SEE ADDENDUM
(No Collect Calls)
W9128F22Q0080 30-Jun-2022
b. TELEPHONE NUMBER
402-995-2049
8. OFFER DUE DATE/LOCAL TIME
02:00 PM 15 Jul 2022
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W9128F9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
NOEMI LOZANO
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
ARMY CORPS OF ENGINEERS
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 966752 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
COE PROGRAMS MANAGEMENT BRANCH
LAURA STEPHENS
USA, OMAHA CENWO-PM-P
1616 CAPITOL AVE
OMAHA NE 68102-4901
TEL: 402-995-2802 FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
X 8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$17,000,000
NAICS:
541990
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF68
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W9128F22Q0080
Section SF 1449 - CONTINUATION SHEET
PERFORMANCE WORK STATEMENT
SP-POL-CMP-INSPECT-PWS-OFF
Offutt AFB, NE
Part 1 General Information
1. GENERAL:
1.1. Scope: This is a non-personnel services contract to perform inspections on
Department of Defense fuel tanks. This service entails removal, disposal, transfer of remaining fuel, tank cleaning, replacing wiper seals, and providing an above-ground storage tank (AST) Inspection on tank(s) listed in Attachment B. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn, is responsible to the Government.
1.2. Background: See attachment K for previous inspection report(s).
1.3. Objectives: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to set floating pan legs to their maintenance level, execute the fuel removal, transfer or disposal of remaining fuel, clean the tank, wiper seal replacement, tanks strapping, and perform an AST Internal inspection on the tank(s) as applicable at the location and tanks specified in attachment B as defined in this Performance Work Statement (PWS) except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.
1.4. Period of Performance: The period of performance shall be for 180 calendar days starting at the date of contract award. Earlier completion of required services is encouraged and acceptable.
1.5. General Information
1.5.1. Quality Assurance: The government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
1.5.2. Recognized Holidays:
New Years Day Martin Luther King Birthday President’s Day Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veteran’s Day Thanksgiving Christmas
1.5.3. Hours of Operation: The contractor is responsible for conducting business, between the hours of 0730-1630 Monday through Friday, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Other than normal duty hours must be coordinated with the KO or his/her designated representative. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall maintain stability and continuity of the workforce.
1.5.4. Place of Performance: The work to be performed under this contract will be performed at the installation and facilities identified in Attachment B.
1.5.5. Type of Contract: The government will award a Firm Fixed Price Contract
1.5.6. Security Requirements: Reference Attachment A – General Installation Security Requirements
1.5.7. Site Access: Contractor shall coordinate with Installation personnel for access to the site. Points of contact for the installation will be provided upon award.
1.5.8. Meetings/Kick-Off Meetings: The Contractor shall coordinate with USACE
PM and conduct a kickoff meeting prior to field activities. This can be accomplished either prior to mobilization and inspection activities or onsite prior to commencement of inspection activities. The Work Plan shall be discussed and further coordination and scheduling accomplished at this meeting. These meetings shall be at no additional cost to the government.
1.5.8.1. The Contractor shall call the installation 72 hours prior to mobilization to verify tank fuel quantities are at the quoted/verified amount as stated in
Attachment B as the contractor is not authorized to remove/transfer or dispose of more fuel than what is stated in the contract per Attachment B.
1.5.8.2. The Contractor shall be responsible to establish a report of findings and coordinate a teleconference after the inspection is complete and at least 24 hours prior to placing tank back into service. This teleconference will review deficiencies found during the inspection with the Government making the final decision on whether or not to place this tank back into service. The Contractor can use Attachment E - API INTERNAL INSPECTION TELECON BRIEFING TEMPLATE or their own format however this document shall include the next recommended inspection intervals for both External and Internal Inspection, and State regulated inspection intervals, if applicable. Also, when listing the findings, they shall be categorized as either “Mandatory”, “Recommended”. Coordinate with POC’s from Service Control Point (SCP), DLA, and USACE. Individuals to be identified after project award.
1.5.9. Contracting Officer Representative (COR): The (COR) will be identified by separate letter.
1.5.9.1. The COR is authorized to perform the following functions:
assure that the Contractor performs the technical requirements of the contract perform inspections necessary in connection with contract performance maintain written and oral communications with the Contractor concerning technical aspects of the contract issue written interpretations of technical requirements, including Government drawings, designs, specification monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies assist in coordinating availability of government furnished property
A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regards to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
1.5.10. Key Personnel: Certified API 653 Inspector and Project Manager.
1.5.11. Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting
Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI.
The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as they deem necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.5.12. Suitability For Service: Evaluate inspection data to determine suitability for continued use. Identify conditions which pose a risk to integrity. Determine a metal loss threshold for mandatory repairs. In the determination of mandatory repairs:
Use a "first, do no harm" approach to classifying tank repairs.
Use Desired Service Interval as the time to next inspection unless notified otherwise by the Contracting Officer.
Use minimum remaining thickness (MRT) no less than 100 mils at the next inspection.
Do not classify as mandatory repair of conditions which are noncompliant with current standards but are un-related to structural or hydraulic integrity (e.g., gouge, improper weld spacing, weld profile).
Apply repair determination to individual indications. Do not average across an entire plate or course.
PART 2
DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1. DEFINITIONS:
2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5. DELIVERABLE. Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.
2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7. MANDATORY REPAIR. Action necessary to preserve or restore the structural and hydraulic integrity of the tank or piping, or to mitigate a safety hazard.
Includes any condition which has or may breach the hydraulic or structural integrity of the tank prior to the next integrity inspection.
2.1.8. PHYSICAL SECURITY. Actions that prevent the loss or damage of
Government property.
2.1.9. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.10. QUALITY ASSURANCE SURVEILANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.11. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.12. RECOMMENDED REPAIR. Action intended to extend the service life of the tank or piping and to address conditions that currently, or within the next service interval, will not have an adverse effect on tank operability or integrity.
Applicability is limited to exclude soft or elastomeric parts for any pressure containing system.
2.1.13. SUBCONTRACTOR. One that enters into a contract with a prime contractor.
The Government does not have privity of contract with the subcontractor.
2.1.14. TANK INSPECTION. A multi-disciplinary engineering assessment of al petroleum, oil, and lubricant storage tank systems within or connected to the tank hydraulic boundary. Systems include nozzles, appurtenances and conveyance systems such as piping, stilling well, valve, flow control, cathodic protection, overfill protection, spill prevention, containment, leak detection, fire suppression, gauging, ventilation, lighting, and other electrical systems.
Inspection includes a review of cathodic protection reports and relevant as-built records when available. Unless stated otherwise, the limits are the boundary of secondary containment.
2.1.15. TANK INSPECTOR. An individual certified as a fuel storage tank inspector.
The recognized certification is API Std 653.
2.1.16. WORKDAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.17. WORK WEEK. Monday through Friday, unless specified otherwise.
2.2. ACRONYMS:
ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement ANG Army National Guard AR Army Regulation AST Aboveground Storage Tank API American Petroleum Institute ATG Automatic Tank Gauging AWWA American Water Works Association CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTR Contracting Officer's Technical Representative COTS Commercial-Off-the-Shelf DAF Department of the Air Force DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DOD Department of Defense
EPA Environmental Protection Agency FAR Federal Acquisition Regulation HIPAA Health Insurance Portability and Accountability Act of 1996 IAP International Airport KO Contracting Officer MOGAS Motor Gasoline NFPA National Fire Protection Association OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program RTO Returned to Operator STI Steel Tank Institute SCP Service Control Point TE Technical Exhibit UFC Unified Facilities Criteria UFGS Unified Facilities Guide Specification
PART 3
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND
SERVICES
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
3.1. Services: No Government furnished items or services are required.
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
4.1. General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.
4.2. Equipment: The Contractor shall provide all tools and inspection equipment needed to perform the inspection and other services to be performed under the PWS.
4.2.1. Precision Equipment: Contractor is responsible to ensure all equipment to be used is certified and calibrated to the parameters and tolerances of the required equipment.
4.2.2. Gaskets: Composition ring, one piece factory cut, compliant with ASME
B16.21, Buna-N. Gaskets must be composed of either graphite or synthetic fibers in a nitrile binder and must be resistant to the effects of aviation hydrocarbon fuels and manufactured of fire-resistant materials. Use full-faced gaskets for flat-face flanged joints. Buna-N material must conform to SAE
AMS3275.
4.2.3. Flange Bolts, Nuts, and Washers: Bolts for manway covers must conform to
ASME B18.2.1. Bolts must be of sufficient length to obtain full bearing on the nuts and must project no more than three full threads beyond the nuts with the bolts tightened to the required torque. Bolts must be regular hexagonal bolts conforming to ASME B18.2.1 with material conforming to ASTM A193/A193M, Class 2, Grade B8. Bolts must be threaded in accordance with ASME B1.1, Class 2A fit, Coarse Thread Series, for sizes one inch and smaller and Eight-Pitch Thread Series for sizes larger than one inch. Use stainless steel washers dimensioned in accordance with ASTM F436 flat circular and fabricated from the same grade of stainless steel as the bolt.
4.2.4. Periphery Double Wiper Seal and Penetration Seals: Periphery seals must be flexible wiper squeegee and made of closed cell cast urethane. The periphery seal must fit the space between the tank shell and the outer edge of the floating pan with two flexible seals, a primary and a secondary. The seals, primary and secondary as a unit, must accommodate a deviation between the path of the floating pan relative to the tank shell of an additional 100 mm 4 inches of compression and an additional extension of 50 mm 2 inches from its normal compressed position at any fluid level. The primary seal must be above the liquid level. Foam filled coated-fabric seals must not be accepted. The secondary seal must be above the primary seal. Seals must be capable of being replaced during tank operations, be durable in the tank's environment, be abrasion resistant, and not discolor or contaminate the liquid stored in the tank. Seals must be manufactured in the United States and must be provided in minimum continuous lengths of 8.54 meter 28 feet with no factory splices. Seals must be compatible with avgas, fuel oil, gasoline/ethanol, gasoline/MTBE 80/20, gasoline (unleaded), aviation turbine fuels, kerosene, and sea water. Material must be compliant with UFGS 33 56
21.17. The wiper seal product data specification sheets from the manufacturer must be submitted for review with the contractor’s proposal.
4.3. Project Inspection Management Plan (PMP): As part of the initial PMP, the
Contractor shall prepare and include a brief (< 10 pages) Work Plan, as an attachment, which will include proposed schedule, inspection activities, personnel performing inspection, required training certificates, and additional data or support requests.
4.4. Health and Safety Plan (HSP) and Accident Prevention Plan (APP): The
Contractor will prepare a Health and Safety Plan (HSP) to comply with 29 Code of Federal Regulations (CFR) 1910 and 1926 as well as applicable Military Service (Army, Air Force, or Navy), OSHA, state, host nation, and local and installation health and safety regulations regarding the proposed work effort. Qualifications for individuals who will be on-site for safety shall be submitted in the HSP.
4.4.1. The Accident Prevention Plan (APP) is required by FAR clause 52.236-13.
The APP describes the methods by which the contractor or USACE personnel will meet the safety and health requirements listed in EM 385-1-1. Entry into Confined Spaces shall comply with the requirements of 29 CFR 1910.146.
Provide additional monitoring for toxic (petroleum) vapors in addition to normal air monitoring requirements.
4.4.2. Abbreviated Accident Prevention Plans may be developed and submitted per
Form A-01 Abbreviated Accident Prevention Plan Checklist page A-13 of the EM 385-1-1. This may be submitted in order to develop a plan more specific to the work performed under this PWS but shall still comply as indicated above.
PART 5
SPECIFIC TASKS
5. Specific Tasks: Per each tank as identified in attachment B
5.1. Basic Services.
5.1.1. Perform a Tel-con kick-off meeting either prior to mobilization or the morning of the commencement of work on-site.
5.1.2. Remove, transfer, and/or dispose of remaining fuel quantities as stated in Attachment B. The contractor will be responsible to coordinate with environmental and safety authorities having jurisdiction to obtain and execute required permits, manifests, etc. Tank cleaning shall be done in accordance with UFGS 33 01 50.55.
5.1.3. The tank Inspection shall be in conformance with applicable industry standards API 653, API RP 575, NFPA 30, NFPA 326, UFGS 33 01 50.65, and in compliance with 40 CFR 112, UFC 3-460-01, UFC 3-460-03 and any other applicable federal, state, local and service requirements. Scan 100 percent of the tank bottom, as interior appurtenances allow, for indications such as metal loss, pits, cracks, gouges, and general corrosion. Distinguish between product and backside indications. Measure metal thickness with an ultrasonic method. Procedures must be compliant with ASME BPVC SEC V.
Record measurements, exclusive of coating, for all tank bottom plates.
Provide UT thickness measurement on no less than five locations per bottom plate and at indications from the screening technologies determined to be relevant. Mark relevant indications on tank surfaces in a neat and professional manner adjacent to the indication. Collect data to be used in the assessment of corrosion growth, structural integrity, brittle fracture, and hydraulic integrity. Complete the API Std 653 checklist and provide them with the DRAFT and FINAL reports. Utilize UFC 3-460-01 Table 8-1 and indicate appurtenances that are not present. The attached Inspection Report template should be utilized in submitting both the DRAFT and FINAL inspection reports. Contractor shall leave a clean and orderly site upon the completion of the inspection.
5.1.4. The contractor shall visually inspect containment for ability to contain the entire contents of the tank in the event of catastrophic failure, assessing for cracks, settlement, and deterioration. Record dimensions of cracks and provide photographic evidence of each deficiency. Visually assess the liner integrity and impermeability where applicable. Containment drain system shall be tested as follows.
5.1.5. Drain Line and Release Valve. The Contractor shall perform a hydrostatic test to ensure the drainpipe and release valve do not leak. Test in accordance with applicable requirements of AWWA C600 for hydrostatic testing. Ensure the release valve is closed and pressurize the end of the pipe within the containment basin sump. Test for leakage by filling the pipe with water and pressurizing to 10 psi using a suitable pump connected to the pipeline. The test pressure shall not vary by more than ±1 psi for the duration of the test. Hold this pressure for not less than 2 hours. If the system does not hold pressure, check the outfall point to see if water is bypassing the valve. Test pressure shall be maintained during the test by adding makeup water through the pressure test pump into the pipeline. Accurately note the amount of makeup water required to maintain pressure during the test.
5.1.6. Containment Drain Inlet. The Contractor shall perform a hydrostatic test to ensure the integrity of the inlet sump. Test for leakage by filling the inlet with water to a level at least 1-2 inches above the top of the inlet structure. The inlet shall hold this water for not less than 2 hours with no measurable change in the water level.
5.1.7. The existing wiper seal (foam log, double wiper etc.) shall be removed and completely replaced with a new double wiper seal in accordance with UFGS 33 56 21.17 and the IFR manufacturer's recommendations; penetration seals in the floating pan will also need replaced.
5.1.8. Upon completion of the Internal inspection the contractor shall provide a legible tank stencil or decal, consisting of black letters at least 1” in height, stating the date cleaned and inspected, the contractor’s name and the name of the contractor’s personnel supervising the work. Remove any existing stencils displaying previous inspection information. New information shall be provided in the following format:
Date Cleaned and Inspected: Day-Month-Year ABC Contracting Supervisor: John Doe
5.1.9. Provide Tel-con out briefing prior to closing up the tank.
5.1.10. When the tank is ready to be closed and RTO, the Contractor is responsible to provide new stainless-steel bolts and manway gasket and ensure there are no leaks at the manway by filling the tank to at least the first shell course.
5.1.11. Provide photographic documentation of the following: PLC make and model, Input/Output Alarm Modules including directories, Level Alarm Panel, Annunciator Panel, and any As-Builts that are in the alarm panel. Coordinate with the installation as needed to obtain this information.
5.1.12. Provide DRAFT and FINAL inspection reports per the attached templates.
The report(s) must include a record of NDE findings with drawings depicting plate layout and thickness measurement locations. Incorporate engineering analysis, suitability for service analysis, corrosion rate determinations, and remaining service life calculations. Provide separate report for each tank inspected. Specify the due date for the next inspection. Include the API Std 653 inspector of record certificate number and signature.
PART 6
APPLICABLE PUBLICATIONS
6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
6.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.
Steel Tank Institute (STI) SP001 Standard for the Inspection of Aboveground Storage Tanks
American Petroleum Institute (API) 653 Standard for the Tank Inspection, Repair, Alteration, and
Reconstruction 650 Welded Tanks for Oil Storage RP 575 Inspection Practices for Atmospheric and Low-pressure Storage
Tanks
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 30 Flammable and Combustible Liquids Code NFPA 70 National Electrical Code (NEC) NFPA 326 Standard for Safeguarding of Tanks and Containers for Entry, Cleaning, or Repairs
UNIFIED FACILITIES CRITERIA (UFC)
UFC 3-460-01 Design: Petroleum Fuel Facilities UFC 3-460-03 Petroleum Fuel Systems Maintenance
UNIFIED FACILITIES GUIDE SPECIFICATIONS (UFGS)
UFGS 33 01 50.55 Cleaning of Petroleum Storage Tanks UFGS 33 01 50.65 Inspection of Field Fabricated Fuel Storage Tanks UFGS 33 56 21.17 Single Wall Aboveground Fixed Roof Steel POL Storage Tank
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 112 EPA: Oil Pollution Prevention
PART 7
ATTACHMENT
7. Attachment/Technical Exhibit List:
7.1. Attachment A – General Installation Security Requirements
7.2. Attachment B – Fuel Storage Tank List
7.3. Attachment C – Fuel Storage Tank Excel Document
7.4. Attachment D – Monthly Contractors Progress, Management and Status Report
7.5. Attachment E – API Internal Inspection Telecon Briefing Template
7.6. Attachment F – API Internal Inspection Report Example
7.7. Attachment G – API Internal Inspection Report Template
7.8. Attachment H – Return to Service Letter
7.9. Attachment I – Not Applicable
7.10. Attachment J – Not Applicable
7.11. Attachment K – FAC 580 Inspection Report
TECHNICAL EXHIBIT 1
Performance Requirements Summary
The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
DELIVERABLES SCHEDULE
Performance Objective
Standard Performance Threshold
Method of Surveillance
PRS # 1.
Kick-Off Meeting with USACE and Stakeholders
Para. 1.5.8.
State, local, and federal requirements regulating fuel storage tanks
100% The contractor will schedule this Meeting either on-site prior to commencement of work or via tel-con prior to being onsite. Submit agenda and meeting minutes to stakeholders.
PRS # 2.
Clean and provide API 653 Internal Inspection and visual inspection of the containment area
Para. 5.1.3 & 5.1.4.
State, local, and federal requirements regulating fuel storage tanks
100% Random Inspection
PRS # 3.
Provide API 653 Internal Inspection reports
Para 5.1.12
State, local, and federal requirements regulating fuel storage tanks
100% Random Inspection.
The contractor is to provide a DRAFT and FINAL report for MCX review and comment
PRS #4
Wiper Seal Replacement Para. 5.1.7.
State, local, and federal requirements regulating fuel storage tanks
100% Random Inspection
PRS # 5.
Out-Brief Meeting with USACE and Stakeholders
Para 5.1.9.
State, local, and federal requirements regulating fuel storage tanks
100% Contractor will coordinate a Tel-con and distribute the report of findings 24 hrs prior to the scheduled conference
PRS #6
Fuel transfer and disposal Para. 5.1.2
State, local, and federal requirements regulating fuel storage tanks
100% Random Inspection
DELIVERABLE SCOPE OF
WORK
PARAGRAPH
DUE DATE
Project Inspection Management Plan/Work Plan, Accident Prevention Plan & Health and Safety Plan (Draft)
4.3 & 4.4 15 days after award
Project Inspection Management Plan/Work Plan, Accident Prevention Plan & Health and Safety Plan (Final)
4.3 & 4.4 5 days after receipt of comments
Inspection and Evaluation Report – (Draft) 5.1.12
28 days after Field Inspection
Inspection and Evaluation Report – to include populated Attachment C Excel Sheet for each base (Final)
5.1.12
7 days after receipt of comments
WAGE DETERMINATION
"REGISTER OF WAGE DETERMINATIONS UNDER | U.S. DEPARTMENT OF LABOR
THE SERVICE CONTRACT ACT | EMPLOYMENT STANDARDS ADMINISTRATION
By direction of the Secretary of Labor | WAGE AND HOUR DIVISION
| WASHINGTON D.C. 20210
| Wage Determination No.: 2015-5005 Daniel W. Simms Division of | Revision No.: 17 Director Wage Determinations| Date Of Last Revision: 03/15/2022
Note: Contracts subject to the Service Contract Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
|If the contract is entered into on or |With certain exceptions Executive Order | |after January 30 2022 or the |14026 applies to the contract. | |contract is renewed or extended (e.g. |The contractor must pay all covered workers | |an option is exercised) on or after |at least $15.00 per hour (or the applicable | |January 30 2022: |wage rate listed on this wage determination| | |if it is higher) for all hours spent | | |performing on the contract in 2022. | |If the contract was awarded on or |With certain exceptions Executive Order | |between January 1 2015 and January 29|13658 applies to the contract. | |2022 and the contract is not renewed |The contractor must pay all covered workers | |or extended on or after January 30 |at least $11.25 per hour (or the applicable | |2022: |wage rate listed on this wage determination| | |if it is higher) for all hours spent | | |performing on the contract in 2022. |
The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the Executive Orders is available at https://www.dol.gov/agencies/whd/government-contracts.
States: Iowa Nebraska
Area: Iowa Counties of Harrison Mills Pottawattamie Nebraska Counties of Cass Douglas Sarpy Saunders Washington
**Fringe Benefits Required Follow the Occupational Listing**
OCCUPATION CODE - TITLE FOOTNOTE RATE
01000 - Administrative Support And Clerical Occupations 01011 - Accounting Clerk I 16.05 01012 - Accounting Clerk II 18.03 01013 - Accounting Clerk III 20.16 01020 - Administrative Assistant 26.25 01035 - Court Reporter 26.10 01041 - Customer Service Representative I 14.28*** 01042 - Customer Service Representative II 15.59 01043 - Customer Service Representative III 17.51 01051 - Data Entry Operator I 15.53 01052 - Data Entry Operator II 16.94 01060 - Dispatcher Motor Vehicle 25.59 01070 - Document Preparation Clerk 19.11 01090 - Duplicating Machine Operator 19.11 01111 - General Clerk I 14.10*** 01112 - General Clerk II 15.38 01113 - General Clerk III 17.51 01120 - Housing Referral Assistant 20.10 01141 - Messenger Courier 13.90*** 01191 - Order Clerk I 14.61*** 01192 - Order Clerk II 15.94 01261 - Personnel Assistant (Employment) I 15.70 01262 - Personnel Assistant (Employment) II 17.58 01263 - Personnel Assistant (Employment) III 19.58 01270 - Production Control Clerk 20.35 01290 - Rental Clerk 12.30*** 01300 - Scheduler Maintenance 16.12 01311 - Secretary I 16.12 01312 - Secretary II 18.03 01313 - Secretary III 20.10 01320 - Service Order Dispatcher 22.87 01410 - Supply Technician 26.25 01420 - Survey Worker 13.58*** 01460 - Switchboard Operator/Receptionist 15.04 01531 - Travel Clerk I 18.18 01532 - Travel Clerk II 19.34 01533 - Travel Clerk III 20.53 01611 - Word Processor I 14.17*** 01612 - Word Processor II 15.92 01613 - Word Processor III 17.80 05000 - Automotive Service Occupations 05005 - Automobile Body Repairer Fiberglass 22.38 05010 - Automotive Electrician 21.70 05040 - Automotive Glass Installer 20.61 05070 - Automotive Worker 20.61 05110 - Mobile Equipment Servicer 18.30 05130 - Motor Equipment Metal Mechanic 22.60 05160 - Motor Equipment Metal Worker 20.61
05190 - Motor Vehicle Mechanic 22.60 05220 - Motor Vehicle Mechanic Helper 17.11 05250 - Motor Vehicle Upholstery Worker 19.44 05280 - Motor Vehicle Wrecker 20.61 05310 - Painter Automotive 21.70 05340 - Radiator Repair Specialist 20.61 05370 - Tire Repairer 13.73*** 05400 - Transmission Repair Specialist 22.60 07000 - Food Preparation And Service Occupations 07010 - Baker 13.48*** 07041 - Cook I 14.99*** 07042 - Cook II 16.89 07070 - Dishwasher 11.82*** 07130 - Food Service Worker 12.68*** 07210 - Meat Cutter 16.84 07260 - Waiter/Waitress 9.92*** 09000 - Furniture Maintenance And Repair Occupations 09010 - Electrostatic Spray Painter 19.46 09040 - Furniture Handler 13.29*** 09080 - Furniture Refinisher 19.46 09090 - Furniture Refinisher Helper 15.34 09110 - Furniture Repairer Minor 17.44 09130 - Upholsterer 19.46 11000 - General Services And Support Occupations 11030 - Cleaner Vehicles 13.86*** 11060 - Elevator Operator 13.86*** 11090 - Gardener 20.78 11122 - Housekeeping Aide 13.92*** 11150 - Janitor 13.92*** 11210 - Laborer Grounds Maintenance 16.83 11240 - Maid or Houseman 11.97*** 11260 - Pruner 15.49 11270 - Tractor Operator 19.44 11330 - Trail Maintenance Worker 16.83 11360 - Window Cleaner 15.11 12000 - Health Occupations 12010 - Ambulance Driver 17.03 12011 - Breath Alcohol Technician 20.33 12012 - Certified Occupational Therapist Assistant 29.52 12015 - Certified Physical Therapist Assistant 25.21 12020 - Dental Assistant 19.75 12025 - Dental Hygienist 35.42 12030 - EKG Technician 24.98 12035 - Electroneurodiagnostic Technologist 24.98 12040 - Emergency Medical Technician 17.03 12071 - Licensed Practical Nurse I 18.18 12072 - Licensed Practical Nurse II 20.33 12073 - Licensed Practical Nurse III 22.66 12100 - Medical Assistant 17.62 12130 - Medical Laboratory Technician 28.03 12160 - Medical Record Clerk 20.44 12190 - Medical Record Technician 22.86 12195 - Medical Transcriptionist 19.50 12210 - Nuclear Medicine Technologist 36.44 12221 - Nursing Assistant I 12.28*** 12222 - Nursing Assistant II 13.80*** 12223 - Nursing Assistant III 15.06 12224 - Nursing Assistant IV 16.92 12235 - Optical Dispenser 17.57 12236 - Optical Technician 16.57 12250 - Pharmacy Technician 17.30 12280 - Phlebotomist 16.84
12305 - Radiologic Technologist 27.03 12311 - Registered Nurse I 23.43 12312 - Registered Nurse II 28.67 12313 - Registered Nurse II Specialist 28.67 12314 - Registered Nurse III 34.68 12315 - Registered Nurse III Anesthetist 34.68 12316 - Registered Nurse IV 41.57 12317 - Scheduler (Drug and Alcohol Testing) 25.19 12320 - Substance Abuse Treatment Counselor 24.88 13000 - Information And Arts Occupations 13011 - Exhibits Specialist I 22.39 13012 - Exhibits Specialist II 27.73 13013 - Exhibits Specialist III 33.92 13041 - Illustrator I 20.94 13042 - Illustrator II 25.93 13043 - Illustrator III 31.73 13047 - Librarian 31.28 13050 - Library Aide/Clerk 11.64*** 13054 - Library Information Technology Systems 28.24 Administrator 13058 - Library Technician 16.37 13061 - Media Specialist I 20.39 13062 - Media Specialist II 22.80 13063 - Media Specialist III 25.41 13071 - Photographer I 15.34 13072 - Photographer II 17.15 13073 - Photographer III 21.25 13074 - Photographer IV 25.99 13075 - Photographer V 31.45 13090 - Technical Order Library Clerk 15.74 13110 - Video Teleconference Technician 19.91 14000 - Information Technology Occupations 14041 - Computer Operator I 18.03 14042 - Computer Operator II 20.16 14043 - Computer Operator III 22.76 14044 - Computer Operator IV 24.98 14045 - Computer Operator V 27.66 14071 - Computer Programmer I (see 1) 24.18 14072 - Computer Programmer II (see 1) 14073 - Computer Programmer III (see 1) 14074 - Computer Programmer IV (see 1) 14101 - Computer Systems Analyst I (see 1) 14102 - Computer Systems Analyst II (see 1) 14103 - Computer Systems Analyst III (see 1) 14150 - Peripheral Equipment Operator 18.03 14160 - Personal Computer Support Technician 24.98 14170 - System Support Specialist 28.10 15000 - Instructional Occupations 15010 - Aircrew Training Devices Instructor (Non-Rated) 30.60 15020 - Aircrew Training Devices Instructor (Rated) 34.46 15030 - Air Crew Training Devices Instructor (Pilot) 41.06 15050 - Computer Based Training Specialist / Instructor 30.60 15060 - Educational Technologist 34.82 15070 - Flight Instructor (Pilot) 41.06 15080 - Graphic Artist 24.10 15085 - Maintenance Test Pilot Fixed Jet/Prop 41.06 15086 - Maintenance Test Pilot Rotary Wing 41.06 15088 - Non-Maintenance Test/Co-Pilot 41.06 15090 - Technical Instructor 24.35 15095 - Technical Instructor/Course Developer 29.79 15110 - Test Proctor 19.66 15120 - Tutor 19.66
16000 - Laundry Dry-Cleaning Pressing And Related Occupations 16010 - Assembler 10.97*** 16030 - Counter Attendant 10.97*** 16040 - Dry Cleaner 12.53*** 16070 - Finisher Flatwork Machine 10.97*** 16090 - Presser Hand 10.97*** 16110 - Presser Machine Drycleaning 10.97*** 16130 - Presser Machine Shirts 10.97*** 16160 - Presser Machine Wearing Apparel Laundry 10.97*** 16190 - Sewing Machine Operator 13.24*** 16220 - Tailor 14.02*** 16250 - Washer Machine 11.49*** 19000 - Machine Tool Operation And Repair Occupations 19010 - Machine-Tool Operator (Tool Room) 21.42 19040 - Tool And Die Maker 24.75 21000 - Materials Handling And Packing Occupations 21020 - Forklift Operator 17.24 21030 - Material Coordinator 20.35 21040 - Material Expediter 20.35 21050 - Material Handling Laborer 15.94 21071 - Order Filler 13.24*** 21080 - Production Line Worker (Food Processing) 17.24 21110 - Shipping Packer 16.45 21130 - Shipping/Receiving Clerk 16.45 21140 - Store Worker I 13.54*** 21150 - Stock Clerk 17.23 21210 - Tools And Parts Attendant 17.24 21410 - Warehouse Specialist 17.24 23000 - Mechanics And Maintenance And Repair Occupations 23010 - Aerospace Structural Welder 26.33 23019 - Aircraft Logs and Records Technician 23.11 23021 - Aircraft Mechanic I 25.21 23022 - Aircraft Mechanic II 26.33 23023 - Aircraft Mechanic III 27.45 23040 - Aircraft Mechanic Helper 20.66 23050 - Aircraft Painter 24.50 23060 - Aircraft Servicer 23.11 23070 - Aircraft Survival Flight Equipment Technician 24.50 23080 - Aircraft Worker 23.40 23091 - Aircrew Life Support Equipment (ALSE) Mechanic 23.40 I 23092 - Aircrew Life Support Equipment (ALSE) Mechanic 25.21
II
23110 - Appliance Mechanic 20.00 23120 - Bicycle Repairer 20.94 23125 - Cable Splicer 38.62 23130 - Carpenter Maintenance 19.66 23140 - Carpet Layer 23.37 23160 - Electrician Maintenance 28.05 23181 - Electronics Technician Maintenance I 23.46 23182 - Electronics Technician Maintenance II 24.71 23183 - Electronics Technician Maintenance III 25.73 23260 - Fabric Worker 22.25 23290 - Fire Alarm System Mechanic 23.57 23310 - Fire Extinguisher Repairer 20.94 23311 - Fuel Distribution System Mechanic 26.39 23312 - Fuel Distribution System Operator 22.22 23370 - General Maintenance Worker 20.70 23380 - Ground Support Equipment Mechanic 25.21 23381 - Ground Support Equipment Servicer 23.11 23382 - Ground Support Equipment Worker 23.40 23391 - Gunsmith I 20.94
23392 - Gunsmith II 23.59 23393 - Gunsmith III 25.87 23410 - Heating Ventilation And Air-Conditioning 25.37 Mechanic 23411 - Heating Ventilation And Air Contidioning 26.49 Mechanic (Research Facility) 23430 - Heavy Equipment Mechanic 27.13 23440 - Heavy Equipment Operator 24.22 23460 - Instrument Mechanic 26.26 23465 - Laboratory/Shelter Mechanic 24.84 23470 - Laborer 15.94 23510 - Locksmith 23.45 23530 - Machinery Maintenance Mechanic 25.13 23550 - Machinist Maintenance 21.49 23580 - Maintenance Trades Helper 14.65*** 23591 - Metrology Technician I 26.26 23592 - Metrology Technician II 27.42 23593 - Metrology Technician III 28.29 23640 - Millwright 29.79 23710 - Office Appliance Repairer 20.24 23760 - Painter Maintenance 17.53 23790 - Pipefitter Maintenance 35.21 23810 - Plumber Maintenance 33.81 23820 - Pneudraulic Systems Mechanic 25.87 23850 - Rigger 25.87 23870 - Scale Mechanic 23.59 23890 - Sheet-Metal Worker Maintenance 28.88 23910 - Small Engine Mechanic 20.61 23931 - Telecommunications Mechanic I 29.09 23932 - Telecommunications Mechanic II 30.38 23950 - Telephone Lineman 25.15 23960 - Welder Combination Maintenance 20.79 23965 - Well Driller 21.19 23970 - Woodcraft Worker 25.87 23980 - Woodworker 20.94 24000 - Personal Needs Occupations 24550 - Case Manager 16.46 24570 - Child Care Attendant 11.78*** 24580 - Child Care Center Clerk 14.68*** 24610 - Chore Aide 12.47*** 24620 - Family Readiness And Support Services 16.46 Coordinator 24630 - Homemaker 16.46 25000 - Plant And System Operations Occupations 25010 - Boiler Tender 26.07 25040 - Sewage Plant Operator 26.33 25070 - Stationary Engineer 26.07 25190 - Ventilation Equipment Tender 19.74 25210 - Water Treatment Plant Operator 26.33 27000 - Protective Service Occupations 27004 - Alarm Monitor 20.00 27007 - Baggage Inspector 16.47 27008 - Corrections Officer 22.21 27010 - Court Security Officer 24.81 27030 - Detection Dog Handler 18.42 27040 - Detention Officer 22.21 27070 - Firefighter 27.79 27101 - Guard I 16.47 27102 - Guard II 18.42 27131 - Police Officer I 30.59 27132 - Police Officer II 34.00 28000 - Recreation Occupations
28041 - Carnival Equipment Operator 13.07*** 28042 - Carnival Equipment Repairer 13.98*** 28043 - Carnival Worker 10.42*** 28210 - Gate Attendant/Gate Tender 15.37 28310 - Lifeguard 11.34*** 28350 - Park Attendant (Aide) 17.19 28510 - Recreation Aide/Health Facility Attendant 12.54*** 28515 - Recreation Specialist 21.29 28630 - Sports Official 13.68*** 28690 - Swimming Pool Operator 17.03 29000 - Stevedoring/Longshoremen Occupational Services 29010 - Blocker And Bracer 26.83 29020 - Hatch Tender 26.83 29030 - Line Handler 26.83 29041 - Stevedore I 25.32 29042 - Stevedore II 28.25 30000 - Technical Occupations 30010 - Air Traffic Control Specialist Center (HFO) (see 2) 40.41 30011 - Air Traffic Control Specialist Station (HFO) (see 2) 27.87 30012 - Air Traffic Control Specialist Terminal (HFO) (see 2) 30.69 30021 - Archeological Technician I 18.46 30022 - Archeological Technician II 20.64 30023 - Archeological Technician III 25.57 30030 - Cartographic Technician 25.57 30040 - Civil Engineering Technician 21.59 30051 - Cryogenic Technician I 27.98 30052 - Cryogenic Technician II 29.43 30061 - Drafter/CAD Operator I 18.46 30062 - Drafter/CAD Operator II 20.64 30063 - Drafter/CAD Operator III 23.02 30064 - Drafter/CAD Operator IV 27.98 30081 - Engineering Technician I 16.00 30082 - Engineering Technician II 17.95 30083 - Engineering Technician III 20.08 30084 - Engineering Technician IV 24.89 30085 - Engineering Technician V 30.45 30086 - Engineering Technician VI 36.83 30090 - Environmental Technician 25.41 30095 - Evidence Control Specialist 24.05 30210 - Laboratory Technician 28.62 30221 - Latent Fingerprint Technician I 23.41 30222 - Latent Fingerprint Technician II 25.85 30240 - Mathematical Technician 27.28 30361 - Paralegal/Legal Assistant I 19.64 30362 - Paralegal/Legal Assistant II 24.32 30363 - Paralegal/Legal Assistant III 29.75 30364 - Paralegal/Legal Assistant IV 35.99 30375 - Petroleum Supply Specialist 29.43 30390 - Photo-Optics Technician 25.37 30395 - Radiation Control Technician 29.43 30461 - Technical Writer I 24.07 30462 - Technical Writer II 29.45 30463 - Technical Writer III 35.63 30491 - Unexploded Ordnance (UXO) Technician I 25.69 30492 - Unexploded Ordnance (UXO) Technician II 31.08 30493 - Unexploded Ordnance (UXO) Technician III 37.25 30494 - Unexploded (UXO) Safety Escort 25.69 30495 - Unexploded (UXO) Sweep Personnel 25.69 30501 - Weather Forecaster I 27.98 30502 - Weather Forecaster II 32.41 30620 - Weather Observer Combined Upper Air Or (see 2) 23.02 Surface Programs
30621 - Weather Observer Senior (see 2) 25.27 31000 - Transportation/Mobile Equipment Operation Occupations 31010 - Airplane Pilot 31.08 31020 - Bus Aide 18.04 31030 - Bus Driver 23.67 31043 - Driver Courier 15.63 31260 - Parking and Lot Attendant 12.66*** 31290 - Shuttle Bus Driver 16.03 31310 - Taxi Driver 13.68*** 31361 - Truckdriver Light 16.71 31362 - Truckdriver Medium 21.01 31363 - Truckdriver Heavy 22.18 31364 - Truckdriver Tractor-Trailer 22.18 99000 - Miscellaneous Occupations 99020 - Cabin Safety Specialist 15.15 99030 - Cashier 11.85*** 99050 - Desk Clerk 11.59*** 99095 - Embalmer 34.13 99130 - Flight Follower 25.69 99251 - Laboratory Animal Caretaker I 13.23*** 99252 - Laboratory Animal Caretaker II 14.15*** 99260 - Marketing Analyst 27.48 99310 - Mortician 34.13 99410 - Pest Controller 20.15 99510 - Photofinishing Worker 17.82 99710 - Recycling Laborer 17.88 99711 - Recycling Specialist 20.64 99730 - Refuse Collector 16.46 99810 - Sales Clerk 12.85*** 99820 - School Crossing Guard 14.74*** 99830 - Survey Party Chief 34.88 99831 - Surveying Aide 18.88 99832 - Surveying Technician 23.95 99840 - Vending Machine Attendant 14.88*** 99841 - Vending Machine Repairer 17.79 99842 - Vending Machine Repairer Helper 14.88***
***Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($15.00 per hour) or 13658 ($11.25 per hour). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 and 13658 are not currently being enforced as to contracts or contract-like instruments entered into with the federal government in connection with seasonal recreational services or seasonal recreational equipment rental for the general public on federal lands.
Note: Executive Order (EO) 13706 Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Service Contract Act for which the contract is awarded (and any solicitation was issued) on or after January 1 2017. If this contract is covered by the EO the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work up to 56 hours of paid sick leave each year.
This is the start of the file's text. The full file is on GovTribe.