This is a draft request for proposal for a $99 million small business multiple award task order contract for airfield paving construction. The solicitation is a 100% small business set-aside issued by the Department of the Army Corps of Engineers Engineering District Omaha. It will result in awards to a target of five contractors for a base period of four years with one three-year option period. Individual firm fixed price task orders will be competed within the pool of awardees. The solicitation includes binding labor rates, escalation terms, and a maximum profit rate. It also requires descriptions of the offeror's past performance, program management approach, quality control processes, and design capabilities. Questions must be submitted by a specified date and proposals are due on another specified date.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INDEFINITE DELIVERY CONTRACT FOR DESIGN-BUILD/DESIGN-BID-BUILD FOR AIRFIELD PAVING CONSTRUCTION, VARIOUS LOCATIONS

WITHIN THE NORTHWESTERN DIVISION.

This solicitation is a Small Business set-aside. A target of f ive (5) Indef inite Delivery Contracts may be aw arded for a base performance period of four (4) years w ith one (1) three (3) year option period. The combined total value of the all contracts shall not exceed $99,000,000.

The minimum contract guarantee is $2,500.

Except as provided below , w ork w ill be performed by the selected qualif ied Contractors pursuant to firm-fixed-price contracts. Task Orders w ill be requested from time to time, as the need arises, during the contract period. There is no value assigned to the task order minimum or maximum. Wage rates applicable to the area of w ork w ill be added to each task order. The offeror agrees to do all the w ork described in these documents.

RETURN WITH PROPOSAL: SECTIONS 00 10 00, 00 45 00, INFORMATION REQUIRED IN SECTION 00 22 00 AND PRICING SUBMISSION

REQUIREMENTS.

ERICKA T COLLINS 402-995-2116

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

08-Oct-2021

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________Per task order

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

W9128F

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

(hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W9128F22R0016 76

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W9128F22R0016

Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule

LABOR RATE & RATE CAP TABLES

Section 00 10 00

CONTRACT RATE PRICING

SCHEDULE

TABLE 1: Binding Hourly Labor Rates

Labor Discipline

U nb ur de ne d

L ab or R at e

(B as e Pe ri od

B ur de ne d L ab or

R at e (B as e

Pe ri od

B ur de ne d L ab or

R at e (B as e

Pe ri od

B ur de ne d L ab or

R at e (B as e

Pe ri od

B ur de ne d L ab or

R at e (B as e

Pe ri od

B ur de ne d L ab or

R at e (O pt io n Pe ri od

B ur de ne d L ab or

R at e (O pt io n Pe ri od

B ur de ne d L ab or

R at e (O pt io n Pe ri od

B ur de ne d L ab or

R at e (6

M on th

E xt en si on

Program Manager/ Construction Operations Manager (Home Office)

Corporate Quality Control Manager (Home Office)

Corporate Safety and Health Manager (Home Office)

Project Manager

Engineer (Home Office)

Engineer (Field Office)

Site Superintendent (Field Office)

Quality Control Specialist/CQC System Manager (Field Office)

Site Safety and Health Officer (Field Office)

1. Firm Fixed Pricing Task Orders

1.1 Binding Capped Hourly Labor Rates

The binding capped labor rates for this contract shall be provided by the Offeror in Table 1 (to also be completed in the excel spreadsheet provided along with the formula(s) or calculations used to burden the labor rates). The amount to be paid to the contractor for each firm-fixed price task order shall not exceed the “maximum” hourly rates proposed by the contractor for the labor disciplines listed in Table 1, “Binding Labor Rates.” The fully burdened labor rates provided in Table 1 will also be used for negotiation of task order modifications.

1.1.1 The capped hourly rates provided on Table 1 shall be “Fully Burdened,” i.e., shall include Overhead (OH), General/Administrative (G&A), Labor Burden Fringes, and any other indirect costs exclusive of profit.

1.1.2 Labor rates used in formulating task order proposals shall not exceed the capped labor rates as of the date of task order requirement.

1.1.3 The Offeror shall indicate for each discipline whether it is employed by the prime or a subcontractor by annotating PRIME or SUB next to the discipline in the first column. For example, “CADD Operator (SUB)”.

The rates shown per labor discipline shall be fully burdened rates, exclusive of profit for the prime contractor or joint venture.

1.1.4 The hourly burdened labor rates proposed in the Binding Capped Labor Rate Schedule are binding upon contract award for the life of the MATOC, to include all option periods and extensions. These rates are applicable to both task orders and modifications.

1.1.5 If a discipline is not listed in the contract rate pricing schedule and is required for the contractor to perform a specific task order, the contractor may propose the required labor category and provide the direct and indirect costs which formulate the fully burdened labor rate (exclusive of profit for the prime contractor or joint venture) in the proposal submitted in response to the issued Request for Task Order Proposal (RTOP).

1.1.6 If during the Contract Period of Performance, the Offeror’s original key personnel (prime or subcontracted) are no longer available, the Offeror shall replace these individuals with personnel whom, at a minimum, have the same qualifications as the personnel being replaced. The Offeror shall be responsible for negotiating labor rates for those personnel that do not exceed the rates provided in Table 1, which are the maximum rates the Government will pay for any personnel. The Contractor shall submit the replacement personnel’s qualifications to the Contracting Officer for approval.

1.1.7 The applicable capped labor rates shall be governed by the effective date of the Task Order. Task Orders will use the prices for the 12-month period effective on the date the Task Order is issued. Modifications to Task Orders will reflect the rates of the “current 12-month” binding labor rate schedule. For example, if the rate schedule changes over on 1 November of each year, and a Task Order is issue on 1 September 2020 for 12 months work, the maximum rates will be the rates that were effective on 1 November 2019. Under the same assumptions, if a modification to the Task Order is required in December 2020, the labor rates effective on 1 November 2020 will apply.

1.1.8 The Offeror has the responsibility to provide labor rates that comply with Davis Bacon wage decisions for each labor discipline subject to those wage determinations/wage decisions. The Government will provide the applicable wage determination(s) for the specific geographic location of the task orders in the Request for Task Order Proposal (RTOP).

1.1.9 Provide one (1) rate per labor discipline, regardless of whether the individuals employed for that discipline are directly employed or subcontracted.

1.1.10 Provide Other than Certified Cost or Price Data, which consists of the formula used to arrive at the burdened rates provided in Table 1.

1.2 Firm-Fixed Price Escalation and Maximum Profit

1.2.1 The escalation rate applied to years 2 through 7 shall be provided by the Offeror in Table 2. The listed rate shall be the rate applied to the hourly labor rates in Table 1 for each year.

TABLE 2: Escalation Rate

Period 1 - Period 2

Period 2 - Period 3

Period 3 - Period 4

Period 4 - Period 5

Period 5 - Period 6

Period 6 - Period 7

Period 7 - 6-Month Extension

Profit will be negotiated at the task order level for each Firm-Fixed Price task order but shall not exceed the maximum profit rate provided by the Offeror in Table 3, “Maximum Profit.” The maximum profit shall be binding for the life of the contract, to include all option periods and extensions, and shall be the maximum profit the Contractor will be allowed to propose for all firm-fixed-price task orders and modifications issued under this contract.

1.2.2 The Contractor may propose a lower profit when responding to a RTOP (or subsequent modifications) based on the tasks identified in the request and the risk associated with the project.

1.2.3 The maximum profit on this contract shall be provided by the Offeror in Table 3:

TABLE 3: Maximum Profit

2. Binding Capped Rates for Firm Fixed Task Orders

The Binding Capped Rates represent the maximum Overhead, G&A, or other Indirect rates that the Contractor shall use when responding to a RTOP issued by the Government. The Offeror may use lower rates in proposals, but not higher.

2.1 The Binding Capped Rates shall be the maximum applied OH, G&A and other indirect rates used for the duration of the contract. The Binding Capped Rates will not be adjusted upward as a result of an audit of the contract or the follow-on task orders. For proposals in response to RTOP that require disciplines not included in the Table 1 labor rates, the Contractor should use the actual labor rate(s) paid to the employee(s) for each discipline and apply the applicable indirect rates up to the binding capped rates listed in Table 4. The proposed task order indirect rates will not be adjusted upward as a result of an audit of the contract or the specific task order.

2.2 The Binding Capped Rates for this contract shall be provided by the Offeror in Table 4 along with the applicability of each rate submitted. If a listed category does not apply to the firm, list as “N/A”. Table 4 shall include all indirect cost rates that the firm may use in their proposals in response to the Government’s RTOP. The capped rates provided by the Offeror are binding upon contract award for the life of the MATOC, to include all option periods and extensions. These rates are applicable to both task orders and modifications.

Indirect Rate Category Indirect Capped Rate

Home Office Overhead (HOOH) or Single OH %

Field Office Overhead (FOOH), if applicable %

Fringe Benefits, if separate from HOOH and/or FOOH %

General & Administrative (G&A), if applicable %

Other (Identify) %

Other (Identify) %

TABLE 4: Binding Indirect Capped Rates_

3. Department of Labor Wage Rates

The appropriate Department of Labor Wage Determination/Decision will be provided for individual Task Orders issued against the contract.

4. Travel

The Contractor shall perform all travel and attend all meetings necessary for completion of the work required by the Task Orders. If Per Diem (lodging and MI & E expenses) and transportation expenses are required to perform the Scope of Work, travel costs may be included in the Firm-Fixed-Price proposals for task orders in accordance with the offeror’s accounting practices. The Government will use the Federal Travel Regulation (FTR) as guidance to assist with a reasonableness determination.

The Government reserves the right to include a separate cost reimbursement CLIN in individual RTOP for travel costs. If the separate CLIN is used on a task order, Per Diem (lodging and MI & E expenses) shall be paid at the current Government rates in accordance with the Federal Travel Regulation (FTR) per person per calendar day spent in travel status. No per diem will be paid for travel less than the number of hours per day stated in the current FTR.

Per Diem rate information may be obtained at http://www.defensetravel.dod.mil/. Actual cost of transportation by public conveyance (plane, limited to coach class) shall be paid. Air travel shall (if possible) be planned in advance in order to acquire the best prices available. Privately owned vehicles shall be paid at the current Government mileage rate in accordance with the FTR. The maximum amount paid for an airline ticket shall be the cost of travel via coach class.

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0001 99,000,000 Job Base Period - AFP SB MATOC (4 Years)

FFP

Base (4 -Year) Design-Build/Design-Bid-Build Construction in support of Air Force Civil Engineering Center (AFCEC), the US Army, and various other DoD customers within the USACE Northwestern Division’s military boundaries. The work shall be in accordance with Request for Proposal documents issued within this solicitation.

FOB: Destination

PSC CD: Y1BD

MAX

NET AMT

UNIT UNIT PRICE MAX AMOUNT

0002 UNDEFINED Job OPTION Option Period - AFP SB MATOC (3 Years)

FFP

Option (3 -Year) Design-Build/Design-Bid-Build Construction in support of Air Force Civil Engineering Center (AFCEC), the US Army, and various other DoD customers within the USACE Northwestern Division’s military boundaries. The work shall be in accordance with Request for Proposal documents issued within this solicitation.

UNIT UNIT PRICE MAX AMOUNT

0003 UNDEFINED Job OPTION Option Period - AFP SB MATOC (6 months)

FFP

Option (6 months) Design-Build/Design-Bid-Build Construction in support of Air Force Civil Engineering Center (AFCEC), the US Army, and various other DoD customers within the USACE Northwestern Division’s military boundaries. The work shall be in accordance with Request for Proposal documents issued within this solicitation.

CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE

The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

2,500.00 $2,500.00 99,000,000.00 $99,000,000.00

DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE

The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

2,500.00 $2,500.00 99,000,000.00 $99,000,000.00

CLIN MINIMUM/MAXIMUM QUANTITY AND CLIN VALUE

The minimum quantity(s) and CLIN value(s) for all orders issued against the CLIN(s) on this contract shall not be less than the minimum quantity(s) and CLIN value(s) stated in the following table. The maximum quantity(s) and CLIN value(s) for all orders issued against the CLIN(s) on this contract shall not exceed the maximum quantity(s) and CLIN value(s) stated in the following table.

CLIN

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

0001 2,500.00 $2,500.00 99,000,000.00 $99,000,000.00 0002 2,500.00 $2,500.00 99,000,000.00 $99,000,000.00 0003 2,500.00 $2,500.00 99,000,000.00 $99,000,000.00

CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE

The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.

CLIN

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

0001 2500.00

$2,500.00

99,000,000.00

$99,000,000.00

0002 2500.00

0003 2500.00

Section 00 21 00 - Instructions

00 21 00 INSTRUCTIONS TO OFFER

Section 00 21 00

INSTRUCTIONS TO OFFERORS

1. PART 1 – CONTRACT INFORMATION

1.1. INDEFINITE DELIVERY TYPE CONTRACTS

The Government intends to award a Multiple Award Task Order Contract (MATOC) for shared capacity of $99M to a target of five (5) contractors. Individual Task Orders will be solicited and competed within the MATOC pool.

Task Orders within the MATOC will be Firm Fixed Price (FFP) task orders.

2. WHO MAY SUBMIT

This solicitation is a 100% small business set aside pursuant to 13 CFR 124.501. All Offerors must be registered in the System for Award Management (SAM).

Proposals submitted must be sufficiently detailed to allow for an effective and equitable evaluation by the Government. There will be no public proposal opening. Proposals submitted will become, upon receipt, the property of the U.S. Government and will not be returned. The Government will retain electronic copies of the proposals for the official file. The government will destroy or forward all other copies to the Field and Areas Offices in support of their contract administration functions.

3. PROPOSAL SUBMISSION

3.1. SUBMISSION DEADLINE

Offerors shall submit as stated and by the time and date as specified in SF 1442, block 13.

3.2. COPIES OF SOLICITATION DOCUMENT AND AMENDMENTS

Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the Governmentwide Point of Entry (GPE), https://sam.gov/.

It is the Offeror’s responsibility to monitor the GPE for any amendments. The offeror shall submit in the proposal all requested information specified in this solicitation.

3.3. BIDDER INQUIRY/QUESTIONS

Prospective Offerors shall submit contracting and technical inquiries and questions concerning this solicitation document via Bidder Inquiry in ProjNet at www.projnet.org/projnet.

***Please Note: Offerors shall only submit one question per inquiry, i.e., each query should have a unique corresponding ProjNet bidder inquiry number assigned. All inquiries containing multiple questions shall be rejected. The Offeror is permitted to submit multiple inquiries.***

Questions relating to the proposal are to be submitted via Bidder Inquiry in ProjNet, at https://www.projnet.org/projnet/, no later than ten (10) calendar days before due date of proposals, in order that they may be given consideration or actions taken prior to receipt of offers. The Bidder Inquiry system is to be used to ask and receive answers to all non-proprietary questions.

To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via ProjNet email notification after an answer to the comment/question has been processed by our technical team.

All timely questions and approved answers will be made available through ProjNet.

The Solicitation Number is: W9128F-22-R-0016 The Bidder Inquiry Key is: 4SR72F-896PZM

a. Registration for ProjNet Bidder Inquiry Access

If you are already registered, go to Entering Bidder Inquiries in ProjNet Bidder Inquiry System below.

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret

Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

b. Entering Bidder Inquiries in ProjNet Bidder Inquiry System

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

8. Follow online screen instructions to enter specific bidder inquiries for the project.

c. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

d. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

3.4. SOURCE SELECTION OVERVIEW

The Source Selection Authority (SSA) will establish a Source Selection Evaluation Board (SSEB) to conduct an evaluation of each proposal received in response to this Solicitation. The evaluation will be based on the source selection criteria identified in Section 00 22 00 for phase 1. The identities of the SSEB personnel are confidential, and any attempt by the offerors to contact these individuals is prohibited.

In Phase 1 of the two-phase selection procedure, Offerors submit certain specified performance capability proposals, demonstrating their capability to successfully execute task orders under a contract resulting from this solicitation.

The Government will evaluate the qualifications submitted in Phase 1 of 2 Selection Procedures and will invite a maximum of eight (8) of the most highly qualified Offerors to compete in Phase 2 for award of the MATOC.

Offerors must submit a complete Phase 1 proposal to be considered for Phase 2. PHASE 1 DOES NOT INVOLVE

PRICING SUBMISSION.

Prior to Phase 2, an amendment will be issued to only the selected Offerors from Phase 1 inviting them to submit Phase 2 technical and price proposals for consideration. The amendment will request additional information needed to complete the submission of Phase 2 proposals. In Phase 2, the Source Selection Authority and Contracting Officer’s intent is to award a target of five (5) contracts under this MATOC to the Offerors whose proposal offers the best value to the Government. DO NOT SUBMIT ANY PHASE 2 DOCUMENTS DURING PHASE 1.

Offerors must submit a complete proposal to be considered for award. If the offeror fails to submit a complete proposal as defined by the instructions to offerors in section 00 21 00 (phase 1) and section 00 21 16 (phase 2), the Government may consider the entire proposal nonresponsive. At its discretion, the Government may exclude nonresponsive offers from advancement or award.

4. CONTRACTOR TEAM ARRANGEMENTS

4.1. CONTRACTOR TEAM ARRANGEMENT OTHER THAN JOINT VENTURE

All Offerors proposing a team arrangement other than a Joint Venture, shall submit the following information:

Provide a listing of the team arrangement members’ legal corporate name (no abbreviations) as it appears in their formal documents with SAM registration or Internal Revenue Service documents, address, point of contact, phone number, DUNS Number, and Cage Code.

4.2. INTEGRITY AND VALIDITY OF CONTRACTOR TEAM ARRANGEMENTS

The Contracting Officer will recognize the integrity and validity of contractor team arrangements; provided that the arrangements are identified and company relationships are fully disclosed and validation of formal agreements and relationships (i.e., Mentor-Protégé agreements, joint ventures, partnerships, etc.) are provided in the offer and submitted with the proposal responding to the solicitation. Nothing in the solicitation authorizes contractor team arrangements in violation of antitrust statutes or limits the Government’s rights to:

a. Require consent to subcontracts (see FAR Subpart 44.2)

b. Determine, on the basis of the stated contractor team arrangement, the responsibilities of the prime contractor (see FAR Subpart 9.1)

c. Provide to the prime contractor data rights owned or controlled by the Government

d. Pursue its policies on competitive contracting, subcontracting, and component breakout at initial production or at any other time

e. Hold the prime contractor fully responsible for contract performance, regardless of team arrangement between the prime contractor and its subcontractors

5. PLAN HOLDER'S LIST

For Viewing a List of Interested Vendors (i.e. plan-holders List) and Receiving Notifications or e-mail of changes regarding a solicitation, SAM has these features available ( https://sam.gov/). For this solicitation, go to https://sam.gov/ and register as a vendor or enter username and password to login. If you wish for General Contractors, Subcontractors, Suppliers, Plan Rooms or Print Shops to have the ability to contact you, click on the "Add me to Interested Vendors" for the solicitation.

***PHASE 1 SPECIFIC ISNTRUCTIONS BELOW***

5.1. SUBMISSION INSTRUCTIONS

All proposals shall be submitted electronically. All submissions shall be in Adobe PDF format with Optical Character Recognition (OCR) applied to all documents that will enable word searches to be conducted using Adobe-compatible PDF software. The two (2) volumes listed below shall be submitted as SEPARATE files via email.

Offerors may use compression utilities such as 7-Zip, WinZip or PKZip to reduce file size and facilitate transmission. Offerors are encouraged to send both files in the same email transmission, if possible.

PHASE 1:

Volume I: Technical Proposal, Factors 1-2 Volume II: Required Documents

Title the single files in the following format:

W9128F22R0016_COMPANY NAME_PHASE1_VOLUME_I

W9128F22R0016_COMPANY NAME_PHASE1_VOLUME_II

For this solicitation, the recipients will be:

1. John Hickman, john.d.hickman@usace.army.mil

2. Ericka T. Collins, ericka.t.collins@usace.army.mil

3. Tyler Hegge, tyler.hegge@usace.army.mil

4. Melanie Caines, melanie.a.caines@usace.army.mil

For the purposes of determining whether the proposal was received “late” in accordance with FAR 15.208, the date and time the file(s) are received via email will be in accordance with the time stamp on the offeror’s proposal submission email. Do not assume that electronic communication is instantaneous. Please make allowances for delays in transmittal. Electronic Proposals shall be received via email No Later Than (NLT) the date and time indicated in Block 13 of the SF 1442 for this solicitation or as identified in subsequent amendments.

The Government is not be responsible for proposals delivered to anyone other than those designated to receive proposals on its behalf. The Offeror is responsible for ensuring that the proposal is submitted to reach the designated recipient and is responsible for allowing sufficient time for the proposal to be received in accordance with the information provided.

Failure to submit a complete proposal in accordance with (IAW) instructions and requirements may result in the Government considering the entire offer as nonresponsive.

5.2. PROPOSAL FORMAT AND SUBMITTAL REQUIREMENTS

1. The proposals shall be submitted in Volumes as follows:

Phase 1:

Phase 1, Volume I, Technical Proposal:

Table of Contents FACTOR 1 Past Performance FACTOR 2 Overall Program Management Approach

Phase 1, Volume II, Required Documentation:

Cover Letter Table of Contents Tab 1 Completed SF 1442 Tab 2 Completed SF 30 (if applicable) Tab 3 Bond Letter Tab 4 Contractor Team Arrangement Requirements

TABLE 1: Phase 1 Evaluation Factors

Volume Eval Factor Tab –Title Page Limitations

I Factor 1 Past Performance

No page limitation on the total number of pages, each project submission is limited to 2 pages.

I Factor 2 Overall Program Management

Approach

10 - If an offeror utilizes 11”x17” paper for the organization structure, it will be counted as one (1) page.

2. Proposal Characteristics

a) All text shall be at least 10 pt. font and easily read. The page size of the Offeror’s proposal shall not exceed

8-1/2 by 11 inches. Diagrams, charts and tables shall conform to the paper size, except for the organizational chart referenced in Table 1, which can utilize 11”x17” paper. All text shall be typed single-spaced. Margins (1-inch) shall be clean and clear of any text except for proprietary statements, security markings and page numbers which may fall within the defined margin area. Solicitation number and company name of Offeror may also be included within the margins. Submit the SF 1442, completed and signed by a person authorized by the Offeror.

b) Offeror shall submit a cover letter containing:

i. Solicitation number

ii. Name, title, address, email, and telephone number of the offeror.

iii. Names, titles, emails, and telephone numbers of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this RFP.

iv. Name, title and signature of the person authorized to sign the proposal.

v. Names, titles, emails, and telephone numbers of proposal coordinators who will handle correspondence with the Government on behalf of the Offeror in connection with this RFP, if different from the personnel provided above (primary and alternate).

vi. A statement specifying agreement with all terms, conditions and provisions included in the RFP.

vii. Cage Code, DUNS Number and Tax Identification Number (TIN) of the offeror.

c) The table of contents for each volume should include all section headings and subheadings worded exactly as they appear in the proposal. Each Volume shall contain a table of contents and all pages of each factor shall be sequentially numbered.

d) Offerors shall submit a completed SF1442 with their proposal.

e) Offerors shall submit a letter from their bonding company agent certifying the current maximum bonding capacity per project and the aggregate capacity.

f) For Contractor Team Arrangements including Joint Ventures, submit the information required by Paragraph 4 “Contractor Team Arrangements”.

g) Offerors shall submit acknowledgement of all amendments to the RFP in accordance with the instructions on the Standard Form 30 (amendment form).

Prior to Phase 2, an amendment will be issued to selected Offerors from Phase 1 inviting them to submit Phase 2 technical and price proposals for consideration. The amendment will request additional information needed to complete the submission of Phase 2 proposals.

5.2. 1. VOLUME 1, TAB 1 – FACTOR 1 – PAST PERFORMANCE

Submission Requirements

5.2.1.1 In this tab, the Offeror shall submit a minimum of two (2), no more than four (4) project examples. The Offeror shall have been the prime contractor or joint venture participants in the construction aspects in each design-bid-build project example submitted, and in the design and construction aspects in each design-build project example submitted.

Project examples should illustrate the types of projects described in Division 01 11 00, Scope of Work. The offeror should present the number of project examples that demonstrate prowess, breadth, and depth of experience as it relates to the scope of work for this requirement. Projects for which the Offeror was a subcontractor or a teaming member of a subcontractor at the time of project execution are not acceptable. Each project example should consist of no more than a two (2) page narrative and should clearly demonstrate the design-build and/or design-bid-build capabilities and experience of the Offeror.

NOTE: If more than four (4) project examples are submitted, only the first four (4) contained in the proposal will be evaluated. If more than a two (2) page narrative per project example is submitted, only the first two (2) pages will be evaluated.

5.2.1.2 Each project example cited shall have a contract (stand-alone contract or single task order) dollar value at award that is $1,000,000 or greater and a Building Occupancy Date (BOD) or date when construction was complete and system was operational within seven (7) years of the date that Phase 1 proposals are due. Indefinite Delivery/Indefinite Quantity (IDIQ) Contracts, where numerous Task Orders are summed to meet the minimum contract dollar value identified herein, are not acceptable.

5.2.1.3 The narrative should include the items below in the following order:

1. Project title

2. Project description

3. Contract number, task order number, or unique customer-assigned identifier

4. Location (include: installation/base/facility, city, state, country)

5. Contract (stand-alone contract or single task order) dollar value at award

6. Final Design Cost

7. Final Construction Cost

8. Notice to proceed date

9. Original construction completion date

10. Actual construction completion date

11. Explanation for any cost or schedule growth

12. Name, address, telephone number, and e-mail address of a representative of the customer or an alternate individual not affiliated with your firm and familiar with your firm’s experience on the project example that can verify the experience cited

13. Briefly explain the relevance of the project example compared to the types of projects stated within this solicitation

5.2.1.4 The Offeror should submit, at a minimum, the past performance ratings for each project the Offeror included in Factor 1 – Previous Experience. Contractor Performance Assessment Reporting System (CPARS) evaluations are preferred. Past Performance Questionnaires (PPQs) are also acceptable (to include those previously completed), as are evaluations in other formats (not CPARS or PPQ) if the evaluation criteria and ratings types are similar to those used in a CPARS and/or a PPQ evaluation, the evaluation includes the same level of detail (or greater) as a CPARS and/or a PPQ evaluation, it is signed by the Customer, and all other RFP requirements are met.

5.2.1.5 If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, Offerors should follow up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Contract Specialist, prior to proposal closing date. Offerors shall instruct the clients to refer to the solicitation number in the subject line. PPQs are source selection materials. All successfully submitted PPQs will receive an email confirmation upon receipt. If the offeror does not receive the confirmation, it is the offeror’s responsibility to follow up to ensure the Government has received the information. The Government reserves the right to contact the personnel listed on the PPQ. The inability to validate the information on the PPQ will affect the Government’s evaluation. Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other procurements. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.

Offerors may provide explanation on problems encountered on past projects and the corrective actions taken by the offeror. Narratives must not be more than one (1) page. Narratives do not absolve the offeror of prior performance.

Narratives provide the offeror an opportunity to frame prior poor performance. The Government will review this data and consider its content when reviewing past performance. Narratives are also encouraged for example projects that may be missing requested elements (i.e. nearly complete projects, non-DOD project that still meets all the complexity requirements, etc) explaining to the Government why it should consider the project as a complete submission. The Government reserves the right to subjectively determine the impact of the content of the narrative and how it will impact the ratings.

In the event that a formal past performance evaluation has not been completed via CPARS, or CCASS, the Past Performance Questionnaire (Form PPQ-0, Attachment 1) is provided for the Offeror or its team partners to submit to the client. The PPQ should be completed by an owner or owner’s representative not affiliated with your firm. Ensure correct phone numbers and email addresses are provided for the client point of contact.

5.2.1.6 Completed PPQs shall be submitted with your proposal or to the designated personnel listed below prior to the Phase 1 proposal due date. Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the designated Government's point of contacts, via email at ericka.t.collins@usace.army.mil and john.d.hickman@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference previously completed PPQs from other RFPs into their proposal. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation at its own prerogative, nor does it preclude the Offeror from utilizing a previously completed PPQ and submitting into their proposal.

5.2.1.7 Do not submit PPQs for projects evaluated via CPARS or CCASS. In the event an Offeror submits a PPQ for a project for which a CPARS evaluation is available, the CPARS evaluation will be considered authoritative.

5.2.1.8 The Government will assess the past performance on projects submitted under the Factor 1 - Past Performance and reserves the right to conduct telephone interviews with points of contact identified in the proposal.

In addition, the Government may review any other sources of information for evaluating past performance of the Offeror on the submitted projects and any other previous work. Other sources may include, but are not limited to, past performance information retrieved through the CPARS using all Commercial and Government Entity (CAGE)/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror's proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate, and complete past performance information rests with the offeror. The Government reserves the right to contact any and all individuals identified in the projects submitted. It is the responsibility of the Offeror to provide current contact information for the individual identified therein. The Offeror may provide additional points of contact (POCs) with the customer (prime contractor, if appropriate). The POC information should include the POC’s title, telephone number and e-mail address. The POCs may be contacted to validate the information provided.

5.2.1.9 The Government intends to assess the relative risks associated with the Offeror's performance based on the past performance information provided in the proposal. A significant achievement, unexplained or unresolved problem, or lack of relevant data may significantly impact the risk rating by the Government. Therefore, it is incumbent upon the offeror to include all relevant information, including demonstrated corrective actions, in its proposal.

5.2.1.10 In addition, the offeror shall provide a list of CPARS entries they feel are most applicable to this acquisition. The Government will review this list and other CPARS entries. No part of this submission restricts the Government’s rights to review past performance data from other sources, or limits what the Government can review from CPARS.

5.2. 2. Additional Requirements:

5.2. 2.1 General Requirements

The Government will review past performance data for recency and relevancy considering the following work factors.

Offerors are encouraged to highlight their prowess and capabilities in the sample submissions to ensure the Government is aware of the offeror’s capabilities in meeting similar elements of work.

All project examples should meet the following criteria.

1. Primary scope of work was airfield design-bid-build/design-build paving as specified in section 01 11 00.

Projects involving installation of only the sub-base materials, crack repair, patching, seal coats, or non-pavement items will not be considered acceptable. The Government expects project examples to be of sufficient complexity to demonstrate the Offeror’s understanding of the RFP requirements.

2. Contract must have been awarded to your firm, or as one of the partners of a Joint Venture, as the Prime Contractor

3. The largest portion of the paving on the Airfield Paving construction project, either Portland Cement Concrete (PCC) or Asphalt Cement Concrete (ACC), must have been self-performed by the Offeror, and not subcontracted or performed by a teaming partner

4. All work was performed at a Department of Defense (DoD) airfield in accordance with UFC and UFGS criteria, or a commercial airfield/airport that required and utilized FAA Advisory Circular (AC) specifications.

5. Projects shall be 100% complete prior to the date this RFP was issued.

6. Each project must have been continuously performed under a single stand-alone contract or under a single task order under an IDIQ contract.

7. Pavement was designed to support turbine engine aircraft.

5.2. 2.2 Special Requirements

The submitted project examples shall collectively satisfy all of the following special requirements. A single project may be used to meet more than one special requirement.

1. Construction of rigid pavements with thicknesses of 12 inches or greater.

2. Construction of flexible pavements with a thickness of 4 inches or greater, placed in multiple lifts.

3. Construction of airfield lighting systems.

4. Construction of airfield subgrade utilities.

5. Construction of airfield pavement markings.

6. Work included airfield pavement demolition.

7. Minimum placement amount of 2500 CY of Portland Cement Concrete (PCC).

8. Minimum placement amount of 1500 tons of Asphalt Cement Concrete (ACC).

5.2. 3. VOLUME 1, FACTOR 2 – OVERALL PROGRAM MANAGEMENT APPROACH

5.2. 3.1 Submission Requirements

This factor rates the effectiveness of the Offeror’s overall program management approach and organization to perform the requirements of a contract resulting from this solicitation. This factor should consist of no more than ten (10) pages. If the offeror submits more than ten (10) pages, then the Government will evaluate only the first ten (10) pages.

Offeror shall describe the management approach for the three (3) subject items listed below in accordance with Division 01-General Requirements of this solicitation. The use of job position titles in position descriptions (e.g.

Program Manager, Corporate QC Manager, Design Manager) and utilizing the actual names of individuals that may be assigned to those jobs (e.g., John Doe) is permitted.

Describe the organizational approach as it pertains to this solicitation, to include the following:

1) Organizational Structure

a. The offeror shall provide organizational structure of the offeror's proposed team for this contract and shall outline it on a diagrammed organizational chart. Offers shall include, at a minimum the subcontractors responsible for PCC pavement; ACC pavement; joint sawing and sealing; supplying of aggregate; supplying of cement; supplying of supplementary cementitious material; electrical/NAVAIDS;

and a validated testing laboratory. In addition, include subsidiaries and other pertinent corporate personnel filling key positions (as noted below in 5.2.3.1 (1)(b)) in this organizational structure and mark them to clearly communicate which positions are subcontracted. The offeror shall describe the relationship of these capabilities to the offeror (i.e., owned, subcontracted effort, joint venture, etc.). The organizational structure can be on an 11” x 17” paper and will be counted as one page.

b. In a related narrative, describe your program’s organization structure, identifying roles, responsibilities, hierarchies, lines of communication, and lines of authority both internally (to include team arrangement partners) and with the Government. Include at a minimum the role of the PM, Superintendent, QC Manager, Concrete Inspector, and the Petrographer. If the offeror is a Joint Venture, or has teaming agreements with subcontractors, suppliers, subsidiaries or other forms of relationships with other firms as a part of the proposal, the offeror shall describe the depth of history of the working partners as well as the formality and specific roles and responsibilities of the members. The narrative should also focus on the methods of subcontractor selection used with the various subcontractor disciplines.

2) Quality Control

a. Provide a one (1) page flow chart illustrating your quality control organizational structure.

b. In a related narrative, describe your quality control organization, identifying roles, responsibilities, hierarchies, and flows of communication both internally and with the Government. At a minimum, include the Construction Quality Control Manager and Design Quality Control Manager. Quality control narrative should address material sourcing. Quality control narrative should also describe how the offeror’s quality control plan is in use currently and should provide supporting data demonstrating the plans measurable success on other projects in accordance with UFGS 01 45 00.00 XX (per the service executing the task order).

3) Designer(s)/A-E Service Capabilities

a. Identify and clearly explain how the offeror intends to execute design efforts for Design-Build projects executed under the RFP scope.

b. Describe the capabilities and specialization (if any) of in-house designer(s)/A-E (for example, airfield lighting and NAVAIDS, BAK System, Geotech, etc.) firm(s). This section should also address the depth of experience the offeror and the designer (in house or subcontracted) have working on design-build projects together.

c. Provide an example of how the offeror, or the design firm coordinated past design and construction efforts, to include design quality control role, and the role of the Government in the Design-Build (DB) project. Example project should have been within 7 years of the date of the RFP. Example should highlight a difficulty or problem that the designer and prime overcame and how that problem affected the overall project, the customer, and how the prime mitigated any associated risk.

CLAUSES INCORPORATED BY REFERENCE

52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.222-5 Construction Wage Rate Requirements--Secondary Site of the

Work

MAY 2014

52.222-24 Preaward On-Site Equal Opportunity Compliance Evaluation FEB 1999

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a…