered as shown in Technical Exhibit 2. The inspection report shall also describe all pertinent field activities, problems encountered, and measures taken to alleviate these problems, and all other appropriate information and data.

1.6.6 Submittals: The following table outlines the schedule and format of submittals presented in this PWS. Any deviation from this submittal schedule shall be approved by the Contracting Officer or approved designee. A draft inspection report including all required documentation shall be submitted to the Corps of Engineers for review within 120 days after Notice to Proceed (NTP). The Corps of Engineers will review the draft inspection reports and information submitted and provide comments that the Contractor shall address in the final inspection report. The final inspection report, incorporating resolution of all comments, will be submitted to the Corps of Engineers within 180 days after NTP.

Submittal Schedule

Submittal Schedule Draft Baseline Schedule & Work Plan 14 days after NTP Final Baseline Schedule & Work Plan 21 days after NTP Tailgate Safety Meeting Forms Daily

Field Work Documentation/Draft Inspection Reports Complete 120 days after NTP Final Inspection Report Complete/All Work Complete 180 days after NTP

Draft Work Plans and Draft Inspection Reports will be provided by hard copy and digital PDF format. One copy of each shall be provided to the Dam Safety Engineer and Project Office POC listed in paragraph 1.6.14. Tailgate Safety Meeting Forms should be provided to the Oahe Project Office POC. Format and number of copies for the Final Inspection Report shall be as indicated in paragraph 5.4.

W9128F22R0085

1.6.7 Recognized Holidays: Contractor’s shall not be required to work on Federal Holidays as listed below.

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Juneteenth Christmas Day Independence Day

1.6.8 Hours of Operation: The Contractor is responsible for conducting business, between the hours of 0700-1630, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Work on the weekend may be acceptable subject to approval of the Oahe Project POC prior to the start of weekend work. For other than firm fixed price contracts, the Contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons.

1.6.9 Place of Performance: The work to be performed under this Contract will be performed at the Oahe Dam Project Spillway, located near Pierre, South Dakota.

1.6.10 Type of Contract: The government will award a Firm Fixed Price Contract.

1.6.11 Security Requirements: The Contractor will be working at a high profile dam where security concerns are paramount, and access is restricted to authorized personnel. The Contractor shall coordinate with the Oahe Project Office POC and provide a list of personnel and equipment that will be on-site. The Contractor and their subcontractors shall display identification placards on all vehicles when the vehicles are on the Oahe Dam Project site. The placards will identify them as a Contractor to the Corps of Engineers and display the Contractor number for this work and will be placed on door panels or other easily identifiable locations.

1.6.12 Physical Security: The Contractor shall be responsible for the security of all contactor equipment at all times. The Contractor shall coordinate with and acquire approval from the Oahe Project Office POC regarding leaving vehicles or equipment at the dam site overnight or otherwise unattended. The Contractor shall also coordinate with and acquire approval from the Oahe Project Office POC regarding acceptable staging areas for the work. The Contractor shall be responsible for safeguarding any government equipment, information and property provided for Contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.

1.6.12.1 Key Control. The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer or designated representative.

In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the Contracting Officer or designated representative, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due the Contractor.

The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer or designated representative.

1.6.12.2 Lock Combinations. The Contractor shall establish and implement methods of ensuring that all lock combinations are not revealed to unauthorized persons. The Contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations.

1.6.13 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5.

The Contractor shall attend one kick-off meeting prior to the work commencing. The Contracting Officer, Government Representative, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer or designated representative will apprise the Contractor of how the government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced.

Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government. Meeting minutes shall be developed by the contactor and provided to the government.

1.6.14 Government Representative: The Government Representative monitors all technical aspects of the Contract and is authorized to perform the following functions:

assure that the Contractor performs the technical requirements of the Contract; perform inspections necessary in connection with Contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the Contract;

issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor Contractor's performance and notifies both the Contracting Officer or designated representative and Contractor of any deficiencies;

coordinate availability of government furnished property, and provide site entry of Contractor personnel. The Government Representative is not authorized to change any of the terms and conditions of the resulting order. The Government Representative(s) for this Contract are the Oahe Project Office POC or the Oahe Project Office Alternate POC. Government and Technical Representatives for this Contract are provided in the table below.

USACE Points-of-Contact

Function Name Office Phone Cell Phone E-Mail Oahe

Project Office POC

Kris Cleveland

(605) 945-

(605) 945-kris.cleveland@usace.army.m il

Oahe Project Office

Alternate

POC

LeeJay Templeton

(605) 945-

(605) 280-leejay.j.templeton@usace.arm y.mil

Dam Safety Engineer, Technical

POC

Ben Letak

(402) 995-

(402) 350-ben.j.letak@usace.army.mil

1.6.15 Key Personnel: The follow personnel are considered key personnel by the government: Contract Manager, Alternate Contract Manager, and Lead On-Site Field Representative. The Contractor shall provide a Contract manager who shall be responsible for the performance of the work. The name of the Contract manager, alternate Contract manager, and lead on-site field representative shall be designated in writing to the Contracting Officer or designated representative. The Contract manager or alternate shall have full authority to act for the Contractor on all Contract matters relating to daily operation of this Contract. The Contract manager or alternate shall be available between 0700 to 1630, Monday thru Friday, except Federal holidays or when the government facility is closed for administrative reasons. Contact information shall include office phone, cell phone, and e-mail address for each individual. In addition, the Contractor shall provide a 24-hour phone number that can be utilized to contact the Contractor’s POCs outside of normal business hours. The Contractor will provide the updated contact lists anytime there is a change in personnel or contact information. All employees shall possess required licenses/certificates/insurance as required by federal, state, and local authorities.

1.6.16 Identification of Contractor Employees: All Contract personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by Contractor’s are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.

1.6.17 Public Affairs: The Contractor shall not make available to the news media or publicly disclose any data generated in the performance of this work. If approached by the news media or general public, the Contractor shall refer them to the Oahe Project Office for a response.

1.6.18 Contractor Travel: N/A

1.6.19 Other Direct Costs: N/A

1.6.20 Data Rights: The Government has unlimited rights to all documents/material produced under this Contract. All documents and materials, to include the source codes of any software, produced under this Contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the Contracting Officer or designated representative. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.6.21 Organizational Conflict of Interest: N/A

1.6.22 PHASE IN /PHASE OUT PERIOD: N/A

PART 2

DEFINITIONS & ACRONYMS

2. DEFINITIONS AND ACRONYMS:

2.1. DEFINITIONS:

2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this Contract refers to the prime.

2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.4. DELIVERABLE. Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.

2.1.5. GOVERNMENT REPRESENTATIVE. An employee of the U.S. Government and designated representative of the Contracting Officer that monitors the technical aspects of the contract, maintains communications between the Contractor and the government, and monitors the contractor’s performance. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9. QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of Contractor performance.

2.1.10. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime Contractor.

The Government does not have privity of contract with the subcontractor.

2.1.12. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.12. WORK WEEK. Monday through Friday, unless specified otherwise.

2.2. ACRONYMS:

AFARS Army Federal Acquisition Regulation Supplement AHA Activity Hazard Analysis APP Accident Prevention Plan AR Army Regulation CAP Cement Asbestos Pipe CFR Code of Federal Regulations CIP Cast Iron Pipe CMP Corrugated Metal Pipe COTS Commercial-Off-the-Shelf DA Department of the Army DOD Department of Defense EM Engineer Manual FAR Federal Acquisition Regulation IAW In Accordance With KO Contracting Officer NTP Notice to Proceed OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) POC Point of Contact PRS Performance Requirements Summary PVC Polyvinyl chloride PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control SSHO Site Safety and Health Officer TE Technical Exhibit VCP Vitrified Clay Pipe

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. GOVERNMENT FURNISHED ITEMS AND SERVICES:

3.1. Services: Access to spillway structure and sub-surface drainage system.

3.2. Facilities: N/A.

3.3. Utilities: Non-potable water to be used for water flushing operations may be obtained from the Oahe Project Office at no cost to the Contractor. Reservoir water will not be allowed for hydro-flushing or cleaning operations.

3.4. Equipment: N/A.

3.5. Materials: NA

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1. General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this Contract that are not listed under Section 3 of this PWS.

4.2. Secret Facility Clearance: N/A.

4.3. Supplies and Materials: The Contractor shall provide all supplies and materials to meet the requirements under this PWS. This includes, but is not limited to, those supplies and materials necessary to flush/clean and inspect, as required, all components of the spillway drainage system included in this Contract. Additionally supplies and materials shall be provided to collect and capture materials flushed from the wall, slab and weir and abutment drains.

4.4. Equipment: The Contractor shall provide all equipment necessary to meet the requirements under this PWS. This includes, but is not limited to, water trucks, downhole camera equipment with remote controlled crawler unit and hydro-flushing equipment. Equipment may also include a crane and operator, as needed, for lowering equipment and supplies into the spillway gallery, into the spillway wall manholes, or onto the spillway slabs from above the spillway walls.

Access to the spillway galleries and stilling basin wall manholes (MH-1E through MH3-E and MH-1W through MH3-W) on each side of the spillway are available via State Highway 1806 and gravel-surfaced access roads on the downstream side of the structure. Access to the apron and basin slabs is available via the gravel-surfaced on the southeast side of the spillway structure only. See Sheet C-102. The Contractor may drive his equipment directly onto the apron and stilling basin slab surface, subject to approval of the Contracting Officer.

Access to the east and west spillway galleries by Contract personnel is by secured doors on each abutment and stairwells. Equipment and supplies may be lowered to the galleries through a 7 ft. x 7 ft. shaft in each abutment of the spillway. The shaft is constructed from the roof level to the gallery access level. A removable hatch covers the opening on the roof. The Contractor shall be responsible for providing the crane and operator for lowering equipment and supplies down the shaft.

PART 5

SPECIFIC SERVICE TASKS

5. SPECIFIC TASKS:

5.1. Basic Services - General: This Contract consists of providing services to clean and inspect the drainage system pipes beneath the spillway apron and stilling basin slabs, embedded within the spillway apron blocks, inside the drainage manholes behind the spillway walls, and in the spillway abutment galleries at Oahe Dam. The Contractor shall clean all pipes by hydro-flushing them, shall perform and digitally record a visual inspection of all pipes with remote-operated camera equipment, and shall thoroughly document the condition of all pipes that are cleaned and inspected. Deliverables will include electronic/digital copies of all camera inspection footage and a detailed formal report that summarizes the procedures and findings of all cleaning and inspection;

including individual inspection logs that summarize the condition each pipe segment and document significant observations.

The total length of pipe to be cleaned and inspected is 2,204 lineal feet for the Base Contract and 822 lineal feet for Option 1. The diameter of pipes to be accessed and cleaned and inspected for this Contract range from 6 to 12 inches (with the exception of access to slab frost blanket drain #5, which is as narrow as 2.5 inches). Pipe material for the pipes to be cleaned/inspected are perforated vitrified clay pipe (VCP) and solid cement asbestos pipe (CAP). Tables 5.1 through 5.6 of Exhibit 3 contain an inventory of the spillway drainage pipes to be cleaned/inspected under this PWS. All cleaning/inspections shall be inclusive of the full pipe length between the ends of the pipes identified in this inventory.

The individual drainage systems to be cleaned and inspected under this Contract were grouped into the Base Contract and Option 1 and are shown in plan view on Sheets C- 101 and C-102, respectively. As-built (record) plans, sections, elevations, and details for the spillway structure drainage systems are provided on For Information Only Sheets FIO-1 through FIO-3.

A summary of the work to be performed under this PWS is listed below. The Base and Option 1 were grouped together with consideration to pipes of similar size, access conditions to pipes, pipe orientation etc.

BASE CONTRACT -- Clean and Inspect 2,204 lineal feet of 8-inch diameter perforated VCP drain pipe for Basin & Apron Slab Frost Blanket Drains #1, #2, #3, #4 & #5.

OPTION 1 -- Clean and Inspect 328 lineal feet of 12-inch solid CAP pipe for

Apron Side Block Collector Drains within the spillway apron side blocks and 494 lineal feet of 12-inch CAP collector pipe for Slab Frost Blanket & Wall

Backfill Drain Collectors between the spillway wall manholes and the spillway abutment galleries.

Site-specific task descriptions, requirements, and other pertinent information for the cleaning and inspection work for each drainage system discussed above are provided in paragraphs 5.2 and 5.3 below. Additional requirements for cleaning and inspection of pipe are provided in paragraphs 5.4 through 5.9.

5.2. BASE CONTRACT -- Clean and Inspect Basin and Apron Slab Frost Blanket Drains #1, #2, #3, #4 and #5 (10 drain pipes total). This work consists of cleaning (hydro-flushing), performing a remote camera inspection, and documenting the condition of a total of 2,204 lineal feet of 8-inch diameter perforated vitrified clay pipe (VCP) for basin and apron slab frost blanket drains #1, #2, #3, #4 and #5, located beneath the concrete slab surface at the base of the frost blanket. There are ten (10) total pipe segments to be cleaned and inspected for the slab frost blanket drains, including an east and west leg for each of the two (2) drains under the stilling basin slab and the three (3) under the apron slab.

The pipes to be cleaned and inspected in the Base Contract are shown in plan view on Sheet C-101. As-built (record) plans, sections, elevations, and details for slab frost blanket drains the individual drainage systems are shown on For Information Only Sheets FIO-2 and FIO-3. Pipe segment names, access locations, beginning and ending information, pipe material types, pipe diameter and segment lengths are summarized in Tables 5.1 and 5.2 in Exhibit 3. The cleaning and inspections for the Base Contract shall be inclusive of the full pipe length between the ends of the pipe identified in Tables

5.1 and 5.2.

It shall be assumed that all pipes are 25% filled with sediment and require hydro-flushing for a complete and thorough inspection. All materials flushed from the drains must be captured and removed from the spillway slab and/or access manholes. The Contractors work plan shall include their method to prevent sediments from washing into downstream or other legs of the drainage system that are not scheduled for inspection. Disposal of the sediments will be directed by the Project POC to a location within 2 miles or less from the site.

General cleaning (hydro-flushing) requirements for the drains shall be as specified in paragraph 5.4. Downhole camera inspection and reporting requirements for the drains shall be as specified in paragraph 5.5.

Access to Basin and Apron Slab Frost Blanket Drains:

Access to the upstream end of basin slab frost blanket drains #1 and #2 and apron slab frost blanket drains #3, #4 and #5 is from atop the concrete slab surface, through a 12-inch by 12-inch square manhole cover bolted to a manhole frame with 4 bolts. Access to the upstream end of these drains is limited by a 5-inch diameter opening for the vertical riser pipe for these drains and a 90 degree bend between the vertical riser pipe and the 8-inch horizontal VCP drain pipe (approximately 7 feet below the slab surface).

See Sheet FIO-3, Detail A.

Access to the downstream end of basin slab frost blanket drains #1 and #2 and apron slab frost blanket drain #3 are from inside of basin wall manholes #MH-1, #MH-2 and #MH-3, respectively, on the backside of the spillway basin walls. There is NO access to the downstream end of apron slab frost blanket drains #4 and #5, as their downstream ends are connected to the apron side block collector drains and these connections are embedded in the monolithic concrete of apron blocks #E-10 and #W-10 and #E-13 and #W-13. The ONLY access for these two drains (drains #4 and #5) is through the access manholes on the slab surface on the upstream end as discussed in the previous paragraph.

It is also noted that both east and west 12-inch by 12-inch square manhole covers and frames and the upper 1.5 feet of the 6-inch diameter vertical riser pipe below the slab surface for slab frost blanket drain #5 have shifted horizontally and limit access to these 2 drains. Access to these two pipes is currently approximately 2.5 inch to 3.0 inches in dimension. See Sheet C-101 for location. These manholes will be modified by the Government prior to cleaning and inspection of the pipes for these two drains to create a larger access opening. The Oahe Project Office will make this modification.

5.3. OPTION 1 -- Clean and Inspect Apron Side Block Collector Drains and Slab Frost Blanket & Wall Backfill Drain Collectors.

5.3.1. Apron Side Block Collector Drains (2 collector drains total). This work consists of cleaning (hydro-flushing), performing a remote camera inspection, and documenting the condition of a total of 328 lineal feet of 12-inch diameter solid cement asbestos collector pipe (CAP) for the apron side block collector drains for frost blanket drains #4 and #5. There are two apron side block collector drains embedded within the side blocks, one each on the east and west sides of the spillway.

The pipes to be cleaned and inspected in Option 1 are shown in plan view on Sheet C-

102. As-built (record) pipe and manhole details for the drains are shown on For Information Only Sheets FIO-2 and FIO-3. Pipe segment names, access locations, beginning and ending information, pipe material types, pipe diameter and segment lengths are summarized in Tables 5.3 and 5.4 in Exhibit 3. The cleaning and inspections for Option 1 shall be inclusive of the full pipe length between the ends of the pipe identified in Tables 5.3 and 5.4.

It shall be assumed that all pipes are 75% to 100% filled with sediment and require hydro-flushing for complete and thorough inspection. All materials flushed from the drains must be captured and removed from the spillway slab and/or access manholes.

The Contractors work plan shall discuss their method to prevent sediments from washing into downstream or other legs of the drainage system that are not scheduled for inspection. Disposal of the sediments will be directed by the Project POC to a location within 2 miles or less from the site.

General cleaning (hydro-flushing) requirements for the drains shall be as specified in paragraph 5.4. Downhole camera inspection and reporting requirements for the drains shall be as specified in paragraph 5.5.

Access to Apron Side Block Collector Drains: The only access to the apron side block collector drains is at the downstream (north) end of the pipe in spillway basin wall manholes #MH-3E and MH-3W at the bottom of the manhole. There is currently NO access to the upstream (south) end of the collector drains as their upstream (south) end connections to frost blanket drains #4 and #5 are embedded in the monolithic concrete of apron blocks #E-10 and #W-10 and #E-13 and #W-13, respectively. See For Information Only Sheet FIO-3 for further information.

It is noted that a 6-inch diameter butterfly valve inset has been constructed into the manhole opening for the apron side block collector drains at the pipe segment’s downstream end. See Sheet C-102 for location. The valve is currently in the closed position. This valve will be removed by the Government and the collector pipe gravity drained as much as reasonably possible prior to cleaning and the inspection of the pipe.

Following removal of the 6-inch valve, access to the 12-inch diameter CAP drain pipes WILL BE LIMITED TO 6-INCHES IN DIAMTER as there will be a 6-inch flange grouted into the 12-inch drain pipe remaining in the end of the pipe.

It is noted that both drain collector pipes are known to be severed (broken) at apron block monolith #E-8 and #W-8 and access will be limited. It is also suspected there are breaks at #E-13 and #W-13. The condition of the collector pipes for access purposes is currently unknown. See Sheet C-102 for known and suspected break locations.

5.3.2. Slab Frost Blanket & Wall Backfill Drain Collectors (10 drain collectors total). This work consists of cleaning (hydro-flushing), performing a remote camera inspection, and documenting the condition of a total of 494 lineal feet of 12-inch diameter solid cement asbestos pipe (CAP) for the slab frost blanket & wall backfill drain collectors between manholes #MH-1, #MH-2 and #MH-3 and the gallery on both the east and west sides of the spillway.

The pipes to be cleaned and inspected in Option 1 are shown in plan view on Sheet C-

102. As-built (record) pipe and manhole details for the drains are shown on For Information Only Sheets FIO-2 and FIO-3. As-built (record) information showing how the collector pipes drain into the abutment galleries is shown on sheet FIO-1. Pipe segment names, access locations, beginning and ending information, pipe material types, pipe diameter and segment lengths are summarized in Tables 5.5 and 5.6 in Exhibit 3. The cleaning and inspection for Option 1 shall be inclusive of the full pipe length between the ends of the pipe identified in Tables 5.5 and 5.6.

It shall be assumed that all pipes are 25% filled with sediment and require hydro-flushing for complete and thorough inspection. All materials flushed from the drains must be captured and removed from the spillway slab and/or access manholes. The

Contractors work plan shall discuss their method to prevent sediments from washing into downstream legs of the drainage system that are not scheduled for inspection.

Disposal of the sediments will be directed by the Project POC to a location within 2 miles or less from the site.

General cleaning (hydro-flushing) requirements for the drains shall be as specified in paragraph 5.4. Downhole camera inspection and reporting requirements for the drains shall be as specified in paragraph 5.5.

Access to Slab Frost Blanket & Wall Backfill Drain Collectors: Both ends of all collector pipes are accessible. Access to the slab frost blanket & wall backfill drain collectors are from inside basin wall manholes #MH-1, #MH-2 and #MH-3 and in the spillway abutment galleries at the downstream end of the collector system.

5.4. Cleaning Requirements for Drains and Collector Pipes. All cleaning equipment, and cleaning procedures for this Contract shall conform to this PWS.

Cleaning generally consists of thoroughly cleaning pipe segments by hydro-flushing (flushing them with large quantities of water or jetting them), or other approved mechanical means) to enable the visual inspection of clean pipes with remote operated camera equipment. Care should be taken during cleaning operations to avoid damaging the existing drains and collector pipes and from washing sediments into adjacent drain systems. The Contractors work plan shall identify the method to clean the pipes, to limit and/or minimize damage to the pipes and to limit and/or minimize the amount of sediment from entering adjacent pipe systems.

It is estimated that up to 30 cubic yards of material will need to be removed from the pipes and disposed of offsite or in the spoil area as directed by the Contracting Officer as part of this contract. The Contractor can expect accumulated soft and hard packed sediments in the pipes up to a thickness of one-third the pipe depth.