20220906 Questions and Government Response.pdf
PDF 94 KB Posted
- Attached to
- Little Beaver Bay Bank Stabilization Federal contract opportunity
- Solicitation number
- W9128F22B0013
About this file
This document contains questions and responses from the U.S. Army Corps of Engineers regarding a solicitation for the Little Beaver Bay Bank Stabilization project. The scope of work involves placing approximately 940 linear feet of riprap along the shoreline of Lake Sakakawea to armor the slope against erosion. Additional requirements include hauling fill material to create a 3:1 slope, removing cut material for disposal, placing geotextile fabric and riprap, and reclaiming and seeding the current and future borrow locations. The anticipated award date is 30 September 2022, with a performance period of 180 calendar days from notice to proceed. The solicitation closes on 7 September 2022 and is restricted to small businesses. Offerors must register in the System for Award Management to access the solicitation documents through SAM.gov.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W9128F22B0013 AMD 0001.pdf | ||
| W9128F22B0013 - Site Visit Attendees.pdf | ||
| W9128F22B0013 - Little Beaver Bay - IFB.pdf | ||
| W9128F22B0013 - Little Beaver Bay - IFB.pdf | ||
| W9128F22B0013 Little Beaver Bay Cultural Bank Stabilization Drawings.pdf | ||
| W9128F22B0013 Little Beaver Bay Cultural Bank Stabilization specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
September 6, 2022
Questions and Government Responses
1. Q - Is the water from Lake Sakakawea available for compaction?
Government Response – Water from Lake Sakakawea can be used for compaction and dust control. The Contractor shall not use the boat ramp for filling water tanks but can use the shoreline that is within the disturbed area of the construction zone.
2. Q - Is it acceptable for the contractor to build turn-arounds at the beginning and end of the project? (These would be on the beach but not in the water)
Government Response – Yes it is acceptable for building turn-arounds at the beginning and end of the project on the shoreline. Construction activities and disturbance shall remain above elevation 1838 and within 30 feet of the toe of the riprap being placed, in areas not designated as turn-arounds. No disturbance will be allowed at the elevation of the water surface or below.
3. Q - What is the anticipated project start date? The concern is if the Government takes 60 days to award it will be too late to compact embankment this year. With no work allowed between 4/15 and 9/5 the project wouldn’t get going until 9/6/23 (after time has already expired).
Government Response – Corps anticipates award by 30 September 2022 and Contractor shall begin performance within 10 calendar days and complete within 180 calendar days after receiving Notice to Proceed (NTP). NTP will be issued upon acceptance of all required contract submittals from the Contractor.
Bid time WILL NOT be extended and an Amendment WILL NOT be issued.
Reviewed by Daniel Monahan, Contracting Officer