This document contains an amendment to a solicitation for construction services as well as the original solicitation opportunity. The amendment modifies the specifications to add payment terms for remaining work under a new CLIN and lighting fixture requirements. The original solicitation seeks offers for the Fort Peck Power House 1 Bridge Crane Rail Replacement project located in Montana. Offerors are invited to replace the existing bridge crane rails and conduct related work with an estimated cost between $500,000 and $1,000,000. The primary NAICS code is 238120 for structural steel and precast concrete contractors. The solicitation will remain open until 19 August 2022. Site visits are scheduled for 2 August 2022 and offerors must register in SAM.gov to access solicitation documents through the Army Corps of Engineers Omaha District contracting office.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate Amendment No. 0001 to the Specifications. See Am0001 in SF30 Block 14 Continuation Page for description of amendment changes. All other terms and conditions remain the same.

Pow erhouse 1 Bridge Crane Rail Replacement Fort Peck Dam, MT Government POC: Brianna Boehne

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Aug-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F22R0068

X 9B. DATED (SEE ITEM 11)

20-Jul-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Aug-2022

CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

W9128F 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9128F22R0068

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMD0001

04 August 2022 Solicitation No. W9128F22R0068

Date of Issue: 20 July 2022 Date of Receiving Proposals: 19 August 2022

SUBJECT: Amendment No. 0001 to Request for Proposal Solicitation Package for Construction of Fort Peck Power House 1 (PH1) Bridge Crane Rail Replacement.

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.)

(1) Section 01 22 00 Page 2, paragraph 1.1.3 Add in the following paragraphs:

“1.1.3 CLIN 0003: All Remaining Work

1.1.3.1 Payment

Payment for all remaining work will be made in a lump sum under that CLIN. Price and payment will constitute full compensation for this item which includes, but is not limited to: temporary trailer facilities, telephones, Contractor staging areas, site preparation, insurance, performance and payment bonds, field office personnel, rail surveying, Contractor's supervision for the duration of the project, house cleaning and site maintenance, and any other incidental and customarily performed work needed to complete rail replacement not covered by bid items 1 and 2.

1.1.3.2 Unit of Measure

Unit of measure: Job.”

(2) Section 41 22 14.33 26 Page 6, paragraph 3.3

Add in the following subparagraph:

“Lighting Fixtures - lighting fixtures adjacent to the crane rails are to be removed, salvaged, and reused upon completion of work. Any fixtures damaged

W9128F22R0068 during the work are to be replaced in kind at no additional cost to the Government.”

2. This amendment is a part of the proposal papers and its receipt shall be acknowledged. All other conditions and requirements of the specifications remain unchanged.

3. See Section 00 21 00 on how to submit electronic offers.

4. Electric Offers will be received until 2:00 p.m., local time at place of receiving proposals, 19 August 2022, as stated in the Request For Proposal.

Attachments: none U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901

04 August 2022