This draft request for proposal (RFP) solicits design-build construction services in support of petroleum, oil, and lubricants facilities infrastructure for various locations in the United States, Alaska, Hawaii, and outlying areas. The U.S. Army Corps of Engineers Omaha District intends to award up to four firm-fixed-price, indefinite-delivery/indefinite-quantity contracts under a multiple award task order contract with a maximum total value of $150 million. The scope of work includes replacement of aging fuel infrastructure and components, repair of storage tanks and containment areas, upgrades and maintenance, facility demolition, construction of support facilities, and regulatory compliance. A final RFP is expected to be released on or about January 1, 2021. Interested offerors are requested to submit any comments or questions to the U.S. Army Corps of Engineers via the ProjNet bidder inquiry system using the provided key by the listed due date.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INDEFINITE DELIVERY CONTRACT FOR DESIGN-BUILD CONSTRUCTION IN SUPPORT OF POL FACILITIES - INFRASTRUCTURE, VARIOUS LOCATIONS IN THE CONTINENTAL UNITED STATES (CONUS), ALASKA, HAWAII AND US TERRITORIES

This solicitation is Unrestricted. A target of four (4) Indefinite Delivery Contracts may be aw arded for a base performance period of four (4) years w ith one (1) three (3) year option period. The combined total value of the all contracts shall not exceed $150,000,000. The minimum contract guarantee is $2,500.

Except as provided below , w ork w ill be performed by the selected qualif ied Contractors pursuant to firm-fixed-price contracts. Task Orders w ill be requested from time to time, as the need arises, during the contract period. There is no value assigned to the task order minimum or maximum. Wage rates applicable to the area of w ork w ill be added to each task order. The offeror agrees to do all the w ork described in these documents.

RETURN WITH PROPOSAL: SECTIONS 00 10 00, 00 45 00, AND INFORMATION REQUIRED IN SECTION 00 22 10 FOR PHASE 1 OF 2. FOR OFFERORS SELECTED TO PARTICIPATE IN PHASE 2 OF 2, SEE SECTION 00 22 20 AND PRICING SUBMISSION REQUIREMENTS.

ERICKA T COLLINS 402-995-2116

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

08-Jan-2021

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________Per task order

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

W9128F

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

(hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W9128F21R0008 74

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W9128F21R0008

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 150,000,000 Job $150M DB Fuels MATOC - UNR

FFP

Base (4 -Year) Design-Build Construction in Support of POL Facilities – Infrastructure for Various locations in the Continental United States (CONUS), Alaska, Hawaii and U.S. Territories. The work shall be in accordance with Request for Proposal documents issued within this solicitation.

FOB: Destination

PSC CD: Y1GC

NET AMT

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0002 UNDEFINED Job OPTION $150M DB Fuels MATOC - UNR

FFP

Option (3 -Year) Design-Build Construction in Support of POL Facilities – Infrastructure for Various locations in the Continental United States (CONUS), Alaska, Hawaii and U.S. Territories. The work shall be in accordance with Request for Proposal documents issued within this solicitation.

MAX

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0003 UNDEFINED Job OPTION $150M DB Fuels MATOC - UNR

FFP

Option (6- months) Design-Build Construction in Support of POL Facilities – Infrastructure for Various locations in the Continental United States (CONUS), Alaska, Hawaii and U.S. Territories. The work shall be in accordance with Request for Proposal documents issued within this solicitation.

MAX

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 N/A N/A N/A N/A

0002 N/A N/A N/A N/A

0003 N/A N/A N/A N/A

Section 00 21 00 - Instructions

INSTRUCTIONS TO OFFERORS

SECTION 00 21 00

INSTRUCTIONS TO OFFERORS (RFP)

10/20

PART 1 GENERAL

1.1 GENERAL SOLICITATION INFORMATION

This Request for Proposal (RFP) is for solicitation of a Multiple Award Task Order Contract (MATOC). This solicitation is unrestricted and open to both large and small business participants.

1.2 SUBMISSION DEADLINE

Offers shall be submitted as stated and by the time and date as specified in Section 00 10 00, Page 1.

{Submit proposals in accordance with instructions found in Section 00 22 10)

ELECTRONIC DELIVERY TO:

Tyler.Hegge@usace.army.mil Glenda.A.Canty@usace.army.mil Ericka.T.Collins@usace.army.mil

See Section 00 22 10 SUPPLEMENTARY INSTRUCTIONS (SUBMISSION REQUIREMENTS AND EVALUATION) for additional submission details.

1.3 COPIES OF SOLICITATION DOCUMENT AND AMENDMENTS

Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the beta.SAM.gov website.

It shall be the Contractor's responsibility to check the websites for any amendments. The offeror shall submit in the proposal all requested information specified in this solicitation. There will be no public opening of the proposals received as a result of this solicitation.

1.4 OFFEROR'S QUESTIONS AND COMMENTS

Questions and/or comments relative to these documents should be submitted via Bidder Inquiry as indicated below.

For any other matters regarding this RFP, please contact:

Contract Specialist - Primary POC:

Ms. Glenda A. Canty Glenda.A.Canty@usace.army.mil 402-995-2059 (Telephone)

1.5 BIDDER INQUIRY

Questions relating to the proposal are to be submitted via Bidder Inquiry in ProjNet at:

https://www.projnet.org/projnet/ No Later Than ten (10) calendar days before due date of proposals, in order that they may be given consideration or actions taken prior to receipt of offers. The Bidder Inquiry system is to be used to ask and receive answers to all non-proprietary questions.

To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via ProjNet email notification after an answer to the comment/question after it has been processed by our technical team.

All timely questions and approved answers will be made available through ProjNet.

The Solicitation Number is: W9128F-21-R-0008

The Bidder Inquiry Key is: 4824PT-AG5VCF

a. Registration for ProjNet Bidder Inquiry Access

If you are already registered, go to Entering Bidder Inquiries in ProjNet Bidder Inquiry System below.

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

b. Entering Bidder Inquiries in ProjNet Bidder Inquiry System

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

8. Follow online screen instructions to enter specific bidder inquiries for the project.

c. The Bidder Inquiry System will be unavailable for new inquires after ten (10) calendar days in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

d. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

1.6 GENERAL DESCRIPTION OF WORK

EVALUATION – PHASE 1) and Section 01 11 00 SUMMARY OF WORK for a general description of work to be performed under this Multiple Award Task Order Contract (MATOC).

1.7 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION AND CONTRACT AWARD

EVALUATION).

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

-- End of Document --

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.204-24 Representation Regarding Certain Telecommunications and

Video Surveillance Services or Equipment.

AUG 2020

52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.215-1 Alt I Instructions to Offerors--Competitive Acquisition (Jan 2017) -

Alternate I

OCT 1997

52.215-22 Limitations on Pass-Through Charges--Identification of Subcontract Effort

OCT 2009

52.216-27 Single or Multiple Awards OCT 1995 52.217-5 Evaluation Of Options JUL 1990 52.222-5 Construction Wage Rate Requirements--Secondary Site of the

Work

MAY 2014

52.232-13 Notice Of Progress Payments APR 1984 52.236-28 Preparation of Proposals--Construction OCT 1997 52.252-3 Alterations in Solicitation APR 1984

CLAUSES INCORPORATED BY FULL TEXT

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be DX rated order; DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation. [Contracting Officer check appropriate box.]

(End of provision)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a target of four (4) Indefinite Delivery/Indefinite Quantity (IDIQ) Firm- Fixed-Price (FFP) Multiple Award Task Order Contracts resulting from this solicitation.

52.222-52 EXEMPTION FROM APPLICATION OF THE SERVICE CONTRACT LABOR STANDARDS TO

CONTRACTS FOR CERTAIN SERVICES--CERTIFICATION (MAY 2014)

(a) The offeror shall check the following certification:

CERTIFICATION

The offeror ( ___ ) does ( ___ ) does not certify that--

(1) The services under the contract are offered and sold regularly to non-Governmental customers, and are provided by the offeror (or subcontractor in the case of an exempt subcontract) to the general public in substantial quantities in the course of normal business operations;

(2) The contract services are furnished at prices that are, or are based on, established catalog or market prices. An “established catalog price” is a price included in a catalog, price list, schedule, or other form that is regularly maintained by the manufacturer or the offeror, is either published or otherwise available for inspection by customers, and states prices at which sales currently, or were last, made to a significant number of buyers constituting the general public. An “established market price” is a current price, established in the usual course of ordinary and usual trade between buyers and sellers free to bargain, which can be substantiated from sources independent of the manufacturer or offeror;

(3) Each service employee who will perform the services under the contract will spend only a small portion of his or her time (a monthly average of less than 20 percent of the available hours on an annualized basis, or less than 20 percent of available hours during the contract period if the contract period is less than a month) servicing the Government contract; and

(4) The offeror uses the same compensation (wage and fringe benefits) plan for all service employees performing work under the contract as the offeror uses for these employees and for equivalent employees servicing commercial customers.

(b) Certification by the offeror as to its compliance with respect to the contract also constitutes its certification as to compliance by its subcontractor if it subcontracts out the exempt services. If the offeror certifies to the conditions in paragraph (a) of this provision, and the Contracting Officer determines in accordance with FAR 22.1003-4(d)(3) that the Service Contract Labor Standards statute--

(1) Will not apply to this offeror, then the Service Contract Labor Standards clause in this solicitation will not be included in any resultant contract to this offeror; or

(2) Will apply to this offeror, then the clause at FAR 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Requirements, in this solicitation will not be included in any resultant contract awarded to this offer, and the offeror may be provided an opportunity to submit a new offer on that basis.

(c) If the offeror does not certify to the conditions in paragraph (a) of this provision--

(1) The clause of this solicitation at 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Requirements, will not be included in any resultant contract to this offeror; and

(2) The offeror shall notify the Contracting Officer as soon as possible if the Contracting Officer did not attach a Service Contract Labor Standards wage determination to the solicitation.

(d) The Contracting Officer may not make an award to the offeror, if the offeror fails to execute the certification in paragraph (a) of this provision or to contact the Contracting Officer as required in paragraph (c) of this provision.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

Tyler Hegge (CENWO-CT AST) US Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, NE 68102

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/content/regulations

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Defense Federal Acquisiton Regulation (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

Section 00 22 00 - Supplementary Instructions

00 22 10 PHASE 1

SECTION 00 22 10

PHASE 1 OF 2 PHASE SELECTION PROCEDURES

INDEX

1. SCOPE OF WORK

1.1. GENERAL DESCRIPTION OF WORK

1.2. TYPES OF PROJECTS

1.3. ON-RAMP PROCEDURES

2. SELECTION PROCEDURE OVERVIEW

3. PHASE 1 PROPOSAL FACTORS IN PHASE 2

4. GENERAL PROPOSAL SUBMISSION INSTRUCTIONS

4.1. SUBMISSION INSTRUCTIONS

4.2. SUBMISSION DEADLINE

5. PROPOSAL FORMAT AND SUBMITTAL REQUIREMENTS

6. INQUIRIES/QUESTIONS

7. CONTRACTOR TEAM ARRANGEMENTS

7.1. CONTRACTOR TEAM ARRANGMENT OTHER THAN JOINT VENTURE

7.2. JOINT VENTURE TEAM ARRANGMENT

7.3. INTEGRITY AND VALIDITY OF CONTRACTOR TEAM ARRANGEMENTS

8. BASIS FOR AWARD

9. RELATIVE IMPORTANCE OF EVALUATION FACTORS

10. SOURCE SELECTION PROCESS

11. TECHNICAL RATING

12. PAST PERFORMANCE RATING

13. SMALL BUSINESS PARTICIPATION PLAN

14. RATING DEFINITIONS

15. CPARS AND CCASS RECORDS

16. DEBRIEFING OFFERORS

17. DEFINITIONS

18. TECHNICAL FACTORS TO BE EVALUATED

18.1. VOLUME 1, TAB 1 – FACTOR 1 – PREVIOUS EXPERIENCE

18.1.1. Submission Requirements

18.1.2. Evaluation Criteria

18.2. VOLUME 1, FACTOR 2 – PAST PERFORMANCE

18.2.1. Submission Requirements

18.2.2. Evaluation Criteria

18.3. VOLUME 1, FACTOR 3 – TECHNICAL/MANAGEMENT APPROACH

18.3.1. Submission Requirements

18.3.2. Evaluation

19. ATTACHMENT 1 - PAST PERFORMANCE QUESTIONNAIRE (FORM PPQ-0)

SECTION 00 22 10

PHASE 1 OF 2 PHASE SELECTION PROCEDURES

1. SCOPE OF WORK

The scope of this request for proposal (RFP) includes all work required for Design-Build Construction in Support of POL Facilities – Infrastructure for Various locations in the United States (CONUS, Alaska, and Hawaii) and outlying areas. In Phase 1 of 2 Phase Selection Procedures a maximum of six (6) of the most highly qualified firms will be selected by the Government to participate in Phase 2 of this solicitation. This solicitation is a open to both large and small business participants. In Phase 2 of this solicitation, the Government intends to award a target of four (4) Firm-Fixed Price, Indefinite Delivery Indefinite Quantity (IDIQ) contracts under one Multiple Award Task Order Contract (MATOC) in support of the Petroleum, Oil and Lubricants – Mandatory Center of Expertise (POL- MCX). The work shall be in accordance with Request for Proposal documents issued within this solicitation.

1.1. GENERAL DESCRIPTION OF WORK

The purpose of this MATOC is to provide design-build and construction services in support of sustainability, restoration, modernization (SRM) and design-build construction of DoD Fuels Infrastructure within the United States (CONUS, Alaska, and Hawaii) and outlying areas. The scope of work for this acquisition includes, but is not limited to: replacement of aging fuel infrastructure and/or components, repair of storage tanks and containment areas, POL system upgrades and maintenance (modernization), facility demolition, construction of fuels support facilities, regulatory compliance, and design to support the construction work projects for primary customer, Defense Logistics Agency (DLA). As requirements develop, Requests for Proposals (RFPs) for projects will be issued under individual Task Orders.

The majority of the work to be performed under these contracts is necessary due to the age of the infrastructure, absence of maintenance, and safety/environmental regulatory compliance requirements for the imperative and successful operation of the POL facilities. The DoD petroleum infrastructure consists largely of real property facilities and supporting infrastructure which transfer, receive, store, and dispense petroleum products in support of day-to-day, training and operational missions across the globe. Petroleum products are typically transferred by rail, pipeline and truck. Storage is accomplished by bulk storage (tank farms) or operational storage tanks.

Dispensing is from operational storage or dispensing points into vehicles, mobile tanks, refueling vehicles or aircraft/equipment refueling points.

The total value of all task orders awarded under this MATOC will not exceed $150,000,000. The minimum guarantee amount for each contract will be $2,500.00. Task orders will be Firm Fixed Price (FFP) and generally within the value range of approximately $2,000,000.00 or above. Orders will follow the ordering procedures in Paragraph 1.3 below.

1.2. TYPES OF PROJECTS

Work anticipated under this MATOC includes design and construction work identified in Table 1 - SPECIALIZED WORK for POL fuel storage complexes, or portions thereof, in support of fuel distribution systems. Task order projects will include fuel system design services, inspection services and other services needed to complete each task order construction project. Task orders may include incidental excavation and proper disposal of POL contaminated soils. Broader mitigation efforts would not be executed under this MATOC. The majority of the task orders will be design-build, with a minor amount being design-bid-build task orders.

Where a project task order includes installation or modification of a control system, such as tank gauging equipment, fuel dispensing management systems, pump control systems, HVAC controls, fire alarm systems, etcetera, the designs completed and the equipment provided shall be in accordance with current cyber security requirements applicable, based upon the security controls required for the system categorization.

All work will be accomplished in compliance with Military Fuel Standards, UFC 3-460-01, DoD, American Petroleum Institute (API), state and federal regulations.

Table 1 – SPECIALIZED WORK

a. Construction, maintenance, repair and demolition of POL facilities and infrastructure, to include design. Facilities and infrastructure include facilities in direct support of the fuel receipt, pipeline, storage, transfer, containment, laboratory testing, POL operations, quality control, equipment, and dispensing systems

b. Tank rehabilitation. Work consists of construction, repairing, replacing, and upgrading coatings, worn components, corrosion, and deficiency to the tank systems necessary to make the tank fully functional for support of mission requirements. Components typically include valves, pumps, piping, controls, dikes/berms, structural components (shell/tank bottom), life safety, and fire safety systems.

c. Tank cleaning prior to inspection and upgrades. Work includes cleaning to remove residual fuel products, water/sludge removal, and preparation of tank for inspection.

d. Repairs and Emergency Inspections Only. This includes POL facility inspections to determine condition. The inspection report documents current conditions and requirements for servicing, repairs, and upgrades.

THE OFFEROR SHALL BE REGISTERED FOR NAICS CODE 237120 AT A MINIMUM BY THE DATE

PHASE 1 PROPOSALS ARE DUE.

1.3. ON-RAMP PROCEDURES

Reference Section 00 73 00, paragraph 1.6 ON-RAMP PROCEDURES.

2. SELECTION PROCEDURE OVERVIEW

In Phase 1 of the two phase selection procedure, Offerors submit certain specified performance capability proposals, demonstrating their capability to successfully execute task orders under a contract resulting from this solicitation. The Government will evaluate the qualifications submitted in Phase 1 of 2 Selection Procedures and will invite a maximum of six (6) of the most highly qualified Offerors to compete in Phase 2 for award of the

MATOC.

Offerors must submit a complete Phase 1 proposal to be considered for Phase 2. PHASE 1 DOES NOT INVOLVE

PRICING SUBMISSION.

Prior to Phase 2, an amendment will be issued to only the selected Offerors from Phase 1 inviting them to submit Phase 2 technical and price proposals for consideration. The amendment will request additional information needed to complete the submission of Phase 2 proposals. In Phase 2, the Source Selection Authority and Contracting Officer’s intent is to award a target of four (4) contracts under this MATOC to the Offerors whose proposal offers the best value to the Government. DO NOT SUBMIT ANY PHASE 2 DOCUMENTS DURING PHASE 1.

Offerors must submit a complete Phase 2 proposal to be considered for award. Failure to submit a complete proposal may result in the entire proposal being rejected.

3. PHASE 1 PROPOSAL FACTORS IN PHASE 2

The Phase 1 evaluations will be carried forward into the Phase 2 evaluation. There is no separate submission of Phase 1 information required or allowed for Phase 2. The Government will incorporate the Phase 1 individual factor ratings, underlying narratives, etc. when evaluating the Phase 2 proposals to determine the proposals which provides the best value to the Government.

4. GENERAL PROPOSAL SUBMISSION INSTRUCTIONS

This solicitation is unrestricted and is open to all potential Offerors.

Offerors formally organized as Design/Build (DB) entities, or design firms and construction contractors that have formed a teaming arrangement specifically for this contract, or any other interested party may submit proposals. All Offerors must be registered in the System for Award Management (SAM) in the same manner as they are proposing for this solicitation (i.e. a single entity proposing as a Joint Venture must be registered as a Joint Venture).

The North American Industry Classification System code for this project is 237120, with a size standard for Small Business of $39.5 million dollars.

In order to effectively and equitably evaluate all proposals, the Contracting Officer must receive information sufficiently detailed to clearly describe the proposal. There will be no public proposal opening. All proposals submitted will become, upon receipt, the property of the U.S. Government and will not be returned. After evaluation of proposals, any extra copies of the proposals deemed unnecessary by the government will be destroyed.

The original will be retained for the official contract file. In addition, extra copies of the awardees’ proposal will be submitted to the Field and Areas Offices in support of their contract administration functions.

4.1. SUBMISSION INSTRUCTIONS

In an effort to reduce paperwork and cost, all proposals shall be submitted electronically. All submissions will be in Adobe PDF format with Optical Character Recognition (OCR) applied to all documents that will enable word searches to be conducted using Adobe-compatible PDF software. The two (2) volumes listed below shall be submitted as SEPARATE files via email. Offerors may use compression utilities such as 7-Zip, WinZip or PKZip to reduce file size and facilitate transmission. Offerors are encouraged to send both files in the same email transmission, if possible.

PHASE 1:

Volume I: Technical Proposal, Factors 1-3 Volume II: Required Documents

Title the single files in the following format:

W9128F21R0008_COMPANY NAME_PHASE1_VOLUME_I

W9128F21R0008_COMPANY NAME_PHASE1_VOLUME_II

For this solicitation, the recipients will be:

1. Tyler Hegge, whose email address is tyler.hegge@usace.army.mil and

2. Glenda Canty, whose e-mail address is glenda.a.canty@usace.army.mil and

3. Ericka T. Collins, whose email address is ericka.t.collins@usace.army.mil

For the purposes of determining whether the proposal was received “late” in accordance with FAR 15.208, the date and time the file(s) are received via email will be the time and date the Government received the proposal. Do not assume that electronic communication is instantaneous. Please make allowances for delays in transmittal.

Electronic Proposals shall be received via email No Later Than (NLT) the date and time indicated in Block 13 of the SF 1442 for this solicitation or as identified in subsequent amendments.

The Government is not be responsible for proposals delivered to any location or to anyone other than those designated to receive proposals on its behalf. The Offeror is responsible for ensuring that the proposal is submitted so as to reach the designated recipient and is responsible for allowing sufficient time for the proposal to be received in accordance with the information provided.

Failure to submit a complete proposal IAW instructions and requirements may result in the entire offer being rejected.

4.2. SUBMISSION DEADLINE

Offers shall be submitted at the location stated and by the time and date specified in Block 13 of Standard Form 1442 (Section 00 10 00, Page 1).

5. PROPOSAL FORMAT AND SUBMITTAL REQUIREMENTS

1. In order to be considered for award of a contract for the requirements of this solicitation, the Offeror must submit a complete proposal with its offer. Failure to submit a complete proposal may result in the entire offer being rejected. The proposals shall be submitted in Volumes as follows:

Phase 1

Phase 1, Volume I, Technical Proposal:

Table of Contents FACTOR 1 Previous Experience FACTOR 2 Past Performance FACTOR 3 Technical/Management Approach

Phase 1, Volume II, Required Documentation:

Cover Letter Table of Contents Completed SF 1442 Bond Letter Contractor Team Arrangement Requirements Completed SF 30 (if applicable)

TABLE 1: Phase 1 Evaluation Factors

Volume Eval Factor Tab –Title Page Limitations

I Factor 1 Previous Experience

I Factor 2 Past Performance No Page Limitations for Past

Performance

I Factor 3 Technical/Management Approach

10 - If an offeror utilizes 11”x17” paper for the organization structure, it will be counted as one (1) page.

2. Proposal Characteristics

a) Each Volume shall contain a table of contents and all pages of each factor shall be sequentially numbered. All text must be legible (no smaller than 10pt.) and easily read. The page size of the Offeror’s proposal shall not exceed 8-1/2 by 11 inches. Diagrams, charts and tables shall conform to the paper size. All text shall be typed single-spaced. Margins (1-inch) shall be clean and clear of any text except for proprietary statements, security markings and page numbers which may fall within the defined margin area. Solicitation number and company name of Offeror may also be included within the margins. Submit the SF 1442, completed and signed by a person authorized by the Offeror.

ONLY PHASE 1 VOLUMES I & II NEED TO BE SUBMITTED DURING PHASE 1 OF THE TWO

PHASE SELECTION PROCEDURE.

b) Offeror shall submit a cover letter containing:

i. Solicitation number

ii. Name, title, address, email, and telephone number of the offeror.

iii. Names, titles, emails, and telephone numbers of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this RFP.

iv. Name, title and signature of the person authorized to sign the proposal.

v. A statement specifying agreement with all terms, conditions and provisions included in the RFP.

c) Offerors shall submit a completed SF1442 with their proposal.

d) Offerors shall submit a letter from their bonding company agent certifying the current maximum bonding capacity per project and the aggregate capacity.

e) For Contractor Team Arrangements including Joint Ventures, submit the information required by Paragraph 7 “Contractor Team Arrangements”.

f) Offerors shall submit acknowledgement of all amendments to the RFP in accordance with the instructions on the Standard Form 30 (amendment form).

3. Prior to Phase 2, an amendment will be issued to selected Offerors from Phase 1 inviting them to submit

Phase 2 technical and price proposals for consideration. The amendment will request additional information needed to complete the submission of Phase 2 proposals. The following evaluation criteria will be included in Phase 2 Selection Procedures:

Evaluation Factor 4: Key Personnel Evaluation Factor 5: Technical Approach for the Sample Project Evaluation Factor 6: Small Business Participation Plan Cost / Price Proposal for the Sample Project

6. INQUIRIES/QUESTIONS

Prospective Offerors shall submit contracting and technical inquiries and questions concerning this solicitation document via Bidder Inquiry in ProjNet at www.projnet.org/projnet. Please refer to Section 00 21 00 of this solicitation for Bidder Inquiry instructions.

***Please Note: Offerors shall only submit one question per inquiry. All inquiries containing multiple questions shall be rejected.

7. CONTRACTOR TEAM ARRANGEMENTS

7.1. CONTRACTOR TEAM ARRANGMENT OTHER THAN JOINT VENTURE

PHASE 1 Requirements:

All Offerors proposing a team arrangement other than a Joint Venture, shall submit the following information in Phase 1:

a. Provide a listing of the team arrangement members’ corporate name (no abbreviations), address, point of contact, phone number, DUNS Number, and Cage Code.

b. Indicate to what extent the members of this team arrangement have worked together in the past, including identifications of magnitude and complexity of projects worked on.

c. Submit a copy of the signed team arrangement agreement or binding letter of commitment between each team member. All team arrangement agreements and letters of commitment shall:

(1) clearly identify the expected relationship, role and responsibility between the firms, prime contractor, and of the subcontractor or other entity (type and proportion of work to be performed);

and

(2) shall be signed by the appropriate individual(s) of each firm.

7.2. JOINT VENTURE TEAM ARRANGMENT

No contract may be awarded to a Joint Venture that is not registered in the System for Award Management (SAM) database. The joint venture must have its own Data Universal Numbering System (DUNS) number and register as such. An 8(a) joint venture agreement must be received by Small Business Administration (SBA) prior to the Phase 1 proposal due date and approved before award of any resulting contract.

PHASE 1 Requirements:

a. In the cover letter of your proposal, provide the complete names, addresses, and phone numbers of the firms comprising the joint venture.

b. A copy of the Joint Venture agreement.

c. Signature requirements: SF 1442, SOLICITATION, OFFER, AND AWARD (pages 00 10 00- 1 and 00 10 00-2), Block 20 requires that the name and title of a person authorized to sign the offer for the joint venture be provided. In the case of a joint venture, subject Standard Form shall be signed by the principal representative of the joint venture (or the alternate principal representative, if the principal representative is unavailable).

d. Indicate to what extent the members of the joint venture have worked together in the past, including identifications of magnitude and complexity of projects worked on.

e. In addition to the requirements stated above, and to assure a single point of contact for resolution of contractual matters and payments, the Offeror shall submit a certificate signed by each participant in the joint venture containing the following statement:

“The parties hereto expressly understand and agree as follows:

1. (name, title, and company) is the principal representative of the joint venture. As such, all communications regarding the administration of the contract and the performance of the work there under may be directed to him or her. In the absence of (same name, title, and company), (enter name, title, and company of alternate) is the alternate principal representative of the joint venture. These individuals have authority to sign on behalf of the joint venture.

2. Direction, approvals, required notices, and all other communications from the Government to the joint venture, including transmittal of payments by the Government, shall be directed to (enter name, title, and company of principal), principal representative of the joint venture.”

NOTE: Provide telephone numbers and email addresses for the points of contact listed in the above statement.

f. Other sections of the proposal shall identify, where appropriate, whether key positions (as noted in paragraph 17.3.1.(1)(b) are employees of the individual Joint Venture parties and identify the party, or hired as employees of the Joint Venture.

g. If one of the Joint Venture parties possesses Prime Contractor or Joint Venture experience and/or past performance as a Federal Government contractor or as a Corps of Engineers contractor, that experience and/or past experience will be included as the experience and/or past experience of the Joint Venture.

PHASE 2 Requirements:

Joint Ventures shall submit the following additional documentation regarding their business entities during Phase 2:

a. For 8(a) Joint Venture agreements, a certified copy of the Joint Venture agreement. This agreement must be certified by SBA before award of any resulting contract.

b. A detailed statement outlining the following in terms of percentages, where appropriate, shall be submitted during Phase 2 of the two phase selection procedures.

1. The relationship of the joint venture parties in terms of business ownership, capital contribution, and profit distribution or loss sharing.

2. The structure of the joint venture and decision-making responsibilities of the Joint Venture parties in terms of who will control the manner and method of performance of the work.

3. Identification of the key personnel having authority to legally bind the Joint Venture to subcontracts and state who will provide or contract for the labor and materials for the Joint Venture.

4. Joint Ventures shall also state who will have custody and control of the assets of the Joint Venture and perform the duties necessary to complete the work. Identification of party maintaining the Joint Venture bank accounts for the payment of all expenses and the deposits of all receipts, keep the books and records, and pay applicable taxes for the Joint Venture.

5. Identification of party having overall control of the Joint Venture.

7.3. INTEGRITY AND VALIDITY OF CONTRACTOR TEAM ARRANGEMENTS

The Contracting Officer will recognize the integrity and validity of contractor team arrangements; provided that the arrangements are identified and company relationships are fully disclosed and validation of formal agreements and relationships (i.e., Mentor-Protégé agreements, joint ventures, partnerships, etc.) are provided in the offer and submitted with the proposal responding to the solicitation. Nothing in the solicitation authorizes contractor team arrangements in violation of antitrust statutes or limits the Government’s rights to:

a. Require consent to subcontracts (see FAR Subpart 44.2);

b. Determine, on the basis of the stated contractor team arrangement, the responsibilities of the prime contractor (see FAR Subpart 9.1);

c. Provide to the prime contractor data rights owned or controlled by the Government;

d. Pursue its policies on competitive contracting, subcontracting, and component breakout initial production or an any other time; and

e. Hold the prime contractor fully responsible for contract performance, regardless of team arrangement between the prime contractor and its subcontractors.

8. BASIS FOR AWARD

The agency will use Two-phase Design-Build Selection Procedures authorized by FAR 36.301.

The Phase 1 selection will be based on evaluation of technical factors and past performance. There are three non-price factors in Phase 1: Factor 1 – Previous Experience, Factor 2 – Past Performance, and Factor 3 – Technical/Management Approach. Price will not be considered during Phase 1. Only those Offerors who submitted the most highly rated proposals in Phase 1 will be invited to submit a proposal for Phase 2, and they will be the only Offerors eligible to compete in Phase 2.

In Phase 2, the Government intends to evaluate proposals and award a contract without conducting discussions with Offerors. However, in the event the Source Selection Authority (SSA)/Procuring Contracting Officer (PCO) concludes conducting discussions is in the best interest of the Government, the Contracting Officer will establish a competitive range. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals. Therefore, the Offerors initial proposal should contain the Offeror’s best terms from a price and technical standpoint.

A sample project may be used to meet price competition requirements for this unrestricted Multiple Award Task Order Contract (MATOC) in Phase 2.

9. RELATIVE IMPORTANCE OF EVALUATION FACTORS

Evaluation Factors are listed below in descending order of importance:

Factor 1: Previous Experience Factor 2: Past Performance Factor 3: Technical/Management Approach Factor 4: Key Personnel (Phase 2 Only) Factor 5: Technical Approach for the Sample Project (Phase 2 Only) Factor 6: Small Business Participation Plan (Phase 2 Only) Factor 7: Cost/Price Proposal for the Sample Project (Phase 2 Only)

All Evaluation Factors other than cost or price, when combined, are significantly more important than cost or price.

Proposals will be evaluated using the Best Value-Tradeoff process as identified in FAR 15.101-1.

10. SOURCE SELECTION PROCESS

All offers received in response to this solicitation will be evaluated in accordance with FAR Part 15.3, DoD Source Selection procedures, and Army Source Selection Supplement. The principal objective of this process is to select responsible Offerors who submit the offers that are the Best Value to the Government. The process is designed to ensure the impartial, equitable, and comprehensive evaluation of all technically acceptable, responsible proposals received in response to this particular solicitation.

11. TECHNICAL RATING

The evaluation ratings for Technical Factors 1, 3, 4, and 5 will be on an adjectival basis in conjunction with a narrative composed of the discussion of the particular strengths, weaknesses, and deficiencies of the proposal. The SST will use a combined technical/risk rating system that includes consideration of risk in conjunction with the strengths, weaknesses, and deficiencies in determining technical ratings. Combined technical/risk evaluations shall utilize the combined technical/risk ratings listed in Table 2. The Combined technical/risk ratings will be used to evaluate Phase 1 – Factor 1 Previous Experience, Phase 1 – Factor 3 Technical/Management Approach, Phase 2 – Factor 4 Key Personnel and Phase 2 – Factor 5 Technical Approach to the Sample Project. The evaluation rating that will be used for Phase 1 - Factor 2 Past Performance is described in Paragraph 12 below. The evaluation rating that will be used for Phase 2 – Factor 6 Small Business Participation Plan is described in Paragraph 13 below.

Table 2: Combined Technical/Risk Ratings

Color Rating Description

Blue Outstanding Proposal indicates and exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.

Purple Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.

Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.

Red Unacceptable Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.

12. PAST PERFORMANCE RATING

The past performance evaluation factor assesses the degree of confidence the Government has in an Offeror’s ability to supply products and services that meet users’ needs, based on a demonstrated record of performance. The past performance evaluation results in an assessment of the Offeror’s probability of meeting the solicitation requirements. The past performance evaluation considers each Offeror's demonstrated recent and relevant record of performance in supplying products and services that meet the contract’s requirements. One performance confidence assessment rating is assigned for each Offeror after evaluating the Offeror's recent past performance, focusing on performance that is relevant to the contract requirements. There are two aspects to the past performance evaluation, Relevancy and Contractor Performance, which are described below:

a. Relevancy. The first aspect of the past performance evaluation is to determine how relevant a recent effort accomplished by the Offeror is to the effort to be acquired through the source selection. Recent is defined as past performance on contracts that had a construction completion date within six (6) years of the date that Phase 1 proposals are due. Relevancy is defined as similarity of items stated within this solicitation such as: types of projects, dollar value, contract type, and customer(s). With respect to relevancy, more relevant past performance will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment. Relevancy is not a separate proposal rating but is used to develop an overall Past Performance Confidence Assessment. The four levels of relevancy ratings are:

Adjectival Rating Description

Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

b. Contractor Performance. The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the Offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the Offeror performed those past contracts.

This is the start of the file's text. The full file is on GovTribe.